AMENDMENT_02_Summary_of_Changes.pdf

PDF 331 KB Posted

Attached to
FY18- Folly Beach Protection Project Federal contract opportunity
Solicitation number
GROUP4-18-R-C001
Issued by
Department of the Army Corps of Engineers Engineering District Charleston

About this file

Summary of Changes/Clarifications

View the file

Other files for this federal contract opportunity

Other files attached to FY18- Folly Beach Protection Project, newest first.
File Type Posted
Pipeline_Corridor_Easements.pdf PDF
H_Submittal_Register_AM0001.pdf PDF
Folly SB Contract Combined Survey (From April 2017).xyz XYZ file
BIDDING_SCHEDULE_AM0001.pdf PDF
20170915_FB_LI_CS_POSTIRMA3X3.xyz XYZ file
SECTION_35_20_23_10_DREDGING_&_BEACHFILL_AM0001.pdf PDF
Summary_of_Changes_Folly_Shore_Protection_AM0001.docx DOCX document
RTA_Drawings_AM0001.pdf PDF
DRAWINGS_-_Folly_Beach_Shore_Protection_Project.pdf PDF
SPECS_-_Folly_Beach_Shore_Protection_Project.pdf PDF
FOLLY_BEACH_SHORE_PROTECTION_RFP.docx DOCX document
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT 02- Summary of Changes

CLARIFICATIONS to SPECIFICATIONS AND DRAWINGS-

Project will be EVALUATED AND AWARDED based on the total bid amount (Base Work + Option Work)

This statement clarifies and confirms our position on utilizing Folly River as the Pipeline corridor.

“Pipeline corridor is the route which the pipeline shall run between the dredge and the placement area via the Folly River. For the purpose of this contract there will be two areas of easement for the pipeline to come ashore from the Folly River and traverse over land to the placement area on Folly Beach.

* 1502 E. Ashley Ave (Parcel ID - 4391400077)

* 1550 E. Ashley Ave (Parcel ID - 4391400059)

The pipeline shall avoid damage to existing marsh. Should it become necessary for pipeline to traverse an area of marsh, Contractor shall minimize impacts to the marsh by traversing the shortest distance through the marsh, utilizing pontoon pipe when traversing areas of the marsh, etc.

I’ve attached two marked up surveys showing 3 easements:

* 1550 E Ashley, Easement 1 (on western edge of property): $6000/month to property owner for each month actually in use

* 1550 E Ashley, Easement 2 (running down property driveway): $8000/month to property owner for each month actually in use

* 1502 E Ashley (only one easement, shown): $5000/month to property owner for each month in use."