G4J031Solicitation IWW St. Augustine Matanzas Inlet
View the file
Other files
| File | Type | Posted |
|---|---|---|
| GROUP4_J031_Revision_0001.pdf | ||
| IWW_St.Augustine-Mantanzas_GDR2016_updated30March2016.pdf | ||
| G4J031Plans.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GROUP4-10-R-J031
Jacksonville District
Intracoastal Waterway, Jacksonville to Miami, Florida, Maintenance Dredging, 12-Foot Project, Vicinity of St. Augustine Inlet and Vicinity of Matanzas Inlet
St. Johns County, Florida
Construction Solicitation and Specifications Task Order
07 SEPTEMBER 2016
IWW, Jax to Miami, FL, Maintenance Dredging, 12-Foot Project GROUP4-10-R-J031 Vic. of St. Augustine Inlet and Vic. of Matanzas Inlet
DESIGN AUTHENTICATION
This project was designed by the Jacksonville District, U.S. Army Corps of Engineers. The initials or signatures and registration designations of individuals appear on these project documents within the scope of their employment as required by ER 1110-1-8152.
JEFF E. BERGEN, P.E.
CHIEF, WATERWAYS SECTION, DESIGN BRANCH
ENGINEERING DIVISION
LUIS A. RUIZ, P.E.
CHIEF, GEOTECHNICAL BRANCH
ENGINEERING DIVISION
DAVID DUDLEY, P.E.
CHIEF, DESIGN BRANCH
ENGINEERING DIVISION
LAUREEN A. BOROCHANER, P.E.
CHIEF, ENGINEERING DIVISION
BERGEN.JEFFREY.
EARL.1071199173
Digitally signed by
BERGEN.JEFFREY.EARL.1071199173
DN: c=US, o=U.S. Government, ou=DoD, ou=PKI, ou=USA, cn=BERGEN.JEFFREY.EARL.1071199173 Date: 2016.06.22 10:15:57 -04'00'
RUIZ.LUIS.ANGEL.123
2169776
Digitally signed by RUIZ.LUIS.ANGEL.1232169776 DN: c=US, o=U.S. Government, ou=DoD, ou=PKI, ou=USA, cn=RUIZ.LUIS.ANGEL.1232169776 Date: 2016.06.22 17:20:48 -04'00'
DUDLEY.DAVID.F.13993
88569
Digitally signed by DUDLEY.DAVID.F.1399388569 DN: c=US, o=U.S. Government, ou=DoD, ou=PKI, ou=USA, cn=DUDLEY.DAVID.F.1399388569 Date: 2016.07.19 08:16:03 -04'00'
WIGNER.WILLIAM.
KEITH.1230084617
Digitally signed by
WIGNER.WILLIAM.KEITH.1230084617
DN: c=US, o=U.S. Government, ou=DoD, ou=PKI, ou=USA, cn=WIGNER.WILLIAM.KEITH.1230084617 Date: 2016.07.25 15:52:18 -04'00'
SF 1442-A1GROUP4-10-R-J031
ADDENDUM TO THE STANDARD FORM 1442
IWW St. Augustine/Matanzas Inlet
SPECIAL NOTIFICATION: THIS OPPORTUNITY IS AVAILABLE ONLY TO THE FOLLOWING
CONTRACTORS AWARDED A CONTRACT UNDER SOLICITATION NUMBER
W912EP-10-R-0026: Orion Marine Construction (W912EP-13-D-0003); Cavache, Inc.
(W912EP-13-D-0004); Cashman Dredging & Marine Contracting (W912EP-13-D-0005);
Cottrell Contracting Corporation (W912EP-13-D-0006); Great Lakes Dredge & Dock Company, LLC (W912EP-13-D-0007); Dutra Dredging Company (W912EP-13-D-0008);
Marinex Construction, Inc. (W912EP-13-D-0009); Norfolk Dredging Company (W912EP-13- D-0010); Mike Hooks, Inc. (W912EP-13-D-0011); Weeks Marine, Inc. (W912EP-13-D-0012);
Southern Dredging Co., Inc. (W912EP-13-D-0013); Manson Construction Company (W912EP-13-D-0014); C. F. Bean LLC (W912EP-13-D-0015) PROPOSALS WILL NOT BE
CONSIDERED FROM ANY ENTITY OTHER THAN THE PREVIOUSLY LISTED FIRMS
INCLUDED IN THE Group 4 Dredging MATOC Pool.
TECHNICAL EVALUATION: The award of the task order will be made on the basis of Lowest Price, Technical Acceptable (LPTA); the technical evaluation factors are:
(1) Availability of technically acceptable dredge(s).
(2) Past performance, to include the MATOC (The government reserves the right to obtain copies of all Contractor Performance Assessment Reporting System (CPARS) records contained in the US Army Corps of Engineers CPARS database for the Prime Contractor (Offeror) and all Major Sub-Contractors).
