Task_1_Reference_Document__NPR_7123.1B.pdf
PDF 2 MB Posted
- Attached to
- Technical Support Services Contract for EROS Cente Federal contract opportunity
- Solicitation number
- G14PS00153
About this file
Reference Document NPR 7123.1B Sample Task 1
View the file
Other files for this federal contract opportunity
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
| NODIS Library | Program Formulation(7000s) | Search |
NASA
Procedural Requirements
NPR 7123.1B
Effective Date: April 18, 2013
Expiration Date: April 18, 2018
COMPLIANCE IS MANDATORY
NASA Systems Engineering Processes and Requirements
Responsible Office: Office of the Chief Engineer
Change History
Table of Contents Preface P.1 Purpose P.2 Applicability P.3 Authority P.4 Applicable Documents and Forms P.5 Measurement/Verification P.6 Cancellation
Chapter 1. Introduction
1.1 Background
1.2 Framework for Systems Engineering Procedural Requirements
1.3 Framework for Systems Engineering Capability
1.4 Document Organization
Chapter 2. Institutional and Programmatic Requirements
2.1 Roles and Responsibilities
2.2 Tailoring and Customization
Chapter 3. Requirements for Common Technical Processes
3.1 Introduction
3.2 Requirements for the Common Technical Processes
Chapter 4. NASA Systems Engineering Activities on Contracted NPR 7123.1B -- TOC Verify current version before use at:
http://nodis3.gsfc.nasa.gov/ Page 1 of 157
NPR 7123.1B -- TOC Verify current version before use at:
http://nodis3.gsfc.nasa.gov/ Page 1 of 157 http://nodis3.gsfc.nasa.gov/main_lib.html http://nodis3.gsfc.nasa.gov/lib_docs.cfm?range=7___ http://nodis3.gsfc.nasa.gov/adv_search.cfm http://nodis3.gsfc.nasa.gov/
Chapter 4. NASA Systems Engineering Activities on Contracted Projects
4.1 Introduction
4.2 Activities Prior to Contract Award
4.3 During Contract Performance
4.4 Contract Completion
Chapter 5. Systems Engineering Life-cycle and Technical Reviews
5.1 Life Cycle
5.2 Life-cycle and Technical Review Requirements
5.3 Completion of Life-cycle Reviews
Chapter 6. Systems Engineering Management Plan
6.1 Systems Engineering Management Plan Function
6.2 Roles and Responsibilities
Appendix A. Definitions Appendix B. Acronyms Appendix C. Practices for Common Technical Processes Appendix D. Systems Engineering Management Plan Appendix E. Technology Readiness Levels Appendix F. Technical Product Maturity Terminology Appendix G. Life-cycle and Technical Review Entrance and Success Criteria Appendix H. Compliance Matrices H.1 Compliance Matrix for Centers H.2 Compliance Matrix for Programs/Projects
Appendix I. References Appendix J. Index
Table of Figures Figure 1-1 - Hierarchy of Related Documents Figure 1-2 - Documentation Relationships Figure 1 3 - SE Framework Figure 3 1 - Systems Engineering (SE) Engine Figure 3-2 - Application of SE Engine Common Technical Processes Within System Structure
NPR 7123.1B -- TOC Verify current version before use at:
http://nodis3.gsfc.nasa.gov/ Page 2 of 157
NPR 7123.1B -- TOC Verify current version before use at:
http://nodis3.gsfc.nasa.gov/ Page 2 of 157
Figure 5 1 - NASA Uncoupled and Loosely Coupled Program Life Cycle Figure 5-2 - NASA Tightly Coupled Program Life Cycle Figure 5-3 - NASA Single-Project Program Life Cycle Figure 5 4 - The NASA Project Life Cycle Figure A-1 - Enabling Product Relationship to End Products Figure C 1 - Stakeholder Expectation Definition Process Figure C 2 - Technical Requirements Definition Process Figure C 3 - Logical Decomposition Process Figure C-4 - Design Solution Definition Process Figure C 5 - Sequencing of Product Realization Processes Figure C 6 - Product Implementation Process Figure C 7 - Product Integration Process Figure C 8 - Product Verification Process Figure C 9 - Product Validation Process Figure C 10 - Product Transition Process Figure C 11 - Technical Planning Process Figure C-12 - Requirements Management Process Figure C-13 - Interface Management Process Figure C-14 - Technical Risk Management Process Figure C-15 - Configuration Management Process Figure C-16 - Technical Data Management Process Figure C 17 - Technical Assessment Process Figure C 18 - Decision Analysis Process Figure D-1 - Systems Engineering Management Plan Title Page
Table of Tables Table 5-1 - SE Product Maturity Table G-1 - SRR Entrance and Success Criteria for a Program Table G-2 - SDR Entrance and Success Criteria for a Program Table G-3 - MCR Entrance and Success Criteria Table G-4 - SRR Entrance and Success Criteria Table G-5 - MDR/SDR Entrance and Success Criteria Table G-6 - PDR Entrance and Success Criteria Table G-7 - CDR Entrance and Success Criteria Table G-8 - PRR Entrance and Success Criteria Table G-9 - SIR Entrance and Success Criteria Table G-10 - TRR Entrance and Success Criteria Table G-11 - SAR Entrance and Success Criteria Table G-12 - ORR Entrance and Success Criteria Table G-13 - FRR Entrance and Success Criteria Table G-14 - PLAR Entrance and Success Criteria Table G-15 - CERR Entrance and Success Criteria Table G-16 - PFAR Entrance and Success Criteria Table G-17 - DR Entrance and Success Criteria Table G-18 - Disposal Readiness Review Entrance and Success Criteria Table G-19 - Peer Review Entrance and Success Criteria Table G-20 - PIR/PSR Entrance and Success Criteria
NPR 7123.1B -- TOC Verify current version before use at:
http://nodis3.gsfc.nasa.gov/ Page 3 of 157
NPR 7123.1B -- TOC Verify current version before use at:
http://nodis3.gsfc.nasa.gov/ Page 3 of 157
Change History
NPR 7123.1B, NASA Systems Engineering Processes and Requirements
Chg
Date Description/Comments
1 03/07/14 Appendix E - Replaced Technology Readiness Level (TRL) definition table with TRL definition table that was in NPR 7120.8, Appendix J.
