This is a delivery timeframe reference document for generator equipment. The file provides recommended lead times for trailer-mounted, diesel-powered portable generators across five size categories required for the Cape Generators pre-solicitation (FA252126QB141) to Patrick Space Force Base, Florida. Delivery timeframes range from 14-16 weeks for 26 kW units to 20-24 weeks for 200 kW units, with intermediate timeframes for 36 kW (14-18 weeks), 60 kW (16-20 weeks), and 100 kW (18-22 weeks) generators. All generators must meet US EPA Tier 4 Final compliance standards as specified in the underlying Air Force Space Command requirement.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Salient Characteristics - CLOIS Portable Generators Draft.pdf | ||
| 26QB141 Sources Sought.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Generator Size Recommended Delivery Timeframe
| 26 kW |
| 14–16 weeks |
| 36 kW |
| 14–18 weeks |
| 60 kW |
| 16–20 weeks |
| 100 kW |
| 18–22 weeks |
| 200 kW |
| 20–24 weeks |
File details come from the government source that posted it. Updated .