GROUP4-10-R-J027 SF 1442-A1 Revision 0005

ADDENDUM TO THE STANDARD FORM 1442

Shore Protection Project, Duval County, Florida, Renourishment 2016

SPECIAL NOTIFICATION: THIS OPPORTUNITY IS AVAILABLE ONLY TO THE FOLLOWING

CONTRACTORS AWARDED A CONTRACT UNDER SOLICITATION NUMBER

W912EP-10-R-0026: Orion Marine Construction (W912EP-13-D-0003); Cavache, Inc.

(W912EP-13-D-0004); Cashman Dredging & Marine Contracting (W912EP-13-D-0005);

Cottrell Contracting Corporation (W912EP-13-D-0006); Great Lakes Dredge & Dock Company, LLC (W912EP-13-D-0007); Dutra Dredging Company (W912EP-13-D-0008);

Marinex Construction, Inc. (W912EP-13-D-0009); Norfolk Dredging Company (W912EP-13- D-0010); Mike Hooks, Inc. (W912EP-13-D-0011); Weeks Marine, Inc. (W912EP-13-D-0012);

Southern Dredging Co., Inc. (W912EP-13-D-0013); Manson Construction Company (W912EP-13-D-0014); C. F. Bean LLC (W912EP-13-D-0015) PROPOSALS WILL NOT BE

CONSIDERED FROM ANY ENTITY OTHER THAN THE PREVIOUSLY LISTED FIRMS

INCLUDED IN THE Group 4 Dredging MATOC Pool.

TECHNICAL EVALUATION: The award of the task order will be made on the basis of Lowest Price, Technical Acceptable (LPTA); the technical evaluation factors are:

(1) Availability of technically acceptable dredge(s). Note: Coast Guard Certified Equipment is REQUIRED.

(2) Past performance, to include the MATOC (The government reserves the right to obtain copies of all Contractor Performance Assessment Reporting System (CPARS) records contained in the US Army Corps of Engineers CPARS database for the Prime Contractor (Offeror) and all Major Sub-Contractors).

SUBMISSION REQUIREMENTS: Contractors are required to submit the following:

(1) A letter on company letterhead identifying the dredge(s) the contractor proposes to do the work and the location of dredge(s). The identified dredge(s) must also have been found technically acceptable by the Contracting Officer prior to the proposal due date.

(2) Completed Bid Schedule (see Section 00010A)

(3) Bid Guarantee per Section 00700, Clause 52.228-1 and Section 00100A, Paragraph 2.4(c) of the MATOC

(4) Completed “Addendum to the Standard Form 1442 with the latest revision”.

(5) Revisions – Offers must acknowledge receipt of this Revision by completing “Notice to Offerors--Blocks 14, 15 and 20” of each revision.

THE FOLLOWING INFORMATION IS APPLICABLE ONLY TO THIS TASK ORDER:

Block 9 -- For additional information contact:

Timothy Humphrey 904-232-1072 Timothy.G.Humphrey@usace.army.mil.

Block 10 -- Magnitude of Construction is between $10,000,000.00 and $25,000,000.00. Coast Guard Load line, Certified Equipment is required for this project.

GROUP4-10-R-J027 SF 1442-A2 Revision 0005

Block 11 -- The Contractor shall begin performance within 45 calendar days and complete it within 130 calendar days after receiving notice to proceed. This performance period is mandatory. NOTE: If there are optional line items, refer to FAR 52.211-10 for breakdown of period of performance.

Block 12 -- The contractor must furnish any required performance and payment bonds within 10 calendar days after award of the task order.

Block 13 -- Sealed offers to perform the work required shall be delivered to the following address not later than June 03, 2016 at 3:00 PM EST June 08, 2016 at 3:00 PM EST.

U.S. Army Corps of Engineers Jacksonville Regional Contracting Center (CESAJ-CT-C) Prudential Office Building 701 San Marco Blvd.

Jacksonville, Florida 32207-8175

NOTICE TO OFFERORS: Offerors are to complete Blocks 14, 15, and 20 below:

Block 14 -- Name and Address of Offeror (including Zip Code):

DUNS: ___________________ CAGE: _______________

Block 15 -- Telephone No. (include area code): _____________________

Block 20 -- Name and Title of Person Authorized to Sign Offer (type or print):

Type/Print ________________________________________________

Signature: ________________________________________________ e-Mail: ________________________________________________

Offer Date: _______________________________________________

Block 26 -- This Task Order will be administered by:

North Florida Area Office 4070 Boulevard Center Drive Suite 201

Jacksonville, FL 32207

Block 27 -- Payment will be made by:

USACE Finance Center 5722 Integrity Drive

ATTN: CEFC-AO-P

Millington, TN 38054-5005

TASK ORDER REVISIONS

SHORE PROTECTION PROJECT

DUVAL COUNTY, FLORIDA

BEACH RENOURISHMENT 2016

GROUP4-10-R-J027 Revision 0005

SUMMARY OF CHANGES

1. SPECIFICATIONS:

The text changes have been updated with additions noted by underlined text and deletions noted by line/cross-outs, and pertain only to changes made by this amendment. The entire section is replaced if there is any change. The Project Table of Contents and Submittal Register are replaced without underlines and cross-outs if there are changes to these documents.

Contract Documents:

There are no changes to Contract Documents.

Technical Specifications:

DELETE Section 35 20 25 BEACH FILL and REPLACE with the attached revised Section 35 20 25 BEACH FILL.

2. DRAWINGS:

DELETE Drawing No. C-22 and REPLACE with the attached revised Drawing No. C-22.

