GROUP4-10-R-J030 SF 1442-A1 REVISION 0003
ADDENDUM TO THE STANDARD FORM 1442
U.S. NAVAL STATION MAYPORT, FLORIDA MAINTENANCE DREDGING, 50-FOOT
PROJECT ENTRANCE CHANNEL AND HARBOR COMPLEX
SPECIAL NOTIFICATION: THIS OPPORTUNITY IS AVAILABLE ONLY TO THE FOLLOWING
CONTRACTORS AWARDED A CONTRACT UNDER SOLICITATION NUMBER
For GROUP 4 use: W912EP-10-R-0026: Orion Marine Construction (W912EP-13-D-0003);
Cavache, Inc. (W912EP-13-D-0004); Cashman Dredging & Marine Contracting (W912EP-13- D-0005); Cottrell Contracting Corporation (W912EP-13-D-0006); Great Lakes Dredge & Dock Company, LLC (W912EP-13-D-0007); Dutra Dredging Company (W912EP-13-D-0008);
Marinex Construction, Inc. (W912EP-13-D-0009); Norfolk Dredging Company (W912EP-13- D-0010); Mike Hooks, Inc. (W912EP-13-D-0011); Weeks Marine, Inc. (W912EP-13-D-0012);
Southern Dredging Co., Inc. (W912EP-13-D-0013); Manson Construction Company (W912EP-13-D-0014); and C. F. Bean LLC (W912EP-13-D-0015)
PROPOSALS WILL NOT BE CONSIDERED FROM ANY ENTITY OTHER THAN THE
PREVIOUSLY LISTED FIRMS INCLUDED IN THE GROUP 4, DREDGING POOL.
TECHNICAL EVALUATION: The award of the task order will be made on the basis of Lowest Price, Technical Acceptable (LPTA); the technical evaluation factors are:
(1) Availability of technically acceptable dredge(s)
(2) Past performance, to include the MATOC (The government reserves the right to obtain copies of all Construction Contract Administration Support System (CCASS) records contained in the US Army Corps of Engineers CCASS database for the Prime Contractor (Offeror) and all Major Sub-Contractors).
SUBMISSION REQUIREMENTS: Contractors are required to submit the following:
(1) All submissions shall be on company letterhead identifying the dredge(s) the contractor proposes to do the work and the location of dredge(s). The identified dredge(s) must also have been found technically acceptable by the Contracting Officer prior to the proposal due date.
(2) Completed Bid Schedule (see Section 00010A)
(3) Bid Guarantee per Section 00700, Clause 52.228-1 and Section 00100A, Paragraph 2.4(c) of the MATOC
(4) Completed “Addendum to the Standard Form 1442”
(5) Revisions- offers shall acknowledge receipt of revisions by completing the “notice to offerors—blocks 14,15 and 20”
THE FOLLOWING INFORMATION IS APPLICABLE ONLY TO THIS TASK ORDER:
Block 9 -- For additional information contact: Timothy A. Donnellan, (904)232-3055 Timothy.A.Donnellan@usace.army.mil
Block 10 -- Magnitude of Construction is between $5,000,000.00 and $15,000,000.00 mailto:Timothy.A.Donnellan@usace.army.mil
GROUP4-10-R-J030 SF 1442-A2 REVISION 0003
Block 11 – The contractor shall begin performance within 45 calendar days and complete performance within 202 212 calendar days after receipt of the notice to proceed (NTP). This performance period is mandatory.
Block 12 -- The contractor must furnish any required performance and payment bonds within 10 calendar days after award of the task order.
Block 13 -- Sealed offers to perform the work required shall be delivered to the following address not later than: 2:00 pm Local Time on 14 October 2016.
Contracting Division – Attn: Timothy A. Donnellan U.S. Army Corps of Engineers 701 San Marco Blvd.
