DB Services New United States Courthouse & Renovation of John Campbell Mobile, Alabama Solicitation Number: GS04P14BVC0027

Statement of Work for

DesignBuild (DB) Contract

SOW for Phase 1 RFQ

PROJECT IDENTIFICATION

Project Name: New U.S. Courthouse and Repair and Alteration of The Historic John Campbell Courthouse, Mobile, AL

Project Number: NAL00147

Region: Southeast Sunbelt, Region 4

Building Name: New Construction TBD Renovation John Campbell Courthouse

DESIGNBUILD STATEMENT OF WORK 1

1 PROJECT DESCRIPTION

The General Services Administration (GSA) intends to award a DesignBuild Contract for a construction of a new courthouse and renovation of the John Campbell Courthouse, located in Mobile, Alabama pursuant to the Federal Acquisition Regulation (FAR) TwoPhase DesignBuild Selection Procedures (FAR Subpart 36.3). The contract will be awarded as a firm fixed price for the Design and Construction of the new Courthouse, a firm fixed price for the design of the renovation of the John Campbell Courthouse, and a Guaranteed Maximum Price option for the renovation construction of the John Campbell Courthouse.

The new construction portion of the project is located in the Downtown Business Improvement District (BID) of Mobile, Alabama and will be sited directly across St Louis St from the existing John A Campbell Courthouse on one city block approximately 1.8 acres and bounded by St Louis, St Joseph, Conception and St Anthony Streets Site is adjacent to the DeTonti Historic District with a small portion of site contained in its boundaries This new project will continue the revitalization of the CBD and be an anchor in the neighborhood. The project is approximately 155,600 Gross Square Feet (GSF) including 38 inside, secure, parking spaces. The courthouse is programmed to include 6 Courtrooms, 9 Judges Chambers, the United States Marshals Service (USMS) prisoner areas, administrative areas for the United States District Court, and the United States Marshals Service.

The designbuild scope of work includes all labor and materials required to provide architectural, engineering, construction, and other related services necessary to design and to construct a United States Courthouse as well as renovation of the existing John A. Campbell Federal Courthouse compliant with applicable codes.

The design should be masterplanned to anticipate an additional 38,000 GSF expansion area on the site. The design should make a distinct architectural statement that is responsive to the national urban and environmental policies of GSA.

The John A. Campbell U.S. Courthouse is located at 113 St. Joseph Street in Mobile, Alabama.

The building, built in 1932, has 73,034 usable and 115,015 gross square feet. The courthouse is programmed for future location of the Court of Appeals, Bankruptcy Court, Bankruptcy Administrator, US Probation, Grand Jury, Congressional offices, and General Services Administration (GSA). Reconfiguration will include 3 existing Courtrooms, 5 Judge’s Chambers , and one courtroom converted to the Grand Jury Suite. The renovations will generally include , but are not limited to, accessibility upgrades; perimeter security; window maintenance (reglaze, replace, remount) and new blast film; elevator upgrades, HVAC upgrades including new penthouse equipment area; plumbing Upgrades (domestic water distribution); electrical upgrades (infrastructure relocation, lighting, transfer switches); hazardous materials abatement; new sprinkler system for building; Upgrade public areas, lobbies, and restrooms; tenant fit up for backfill; and security upgrades at main lobby.

The GSA will contract separately for Construction Manager as Agent (CMa). The CMa will partner with the successful Offeror in the design process with administration functions, Building Information Modeling (BIM) coordination and for functional/constructability reviews. There will be a formal partnering process throughout the design and construction phases to promote

DESIGNBUILD STATEMENT OF WORK 2

successful project development and execution through integrated project delivery that will be mutually beneficial for all parties involved.

1.1 Project Type

Project is defined as a New Construction project, using a Collaborative Design Build approach that follows GSA’s design excellence guidelines.

1.2 Project Goals and Objectives

New Construction

Project Goals

● Continue a legacy of outstanding public architecture, the General Services Administration (GSA) Design Excellence Program seeks to commission our nation’s most talented designers and artists to design federal buildings of outstanding quality and value

● Design & construct a safe, productive, and attractive workspace.

● Meet the functional requirements of all facility users.

● Complete the design and construction operations in an efficient and effective manner – keep the project on time and on budget.

● The new Courthouse should be designed to contribute to the community and be compatible with its context including the adjacent historic properties..

● Ensure that the project responds positively to national, historic, and environmental policies.

● Create a facility that becomes a respected landmark.

● Provide the best value to GSA’s customer agencies and the American taxpayer.

● Coordinate project with renovation of the existing Campbell Courthouse

● Ensure implementation of the cost effective soil and groundwater mitigation strategies to comply with the Alabama Department of the Environment (ADEM) regulations including Bronwfield Redevelopment and Voluntary Cleanup Program.

Project Objectives

● Complete all work within the current Congressionallyauthorized budget.

● The project should continue the revitalization of the CBD (Central Business District) and serve as a transition between the BID and the Historic District. The design should respect both the scale of the Campbell USCH to the south of the site, and of the DeTonti Square residential area to the north of the site.