SUBMISSION REQUIREMENTS: Contractors are required to submit the following:
(1) A letter on company letterhead identifying the dredge(s) the contractor proposes to do the work and the location of dredge(s). The identified dredge(s) must also have been found technically acceptable by the Contracting Officer prior to the proposal due date.
(2) Completed Bid Schedule (see Section 00010A)
(3) Bid Guarantee per Section 00700, Clause 52.228-1 and Section 00100A, Paragraph 2.4(c) of the MATOC
(4) Completed “Addendum to the Standard Form 1442 with the latest revision”.
(5) Revisions – Offers must acknowledge receipt of this Revision by completing “Notice to Offerors--Blocks 14, 15 and 20” of each revision.
THE FOLLOWING INFORMATION IS APPLICABLE ONLY TO THIS TASK ORDER:
Block 9 -- For additional information contact:
Susan Forchette 904-232-2158 Susan.j.forchette@usace.army.mil.
Block 10 -- Magnitude of Construction is between $5,000,000.00 and $10,000,000.00.
mailto:Susan.j.forchette@usace.army.mil
SF 1442-A2GROUP4-10-R-J031
Block 11 -- The Contractor shall begin performance within 45 calendar days and complete it within 223 calendar days after receiving notice to proceed. This performance period is mandatory. NOTE: If there are optional line items, refer to FAR 52.211-10 for breakdown of period of performance.
Block 12 -- The contractor must furnish any required performance and payment bonds within 10 calendar days after award of the task order.
Block 13 -- Sealed offers to perform the work required shall be delivered to the following address not later than September 20, 2016 at 3:00 P.M. EDT.
U.S. Army Corps of Engineers Jacksonville Regional Contracting Center (CESAJ-CT-C) US Army Corps of Engineers, Jacksonville District 701 San Marco Blvd.
Jacksonville, Florida 32207-8175
NOTICE TO OFFERORS: Offerors are to complete Blocks 14, 15, and 20 below:
Block 14 -- Name and Address of Offeror (including Zip Code):
DUNS: ___________________ CAGE: _______________
Block 15 -- Telephone No. (include area code): _____________________
Block 20 -- Name and Title of Person Authorized to Sign Offer (type or print):
Type/Print ________________________________________________
Signature: ________________________________________________ e-Mail: ________________________________________________
Offer Date: _______________________________________________
Block 26 -- This Task Order will be administered by:
North Florida Area Office 4070 Boulevard Center Drive Suite 201 Jacksonville, FL 32207 PH:
(904)232-3086
Block 27 -- Payment will be made by:
USACE Finance Center 5722 Integrity Drive Millington, TN 38054-5005
ATTN: CEFC-AO-P
SECTION 00010A
LINE ITEMS AND PRICING SCHEDULE
INTRACOASTAL WATERWAY, JACKSONVILLE TO MIAMI, FLORIDA, MAINTENANCE DREDGING, 12-FOOT PROJECT
VICINITY OF ST. AUGUSTINE INLET AND VICINITY OF MATANZAS INLET
ST. JOHNS COUNTY, FLORIDA
GROUP4-10-R-J031 00010A-1
LINE ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL
0001 MOBILIZATION AND DEMOBILIZATION LUMP SUM $_______________
0002 EXCAVATION, UNCLASSIFIED
ST. AUGUSTINE INLET
(ESTIMATED QUANTITY, SEE NOTE 1) 178,000 CUBIC YARD $___________ $_______________
0003 TURBIDITY MONITORING
ST. AUGUSTINE INLET LUMP SUM $_______________
0004 BEACH TILLING, ANASTASIA STATE PARK
(ESTIMATED QUANTITY) 7 ACRE $___________ $_______________
0005 ENVIRONMENTAL SPECIES MONITORING
ANASTASIA STATE PARK LUMP SUM $_______________
0006 EXCAVATION, UNCLASSIFIED
MATANZAS INLET
(ESTIMATED QUANTITY, SEE NOTE 1) 412,000 CUBIC YARD $___________ $_______________
0007 TURBIDITY MONITORING
MATANZAS INLET LUMP SUM $_______________
0008 BEACH TILLING, SUMMER HAVEN
(ESTIMATED QUANTITY) 10 ACRE $___________ $_______________
0009 VIBRATION CONTROL AND MONITORING
SUMMER HAVEN LUMP SUM $_______________
0010 ENVIRONMENTAL SPECIES MONITORING
SUMMER HAVEN LUMP SUM $_______________
0011 LIABILITY INSURANCE (SEE NOTE 3) LUMP SUM $_______________
TOTAL BID (LINE ITEMS 0001 THROUGH 0011) $_______________
NOTES: (1) THE TOTAL QUANTITY SHOWN FOR EACH EXCAVATION CLIN INCLUDES REQUIRED DEPTH, ALLOWABLE OVERDEPTH, AND SHOALING ESTIMATED TO OCCUR BETWEEN THE DATES OF SURVEYS SHOWN ON THE DRAWINGS AND ACTUAL DREDGING. THE CONTRACTOR SHALL NOT PERFORM WORK IN EXCESS OF THE TOTAL ESTIMATED QUANITITY GIVEN FOR EACH CLIN WITHOUT PRIOR APPROVAL OF THE CONTRACTING OFFICER. THE CONTRACTOR SHALL NOTIFY THE CONTRACTING OFFICER AT LEAST ONE WEEK PRIOR TO THE ANTICIPATED DATE THAT THE ESTIMATED QUANTITY MAY
BE EXCEEDED. ACTUAL QUANTITIES MAY VARY.