(End of Summary of Changes)

SECTION TABLE OF CONTENTS

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

SECTION 35 20 25

BEACH FILL

PART 1 GENERAL

1.1 SUMMARY

1.2 REFERENCES

1.3 DEFINITIONS

1.3.1 Acceptance Sections

1.3.2 Compensating Slopes

1.3.3 Construction Baseline (CBL)

1.3.4 Target Depth

1.3.5 Tolerance Depth

1.3.6 Work Area

1.4 SYMBOL AND ACRONYM USE

1.5 SUBMITTALS

1.6 PROJECT SCOPE

1.6.1 Order of Work

1.6.2 Project Coordination

1.6.3 Permits and Responsibilities

1.6.3.1 Traffic and Navigation

1.6.4 Protection of Existing Structures from Construction Activity

1.6.4.1 Protection of Existing Utilities from Construction Activity

1.6.4.2 Damages to Adjacent Property and Structures

1.6.5 Work Violations

1.6.6 Final Cleanup

1.7 ENVIRONMENTAL PROTECTION

1.7.1 Pumping of Bilges

1.7.2 Fuel Oil Transfer Operations

1.7.3 Turbidity

1.7.4 Historical Period Shipwreck Sites

1.8 NOTIFICATION OF COAST GUARD

1.8.1 Navigation Aids

1.8.2 Dredging Aids

1.9 WORK AND ACCESS AREA

1.10 SIGNAL LIGHTS

1.11 CRANE AND DRAGLINE SAFETY REQUIREMENTS

PART 2 PRODUCTS- NOT USED

PART 3 EXECUTION

3.1 OVERALL WORK AREA PROVISIONS

3.1.1 Construction Plans and Contract Documents

3.1.2 Staging and Access Areas

3.1.2.1 Locations

3.1.2.2 Existing Conditions Documentation

3.1.3 Public Protection

GROUP4-10-R-0027 SECTION 35 20 25 Page 1 Revision 0005

3.1.3.1 Work Area Signs and Barriers

3.1.3.2 Dedicated Safety and Flag Person

3.1.4 Noise Control

3.1.4.1 Hauling and Excavating Equipment

3.1.4.2 Booster Pumps Noise Control

3.1.4.3 Sound Pressure Measurements

3.1.5 Buoy and Anchoring Inventory

3.1.6 Protection of Existing Vegetation

3.1.7 Protection of Sea Turtles

3.2 EXCAVATION

3.2.1 General

3.2.2 Borrow Area Characteristics

3.2.3 Borrow Area Dredging

3.2.4 Overflow Dredging

3.2.5 Borrow Area Excavation Limitations

3.2.6 Unsuitable Material

3.2.7 Magnetic Anomalies

3.2.8 Probability of Rock in Borrow Area

3.2.9 Dredge Location Control

3.2.9.1 Hopper and Scow Control

3.2.9.2 Other Dredge Type Control

3.2.10 Deduction for Nonconforming Work

3.3 TRANSPORT OF EXCAVATED MATERIALS

3.3.1 Hopper Dredge/Scow

3.3.1.1 Mis-Dump

3.3.2 Pipeline Transportation

3.3.2.1 Submerged Pipeline

3.3.2.2 Floating Pipeline

3.3.2.3 Upland Pipeline

3.3.2.4 Visual Inspection of Pumpout and Pipeline Locations

3.3.3 Spillage and Leakage

3.3.3.1 Hopper Dredge/Scows

3.3.3.2 Pipeline

3.4 BEACH FILL

3.4.1 General

3.4.2 Construction

3.4.2.1 Construction Equipment Limitations

3.4.2.2 Grade Stake Installation and Recovery Operations

3.4.2.3 Control of Fill

3.4.2.4 Ramps and Walkways

3.4.3 Placement

3.4.3.1 Screening and Disposal of Material

3.4.3.2 Dressing for Payment

3.4.3.3 Dressing for Final Acceptance

3.4.4 Escarpments

3.4.5 Tolerances

3.4.6 Misplaced Materials

3.5 QUALITY CONTROL

3.5.1 Preparatory Inspection

3.5.2 Initial Inspections

3.5.3 Follow-up Inspection

3.6 QUALITY CONTROL FOR BEACH FILL

3.6.1 Compliance Criteria for Beach Fill Material

3.6.2 Beach Fill Observation and Sampling

3.6.3 Determination of Areal Extent of Noncompliant Beach Fill

3.6.4 Remediation

3.6.5 Noncompliant and Unacceptable Material Contingency Plan

3.7 INSPECTION

3.7.1 Quality Assurance Representative (QAR)

GROUP4-10-R-0027 SECTION 35 20 25 Page 2 Revision 0005

3.7.2 Failure to Comply

3.8 CONSTRUCTION FORMS AND DETAILS

-- End of Section Table of Contents --

GROUP4-10-R-0027 SECTION 35 20 25 Page 3 Revision 0005

SECTION 35 20 25

BEACH FILL

PART 1 GENERAL

1.1 SUMMARY

The project work covered by this section consists of furnishing all plant, labor, equipment, supplies, and material, and of performing all operations in connection with excavating, transporting, and placing beach fill along the project shoreline as indicated on the drawings, as described by applicable permits, and/or as specified herein. Related sections are

01 11 00 SUMMARY OF WORK, 01 57 20 ENVIRONMENTAL PROTECTION, 01 57 25

TURBIDITY AND DISPOSAL MONITORING, and 02 22 13 VIBRATION MONITORING

REQUIREMENTS FOR EXISTING STRUCTURES.

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM D422 (1963; R 2007) Particle-Size Analysis of Soils

<REF> FLORIDA WILDLIFE COMMISSION (FWC)

FWC SCHEME Development of a System for Classification of Habitats in Estuarine and Marine Environments (SCHEME) for Florida<REF>

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 Safety and Health Requirements Manual

1.3 DEFINITIONS

1.3.1 Acceptance Sections

Fill placement acceptance sections are defined as the portion of the renourished beach lying between two immediately adjacent pay profile lines.

