Summary_of_Changes_Folly_Shore_Protection_AM0001.docx

DOCX document 21 KB Posted

Attached to
FY18- Folly Beach Protection Project Federal contract opportunity
Solicitation number
GROUP4-18-R-C001
Issued by
Department of the Army Corps of Engineers Engineering District Charleston

About this file

Amendment 01- Summary of Changes

View the file

Other files for this federal contract opportunity

Other files attached to FY18- Folly Beach Protection Project, newest first.
File Type Posted
AMENDMENT_02_Summary_of_Changes.pdf PDF
Pipeline_Corridor_Easements.pdf PDF
H_Submittal_Register_AM0001.pdf PDF
Folly SB Contract Combined Survey (From April 2017).xyz XYZ file
BIDDING_SCHEDULE_AM0001.pdf PDF
20170915_FB_LI_CS_POSTIRMA3X3.xyz XYZ file
SECTION_35_20_23_10_DREDGING_&_BEACHFILL_AM0001.pdf PDF
RTA_Drawings_AM0001.pdf PDF
DRAWINGS_-_Folly_Beach_Shore_Protection_Project.pdf PDF
SPECS_-_Folly_Beach_Shore_Protection_Project.pdf PDF
FOLLY_BEACH_SHORE_PROTECTION_RFP.docx DOCX document
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FY18 Folly Beach Shore Protection Project Amendment 0001

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

1. CONTRACT DRAWINGS, SHEETS C-001 TO C-011

DELETE “Sheets C-001 to C-011” and REPLACE with “Sheets C-001 to C-011” denoted by AM0001 (attached).

2. BID OPENING DATE

Change BID OPENING DATE to 20 November 2017.

3. CONTRACT SPECIFICATIONS, SECTION 00 10 00 “SOLICITATION, OFFER AND AWARD (SF 1442)”, Paragraph “DESCRIPTION OF WORK” DELETE “550,000 cubic yards” and REPLACE with “990,000 cubic yards”

4. CONTRACT SPECIFICATIONS, SECTION 00 10 00 “SOLICITATION, OFFER AND AWARD (SF 1442)”, Paragraph “MAGNITUDE OF WORK” DELETE “$5,000,000 to $10,000,000” and REPLACE with “$5,000,000 to $15,000,000”

5. CONTRACT SPECIFICATIONS, SECTION 00 10 00 “SOLICITATION, OFFER AND AWARD (SF 1442)”, Paragraph “BIDDING SCHEDULE” DELETE “BIDDING SCHEDULE” and REPLACE with “BIDDING SCHEDULE_AM0001” (attached).

6. CONTRACT SPECIFICATIONS, SECTION 00 73 00 “SPECIAL CONTRACT REQUIREMENTS”, Paragraph “Supplemental Instructions” DELETE “(a) Prosecution of Work” and “(b) Continuously Working” and REPLACE with:

“(a) Prosecution of Work

The Contractor will be required to commence work under this contract within 30 calendar days after the date of receipt by him of Notice to Proceed. The dredging and placement operations shall not commence until all environmental clearances have been obtained. The dredging and placement work required shall be performed in its entirety, final acceptance/compliance of all sections, and demobilization shall be complete by 15 September 2018. Dredging shall be scheduled and diligently pursued in a continuous manner until completed.

The Contractor shall provide the Government a schedule not later than 10 calendar days after date of Notice to Proceed depicting, at a minimum, the following information:

- Commencement date of mobilization and demobilization;

- Date dredging/placement shall begin following mobilization;

- Duration of dredging/placement (must at least meet the specified completion date);

- Date dredging/placement is to be completed, at a minimum, for each acceptance section;

- Anticipated schedule of earnings.

Once this schedule is approved, it will be incorporated into the contract by a no cost modification and become the performance period for the contract. Liquidated damages will be assessed for every day work continues beyond this incorporated scheduled completion date (as adjusted for excusable delays as allowed per other clauses within the contract).

(End of supplemental instructions)”

7. CONTRACT SPECIFICATIONS, SECTION 00 73 00 “SPECIAL CONTRACT REQUIREMENTS”

ADD FAR CLAUSE “52.217-7 OPTION FOR INCREASED QUANTITY—SEPARATELY PRICED LINE ITEM (MAR 1989)

ADD FAR CLAUSE “52.232-18 AVAILABILITY OF FUNDS (APR 1984)

8. CONTRACT SPECIFICATIONS, SECTION 01 57 20.00 10 “ENVIRONMENTAL PROTECTION”, PARAGRAPH “HISTORICAL, ARCHAEOLOGICAL, AND CULTURAL RESOURCES” After Paragraph “HISTORICAL, ARCHAEOLOGICAL, AND CULTURAL RESOURCES” ADD new Subparagraph, “Cultural Resource Surveys

The contractor shall perform magnetometer and side-scan surveys of the pipeline alignment from the identified Borrow Area to insure that no cultural resources are being impacted. The spacing between survey lines should be no more than 20 meters (65 feet). As a general guidance, two passes (basically out and back, should provide about a 125-foot wide corridor) of the planned corridor should be sufficient to accomplish this. A letter report shall be submitted, documenting what and how the assessment was performed and the findings. Should any cultural resources be identified along the planned alignment corridor during the survey effort, additional surveys shall be conducted to identify potential areas to relocate any pipeline, anchors, buoys, and anything associated with the dredge pipeline at least 100 feet from the cultural resources.”

9. CONTRACT SPECIFICATIONS, SECTION 01 57 20.00 10 “ENVIRONMENTAL PROTECTION”, SUBPARAGRAPH “SEA TURTLE NESTING AND HATCHING SEASON” DELETE from the first sentence of the second paragraph, “In order to minimize potential impact to sea turtles,” DELETE from the first sentence of the second paragraph “May 1.” and REPLACE with “September 15, 2018.”

10. CONTRACT SPECIFICATIONS, SECTION 35 20 23 10 “DREDGING & BEACHFILL”

DELETE entire section REPLACE with SECTION 35 20 23 10 “DREDGING & BEACHFILL” bearing notation AM0001 (attached).

11. CONTRACT SPECIFICATION, ATTACHMENTS, H “Submittal Register” DELETE “Submittal Register” and REPLACE with “H_Submittal Register_AM0001” (attached).

12. XYZ DATA

- Folly SB Contract Combined Survey (From April 2017).XYZ (attached)

- 20170915_FB_LI_CS_POSTIRMA3X3.XYZ (attached)

File details come from the government source that posted it. Updated .