(2) ALL OFFERS MUST BE FOR THE ENTIRE WORK AND MUST HAVE EACH BLANK SPACE COMPLETED.
(3) THE CONTRACTOR SHALL OBTAIN A PROPERTY DAMAGE LIABILITY INSURANCE POLICY FOR FIVE MILLION DOLLARS ($5,000,000.00) OF COVERAGE. THE POLICY SHALL MEET ALL THE REQUIREMENTS OF FAR 52.228-5 IN SECTION 00700
AND PARAGRAPH 999.228-4000 IN SECTION 00800.
SECTION 00010A, Attachment A
INSTRUCTIONS FOR TECHNICAL INQUIRIES AND QUESTIONS
Technical inquiries and questions relating to this solicitation are to be submitted via Bidder Inquiry in ProjNet at (https://www.projnet.org) No Later Than (NLT) 11 September 2016, end of day. To submit and review inquiry items, prospective vendors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below the key for access. A prospective vendor who submits a comment /question will receive an acknowledgement of their comment/question via email, followed by an answer to the comment/question after it has been processed by our technical team.
All timely questions and approved answers will be made available through ProjNet. Approved answers to all timely questions will also be posted on the FedBizOps in the form of a report generated from ProjNet as soon as the comment/question entering period is over and all answers are all finalized.
The Solicitation Number is: GROUP4-10-R-J031
The Bidder Inquiry Key is: 58GT6H-U97TGQ
Specific Instructions for ProjNet Bid Inquiry Access from ProjNet home page:
1. Identify the Agency. This should be marked as USACE.
2. Email. Enter the email address you would like to use for communication.
3. Key. Enter the Bidder Inquiry Key listed above.
4. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.
5. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret
Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.
6. Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.
Specific Instructions for Future ProjNet Bid Inquiry Access from ProjNet home page:
1. For future access to ProjNet, you will not be emailed any type of password. You will utilize your Secret Question and Secret Answer to log in.
2. Identify the Agency. This should be marked as USACE.
3. Email. Enter the email address you used to register previously in ProjNet.
4. Key. Enter the Bidder Inquiry Key listed above.
5. Click Continue. A page will then open asking you to enter the answer to your Secret Question.
6. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.
THE FOLLOWING PAGES CONTAIN ADDENDUMS TO SPECIFIC SECTIONS OF THE
ORIGINAL SOLICITATION NUMBER W912EP-10-R-0026
THESE ADDENDUMS ARE ONLY APPLICABLE TO THIS
SPECIFIC TASK ORDER
REQUEST FOR PROPOSAL NUMBER: GROUP4-10-R-J031
TASK ORDER PROJECT TITLE:
INTRACOASTAL WATERWAY,
JACKSONVILLE TO MIAMI,
FLORIDA, MAINTENANCE
DREDGING, 12-FOOT
PROJECT, VICINITY OF ST.
AUGUSTINE INLET AND
VICINITY OF MATANZAS INLET
ST. JOHNS COUNTY, FLORIDA
NOTICE TO OFFERORS: The information on the following pages is provided for the various clauses and/or paragraphs which require information to be filled in (when applicable) on each Request for Proposal for Task Orders issued under the awarded contracts. All applicable clauses, terms and conditions contained in the original solicitation and subsequently awarded contracts become part of each Task Order.
GROUP-10-R-J031 Clause Addendum-1
ADDENDUM TO SECTION 00100, INSTRUCTIONS TO OFFERORS
THE REQUIRED FILL-INS FOR FOLLOWING CLAUSES OF SECTION 00100 ARE HEREBY PROVIDED:
52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL
EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for minority participation for each trade
Goals for female participation for each trade
21.8% 6.9%
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is St John’s County, Florida.
(End of provision)
GROUP4-10-R-J031 00100-A1
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) (ALTERNATE I) (FEB 1995) (CESAJ
ADAPTATION)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for – 13 September 2016 at 9:30 AM EDT.
(c) Participants will meet at -- (Location will be provided by the contract administration office via telephone. See (d) below.)
(d) Participants should call Geoffrey Klug at 904-232-3808 (office) or 904-228-2970 (cell) on or before 9 September 2016 to make arrangements.
(e) Core borings are available. (If available, follow the instructions in the Physical Data paragraph in Section 00 31 32 of individual request for proposals issued for task orders under this contract to make arrangements to inspect the borings. Failure to follow the instructions may result in a delay ranging in duration from one hour to 4 days.)
(f) After the site visit, a memorandum summarizing the visit may be posted to the appropriate website under the solicitation number. This posting will be strictly for informational purposes only.