1.3.2 Compensating Slopes

The allowance for pay volume above the fill tolerance to compensate for foreshore slope vacancies within the fill template due to sediment relocated by natural forces between the time of placement and payment surveys, or presence of existing utilities as depicted in the Contractor's work plan.

GROUP4-10-R-0027 SECTION 35 20 25 Page 4 Revision 0005

1.3.3 Construction Baseline (CBL)

To closely resemble the shoreline, a Construction Baseline (CBL) was established. The CBL determines the seaward berm crest width and the construction stationing for pre- and post-payment surveys.

1.3.4 Target Depth

The material actually removed from the designated borrow area, to a depth of not more than the target depth shown on the drawings.

1.3.5 Tolerance Depth

To cover the inaccuracies of the dredging process, material actually removed from the designated areas to be dredged, to a depth below the target depth of not more than the tolerance depth shown on the drawings.

1.3.6 Work Area

Work area is defined as the area where Contract work is to be performed, as shown on the contract drawings, impacted by contractor operations, and additional areas agreed by the Contracting Officer.

1.4 SYMBOL AND ACRONYM USE

/ = or b/c = because CBL = Construction Baseline FDEP = Florida Department of Environmental Protection

1.5 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-02 Shop Drawings

Unless otherwise indicated below, Shop Drawings shall be submitted no later than 20 calendar days after Notice of Award or 5 calendar days after Notice to Proceed, whichever is later.

General Work Plan; G, RO

The Contractor shall submit a Work Plan for review and approval by the Contracting Officer. The work plan shall include but not be limited to the following:

a. Excavation Depth Protection: Provide a detailed description of methods and equipment to be used for each operation, and the sequence of operations, including sketches showing how the Contractor will not exceed the tolerance depth at each the project borrow area.

b. Protection of Existing Utilities: Provide a plan of how protecting existing utilities shown on the plans will be performed including how utility companies will be notified, how utilities

GROUP4-10-R-0027 SECTION 35 20 25 Page 5 Revision 0005 will be identified by the contractor, and how dressing of fill and tilling within the area where utilities exist will be accomplished. Furthermore provide a contingency notification if a utility has been impacted by contractor activities. Refer herein and to specifications Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS and Section 01 50 02 TEMPORARY CONSTRUCTION FACILITIES for managing existing utilities.

c. Buoy Log: The Contractor shall develop a method of inventory for all anchors, buoys, and buoy cables used in the construction of the project. This record shall be used by the Contractor to recover all buoys and anchoring equipment at the completion of the project

d. Grade Stake Log: The Contractor shall provide a sample Grade Stake Log to be used on the project and indicate how the log is prepared and maintained to inventory the grade stakes used on the project. The log shall include information concerning the location, installation, and recovery of all grade stakes. The Contractor shall make this log available for review by the appropriate Government personnel upon request. Upon completion of the project, the Contractor shall furnish the log to the Contracting Officer.

e. Staging and Access Area: The Contractor shall indicate if they plan on obtaining additional access or staging areas for their construction operations other than what is shown on the drawings. If the Contractor plans on obtaining additional access/staging areas, submit proposed drawings depicting the areas for Contracting Officer approval. Contractor shall also provide staging and access area existing conditions plans documentation.

f. Public Protection: Provide a Contractor's plan for ensuring pedestrian, worker, and vehicular safety at each access location used by the Contractor. Submit means and methods for pedestrian protection during beach fill operations for review and approval by the Contracting Officer. Submit product information and methods of installation for orange safety fencing for crowd control.

Submit methods of staking in place and maintenance of system for duration of construction.

Progress Map; G, RO

Provide a progress schedule map of the contractor's design. The progress schedule map shall be a plan view drawing depicting the beach fill site and access areas to used on the project. The map shall show all acceptance sections (AS), access/staging areas, and pipeline landings anticipated to be used on the project. For each AS, the information shall list the following: Anticipated quantity of material per acceptance section, projected dates for fill to be placed and completed. The map shall provide dates when access areas are to be used and ready for public use. The map will be color coordinated with the following color scheme: Red depicting an area not ready for construction; Orange depicting an area currently being worked, and Green meaning an area accepted by the Contracting Officer and ready for public use. The map shall be updated at least weekly and whenever significant changes occur to the projected dates. Since the map will be used by the Government for coordination with the public and to track progress, GROUP4-10-R-0027 SECTION 35 20 25 Page 6 Revision 0005 the update shall be provided prior to the weekly project progress meeting.

Relocation of Navigation Aids

Within 7 calendar days following receipt of Notice of Award, the Contractor shall notify the Commander, Seventh Coast Guard District, Miami, Florida of their plan to dredge adjacent to any aids which require relocation to facilitate dredging for each project fill segment. The notification shall be sent via Fax to 305-415-6757, ATTN: Mr. Gene Stratten. This notification shall be immediately followed by a formal written request with a copy to the Contracting Officer. The Contractor shall also contact the U.S. Coast Guard at 305-415-6750 for information concerning the position to which the aids will be relocated.

Material Screening and Removal Plan; G, DO

The Contractor shall submit to the Contracting Officer a plan detailing the method for screening and removal of material. The plan shall also include the method for which the quantity of material removed is measured and the location of material disposal for acceptance by the Contracting Officer.

Noncompliant and Unacceptable Material Contingency Plan

Submit a Noncompliant Material Contingency Plan as indicated in paragraph QUALITY CONTROL FOR BEACH FILL below.

Electronic Tracking System Charts

The Contractor shall furnish required plotted charts to the Contracting Officer.

Dredge Location Control Color-Coded Plot

The Contractor shall furnish the required color-coded plots to the Contracting Officer.