Jacksonville, FL 32207
NOTICE TO OFFERORS: Offerors are to complete Blocks 14, 15, and 20 below:
Block 14 -- Name and Address of Offeror (including Zip Code):
DUNS: ___________________ CAGE: _______________
Block 15 -- Telephone No. (Include area code): _____________________
Block 20 -- Name and Title of Person Authorized to Sign Offer (type or print):
Type/Print ________________________________________________
Signature: ________________________________________________
E-Mail: ________________________________________________
Offer Date: _______________________________________________
Block 26 -- This Task Order will be administered by:
North Florida Area Office
4070 Boulevard Center Drive
Suite 201
Jacksonville, FL 32207
Block 27 -- Payment will be made by:
USACE Finance Center
5722 Integrity Drive
ATTN: CEFC-AO-P
Millington, TN 38054-5005
SF 30 CONTINUATION SHEET
U.S. NAVAL STATION MAYPORT, FLORIDA MAINTENANCE DREDGING, 50-
FOOT PROJECT ENTRANCE CHANNEL AND HARBOR COMPLEX
THE PURPOSE OF THIS REVISION IS TO PROVIDE:
1) Correct the Period of Performance (BLOCK 11 ADDENDUM TO THE
STANDARD FORM 1442)
2) Change the LINE ITEM AND PRICING SCHEDULE (SECTION 00010A, LINE ITEM AND PRICING SCHEDULE).
CONTRACTING DOCUMENTS:
1) ADDENDUM TO THE STANDARD FROM 1442.
a. Remove and Replace with Revision 0003.
2) SECTION 00010A, LINE TEMS AND PRICING SCHEDULE.
a. Remove and Replace with Revision 0003.
TECHNICAL SPECIFICATIONS:
No Changes.
DRAWINGS:
1) Delete and replace with the attached Drawings G-01, C-01, C-02, C-03, C- 05 and C-09.
2) Add new attached Drawing C-03A.
GROUP4-10-R-J030 REVISION 0003
SECTION 00010A
LINE ITEMS AND PRICING SCHEDULE
U.S. NAVAL STATION MAYPORT, FLORIDA, MAINTENANCE DREDGING
50-FOOT PROJECT, ENTRANCE CHANNEL AND HARBOR COMPLEX
DUVAL COUNTY, FLORIDA
GROUP4-10-R-J030 00010A-1 REVISION 0003
LINE ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL
0001 MOBILIZATION AND DEMOBILIZATION LUMP SUM $_______________
0002 EXCAVATION, UNCLASSIFIED
BAR CUT-3 AND WIDENER (ESTIMATED QUANTITY,
SEE NOTES 1 AND 6) 513,000 CUBIC YARD $___________ $_______________
0003 EXCAVATION, UNCLASSIFIED
ENTRANCE CHANNEL (ESTIMATED QUANTITY,
SEE NOTES 1 AND 6) 93,000 CUBIC YARD $___________ $_______________
0004 EXCAVATION, UNCLASSIFIED
TURNING BASIN (ESTIMATED QUANTITY, SEE
NOTES 1 AND 6) 837,000 CUBIC YARD $___________ $_______________
0005 EXCAVATION, UNCLASSIFIED
DESTROYER BASIN (ESTIMATED QUANTITY, SEE
NOTES 1 AND 6) 61,000 CUBIC YARD $___________ $_______________
0006 EXCAVATION, UNCLASSIFIED
SMALL BOAT BASIN (ESTIMATED QUANTITY, SEE
NOTES 1 AND 6) 1,000 CUBIC YARD $___________ $_______________
0007 TURBIDITY MONITORING LUMP SUM $_______________