The memorandum will not become a part of the solicitation. If the solicitation needs to be changed as a result of information obtained during the site visit, a written amendment will be made available to all registered vendors. Questions regarding any information given in the memorandum must be directed to the person whose name appears in item 9 of the Addendum to the Standard Form 1442.
(End of provision)
GROUP4-10-R-J031 00100-A2
ADDENDUM TO SECTION 00700, CONTRACT CLAUSES
THE REQUIRED FILL-INS FOR FOLLOWING CLAUSES OF SECTION 00700 ARE HEREBY PROVIDED:
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 45 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 223 calendar days after the Contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises.
(End of clause)
52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $1,810.00 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
(End of clause)
GROUP4-10-R-J031 00700-A1
252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)
(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.
(b) The Contractor shall--
(1) Check all drawings furnished immediately upon receipt;
(2) Compare all drawings and verify the figures before laying out the work;
(3) Promptly notify the Contracting Officer of any discrepancies;
(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and
(5) Reproduce and print contract drawings and specifications as needed.
(c) In general—
(1) Large-scale drawings shall govern small-scale drawings; and
(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.
(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.
(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:
Title File Drawing Index No.
INTRACOASTAL WATERWAY, PLANS INDEX DRAWING
JACKSONVILLE TO MIAMI, FL, NUMBER G-102
PLANS FOR MAINTENANCE
DREDGING, 12-FOOT PROJECT,
VICINITY OF ST. AUGUSTINE
INLET AND VICINITY OF MATANZAS
INLET
(End of clause)
GROUP4-10-R-J031 00700-A2
ADDENDUM TO SECTION 00800, SPECIAL REQUIREMENTS
THE REQUIRED FILL-INS FOR FOLLOWING CLAUSES OF SECTION 00800 ARE HEREBY PROVIDED:
LIMITATIONS ON SUBSTITUTIONS FOR CERTAIN POSITIONS AND/OR
SUBCONTRACTORS
The award decision for this contract was based, in part, on an evaluation of the personnel and/or subcontractors the Contractor included in its proposal for the positions and/or items of subcontracted work identified at the end of this paragraph. The Contractor agrees these personnel and/or subcontractors will be employed as described in its proposal and no substitutes will be employed without prior written approval of the Contracting Officer or Administrative Contracting Officer. The Contractor further agrees that any proposed substitutes shall meet or exceed the qualifications of the original personnel and/or subcontractors. If the Contractor’s proposal did not name a subcontractor for an identified item of work, the Contractor will not be allowed to subcontract that item of work without prior approval of the Contracting Officer or Administrative Contracting Officer. The limitations described herein shall apply to the following:
plant and equipment.
(End of paragraph number 999.215-4001)
GROUP4-10-R-J031 00800-A1
Group4-10-R-J031
SECTION 00800A
WAGES DETERMINATIONS AND OTHER
ATTACHMENTS
THE FOLLOWING WAGES RATES ARE HEREBY INCORPORATED INTO
THIS CONTRACT:
No. TITLE DATE NO. OF PAGES
1 NOTE 1
2 General Decision FL160002 (FL2) 01/08/2016 5 3 General Decision FL160178 (FL178) 08/05/2016 5
NOTE NOTE NOTE
THIS PROJECT INCORPORATES HEAVY CONSTRUCTION AND HEAVY DREDGING
WAGE DETERMINATIONS FOR ST. JOHNS COUNTY, FLORIDA
EXECUTIVE ORDER (EO) 13658 ESTABLISHES AN HOURLY MINIMUM WAGE OF
$10.15 FOR 2016 THAT APPLIES TO ALL CONTRACTS SUBJECT TO THE DAVIS-
BACON ACT FOR WHICH THE SOLICITATION IS ISSUED ON OR AFTER
JANUARY 1, 2016.
IF YOU HAVE ANY QUESTIONS CONCERNING THE APPLICATION OF THE WAGE
DECISIONS FURNISHED FOR THIS PROJECT, PLEASE CONTACT:
FRAN RUSSELL, OFFICE OF COUNSEL, JACKSONVILLE DISTRICT, U.S. ARMY
CORPS OF ENGINEERS AT 904-232-3761, FAX 904-232-1954.
Group 4-10-R-J031
General Decision Number: FL160002 01/08/2016 FL2
Superseded General Decision Number: FL20150002
State: Florida
Construction Type: Heavy Dredging
Counties: Florida Statewide.