● Meet all Federal energy and water conservation goals and security requirements specifically the Guiding Principles for Sustainable New Construction and Major Renovations, of Executive Orders 13423, 13514, and the Energy Policy Act of 2005, as well as the fossil fuel reductions, renewable energy and water conservation goals of the Energy Independence and Security Act of 2007, as per P100 2014.

● Provide a facility that efficiently and effectively addresses the functionality of the US Courts and US Marshals with specific care taken with regard to security, plan organization, adjacencies, workplace excellence and spatial issues.

● Attain the sustainability goal of LEED Gold NC certification.

● Provide effective environmental coordination with ADEM, Environmental Consultant, and GSA to ensure the environmental goal is met.

DESIGNBUILD STATEMENT OF WORK 3

Repair and Alteration (R&A) Project

Project Goals

● Design & renovate existing courthouse to provide a safe, productive, and attractive workspace.

● Complete the design and construction operations in an efficient and effective manner – keep the project on time and on budget.

● Ensure that the project responds positively to national, historic, and environmental policies.

● Preserve the architectural character defining features and spaces in the existing historic courthouse while allowing for modernization and functionality .

● Provide the best value to GSA’s customer agencies and the American taxpayer.

● Coordinate project with construction of the new courthouse.

Project Objectives

● Complete all work within the current Congressionallyauthorized budget.

● Meet all Federal energy and water conservation goals and security requirements specifically the

Guiding Principles for Sustainable New Construction and Major Renovations, of Executive Orders 13423, 13514, and the Energy Policy Act of 2005, as well as the fossil fuel reductions, renewable energy and water conservation goals of the Energy Independence and Security Act of 2007. as per P100 2014.

● Attain the sustainability goal of LEED Gold major renovation certification.

● Renovate the facility that efficiently and effectively addresses the functionality of the US Courts and the other occupying agencies with specific care taken with regard to security, plan organization, adjacencies, workplace excellence and spatial issues.

● Address all issues and deficiencies in the current facility’s functioning and operations while preserving significant historic features and spaces.

1.3 Project Delivery Approach

This project will utilize the DesignBuild (DB) delivery method, with the DB contract procured by competitive negotiation using a two phase designbuild selection procedure (FAR Subpart 36.3).

A single DB contract will be issued for a revised design concept submission (if necessary), Design Development Phase and Construction Documents Phase services, as well as all construction work including tenant improvements and all required specialty construction work.

A separate, but related Construction Manager as agent (CMa) contract will be awarded for Design Stage CMa services, Construction Documents Phase CMa services, Construction Delivery Phase CMa services, and Closeout Stage and Tenant Occupancy Stage services. The CMa will also serve as the Commissioning Agent (CxA) and develop the DB contract commissioning performance requirements for the Design Stage, Construction Documents Phase, Construction Delivery Phase, Closeout Stage, and Tenant Occupancy Stage commissioning.

The Design effort for this contract is allinclusive (i.e., for full project scope), based on the approved concept established by the Government and the D/B firm.. Phased construction documents and construction will begin after design development

DESIGNBUILD STATEMENT OF WORK 4

1.4 Reference Materials

Reference materials will be provided with the DB SOW issued under Phase 2 of the RFP

2 Project Delivery Team In the performance of the requirements of this contract, the Design Build Contractor shall work in concert with all other parties on the Project Delivery Team. The Project Delivery Team will include the General Services Administration (GSA) personnel, multiple Tenant Representatives, Construction Management Assist (CMa) to include the Commissioning Agent (Cx) and Energy Engineer (EE), and other stakeholders. The GSA will develop, periodically update, and maintain throughout the course of the project, a listing of the Project Delivery Team membership and respective roles and responsibilities. The major parties involved or to be involved in the Project Delivery Team, and their respective overall roles and general responsibilities, are as follows:

General Services Administration is the project owner and will be responsible for project management to include coordination of the parties and contract execution of the entire project.

The CMa will be responsible for assisting GSA with requirements development, estimating, design reviews, price/cost analysis, quality assurance, construction schedule reviews, monitoring LEED process, etc. The Cx will be part of CMa team and is responsible for developing commissioning requirements, drafting a Cx Plan, verifying that the installed systems meet objectives, functional and performance testing, seasonal/warranty testing, and submission of Cx report. Energy Engineer/Energy Modeling will be a part of the CMa team and will collaborate with the DB team to monitor progress in achieving the target energy goal.

The DesignBuild (DB) Team is required to perform two components of work: Design Stage services and Construction Stage work. The LEED consultant will be part of the DB team and will be responsible for maintaining all LEED documentation necessary to meet the stated project LEED goal. The LEED consultant will be responsible for registering and submission of all required documents for LEED certification.

Energy Modeler of record will be a part of the DB team and will be responsible for developing the energy model that reflects achievement of energy targets. The DB Contractor will be the Architect of Record for the project and will bear all responsibilities and liabilities attendant thereto.

The specific activities, tasks, and deliverables required of the DB Contractor will be further delineated in the DB Phase 2 RFP Scope of Work.