SD-04 Samples

Quality Control for Beach Fill

Beach sediment samples shall be collected and stored a the on-site trailer for inspection. Refer to paragraph QUALITY CONTROL FOR BEACH FILL below for further details on sampling.

SD-07 Certificates

Notice of Intent to Dredge; G, RO

Prior to commencement of work on this contract, the Contractor will be required to notify the Commander, Seventh Coast Guard District of their intent to dredge and request that it be published in the Local Notice to Mariners. This notification must be given in sufficient time so that it appears in the Notice to Mariners at least 30 calendar days prior to the commencement at each project segment. A copy of the notification shall be provided to the Contracting Officer.

GROUP4-10-R-0027 SECTION 35 20 25 Page 7 Revision 0005

Equipment and Performance Data; G, RO

The Contractor shall furnish proof of electronic positioning equipment calibration to the Contracting Officer.

Grade Stake Recovery; G, DO

After completion of the project, the Contractor shall provide a letter to the Contracting Officer certifying that all grade stakes have been recovered in accordance with the Contractor's approved Construction and Grade Stake Recovery Plan. With the certification, the Contractor shall also furnish the completed Grade Stake log to the Contracting Officer. Refer to paragraph GRADE STAKING AND REMOVAL below.

Buoy and Anchoring Inventory Recovery; G, DO

After completion of the project, the Contractor shall provide a letter to the Contracting Officer certifying that all anchors, buoys, buoy cables used in the construction of the project have been recovered in accordance with the Contractor's approved Anchor and Buoy Recovery below. With the certification, the Contractor shall also furnish the completed Buoy and Anchoring Inventory Record

Notification of Discovery of Historical Period Shipwreck Sites

The Contractor shall immediately notify the Contracting Officer if any shipwreck, artifact, or other objects of antiquity that have scientific or historical value, or are of interest to the public, are discovered, located, and/or recovered.

Daily/Monthly Report of Operations

The Contractor shall prepare on QCS and submit two (2) hard copies of the Daily Report of Operations, using either ENG Form No. 27A or ENG Form No. 4267, for each dredge and/or unloader working. This report shall be submitted on a daily basis and not in groups (groups = multi-days reports packaged together at one time). In addition to the daily report, the Contractor shall prepare a Monthly Report of Operations for each month or partial month's work on either ENG Form No. 27A or ENG Form No. 4267. The monthly report shall be submitted on or before the 7th of each month, consolidating the previous month's work. Upon completion of the job, the Contractor shall submit a consolidated job report, combining the monthly reports. The Contractor shall distribute one copy of each report to the District Engineer, ATTN:

CESAJ-EN-C; U.S. Army Engineer District, Jacksonville, P.O. Box 4970, Jacksonville, Florida 32232-0019. Reports shall be submitted on a monthly basis with daily reports accompanying the monthly report and job report.

Additionally, one copy of these forms shall be maintained by the Contractor on the dredge(s) for the Contracting Officer's inspection purpose. Further instructions on the preparation of the reports will be furnished at the Preconstruction Conference.

Notice of Misplaced Material

GROUP4-10-R-0027 SECTION 35 20 25 Page 8 Revision 0005

The Contractor shall notify the U.S. Coast Guard Marine Safety Office of any misplaced material as stated in Clause OBSTRUCTION OF NAVIGABLE WATERWAYS of Section 00700 CONTRACT CLAUSES.

Declaration of Inspection

Refer to paragraph FUEL OIL TRANSFER OPERATIONS below for submittal.

1.6 PROJECT SCOPE

The Contractor shall provide the dredge and support vessels, labor, equipment, supplies, and materials to perform all operations for excavating, transporting, placing, dressing and grading (and possible tilling) beach fill on the beaches as indicated in the drawings and further specified herein. The Contractor shall accomplish the work in such a manner so as to minimize disruption to road and maritime traffic or use of the public beach as well as minimize impacts to existing infrastructure.

1.6.1 Order of Work

At the Preconstruction Conference, the Contractor shall propose the order in which the work will be performed, including the anticipated progression of fill placement throughout the project area and excavation of the borrow areas. The Contractor shall begin their filling operations at any point along the project beach, but the Contractor shall maintain a continuous filling operation without any intervening gaps.

1.6.2 Project Coordination

Project coordination with the Contracting Officer shall occur during all phases of construction. Coordination also includes but is not limited to coordinating with local officials including police, Public, FDEP, US Coast Guard, and others as agreed during coordination meetings. See paragraph PROJECT COORDINATION of Section 01 30 00 ADMINISTRATIVE PROCEDURES and Paragraph COORDINATION MEETING of Section 01 45 05 DREDGING/BEACH FILL

PLACEMENT - CONTRACTOR QUALITY CONTROL.

1.6.3 Permits and Responsibilities

The Contractor's attention is directed to the Clause PERMITS AND RESPONSIBILITIES of Section 00700 CONTRACT CLAUSES and paragraph PERMITS AND AUTHORIZATIONS of Section 01 57 20 ENVIRONMENTAL PROTECTION. Any other licenses or approvals required for the prosecution of the work shall be secured and paid for by the Contractor. The Contractor shall obtain any and all approvals required to conduct work in the Atlantic Ocean.

1.6.3.1 Traffic and Navigation

The Contractor shall so conduct their operations that they shall not close any thoroughfare nor interfere in any way with traffic on railway, highways, or on water, without the written consent of the Contracting Officer. The regulations the Contractor shall adhere to are those established by, but not necessarily limited to, the Department of the Navy, U.S. Coast Guard, Department of the Army, American Bureau of Shipping, Florida Department of Environmental Protection, Florida Department of Transportation, Florida Law Enforcement Agencies, county and municipal.

GROUP4-10-R-0027 SECTION 35 20 25 Page 9 Revision 0005

1.6.4 Protection of Existing Structures from Construction Activity

The Contractor shall be responsible for determining and documenting the pre-construction condition of existing structures within the project area.