Dredging Construction Projects FLORIDA (Excluding West of the Aucilla River and its tributary waterways)
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.15 for calendar year 2016 applies to all contracts subject to the Davis-Bacon Act for which the solicitation was issued on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.15 (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2016. The EO minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/08/2016
* ENGI0025-002 10/01/2014
Rates Fringes
Dredging : (Hydraulic Dredges Over 20")
CLASS A.....................$ 35.63 12.39+a CLASS B1....................$ 30.81 12.00+a CLASS B2....................$ 29.01 11.86+a CLASS C1....................$ 28.22 11.55+a CLASS C2....................$ 27.30 11.47+a CLASS D.....................$ 22.68 10.85+a
Hydraulic Dredges Under 20" Cook........................$
8.11 1.73+b
Deckhand....................$ 7.77 1.73+b Engineer....................$ 9.59 1.73+b Launchman...................$ 8.19 1.73+b Leverman....................$ 10.03 1.73+b Mate........................$ 8.82 1.73+b Mess Cook...................$ 7.71 1.73+b Messman & Janitor...........$ 7.53 1.73+b Oiler & Fireman.............$ 8.11 1.73+b Shoreman....................$ 7.82 1.73+b Spider Barge Operator.......$ 8.68 1.73+b Spill Barge Operator........$ 8.68 1.73+b Welder......................$ 9.79 1.73+b
CLASSIFICATIONS:
CLASS A: Leverman, Operator.
CLASS B1: Licensed Tug Operator over 1000 HP, Derrick Operator, Spider/Spill Barge Operator, Timber Fork Operator, Dozer Operator, Engineer, Blaster/Driller, Fill Placer, Electrician.
CLASS B2: Licensed Boat Operator, Certified Welder.
CLASS C1: Mate, Drag Barge Operator, Welder, Assistant Fill Placer, Steward.
CLASS C2: Boat Operator.
CLASS D: Shoreman, Deckhand, Rodman, Scowman, Cook, Messman, Oiler, Janitor.
PREMIUMS: Additional 20% for hazardous material work
FOOTNOTE APPLICABLE TO ABOVE CRAFTS:
a. New Year's Day, Good Friday, Memorial Day, Independence Day, Labor Day, Thanksgiving Day and Christmas Day.
Vacation Contribution of 8% of straight time rate multiplied by the total hours worked.
b. New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day. Plus Vacation contribution of 8% of straight time pay for all hours worked.
INCENTIVE PAY : (Add to Hourly Rate)
Operator (NCCCO License/Certification) $0.50; Licensed Tug Operator over 1000 HP (Assigned as Master) USCG licensed Master of Towing Vessels (MOTV) $1.00; Licensed Boat Operator (assigned as lead boat captain) USCG licensed boat operator $0.50; Engineer (QMED and Tankerman endorsement or licensed engineer (USCG) $0.50; Oiler QMED and Tankerman endorsement (USCG) $0.50; All classifications Tankerman endorsement only (USCG) $0.50; Deckhand or Mater AB w/Lifeboatman only (USCG) $0.25; Welder (ABS certification) $0.50
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION
General Decision Number: FL160178 08/05/2016 FL178
Superseded General Decision Number: FL20150178
State: Florida
Construction Type: Heavy
County: St Johns County in Florida.
HEAVY CONSTRUCTION PROJECTS (Including Sewer and Water Lines)
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.15 for calendar year 2016 applies to all contracts subject to the Davis-Bacon Act for which the solicitation was issued on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.15 (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2016. The EO minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date
0 01/08/2016 1 04/01/2016 2 08/05/2016
ELEC0177-002 11/30/2015
Rates Fringes
ELECTRICIAN......................$ 26.49 11.23
ENGI0673-014 05/01/2013
Rates Fringes
OPERATOR: Oiler.................$ 19.52 9.05
* IRON0597-004 04/01/2016
IRONWORKER, STRUCTURAL AND
REINFORCING......................$ 24.00 9.40
LABO0517-002 05/01/2014
LABORER: Grade Checker..........$ 18.35 6.45
PAIN0164-007 08/01/2014
PAINTER: Brush Only.............$ 19.50 8.83
SUFL2009-174 06/24/2009
Rates Fringes
CARPENTER........................$ 15.80 0.00
CEMENT MASON/CONCRETE FINISHER...$ 13.23 2.15
LABORER: Common or General......$ 9.89 1.58
LABORER: Landscape..............$ 7.25 0.00
LABORER: Pipelayer..............$ 12.85 1.21
LABORER: Power Tool Operator (Hand Held Drills/Saws, Jackhammer and Power Saws Only)............................$ 10.63 2.20
OPERATOR: Asphalt Paver.........$ 11.59 0.00
OPERATOR: Backhoe Loader Combo............................$ 16.10 2.44
OPERATOR: Backhoe/Excavator.....$ 13.91 1.39
OPERATOR: Bulldozer.............$ 13.40 1.19
