This is a Cost Proposal Form for RFP No. 2026-08 issued by GEC (governmental entity) for Debris Cleanup in Post-Disaster Environment services in Florida. The scope of services includes utility pole pick-up and disposal, utility transformer pick-up and area cleanup, and disposal operations following major storm restoration activities. The services are non-exhaustive, and GEC will activate work through a Notice to Proceed, Task Order, or Task Release with specific locations and details. Contractors must coordinate with GEC, maintain chain of custody records, ensure compliance with environmental regulations, and document all disposal quantities and corresponding landfill costs. The contract term spans 2026 and 2027, with the form requiring bidders to submit separate rate structures for each year.
Bidders must complete labor rates for 2026 and 2027 across three categories: straight time (ST), overtime (OT), and double time (DT) for positions including Supervisor, Operator, Laborer, and Laborer Assistant. Equipment rates must also be provided for 2026 and 2027 for vehicles ranging from half-ton to one-ton trucks in both two-wheel and four-wheel drive configurations, flatbed trailers, skid steers, and chain saws, with provisions for additional equipment as applicable. All lodging, meals, and fuel costs must be documented as pass-through costs with no markup to maintain FEMA compliance. The form requires bidders to identify bid and contract contacts and provide clarifications regarding rate assumptions, such as overtime applicability to storm work and double-time rates for holidays.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP No. 2026-08
| Cost Proposal Form |
| Instructions: Please complete all items highlighted yellow. |
| Bid Name | RFP No. 2026-08 Debris Cleanup in Post-Disaster Environment |
| Company Name: | |
| Corporate Address: | |
| Bid Contact | Please list the individual responsible for completing the Form. |
| Person Name: | |
| Email: | |
| Phone #: | |
| Contract Contact | Please list the individual responsible for signing the contract. |
| Name: | |
| Email: | |
| Phone #: |
| Rates | |||||||
| Instructions: Please enter the applicable rates in the Form below. | |||||||
| Labor Rates | |||||||
| 2026 Rates | 2027 Rates | ||||||
| Labor Description | ST | OT | DT | Labor Description | ST | OT | DT |
| Supervisor | Supervisor | ||||||
| Operator | Operator | ||||||
| Laborer | Laborer | ||||||
| Laborer Assistant | Laborer Assistant |
| Additional Labor Rates: Please list any other positions below. Insert additional rows if needed. However, Cost Forms will be evaluated based on the positions and rates above. | |||||||
| Labor Description | ST | OT | DT | Labor Description | ST | OT | DT |
| Labor Pricing Assumptions and Clarifications |
| Instructions: Using the space below, please provide additional assumptions and clarifications needed for the above rates. Example: OT applies all storm work, DT rate on Holidays. NOTE: Lodging, meals, and fuel (if not included in above rates) must be properly documented pass-through costs with no markup in order to be FEMA compliant. |
| Instructions: Please enter the applicable rates in the Form below. Not necessary to complete all rates, just complete what is applicable. | |||
| Equipment Rates | |||
| 2026 Rates | 2027 Rates | ||
| Equipment | Rate per Hour | Equipment | Rate per Hour |
| 1/2 Ton Pick-up Truck 2 WD | 1/2 Ton Pick-up Truck 2 WD | ||
| 1/2 Ton Pick-up Truck 4WD | 1/2 Ton Pick-up Truck 4WD | ||
| 3/4 Ton Pick-up Truck 2 WD | 3/4 Ton Pick-up Truck 2 WD | ||
| 3/4 Ton Pick-up Truck 4WD | 3/4 Ton Pick-up Truck 4WD | ||
| 1 Ton Truck 2 WD | 1 Ton Truck 2 WD | ||
| 1 Ton Truck 4 WD | 1 Ton Truck 4 WD | ||
| Flatbed Trailer | Flatbed Trailer | ||
| Skid Steer | Skid Steer | ||
| Chain Saw | Chain Saw |
Additional Equipment Rates: Please list any other offered equipment below. Insert add additional rows if needed.
Equipment Type Rate Equipment Type Rate
| Equipment Pricing Assumptions and Clarifications |
| Instructions: Using the space below, please provide additional assumptions and clarifications needed for the above rates. Example: OT applies all storm work, DT rate on Holidays. NOTE: Lodging, meals, and fuel (if not included in above rates) must be pass-through costs with no markup in order to be FEMA compliant. |