The Contractor shall take appropriate measures to prevent damage to any structures during construction, and for performing a post-construction verification inspection of those structures previously inspected. Refer to Section 02 22 13 VIBRATION MONITORING REQUIREMENTS FOR EXISTING STRUCTURES for further details and guidelines.

1.6.4.1 Protection of Existing Utilities from Construction Activity

Prior to placement of beach fill material within the 400' buffer protecting the fiber optic cable, the Contractor shall contact and coordinate with the utility owners of the fiber optic cables for locating the cables and placement of beach fill on top of and around the cables. If location of the cable is necessary, the Contractor shall use the Utility Owner's preferred method of location. The contractor may use compensating slopes for placement and payment within these buffers. The Utility Owner contacts are as follows:

a.) PCCS (Telefonica) 786-521-2885 b.) AMX (American Mobile) 904-557-3244 c.) AT&T 855-293-7676

1.6.4.2 Damages to Adjacent Property and Structures

Any damage to private or public property within the project boundaries, including staging site(s) and work and access areas/roads, shall be repaired promptly by the Contractor. Any damage as a result of the Contractor's operations shall be repaired at no cost to the Government.

The Contractor will not receive final payment until all damages are restored to the satisfaction of the Contracting Officer.

1.6.5 Work Violations

Work done in violation of these specifications or a verbal or written stop order of the Contracting Officer will be considered as unsatisfactory progress for purposes of progress payments in accordance with clause PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS of Section 00700 CONTRACT

CLAUSES.

1.6.6 Final Cleanup

Final cleanup, as stated in the paragraph COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK of Section 00700 CONTRACT CLAUSES, shall include the removal of all of the Contractor's plant and equipment either for disposal or reuse. Plant and/or equipment to be disposed of shall ONLY be disposed of in a manner and at locations approved by the Contracting Officer.

Unless otherwise approved in writing by the Contracting Officer, the Contractor will not be permitted to abandon pipelines, pipeline supports, pontoons, or other equipment in the disposal area, pipeline access areas, water areas, or other areas adjacent to the work site. Pilings and any other debris removed or created as a result of the execution of this

GROUP4-10-R-0027 SECTION 35 20 25 Page 10 Revision 0005 contract shall be disposed of in a manner and at locations approved by the Contracting Officer.

1.7 ENVIRONMENTAL PROTECTION

The Contractor shall protect the environment during all phased of work.

See Section 01 57 20 ENVIRONMENTAL PROTECTION for additional details.

1.7.1 Pumping of Bilges

Contractors are warned that pumping oil or bilge water containing oil into navigable waters, or into areas which would permit the oil to flow into such waters, is prohibited by Section 13 of the River and Harbor Act of 1899, approved 3 March 1899 (30 Stat. 1152; 33 U.S.C. 407). Violation of this prohibition is subject to penalties provided under the referenced Act.

1.7.2 Fuel Oil Transfer Operations

In accordance with U.S. Coast Guard regulations (33 CFR 156.120), couplings used in fuel oil transfer operations on any vessel with a capacity of 250 or more barrels of oil shall be either a bolted or full-threaded connection; or a quick-connect coupling approved by the Commandant; or an automatic back-pressure shutoff nozzle used to fuel the vessel. An executed fuel oil transfer (Declaration) form signed by the tanker operator shall be submitted to the Contracting Officer for each refueling operation. The U.S. Coast Guard shall also be notified prior to any refueling. A copy of the Declaration of Inspection for Refueling is on the web site indicated in paragraph CONSTRUCTION FORMS AND DETAILS below.

1.7.3 Turbidity

Excavation, transport, and filling operations shall be performed in a manner that will minimize turbidity. The Contractor shall meet the requirements to maintain the quality of the State's waters as stipulated in Section 01 57 25 TURBIDITY AND DISPOSAL MONITORING, project permits and in the Florida Administrative Code Rule 62-3.121. The Contractor will be required to make inspections, measurements and observations required by those regulations and the FDEP permit in the vicinity of the dredge and at the placement site (beach).

1.7.4 Historical Period Shipwreck Sites

If any shipwreck, artifact, or other objects of antiquity that have scientific or historical value, or are of interest to the public, are discovered, located, and/or recovered, the Contractor acknowledges that:

a. The site(s), articles, or other materials are the property of the State of Florida, with title vested in the Department of State, Division of Historical Resource; and

b. shall immediately notify the Contracting Officer.

Refer to subparagraph "Preservation and Recovery of Historic, Archeological, and Cultural Resources" of Section 01 57 20 ENVIRONMENTAL

PROTECTION.

GROUP4-10-R-0027 SECTION 35 20 25 Page 11 Revision 0005

1.8 NOTIFICATION OF COAST GUARD

1.8.1 Navigation Aids

Navigation aids located within or near the areas required to be dredged will be removed, if necessary, by the U.S. Coast Guard in advance of dredging operations. The Contractor shall not remove, change the location of, obstruct, willfully damage, make fast to, or interfere with any aid to navigation.

1.8.2 Dredging Aids

The Contractor shall obtain approval from the U.S. Coast Guard for all buoys, dredging aid markers to be placed in the water, and dredging aid markers affixed with a light prior to the installation. Dredging aid markers and lights shall not be colored or placed in a manner that they will obstruct or be confused with navigation aids.

1.9 WORK AND ACCESS AREA

Comply with work and access area requirements indicated herein and in Section 01 57 20 ENVIRONMENTAL PROTECTION.

1.10 SIGNAL LIGHTS

The Contractor shall display signal lights and conduct operations in accordance with the General Regulations of the Department of the Army and of the Coast Guard governing lights and day signals. Lights and day signals shall be displayed by towing vessels with tows on which no signals can be displayed, vessels working on wrecks, dredges, and vessels engaged in laying cables or pipe or in submarine or bank protection operations.