OPERATOR: Crane.................$ 22.38 0.00
OPERATOR: Grader/Blade..........$ 16.00 2.84
OPERATOR: Loader................$ 11.31 2.02
OPERATOR: Mechanic..............$ 14.32 0.00
OPERATOR: Roller................$ 10.93 0.00
OPERATOR: Scraper...............$ 11.00 1.74
OPERATOR: Trackhoe..............$ 20.92 5.50
OPERATOR: Tractor...............$ 10.54 0.00
TRUCK DRIVER, Includes Dump Truck............................$ 14.63 0.00
TRUCK DRIVER: Lowboy Truck......$ 13.06 2.18
TRUCK DRIVER: Off the Road Truck............................$ 12.21 1.97
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
c. an existing published wage determination
d. a survey underlying a wage determination
e. a Wage and Hour Division letter setting forth a position on a wage determination matter
f. a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION
IWW, Jax to Miami, FL, Maintenance Dredging, 12-Ft Project GROUP4-10-R-J031
PROJECT TABLE OF CONTENTS
DIVISION 00 - TECHNICAL INFORMATION
00 31 21 CONTROL MONUMENT DESCRIPTIONS - St. Augustine Inlet 00 31 22 CONTROL MONUMENT DESCRIPTIONS - Matanzas Inlet
00 33 50 WEATHER, WATER STAGE AND TIDE DATA
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 22 00 MEASUREMENT AND PAYMENT
01 30 00 ADMINISTRATIVE PROCEDURES
01 32 01 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 25 OWNER SAFETY REQUIREMENTS - DIVING
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 45 05 DREDGING/BEACH FILL PLACEMENT - CONTRACTOR QUALITY CONTROL
01 50 02 TEMPORARY CONSTRUCTION FACILITIES
01 57 20 ENVIRONMENTAL PROTECTION
01 57 25 TURBIDITY AND DISPOSAL MONITORING
DIVISION 02 - EXISTING CONDITIONS
02 22 13 VIBRATION MONITORING REQUIREMENTS FOR EXISTING STRUCTURES
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 20 23 DREDGING AND BEACH DISPOSAL
35 20 26 NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM SCOW -
TRACKING PROFILE
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION 00 31 21 CONTROL MONUMENT DESCRIPTIONS – St. Augustine Inlet
SECTION 00 31 21 Page 1
Designation: RAMP RESET
PID: BBCB11
Designation: RAMP RESET Stamping: RAMP-RESET 2010 JAX. DIST.
Stability:
Setting: Massive retaining walls Description: Station is located in St. Augustine, Florida at the Vilano public boat ramp on A1A North, approximately
1,000 feet southwest of the Francis and Mary Usina Bridge leading to Vilano Beach. Monument is 96 feet west of the west side of boat ramp and is a standard Corps of Engineers bronze disk set in top of concrete seawall.
Observed: 2010-03-12T11:58:00Z See Also Original Source: OPUS - page5 1209.04
SECTION 00 31 21 CONTROL MONUMENT DESCRIPTIONS – St. Augustine Inlet
SECTION 00 31 21 Page 2
DESIGNATION - 872 0554 B
PID - DL5712
TIDAL BM - This is a Tidal Bench Mark.
STATE/COUNTY- FL/ST JOHNS
MARKER: TIDAL STATION DISK
SETTING: SET IN A PAVEMENT SUCH AS STREET, SIDEWALK, CURB, ETC.
SP_SET: WALKWAY
STAMPING: 0554 B 1996
MARK LOGO: NOS
MAGNETIC: NO MAGNETIC MATERIAL
STABILITY: MARK OF QUESTIONABLE OR UNKNOWN STABILITY
SATELLITE: THE SITE LOCATION WAS REPORTED AS NOT SUITABLE FOR
SATELLITE OBSERVATIONS - April 26, 2007
HISTORY - Date Condition Report By
HISTORY - 1996 MONUMENTED FLDEP
HISTORY - 20070426 GOOD FLDEP
STATION DESCRIPTION
THE MARK IS ABOUT 2.0 MI EAST OF SAINT AUGUSTINE. TO REACH THE MARK
FROM THE JUNCTION OF STATE HIGHWAY 16 (GREEN COVE SPRINGS ROAD) AND
U.S. HIGHWAY 1 (PONCE DE LEON BOULEVARD) ON THE NORTH SIDE OF SAINT
AUGUSTINE, GO SOUTH ON U.S. HIGHWAY 1 (PONCE DE LEON BOULEVARD) FOR
0.55 MI TO THE JUNCTION OF WEST SAN CARLOS AVENUE (STATE HIGHWAY A1A
NORTH) ON THE LEFT, TURN LEFT ON WEST SAN CARLOS AVENUE AND GO EAST
FOR 0.1 MI TO THE T-JUNCTION OF SAN MARCO AVENUE (STATE HIGHWAY A1A
NORTH), TURN LEFT ON SAN MARCO AVENUE (STATE HIGHWAY A1A NORTH) AND GO
NORTH FOR ABOUT 100.0 FT TO THE JUNCTION OF MAY STREET (STATE HIGHWAY
A1A NORTH) ON THE RIGHT, TURN RIGHT ON MAY STREET (STATE HIGHWAY A1A
NORTH) AND GO EAST FOR 1.85 MI TO THE T-JUNCTION OF STATE ROAD A1A
(COASTAL HIGHWAY), TURN RIGHT ON STATE ROAD A1A (COASTAL HIGHWAY) AND
GO SOUTH FOR ABOUT 100.0 FT TO THE JUNCTION OF POPLAR AVENUE ON THE
RIGHT, TURN RIGHT ON POPLAR AVENUE AND GO WESTERLY FOR 0.15 MI TO THE
INTERSECTION OF VILANO ROAD ON THE RIGHT, TURN RIGHT ON VILANO ROAD
AND GO WEST FOR 0.3 MI TO THE END OF VILANO ROAD AND THE VILANO BEACH
FISHING PIER, NOW BY WALKING GO WEST ON THE FISHING PIER FOR 684.0 FT
TO THE MARK ON THE RIGHT A NOS DISK SET FLUSH IN THE CONCRETE WALKWAY
ON THE NORTHWEST END OF THE VILANO BEACH FISHING PIER.
