GROUP4-10-R-J027 SF 1442-A1 Revision 0004
ADDENDUM TO THE STANDARD FORM 1442
Shore Protection Project, Duval County, Florida, Renourishment 2016
SPECIAL NOTIFICATION: THIS OPPORTUNITY IS AVAILABLE ONLY TO THE FOLLOWING
CONTRACTORS AWARDED A CONTRACT UNDER SOLICITATION NUMBER
W912EP-10-R-0026: Orion Marine Construction (W912EP-13-D-0003); Cavache, Inc.
(W912EP-13-D-0004); Cashman Dredging & Marine Contracting (W912EP-13-D-0005);
Cottrell Contracting Corporation (W912EP-13-D-0006); Great Lakes Dredge & Dock Company, LLC (W912EP-13-D-0007); Dutra Dredging Company (W912EP-13-D-0008);
Marinex Construction, Inc. (W912EP-13-D-0009); Norfolk Dredging Company (W912EP-13- D-0010); Mike Hooks, Inc. (W912EP-13-D-0011); Weeks Marine, Inc. (W912EP-13-D-0012);
Southern Dredging Co., Inc. (W912EP-13-D-0013); Manson Construction Company (W912EP-13-D-0014); C. F. Bean LLC (W912EP-13-D-0015) PROPOSALS WILL NOT BE
CONSIDERED FROM ANY ENTITY OTHER THAN THE PREVIOUSLY LISTED FIRMS
INCLUDED IN THE Group 4 Dredging MATOC Pool.
TECHNICAL EVALUATION: The award of the task order will be made on the basis of Lowest Price, Technical Acceptable (LPTA); the technical evaluation factors are:
(1) Availability of technically acceptable dredge(s). Note: Coast Guard Certified Equipment is REQUIRED.
(2) Past performance, to include the MATOC (The government reserves the right to obtain copies of all Contractor Performance Assessment Reporting System (CPARS) records contained in the US Army Corps of Engineers CPARS database for the Prime Contractor (Offeror) and all Major Sub-Contractors).
SUBMISSION REQUIREMENTS: Contractors are required to submit the following:
(1) A letter on company letterhead identifying the dredge(s) the contractor proposes to do the work and the location of dredge(s). The identified dredge(s) must also have been found technically acceptable by the Contracting Officer prior to the proposal due date.
(2) Completed Bid Schedule (see Section 00010A)
(3) Bid Guarantee per Section 00700, Clause 52.228-1 and Section 00100A, Paragraph 2.4(c) of the MATOC
(4) Completed “Addendum to the Standard Form 1442 with the latest revision”.
(5) Revisions – Offers must acknowledge receipt of this Revision by completing “Notice to Offerors--Blocks 14, 15 and 20” of each revision.
THE FOLLOWING INFORMATION IS APPLICABLE ONLY TO THIS TASK ORDER:
Block 9 -- For additional information contact:
Timothy Humphrey 904-232-1072 Timothy.G.Humphrey@usace.army.mil.
Block 10 -- Magnitude of Construction is between $10,000,000.00 and $25,000,000.00. Coast Guard Load line, Certified Equipment is required for this project.
GROUP4-10-R-J027 SF 1442-A2 Revision 0004
Block 11 -- The Contractor shall begin performance within 45 calendar days and complete it within 104 130 calendar days after receiving notice to proceed. This performance period is mandatory. NOTE: If there are optional line items, refer to FAR 52.211-10 for breakdown of period of performance.
Block 12 -- The contractor must furnish any required performance and payment bonds within 10 calendar days after award of the task order.
Block 13 -- Sealed offers to perform the work required shall be delivered to the following address not later than June 03, 2016 at 3:00 PM EST.
U.S. Army Corps of Engineers Jacksonville Regional Contracting Center (CESAJ-CT-C) Prudential Office Building 701 San Marco Blvd.
Jacksonville, Florida 32207-8175
NOTICE TO OFFERORS: Offerors are to complete Blocks 14, 15, and 20 below:
Block 14 -- Name and Address of Offeror (including Zip Code):
DUNS: ___________________ CAGE: _______________
Block 15 -- Telephone No. (include area code): _____________________
Block 20 -- Name and Title of Person Authorized to Sign Offer (type or print):
Type/Print ________________________________________________
Signature: ________________________________________________ e-Mail: ________________________________________________
Offer Date: _______________________________________________
Block 26 -- This Task Order will be administered by:
North Florida Area Office 4070 Boulevard Center Drive Suite 201
Jacksonville, FL 32207
Block 27 -- Payment will be made by:
USACE Finance Center 5722 Integrity Drive
ATTN: CEFC-AO-P
Millington, TN 38054-5005
Shore Protection Project, Duval County, Florida, Renourishment 2016
GROUP4-10-R-J027 SF 1442 Addendum A3 Revision 0004
REVISION 0004 CONTINUATION SHEET
The purpose of this revision is to:
1. Change the Period of Performance from 104 calendar days to 130 calendar days.
***Please note the Government may not respond to any Questions submitted after 27 May 2016***
| Continuation Sheet - Duval Conty SPP, Revision 0004.pdf |
| Revision 0004 CONTINUATION SHEET |