Questions and Answers 04 22 10.pdf
PDF 70 KB Posted
- Solicitation number
- GS-01P-10-BW-C-0054
About this file
Questions and Answers 3
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Q&A April 22, 2010
Solicitation No. GS-01P-10-BW-C-0054
1. Is there any current Net Sales for 2010 available for January, February or March?
January Café - 31,121.00 January Drop Off - 9,881.00
February Café - 41,489.00 February Drop Off - 3,652.00
March Café - 46,209.00 March Drop Off - 16,755.00
2. Are the Previous Sales Provided for 2009 and prior Net Revenue or Gross Revenue Figures?
Net.
3. Repairs - Is there any historical data regarding current levels, dollars expensed by the contractor? Do You have a dollar figure that all vendors should use in their pro-forma ?
GSA hopes to have a answer to this question by Monday April 26.
4. Is it fair to say that prior to a change in Cafe Contractor all equipment will be inspected and to be properly working ?
Yes.
5. Vendor required Equipment - Page 14 of RFP - Samples of equipment to be provided by vendor includes the POS system. Then, on Attachment 2 - Inventory of Food Service Equipment Supplied by Government # 107 & 126 are registers. Should we include a POS in our Performa ?
Yes, they will need to set up a POS for credit cards.
6. Pricing - When was the last change in Cafe Pricing?
The last change in café pricing was in Feb 2009.
7. Child Care- Are the Meals provided part of the current contract or separate agreement between child care and the contractor ? Is there a set or pre-fixed meal price ? Is there a sample menu that can be provided ?
The meals provided to the Day care center are not part of the current contract. The menu is a pre-fixed price menu..
8. Is the Proposal date being extended ?
The proposal date is now extended to April 29, 2010.
File details come from the government source that posted it. Updated .