LOCATED ABOUT 684.0 FT WEST OF THE EAST END OF THE PIER, 32.0 FT
NORTHEAST OF 872 0554 AQUA TRAK (TIDE GAGE), 11.0 FT NORTH OF THE
CENTERLINE OF THE FISHING PIER AND 4.0 FT EAST OF THE NORTHWEST END OF
THE PIER.
SECTION 00 31 22 CONTROL MONUMENT DESCRIPTIONS – Matanzas Inlet
SECTION 00 31 22 Page 1
Designation: IWSJ-224
PID: BBCD52
Designation: IWSJ-224 Stamping: IWSJ-224 1977 JAX FLA Stability:
Setting: Set in top of concrete monument Description: Located on Rattlesnake Island, St. Johns County, Florida. To reach from the Matanzas River Bridge on
Hwy A1A, go approximately 700 feet to dirt road on the west side of highway. Proceed west and north along dirt road approximately 0.5 to station location. Station is located 82 feet west of dirt road, 7 feet northwest of lone palm, approximately 25 east of IWW, and 3.8 feet east of row of sheet piling in jetty rock. Mark is set in an 8x8 inch concrete filled wood frame 0.3 feet above ground.
Observed: 2010-12-14T15:55:00Z See Also Original Source: OPUS - page5 1209.04
SECTION 00 33 50 WEATHER, WATER STAGE AND TIDE DATA
SECTION 00 33 50 Page 1
1. The following water stage, wave, wind, and weather data are provided for inclusion into the subject Plans and Specifications. The following water level datums are provided for information only and are not to be utilized in conjunction with any contract related hydrographic surveying.
a) Water Stages. Water levels in the project area are mainly affected by semi-diurnal tidal fluctuations in the Atlantic Ocean. The project area is also subject to storm surges from hurricanes and tropical storms from June through November. Surges from extratropical storms may affect the area during any time of the year.
Elevations of tidal datums in the vicinity of the project area are provided in the following tables (next page). All datum elevations in these tables are referred to mean lower low water (MLLW) and are based on a control tide station located in Mayport, Florida.
The datums in Table 1 are taken from tide station 8720576 (ST. AUGUSTINE, FL). These datums are based on values from the tide station located at St. Augustine which is approximately
2.5 to 0.5 miles south of cuts SJ-28, SJ-28A, SJ-29, SJ-29A, SJ-30, and SJ-30A. These values are applicable to dredging taking place in the vicinity of the St. Augustine Inlet.
The datums in Table 2 are taken from tide station 8720686 (FORT MATANZAS, FL). These datums are based on values from the tide station located at Fort Matanzas which is approximately 0.5 miles east of cuts SJ-60 and SJ-61. These values are applicable to dredging taking place landward of the Matanzas Inlet throat.
Table 3 provides datums taken from tide station 8720587 (St. Augustine Beach, FL). These datums are based on values from the tide station located at St. Augustine Beach which is approximately 1 mile south of the proposed beach placement area for the material dredged from cuts SJ-28, SJ-28A, SJ-29, SJ-29A, SJ-30, and SJ-30A (FDEP monuments R-134 to R-139), and approximately 12.5 mile north of the proposed beach placement area for the material dredged from cuts SJ-60 and SJ-61 (FDEP monuments R-205 to R-208). These values are applicable to material placement taking place seaward of the St. Augustine Inlet jetties and the Matanzas Inlet throat.
