Generator Delivery Timeframes.docx

DOCX document 14 KB Posted

Attached to
Cape Generators
Solicitation number
FA252126QB141
Issued by

About this file

This is a delivery timeframe reference document for generator equipment. The file provides recommended lead times for trailer-mounted, diesel-powered portable generators across five size categories required for the Cape Generators pre-solicitation (FA252126QB141) to Patrick Space Force Base, Florida. Delivery timeframes range from 14-16 weeks for 26 kW units to 20-24 weeks for 200 kW units, with intermediate timeframes for 36 kW (14-18 weeks), 60 kW (16-20 weeks), and 100 kW (18-22 weeks) generators. All generators must meet US EPA Tier 4 Final compliance standards as specified in the underlying Air Force Space Command requirement.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Generator Size Recommended Delivery Timeframe

26 kW
14–16 weeks
36 kW
14–18 weeks
60 kW
16–20 weeks
100 kW
18–22 weeks
200 kW
20–24 weeks