RFP No. 2026-08 Debris Cleanup Scope of Work Summary
This is a Scope of Work document for RFP No. 2026-08 issued by GEC (presumably a utility or governmental entity in Florida) for debris cleanup services in post-disaster environments related to major storm restoration activities. The contractor will be activated through a Notice to Proceed, Task Order, or Task Release Authorization with specific work details and locations within GEC's territory. The services scope includes utility pole pick-up and disposal, utility transformer pick-up with area cleanup and spill assessment, and general utility material disposal and recycling (metal hardware, wire scraps, packaging material). The contractor must provide necessary personnel (typically two per rig: an operator and assistant), standard equipment including pickup trucks, flatbed trailers, and skid steers, and additional equipment as needed. All work must comply with applicable Federal, State, and local regulations, the Master Service Agreement (MSA), and specific task authorizations.
The contract utilizes a time and materials fee structure with hourly rates to be proposed by the contractor in response to the RFP, reflecting the uncertain nature of post-disaster work quantities and territorial impact. The contractor is responsible for maintaining comprehensive records documenting chain of custody, material quantities disposed, landfill costs, personnel hours by position, and daily operational data. Daily reports must be submitted by close of business each day with cumulative information, and failure to provide audit-quality information by 5:00 p.m. the following day may result in financial penalties. The contractor must also provide data management support using compatible systems for tracking and documenting all work elements and must substantiate all costs with appropriate records consistent with MSA and Authorization requirements.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP No. 2026-08 – Debris Cleanup in Post-Disaster Environment
Scope of Work
I. General
The scope of services under this RFP includes debris cleanup for major storm restoration activities (the Services). GEC will activate the MSA through a Notice to Proceed, Task Order, or Task Release (Authorization) with the specific details of the work, including exact locations within its territory requiring assessments. The Services described below are non-exhaustive examples of services that may be requested; however, GEC may request less than all the services described, or additional services not specifically listed below but within the general scope of the RFP.
II. Services
Scope
Utility Pole Pick-up and Disposal o Contractor shall coordinate with GEC to pick up utility poles at designated bulk locations or along assigned roadways where poles have been left for pickup.
o Contractor shall be responsible for disposing in a manner that meets all applicable environmental regulations and maintaining records for establishing chain of custody of removed and disposed of material.
o Contractor will maintain records establishing quantity of material disposed of and corresponding landfill costs. All charges will be backed up with appropriate record and based on contract pricing.
o Contractor shall handle any situations where poles are transferred to the property owner where damaged pole was located. Proper chain of custody will be maintained.
Utility Transformer Pick-up, Area Cleanup, Disposal o Contractor shall coordinate with GEC to pick up utility transformers at designated bulk locations or along assigned roadways where transformer have been left for pickup.
o Contractor shall be responsible for disposing in a manner that meets all applicable environmental regulations and maintaining records for establishing chain of custody of removed and disposed of material.
o Contractor will be responsible for assessing any transformer clean-up needs and carrying out proper spill cleanup as regulations require.
o Contractor will maintain records establishing quantity of material disposed of and corresponding costs. All charges will be backed up with appropriate record and based on contract pricing.
General Utility Material Disposal and Recycling o Contractor shall coordinate with GEC to pick up general utility material (metal hardware, wire scraps, packaging material, misc) at designated bulk locations or along assigned roadways where transformer have been left for pickup.
o Contractor shall be responsible for disposing in a manner that meets all applicable environmental regulations and maintaining records for establishing chain of custody of removed and disposed of material.
o Contractor may provide containers where needed for project need.
o Contractor will maintain records establishing quantity of material disposed of and corresponding costs.
Personnel
Contractor shall provide the necessary personnel to complete the scope. This is typically 2 people per rig. An operator and an assistant. However, please provide all necessary labor rates.
Equipment
Pickup Flatbed Trailer Skid Steer The above equipment is what is typically needed to complete this scope of work. If more equipment will be used, please include those rates in the excel template provided.
Contract Terms
In addition to compliance with applicable Federal, State, and local rules and regulations, Contractor must also comply with the MSA and the terms and conditions in the Authorization, which will dictate the anticipated effort needed to complete the Services and include applicable terms and conditions for the Services.
Fee Structure
Given the uncertain nature of the quantity of work required and the percentage of service territory that will be impacted by the disaster, Contractor will have a time and materials fee structure at the rates proposed in response to this RFP. Please provide an hourly rate of the services.
Documentation Management & Support
Contractor shall provide data management and support as a part of the Services, including use of a compatible system for clearly tracking and documenting all elements identified above. Contractor must also substantiate its costs. Contractor must maintain all records pertaining to work performed consistent with the requirements set forth in the MSA and Authorization. Contractor shall submit a report by close of business each day with, at a minimum, the following information:
Contractor’s Name;
Contract Number;
Daily and cumulative hours for personnel, by position, if appropriate;
Other operational and complaint tracking information, as requested.
Failure to provide audit quality information by 5:00 p.m. of the following day of operation may result in financial penalty to the Contractor.