All of these tide stations were established by the National Oceanic and Atmospheric Administration (NOAA), National Ocean Service (NOS) and are applicable within the project vicinity. Additional information on these and other nearby tide stations is available at this NOAA website: http://tidesandcurrents.noaa.gov/stations.html?type=Bench+Mark+Data+Sheets http://tidesandcurrents.noaa.gov/stations.html?type=Bench+Mark+Data+Sheets
SECTION 00 33 50 Page 2
Table 1 Tide Station 8720576 (ST. AUGUSTINE FL)
Lat 29° 53.5’N, Lon 81° 6.0’W Highest Observed Water Level (03 Nov 1978) = 7.06 Feet Mean Higher High Water (MHHW) = 4.98 Feet Mean High Water (MHW) = 4.65 Feet North American Vertical Datum 1988 (NAVD) = 2.94 Feet Mean Sea Level (MSL) = 2.43 Feet Mean Tide Level (MTL) = 2.40 Feet Mean Low Water (MLW) = 0.17 Feet Mean Lower Low Water (MLLW) = 0.00 Feet Lowest Observed Water Level (05 Apr 1977) = -2.65 Feet
Table 2 Tide Station 8720686 (FORT MATANZAS, FL)
Lat 29° 42.9’N, Lon 81° 14.3’W Highest Observed Water Level (06 Oct 1974) = 6.65 Feet Mean Higher High Water (MHHW) = 4.35 Feet Mean High Water (MHW) = 4.04 Feet North American Vertical Datum (NAVD) = 2.65 Feet Mean Sea Level (MSL) = 2.19 Feet Mean Tide Level (MTL) = 2.11 Feet Mean Low Water (MLW) = 0.18 Feet Mean Lower Low Water (MLLW) = 0.00 Feet Lowest Observed Water Level (26 Feb 1975) = -1.74 Feet
Table 3 Tide Station 8720587 (St. Augustine Beach, FL)
Lat 29° 51.4’N, Lon 81° 15.8’W
Highest Observed Water Level (24 Sep 1992) = 7.70 Feet Mean Higher High Water (MHHW) = 5.15 Feet Mean High Water (MHW) = 4.77 Feet North American Vertical Datum 1988 (NAVD) = 3.14 Feet Mean Tide Level (MTL) = 2.47 Feet Mean Sea Level (MSL) = 2.43 Feet Mean Low Water (MLW) = 0.16 Feet Mean Lower Low Water (MLLW) = 0.00 Feet Lowest Observed Water Level (13 Mar 1993) = -3.24 Feet
SECTION 00 33 50 Page 3
Daily tidal predictions at locations along the coastline of North and South America, including locations in the vicinity of the project area can be found in the publication East Coast of North and South America Tide Tables, U.S. Department of Commerce, National Oceanic and Atmospheric Administration, National Ocean Service. In addition to daily tidal predictions, this publication also provides mean and spring tide ranges and mean tide levels. Some astronomical data is also included, such as time of sunrise, sunset, moonrise, and moonset. This publication is
Station 8720686
Station 8720587
Station 8720576 St. Augustine Inlet
Matanzas Inlet
IWW Cuts SJ-28, SJ-28A, SJ-29, SJ-29A, SJ-30, and SJ-30A
IWW Cuts SJ-60 and SJ-61
SECTION 00 33 50 Page 4 available through NOAA. Tidal data provided in this publication can also be found at the following NOAA website: http://tidesandcurrents.noaa.gov.
b) Wind and Wave Data. The following publications include wind and wave information in the vicinity of the project area, and are available for review in the Jacksonville District Office or may be ordered directly from the agencies indicated.
1. U.S. Coast Pilot Volume 4, Atlantic Coast: Cape Henry to Key West, U.S.
Department of Commerce, National Oceanic and Atmospheric Administration, National Ocean Service. This publication supplements the navigational information shown on the NOAA/NOS nautical charts. It also provides miscellaneous meteorological data. This publication is available through NOAA. This publication is available at the following website:
http://nauticalcharts.noaa.gov/nsd/cpdownload.htm.
2. U. S. Army Corps of Engineers’ Coastal & Hydraulics Laboratory, Wave Information Study (WIS) Database. This Internet webpage presents wave hindcast data for various stations located along the Atlantic and Gulf of Mexico coastlines within the United States. The closest of these stations (#63418) lies approximately 12 miles east of the project vicinity. Available data includes a hindcast time series of wave heights, periods, and directions taken at 1-hour intervals for the 20-year period extending from 1980-1999, at a station located in 20 meters (66 feet) of water. This webpage also provides links to WIS summary tables and plots, as well as other sources of wave data. These data products are available at the following website: http://wis.usace.army.mil/wis.shtml.
3. National Data Buoy Center (NDBC) Website. This Internet website provides a wide range of real-time and archived meteorological and oceanographic data collected at offshore and nearshore stations worldwide. Data provided on this website includes wind speed, wind gusts, atmospheric pressure, air temperature, sea temperature, wave height, and wave period. Gage readings are updated hourly, and archived data is available for most stations. The website address for data relevant to this project site is:
http://www.ndbc.noaa.gov/maps/Florida.shtml.
c) Weather Conditions. The project area is subject to tropical storms and hurricanes from June through November, and to windy and/or rainy weather during any time of the year.
The climate of the area is essentially subtropical, with temperatures below freezing occurring periodically during winter months. The wet season in the project area is from May through October. Rainfall during these months is closely associated with convective activity. These rainfall events are normally of short duration and amounts are spatially variable. In general, the winter months constitute the dry season. Rainfall during the winter months is usually associated with mid-latitude systems (fronts and low pressure systems) and is distributed in a more spatially uniform pattern. Occasionally, daily rainfall in the dry season can be quite heavy as mid-latitude systems penetrate into south Florida. Dangerous thunderstorms can occur in this area at any time of the year.
http://tidesandcurrents.noaa.gov/ http://nauticalcharts.noaa.gov/nsd/cpdownload.htm http://wis.usace.army.mil/wis.shtml…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .