Gibraltar Schools - Asbestos Abatement Project Addendum.pdf
PDF 98 KB Posted
- Attached to
- 2019 Summer Renovation Projects.
- Solicitation number
- RFP-GIB-190000001989-2
- Issued by
- Macomb County, Galien Village, Michigan
About this file
This is Addendum 1 for the Gibraltar School District Asbestos Materials Removal project, issued on April 25, 2019. The addendum revises the scope of work for the Parsons Elementary Media Center by removing the carpeted area wood flooring abatement from the project scope. The remaining scope includes removing 642 square feet of black mastic under wood flooring and black mastic under cork flooring on concrete in the front of stage, sides of stage, and stage built-out area. Additionally, the abatement contractor is responsible for demolishing and disposing of the ramp and front stage area measuring 42'x6', along with the abatement of wood flooring under both areas.
The addendum does not contain any information about pricing terms, set-asides, funding sources, or other financial details. All bidders are required to acknowledge receipt of this addendum on their Bid Form, as it supplements and amends the original Project Specifications and becomes part of the Contract Documents.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Gibraltar School District - Asbestos Removal RFP - Summer 2019 Projects.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM 1
GIBRALTAR SCHOOL DISTRICT
ASBESTOS MATERIALS REMOVAL
Issue Date: April 25, 2019
TO ALL BIDDERS:
This Addendum supplements and amends the original Project Specifications and shall be taken into account in preparing proposals and shall become part of the Contract Documents.
All Bidders are reminded to acknowledge receipt of this Addendum, where indicated, on the Bid Form.
ITEM 1: REVISION OF SCOPE OF WORK – PARSONS ELEMENTARY MEDIA CENTER
The carpeted area of the Media Center will not have the wood flooring abated and is deleted from the scope of work. All other work in the Media Center remains the same.
The revised scope of work is as follow:
BUILDING 3: Parsons Elementary School
ASBESTOS MATERIAL BUILDING LOCATIONS
QUANTITY
OF ACM
Black mastic under wood flooring and black mastic under cork flooring on concrete (includes removal and disposal of the cork under mastic)
Front of stage, sides of stage, and stage built-out area.
642 sf
• The ramp and front stage area (42’x6’) are to demolished and disposed of by the abatement contractor (along with the abatement of the wood flooring under both).
- END OF ADDENDUM -