3 SCOPE OF WORK: (This is a representative list of expected critical tasks, Scope will be further defined in PHASE 2 RFP)

3.1 Design:

3.1.1 Design Excellence and Peer Review

This project requires concept development reviews, involving the DB Contractor, the GSA regional and national office staff, and professional privatesector peers serving on the behalf of the GSA. The broad objective of these reviews is to have discussions among professionals that focus on design, not only as it

DESIGNBUILD STATEMENT OF WORK 5

impacts issues of program requirements, function, form, and detail, but also as it affects ontime and on budget delivery. These conversations can address general design strategies and urban context as well as more specific topics such as materials and building systems. At the Design Development Phase, a similar review is conducted to focus on the design of the HVAC system

3.1.2 Design Quality Assurance

The GSA requires that DB Contractor design submissions and construction documents submissions undergo two general types of design review: Owner’s review and codes and standards review. The GSA staff and GSA customer agencies will conduct reviews of all DB Contractor design submissions and construction documents submissions. The GSA OCA may also conduct independent quality assurance/quality control reviews of some DB Contractor design submissions. These GSA reviews will focus primarily on program goals and design objectives. 3.1.3 Constructability

Constructability of the project as designed is the sole responsibility of the DB Contractor. DB shall ensure that the design can be constructed within schedule and budget and that the sequencing of construction is planned for optimum efficiency.

3.1.4 Building Information Modeling (BIM)

BIM for spatial program validation is a minimum BIM requirement performed by the DB contractor. Additional BIM may include:

• use of 3D geometric models for visualization

• use of 4D models for phasing analysis

• use of 3D/BIM for design and construction coordination

• use of BIM (with “smart” objects) for an array of analyses

GSA and the DB contractor will determine the level of BIM required to the project

3.2 Construction: GSA anticipates that this project will be very collaborative. During construction the Contractor shall provide all services required of a general contractor. Specific details of the work are provided below but they shall in no way limit the Contractor's overall duty to provide DB services.

3.2.1. The Contractor shall conduct weekly progress meeting(s) and weekly subcontractor meeting(s) and maintain minutes for it. The Contractor shall also be required to attend construction oversight meetings with representatives from GSA and the Design Team on a monthly basis. The Contractor shall conduct site tours for GSA and other officials as required.

3.2.2 Develop a Construction Schedule current with the design resolution process. Revise the construction schedule as required to reflect changes that have occurred during design or to reflect a change or more refined schedule for procurement of materials, subcontract buyout or construction. Provide updates at the design review meetings.

3.2.3 Develop Value Engineering proposals, which will provide savings to the Government.

3.2.4 Identify subcontract bid packages and material procurement packages that could be advertised prior to the completion of construction documents. If GSA concurs that the project will benefit GSA will authorize the Contractor to advertise and award subcontracts or material procurements for long leadtime items in advance of completion of construction documents.

3.2.6 Prepare and process the application(s) for all necessary building permits. Monitor and expedite the permitting process as necessary to ensure that the construction permits are received in a timely fashion.

3.2.7 The Contractor shall be responsible for superintendence, providing ongoing coordination between

DESIGNBUILD STATEMENT OF WORK 6

crafts, job site safety, quality control, settling disputes between subcontractors, negotiating any Change Orders with the subcontractors (GSA expects the DB to negotiate with subcontractors, but reserves the right to reject any subcontractor proposal), negotiating Change Orders with GSA. Reviewing, coordinating and forwarding submittals and RFIs to GSA's Representative for action and for responding to all correspondence related to the effort required for any procurement activities that arise from a subcontractor's inability or unwillingness to perform.

3.2.8 The Contractor shall be responsible for general building layout, and for the coordination of layout work provided by separate trades for their own work, to insure that no conflict exists with the work of other trades.

This work shall include the layout of all partitions and door openings, electrical panels, and fixed casework outlines (including knee spaces) on the floor slab prior to mechanical, plumbing, and electrical roughin work.

3.2.9 The Contractor shall provide sufficient staff of project managers, field engineers, superintendents, engineers, CQC representatives, testing engineers, scheduling engineers, cost engineers, clerical and accounting personnel to ensure timely processing of Change Order Proposals, RFIs, submittals and general correspondence

3.2.10 DB shall complete all work necessary to turnover the building to GSA to include the following closeout activities:

3.2.10.1 Construction Substantial Completion is defined as a level of construction, which allows the Government to occupy and operate the entire building or portions of the building according to a phased occupancy schedule. The only remaining work in the building shall not restrict occupancy or the normal business operations of the building tenants. Such remaining work is normally cited on a punch list, which is included in the documentation of Substantial Completion.

3.3 Art in Architecture

The GSA Art in Architecture program involves the selection of an artist to create and install artwork within the project. Artwork should respond to the context of both the facility design and the surrounding community. The DB contractor will coordinate with the GSA Art in Architecture staff on recommendations to incorporate art as an integral component of the building, participate in the selection of the artist, and accommodate the installation of the final artwork within the building design. Structural support and utilities for the artwork installation shall be included in the construction contract and the associated cost must be accommodated within the construction funding limitation. The artwork will be procured, furnished and installed under separate contracts. The cost of separate contracts for the artwork is not included in the construction funding limitation.

DESIGNBUILD STATEMENT OF WORK 7