Lights shall be displayed on dredge pipe lines, and day signals shall be displayed by vessels of more than 65 feet in length and floating plant vessels moored or anchored in a fairway or navigable channels where other vessels pass. Lights and days signals shall also comply with the requirements of Section 01 57 20 ENVIRONMENTAL PROTECTION, the Secretary of the Army, and Commandant U.S. Coast Guard Instruction M16672.2, Navigation Rules: International-Inland (COMDTINST M16672.2), or 33 CFR 81 Appendix A (International) and 33 CFR 84 through 33 CFR 89 (Inland) as applicable.

1.11 CRANE AND DRAGLINE SAFETY REQUIREMENTS

All cranes and draglines used in performing the Work set forth in these specifications shall comply with EM 385-1-1. Please refer to Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS for further details.

PART 2 PRODUCTS- NOT USED

PART 3 EXECUTION

3.1 OVERALL WORK AREA PROVISIONS

The construction and borrow area limits available to the Contractor for accomplishing the work are shown on the drawings. The Contractor shall accomplish the work in such a manner so as to minimize disruption to road traffic and use of the public beach as well as keep all work areas in a neat, orderly and in a safe manner. The Contractor will be required to maintain all access roads and all other work areas within or without the project boundaries free from dust and noise which would cause a hazard or

GROUP4-10-R-0027 SECTION 35 20 25 Page 12 Revision 0005 nuisance to others.

3.1.1 Construction Plans and Contract Documents

A minimum of one (1) complete set of construction plans (drawings) and contract documents (with permits and Notice to Proceed placards) shall be kept in the construction site field office. The dredge must have a complete set of drawings, including borrow area coordinates, at all times to avoid dredging outside of the borrow areas.

3.1.2 Staging and Access Areas

a. The final limits of the staging and access areas indicated on the drawings shall be field-determined by the Contracting Officer in coordination with the local sponsor and the Contractor. It shall be the responsibility of the Contractor to investigate and obtain any additional areas which may be necessary for their construction operations. The additional areas will be subject to the approval of the Contracting Officer.

b. The access and staging areas shall be restored to the pre-construction condition upon project completion at cost to the Contractor.

c. The staging areas shall be kept neat, orderly and in a safe manner.

d. The Contractor shall cordon off and/or fence the staging areas to secure all staging areas from the public.

e. The staging areas shall be restored to the pre-construction condition upon project completion at cost to the Contractor.

f. For staging areas on the beach, construction equipment shall be located off the beach as much as practicable during sea turtle monitoring. Regardless of time, all construction pipes that are placed on the beach shall be located as far landward as possible without compromising the integrity of the existing or reconstructed dune system. Temporary storage of pipes shall be off the beach to the maximum extent possible. If the pipes are placed on the beach, they shall be placed in a manner that will minimize the impact to nesting habitat and shall not compromise the integrity of the dune systems.

The staging areas shall not be used for stockpiling of beach fill material. Refer to Section 01 57 20 ENVIRONMENTAL PROTECTION.

3.1.2.1 Locations

1) 15th St., Atlantic Beach: Available for limited vehicle access.

2) 7th St., Atlantic Beach: Available for vehicle access.

3) Atlantic Blvd., Atlantic Beach: Available for vehicle access. This site contains decorative pavers, many of which are customized with names and would be difficult to repair. The Contractor shall keep heavy equipment off pavers and avoid driving trucks over landscape circle.

4) Seagate Ave., Neptune Beach: Available for vehicle access.

GROUP4-10-R-0027 SECTION 35 20 25 Page 13 Revision 0005

5) 8th Ave. North, Jacksonville Beach: Available for vehicle access and limited staging area. Public sidewalks on the northside shall remain open and public vehicular access and parking on the southside shall also remain open.

6) 16th Ave. South Jacksonville Beach: Available for vehicle access and limited staging area. The Contractor shall call the city public works department to arrange closure of the street end and for placement of barricades (904) 247-2619 or (904) 247-6211.

Limited access refers to areas which are typically limited by their overall size, or lack thereof. The Contractor shall investigate and determine how they will use, or not use, the locations provided.

3.1.2.2 Existing Conditions Documentation

At all access sites and staging areas to be used, the Contractor shall:

a. Photo-document the condition of the access location prior to disrupting the site.

b. Limit access width through existing vegetation to 20 feet or less.

c. Replace any fencing, signage, curbing, or other items disturbed by the Contractor's activities.

d. Restore and revegetate the access route with native dune plants subject to the approval of the Contracting Officer. Revegetation of access and staging areas shall be with sod (non-dune areas) or viable plant units (dune areas) at 18-inch maximum spacing with species and diversity equivalent to preconstruction conditions. Revegetation shall include a survival warranty of 90 percent of the plant material for 90 days. Vegetation shall be installed with fertilization and irrigation, or with initial irrigation, fertilization and approved water-absorbent polymeric gels, at no additional expense to the Government. Shrubs and trees shall be replaced to preconstruction conditions per the requirements of Section 01 57 20 ENVIRONMENTAL PROTECTION.

3.1.3 Public Protection

a. The Contractor will be required to exclude the public for safety purposes from the work areas in the vicinity of the hydraulic fill placement, grading and transporting operations, or any other area which may present a safety risk to the public, such as the discharge end of their pipeline and all associated equipment such as fuel tanks, booster bumps, etc.

b. The Contractor shall minimize the areas closed to the public.

Where practicable, the Contractor shall provide lateral access along the toe of the dune, landward of the work area and separated therefrom by orange safety fence, a narrow public access corridor to beyond the restricted work area.

c. The Contractor shall be responsible for providing and maintaining all water and land access routes necessary for their equipment and plant to and from the work sites.

d. The Contractor shall ascertain the environmental conditions which

GROUP4-10-R-0027 SECTION 35 20 25 Page 14 Revision 0005 can affect water and land access, such as climate, terrain, winds, current, waves, swells, depths, shoaling, and scouring tendencies.

3.1.3.1 Work Area Signs and Barriers

The Contractor shall install warning signs to warn the public and all commercial and recreational boats of all construction activities. See Section 01 50 02.

a. Any existing signs, buoys or other structures within the work lines shall be protected and/or removed and later replaced by the Contractor as directed.

b. The Contractor shall be required to erect, maintain, and move as necessary, a restrictive barrier around the active construction zone including the area of discharge of the hydraulic pipeline (or other mechanical off loader), where bulldozers are working, or any other active area where Work may present a safety hazard to the public. In the vicinity of the discharge, the barrier shall be constructed so as to prevent the public from approaching the discharge from any direction closer than 100 feet, and will provide an area sufficient in size for the safe progression of the Work. The Contractor shall post signs in a conspicuous manner designating the closed area.

c. The Contractor shall post signs in a conspicuous manner stating

"DANGER - HIGH PRESSURE DISCHARGE FROM DREDGE".

d. Enforcement shall be the Contractor's responsibility at no additional cost to the Government. The enforcement shall be coordinated with local enforcement agencies, and will be subject to approval of the Contracting Officer.

3.1.3.2 Dedicated Safety and Flag Person

The Contractor shall have a dedicated safety and flag person on site at all times, whose sole responsibility is preventing the public from entering the work area. Additionally, the Contractor shall place a safety person at the discharge end of the disposal pipeline. The safety person shall be present at all times during discharge operations and will maintain radio communication between the dredge and the disposal operation.

3.1.4 Noise Control

3.1.4.1 Hauling and Excavating Equipment

All hauling and excavation equipment used on this work shall be equipped with satisfactory mufflers or other noise abatement devices. The Contractor shall conduct his operations so as to comply with all federal, state, and local laws or ordinances pertaining to noise abatement. The use of horns, bells, or the use of whistle signals shall be held to the minimum necessary in order to insure as safe and as quiet an operation as possible.

3.1.4.2 Booster Pumps Noise Control

Booster pumps used on this work shall be equipped with satisfactory mufflers and/or other sound abatement devices to reduce engine noise. A sound barrier will be constructed landward of booster pumps in order to reflect noise waterward. Booster pumps shall not be allowed within 1,000 feet of residential areas. The Contractor shall conduct his operations so

GROUP4-10-R-0027 SECTION 35 20 25 Page 15 Revision 0005 as to comply with all Federal, State, and local laws pertaining to noise.

3.1.4.3 Sound Pressure Measurements

a. Sound pressure measurements shall be made with a sound level meter and shall be reported to the Contracting Officer under provisions for contractor quality control.

b. The measurements shall be made by personnel qualified to make such measurements and whose credentials have been verified by the Contracting Officer.

c. For Land based equipment other than booster pumps, sound pressure measurements shall be made at distances of 50 feet, 100 feet, 300 feet, and 500 feet from each major piece of equipment such as draglines, dump trucks, dewatering pumps, pneumatic drills, bulldozers, etc., at locations approved by the Contracting Officer. The measurements shall be taken during operations every 4 weeks.

d. Sound pressure measurements shall be made by the Contractor at 50-foot, 100-foot, 200-foot, and 300-foot distances from the (1) dredge, (2) booster pumps, if any, and (3) dredge pipeline at locations approved by the Contracting Officer. These measurements shall be taken during pumping operations every 4 weeks. The sound pressure measurements and type of material being dredged at the time measurements are taken shall be reported to the Contracting Officer.

Sound pressure measurements shall be made twice at the direction of the Contracting Officer during the first 4 weeks of use of whistle signals and drill barges in operation at 50-foot, 100-foot, 200-foot, and 300-foot distances.

e. Temperature, atmospheric pressure and general weather conditions shall also be recorded with the measurements.

f. In addition to the testing indicated above, more testing may be requested by the Contracting Officer.

3.1.5 Buoy and Anchoring Inventory

The Contractor shall inventory all anchors, buoys, and buoy cables deployed in the prosecution of work in a manner acceptable to the Contracting Officer. The Contractor shall use this information to account for and recover these items upon completion of work.

3.1.6 Protection of Existing Vegetation

In areas where the design fill template would cover existing vegetation greater than 25 square feet in area, the Contractor shall avoid impacts as much as possible or as directed by the Contracting Officer. In these areas, the Contractor can slope down at 1V:3H to existing grade so that existing vegetation is not covered as much as practicable

3.1.7 Protection of Sea Turtles

The project permits contain specific requirements for beach and dredge lighting during sea turtle nesting season. It is the responsibility of the Contractor to meet lighting requirements contained in the permits for the project, while also meeting OSHA lighting requirements and to ensure safety on the job site. Please refer to Section 01 57 20 ENVIRONMENTAL PROTECTION

GROUP4-10-R-0027 SECTION 35 20 25 Page 16 Revision 0005 and EM 385-1-1 for further details.

3.2 EXCAVATION

3.2.1 General

Contractor's equipment mobilized to the project site for excavation shall be suitable for excavation in the borrow area shown in the plans and capable of dredging at the borrow areas maximum depth.

3.2.2 Borrow Area Characteristics

The characteristics of the materials in the borrow areas may be as generally indicated by the sediment boring logs and grain size distribution curves area located in Section 00 31 32 GEOTECHNICAL DATA REPORT (GDR).