0008 ENDANGERED SPECIES OBSERVER
(HOPPER DREDGE ONLY) LUMP SUM $_______________
0009 DEDICATED MANATEE OBSERVER
(CLAMSHELL DREDGING ONLY) LUMP SUM $_______________
0010 MOBILIZATION AND DEMOBILIZATION FOR
NON-CAPTURE SEA TURTLE TRAWL SWEEPING
(HOPPER DREDGE ONLY, SEE NOTE 5) LUMP SUM $_______________
0011 SEA TURTLE NON-CAPTURE TRAWL SWEEPING
(HOPPER DREDGE ONLY, SEE NOTE 5) 1 DAY $___________ $_______________
0012 STANDBY TIME (SEE NOTE 4) 24 HOUR $___________ $_______________
TOTAL BID (LINE ITEMS 0001 THROUGH 0012) $_______________
NOTES: (1) THE TOTAL QUANTITY SHOWN FOR EACH EXCAVATION CLIN INCLUDES REQUIRED DEPTH, ALLOWABLE OVERDEPTH, AND SHOALING ESTIMATED TO OCCUR BETWEEN THE DATES OF SURVEYS SHOWN ON THE DRAWINGS AND ACTUAL
DREDGING. THE CONTRACTOR SHALL NOT PERFORM WORK IN EXCESS OF THE TOTAL ESTIMATED QUANITITY GIVEN FOR
EACH CLIN WITHOUT PRIOR APPROVAL OF THE CONTRACTING OFFICER. THE CONTRACTOR SHALL NOTIFY THE
CONTRACTING OFFICER AT LEAST ONE WEEK PRIOR TO THE ANTICIPATED DATE THAT THE ESTIMATED QUANTITY MAY
BE EXCEEDED.
(2) ALL OFFERS MUST BE FOR THE ENTIRE WORK AND MUST HAVE EACH BLANK SPACE COMPLETED.
(3) AN ENDANGERED SPECIES OBSERVER IS REQUIRED FOR A HOPPER DREDGE ONLY. A DEDICATED MANATEE
OBSERVER IS REQUIRED FOR CLAMSHELL DREDGING ONLY.
SEE NEXT PAGE FOR NOTES 4, 5 AND 6.
SECTION 00010A
LINE ITEMS AND PRICING SCHEDULE
U.S. NAVAL STATION MAYPORT, FLORIDA, MAINTENANCE DREDGING
50-FOOT PROJECT, ENTRANCE CHANNEL AND HARBOR COMPLEX
DUVAL COUNTY, FLORIDA
GROUP4-10-R-J030 00010A-2 REVISION 0003
(4) STANDBY TIME IS DEFINED AS WHEN THE DREDGE PLANT IS NOT IN OPERATION AT THE DIRECTION OF THE
CONTRACTING OFFICER OR ADMINISTRATIVE CONTRACTING OFFICER. STANDBY TIME SHALL BE UTILIZED ONLY DUE
TO THE PRESENCE OF ENDANGERED SPECIES IN THE IMMEDIATE AREA OF THE DREDGING OPERATIONS, DIFFERIING
SITE CONDITIONS, SECURITY OPERATIONS OR OTHER CONDITIONS AS DETERMINED BY THE CONTRACTING OFFICER.
STANDBY TIME IS NOT AFFORDED FOR DELAYS CAUSED BY ADVERSE WEATHER CONDITIONS. THIS LINE ITEM IS NOT
SUBJECT TO THE VARIATION IN ESTIMATED QUANTITY CLAUSE, AND PAYMENT WILL ONLY BE MADE FOR ACTUAL
STANDBY TIME REQUIRED BY THE CONTRACTING OFFICER. SEE SECTION 01 22 00 MEASUREMENT AND PAYMENT
AND SECTION 01 57 20 ENVIRONMENTAL PROTECTION.
(5) SEA TURTLE NON-CAPTURE TRAWL SWEEPING IS REQUIRED FOR HOPPER DREDGE ONLY WHEN DIRECTED BY THE
CONTRACTING OFFICER. SEE SECTION 01 57 20 ENVIRONMENTAL PROTECTION, SUBPARAGRAPH "SUSPENSION OF
DREDGING (HOPPER DREDGE ONLY).
(6) HOPPER DREDGING IS SUBJECT TO SEASONAL RESTRICTIONS. SEE SECTION 01 57 20 ENVIRONMENTAL PROTECTION
FOR APPLICABLE SPECIAL OPERATING CONDITIONS.