PRICE
| 1 |
| Base Contract - New Pavilion, modifications to the existing Pearl Street security screening station, and new vent stacks located in the adjacent lower plaza. The new pavilion will be registered with the USGBC for LEED Gold rating |
| $ |
| 2 |
| Option No. 1 – Worth Street Vent Stack and New Plantings |
| 3 |
| Option No. 2 – Pearl Street HVAC Intake |
| 4 |
| Option No. 3 – Sounding Stones Sculptures Water Lines and Lighting |
| 5 |
| Option No. 4 – Lift Net Monitor System to Elevator Controls |
| $ |
Option No. 5 – Elevator Intercom System
Option No. 6 – Alum. Vs. Stainless Steel at Sunshade, Roof Canopy & Coping
| 8 |
| Option No. 7 – Delete Glass Pavers at Roof |
| $ |
| 9 |
| Option No. 8 – Smaller Glass Panels at Five Plaza Vent Stacks |
| $ |
| Option No. 9 – Porcelain vs. Granite Tile at Pavilion Flooring |
| $ |
| 11 |
| Option No. 10 – Relocation of Existing Fire Alarm Control Panel |
| 1 |
| Total price for Options 1 through 10 |
| $ |
| 2 |
| Total Evaluated Price (Base Contract plus Options 1 -10) |
| $ |