The descriptions of the material found within the GDR are based on the site investigations and core borings and only describe the materials obtained from those investigations. The Contractor is solely responsible for any interpretation or conclusions drawn therefrom. The Contractor may visit the location to view the core samples prior to the start of construction. The Contractor shall provide a five (5) day notice to the Contracting Officer or their represent agent of their requested visit. The material found in each of the borrow area sediment core borings (vibracores) is indicative only of the sand at that discrete location. The CONTRACTOR should be aware that it is possible for material of differing characteristics to be present in the borrow areas, including material differing from that contained in the vibracores.

3.2.3 Borrow Area Dredging

The borrow area and each subdivision selected by the Contracting Officer for excavation shall be completely excavated within reasonable limitations before relocating the dredge to another borrow area. Excavation shall be performed in a uniform and continuous manner so as to avoid creating multiple holes, valleys, or ridges. The borrow area shall be dredged to maximize the removal of sand from each sub-area of each provided borrow area. The purpose of this requirement is to avoid "wasting" sediment which could be used to renourish the beach now and in the future. The Contractor is not permitted to dredge within the dredging exclusion zone unless otherwise directed by the Contracting Officer.

3.2.4 Overflow Dredging

Overflow is considered a part of the dredging process and is permitted to occur within the borrow site during loading to the extent that turbidity and water quality standards required by Sections 01 57 20 ENVIRONMENTAL PROTECTION and 01 57 25 TURBIDITY AND DISPOSAL MONITORING are met.

3.2.5 Borrow Area Excavation Limitations

All excavation shall be performed within the horizontal and vertical limits of the borrow areas shown in the drawings. Under no circumstances shall excavation occur below the designated tolerance limit of excavation as shown in the drawings. No dredging is permitted in excess of the dredge depth shown in the drawings, referenced to NAVD88. Additionally, the Contractor shall not disturb the sediment in any manner below the depth of allowable disturbance which is one (1) foot below the maximum target depth of excavation. The material located below the indicated allowable tolerance depth is of unknown quality and may not be suitable for beach

GROUP4-10-R-0027 SECTION 35 20 25 Page 17 Revision 0005 renourishment. The Contractor will be required to certify in each Daily Quality Control Report that the excavation was conducted in compliance with the Drawings and Specifications including excavation and sediment tolerance depth.

3.2.6 Unsuitable Material

If continuous reaches of rock, clay or other unsuitable materials or unacceptable materials as defined in the paragraph titled "QUALITY CONTROL FOR BEACH FILL" are encountered in the borrow area, the Contractor shall change the location and depth of excavation within the borrow limits when necessary to provide the best fill material available at no additional cost to the Government. The location of unsuitable material encountered within the borrow area shall be noted on the Contractor's Quality Control Report (copy appended to the end of Section 01 45 05 DREDGING/BEACH FILL PLACEMENT

- CONTRACTOR QUALITY CONTROL). If the Contracting Officer determines the quality of beach fill is being adversely affected, that location shall be avoided in future passes of the dredge.

3.2.7 Magnetic Anomalies

A magnetometer survey was conducted at the borrow site with buffered returns shown on the drawings.

3.2.8 Probability of Rock in Borrow Area

It is not anticipated that material greater than 3/4" will be encountered at each borrow area. Dredging shall be restricted to the borrow area limits shown on the plans. The Contractor is put on notice that materials outside the borrow area contain a higher percentage or rock fragments within the sand and continuous rock surfaces.

3.2.9 Dredge Location Control

The Contractor shall have, in continuous operation on the dredge, electronic positioning equipment that will accurately and continuously compute and plot the position and the deepest penetration of the dredge.

3.2.9.1 Hopper and Scow Control

See Section 35 20 26 NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM SCOW - ULLAGE PROFILE and Section 35 20 28 NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM HOPPER DREDGE. However, in the event of NDQMP System failure (not fully operational), the Contractor shall notify the Contracting Officer and continue tracking using the vessel electronic positioning equipment for up to 48 hours until the NDQMP System is fully operational and in use. If, upon NDQMP System failure, the Contractor cannot use vessel electronic positioning equipment or cannot use the NDQMP System within 48 hours of failure, all dredging operations for the vessel shall cease until the NDQMP System is fully operational. Any delays resulting from NDQMP System failure shall be at the Contractor's expense.

3.2.9.2 Other Dredge Type Control

Other dredge types shall meet all of the following requirements, and this information shall be compiled and submitted to the Contracting Officer bi-weekly:

a. The Contractor is required to have electronic positioning

GROUP4-10-R-0027 SECTION 35 20 25 Page 18 Revision 0005 equipment that shall horizontally locate the dredge when operating on the project, as well as determine the depth of dredging. Continuous locations of the dredge shall be made at all times during dredging.

b. A color-coded plot, in the project reference datum, of the draghead, cutterhead, or other hydraulic or mechanical dredging device shall also be recorded daily depicting the vertical and horizontal limits of the material dredged that day. Any horizontal or vertical dredge violations shall be clearly defined.

c. The Contractor is required to calibrate the equipment as required by the manufacturer or as required by the Contracting Officer. Proof of calibration shall be submitted to the Contracting Officer.

d. For Horizontal control, the location of the dredge is to be computed by coordinates with a probable range error not to exceed +/- 3 feet. The Contractor's method of horizontal location of the dredge shall be submitted for review. LORAN-C shall not be permitted for location control.

e. The Contractor is also required to have a depth of dredging indicator accurate to within one half a foot (0.5 feet). The instrument used shall indicate the depth of dredging at all times. This equipment shall include real-time measurement of the water (tide) level. The reported elevation of dredging shall be adjusted by the measured water level elevation and shall have a probable range error not to exceed 0.5-feet vertical.

f. If the dredge is outside the borrow area limits, the Contractor shall provide reason the dredge is outside the borrow area limits such as turning around annotated on the position chart and the dredge depth…