SiteVisitMinutesPublish.doc

DOC document 104 KB Posted

Attached to
Site preparation for relocation of Radiation Portal Monitor at US Border Station, Rt. 91 Derby Line VT.
Solicitation number
GS-01P-08-BZ-C-0004
Issued by

About this file

Site Visit Q A

View the file

Other files

File Type Posted
DerbyLineVisitRevA.doc DOC document
sitevisit.pdf PDF
Volume1FinalDoc.pdf PDF
Volume2FinalDoc.pdf PDF
Volume3FinalDoc.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. General Services Administration

Pre-Bid Site Visit

Solicitation: GS-01P-BZ-C-0004

Site Prep and Relocation of Radiation Portal Monitor

US Border Station, Derby Line VT

Issue Date:

27 February 08

Date of Visit:

19 February 08

Place:

US Border Station Derby Line VT

Government Representatives:

Thomas Eberhardt, COR

Wally Rogowicz, Project Engineer

Vendor Representatives:

See Attachment 1

Summary:

Meeting was convened at 10:00AM, 19 Feb 08 at US Border Station Derby Line VT for the purpose of providing prospective bidders an opportunity to view the place of performance for the contract. Mr. Eberhardt and Mr. Rogowicz conducted a tour of the work site and as a result of the tour several questions were generated. The questions were forwarded to the contracting officer, and specific responses are provided as attachment 2.

The responses are intended to provide clarification only and do not modify the requirements contained in the Technical Specification and drawing package.

Donna Maffeo

Contracting Officer

North Service Center, 1PK

(617)565-6012, Fax:(617)565-7145 Attach:

1. List of Attendees

2. Site Visit Questions and Responses

Attachment1

List of Attendees

Derby Line Border Station Relocation of Primary Cargo RPM
Pre-Bid Conference

Solicitation GS-01P-BZ-C-0004

U.S. Border Station

Derby Line, Vermont

Date: 2/19/2008

Name
Agency/Company
Telephone #
email/fax
Arthur Means
South Bay E.D.C.
office: 207-279-3483
email: southbayameans@edc.com
cell:
fax:
Mike Pitonyak
Capital Earthmoving
office: 802-476-4833
email:
cell:
fax:
Tom Emler
Capital Earthmoving
office: 802-476-4833
email:
cell:
fax:
Dmitri Ivanov
Mill City Environmental
office: 978-654-6741
email: divanov@millcityenv.com
cell:
fax:
John Gobeil
Roger Gosselin, Inc.
office: 802-766-8815
email: jgobeil1@comcast.net
cell:
fax:
Norman Patenaude
Pike Industries, Inc.
office: 802-748-9391
email: npatenaude@pikeinc.com
cell:
fax:
Jay Lafontaine
J.P. Sicard, Inc.
office: 802-525-9506
email: jay@jpsicard.com
cell:
fax:
Jason Sicard
J.P. Sicard, Inc.
office: 802-525-9506
email: jason@jpsicard.com
cell:
fax:
Harold Lunn's
Harold's Concrete
office: 802-695-1341
email: harr1@charter.net
cell:
fax:
Gerard Ginge
Ginge Construction, Inc.
office: 802-626-8666
email:
cell:
fax:
Arnie Gray
Gray's Paving
office: 802-334-5225
email:
cell:
fax:
Martin Hazelton
SCI
office: 802-766-5000
email: martinh@scigroupvt.com
cell:
fax: 802-766-2142
Rod Amos
Amos Electric
office: 802-334-6614
email: rod@amos-electric.com
cell:
fax: 802-334-5132
Tom Lafollette
Far East
office: 860-761-4851
email: tlafollette@gmail.com
cell:
fax:
Jay Whitcomb
Mike's Electric
office: 802-988-9678
email: mej-vt@comcast.net
Name
Agency/Company
Telephone #
email/fax

Attachment 2

Questions and Responses

RELOCATION OF PRIMARY CARGO RPM

U.S. BORDER STATION

DERBY LINE, VERMONT

Questions during Pre-bid Conference:

1. Q: When trenching is completed at concrete roadway, can asphalt be installed in its place?

A: When trenching is completed in any type of surface, i.e., concrete or asphalt, the same type of material must be used to replace what was removed and to the original thickness of the material removed.

2. Q: In lieu of trenching along the existing cargo RPM, is it feasible to run the group B conduit runs, four 1" conduits, above the existing RPM and to the new cargo RPM that is being installed? This would reduce the down time of the existing primary cargo RPM. There are two conduit runs that already run above it and there is uni-strut above the RPM that would be sufficient to install the four conduit runs.

A: Running the conduit above ground would be acceptable.

3. Q: In lieu of trenching is boring under the roadway acceptable? This would also minimize down time of the RPM.

A: This would be acceptable.

4. Q: Is a new power feed required for the new RPM or can it be run off the power from the existing RPM?

A: Refer to Page 6 of 23 in the Radiation Portal Monitor Project Statement of Work as prepared by PNNL. Item C-3 Electrical Power for RPMs. Provisions shall be made such that the RPM power supplies are connected to site backup power at a nominal 110/120 VAC. For long runs, the contractor may use higher voltages between the source panel and RPM power panel. Item C-3-1 indicates that the power circuit for the new RPM in cargo lane 2 shall run from a new 20A breaker in the RPM panel to the control box on that RPM. The contractor shall ensure that wires are sized to meet code. A separate circuit is needed for each RPM; the new RPM will require a new circuit with its own breaker.

5. Q: Is doweling required at the expansion joint between the existing and new concrete roadway?

A: Yes. Refer to Sheet 3 of 3 as prepared by GSA. Note on the drawings between the existing and new roadway indicates to provide an expansion joint to match detail 3 on the drawings. Approximately 100 lf. It is required at connection of new to existing concrete roadways as well as at any expansion joint that is required between concrete pours based on the distances allowed to be carried for concrete pours.

6. Q: What is the contract duration?

A: The contract duration is 60 days after Notice to Proceed.

7. Q: When does the project have to be completed?

A: The project shall be completed within 60 days after receipt of Notice to Proceed.

8. Q: When do you anticipate contract award?

A: Contract award is anticipated on or about 18 March 08. We anticipated the Notice to Proceed will be issued in mid-April.

9. Q: Will VAOT be conducting any testing on this project?

A: VAOT will not be conducting any testing on this project.

10. Q: What testing is required for materials being installed?

A: Refer to respective material specification sections for testing that is required as part of this contract.

11. Q: Is IBC approval required on this contract?

A: IBC approval is not required since all work that is being accomplished is on U.S. Government property.

12. Q: Where will stockpiled materials be stored?

A: The contractor will be allowed to store materials at the northwest corner of the property. This area is located directly west of the new roadway work that will be conducted for the new Cargo RPM.

13. Q: What is the required bid bond amount for this project?

A: A Bid Guarantee in the amount of 20% of the bid price or $3,000,000, whichever is less, is required. See solicitation, Volume 1 of 3, Supplementary Conditions, Clause 52.228-1, Bid Guarantee (Sep 1996)