Text version
Solicitation Number GS04P15BVC0013 Page 1 of 1 Amendment 0001 07/01/2015
U.S. GENERAL SERVICES ADMINISTRATION
Public Buildings Service, Design & Construction Division Region 4 / Southeast Sunbelt Region
REVISIONS TO SOLICITATION DOCUMENTS:
*Deletions are indicated with a strikeout and additions are indicated with an underline, unless section or paragraph is added or replaced in its entirety. A complete revised set of solicitation documents will be issued with the award documents to the successful firm.
0013 RFP Revisions:
1. The attached SF1442 entitled “REVISED SF1442” and dated 07/01/2015 hereby replaces the SF1442 issued on 6/19/2015. All offerors are required to complete and submit a copy of this revised SF1442 with their proposal.
2. The period of performance identified in block 11 of the SF1442 and para I.C. of the Draft Agreement is amended and clarified as follows: The contractor shall reach substantial completion within 120 calendar days of Notice to Proceed for all work items except the specific work items listed below:
1. Installation of the new exterior preformed polymer concrete panels
2. New decorative aluminum screens / grills at new curtain wall opening (Deductive Option #2)
3. Construction of Restrooms 303 & 305 and janitor's closet 304.
For the three work items listed above only, the contractor shall reach substantial completion within 160 calendar days of Notice to Proceed.
3. The attached document identified as “Supplemental Proposal Breakout” is required to be completed by the successful offeror and submitted to the Contracting Officer within 10 calendar days of award. This document is not required to be submitted with the offeror’s proposal.
All other terms and conditions remain unchanged.