2 05/27/14 Editorial changes to the definitions in Appendix A, Appendix E, TRL 6 Definition: System/sub-system model or prototype demonstration in a an operational relevant environment, updates to figures and text in Appendix C and Table G-2.
NPR 7123.1B -- ChangeHistory Verify Current version before use at:
http://nodis3.gsfc.nasa.gov/ Page 4 of 157
NPR 7123.1B -- ChangeHistory Verify Current version befor use at:
http://nodis3.gsfc.nasa.gov/ Page 4 of 157
Preface P.1 Purpose The purpose of this document is to clearly articulate and establish the requirements on the implementing organization for performing systems engineering. Systems Engineering (SE) is a logical systems approach performed by multidisciplinary teams to engineer and integrate NASA's systems to ensure NASA products meet customers' needs. Implementation of this systems approach will enhance NASA's core engineering capabilities while improving safety, mission success, and affordability. This systems approach is applied to all elements of a system (i.e., hardware, software, human system integration) and all hierarchical levels of a system over the complete project life cycle.
P.2 Applicability
a. This NASA Procedural Requirement (NPR) applies to NASA Headquarters and NASA Centers, including component facilities and technical and service support centers. This NPR applies to NASA employees and NASA support contractors that use NASA processes to augment and support NASA technical work. This NPR applies to JPL, other contractors, grant recipients, or parties to agreements only to the extent specified or referenced in the appropriate contracts, grants, or agreements. (See Chapter 4.)
b. This NPR applies to space flight, research and technology, and institutional programs and projects (including Information Technology (IT)), as appropriately tailored and customized for size and complexity. See Paragraph 2.2 for tailoring and customization descriptions.
c. In this document, a project is a specific investment having defined goals, objectives, requirements, life-cycle cost, a beginning, and an end. A project yields new or revised products or services that directly address NASA's strategic needs. Projects may be performed wholly in-house; by Government, industry, or academia partnerships; or through contracts with private industry.
d. The requirements enumerated in this document are applicable to all new programs and projects, as well as to all programs and projects currently in Formulation Phase as of the effective date of this document. (See NPR 7120.5, NPR 7120.7, and NPR 7120.8, as appropriate, for definitions of program phases.) This NPR also applies to programs and projects in their Implementation Phase as of the effective date of this document. For existing programs/projects regardless of their current phase, the Designated Governing Authority (DGA) may grant waivers/deviations allowing continuation of current practices that do not comply with all or sections of this NPR.
e. Many other discipline areas such as health and safety, medical, reliability, maintainability, quality assurance, IT, security, logistics, and environmental perform functions during project life-cycle phases that influence or are influenced by the engineering functions performed and need to be fully integrated with the engineering functions. The description of these disciplines and their relationship to the overall management life cycle are defined in other NASA directives; for example, the safety, reliability, maintainability, and quality assurance requirements are defined in the 8700 series of directives, and health and medical requirements are defined in the 8900 series. To that end, this document contains human systems integration language and requirements. (See NASA Standard 3001, NASA Space Flight Human System Standard, and NPR 8705.2, Human-Rating Requirements for Space Systems.)
NPR 7123.1B -- Preface Verify Current version before use at:
http://nodis3.gsfc.nasa.gov/ Page 5 of 157
NPR 7123.1B -- Preface Verify Current version befor use at:
http://nodis3.gsfc.nasa.gov/ Page 5 of 157
f. In this NPR, all mandatory actions (i.e., requirements) are denoted by statements containing the term "shall." The requirements are explicitly shown as [SE-XX] for clarity and tracking purposes.
The terms "may" or "can" denote discretionary privilege or permission, "should" denotes a good practice and is recommended but not required, "will" denotes expected outcome, and "are/is" denotes descriptive material.
g. In this NPR, all document citations are assumed to be the latest version, unless otherwise noted.
P.3 Authority
a. National Aeronautics and Space Act, as amended, 51 U.S.C. § 20113(a).
b. NPD 1000.0, NASA Governance and Strategic Management Handbook.
c. NPD 1000.3, The NASA Organization.
d. NPD 1001.0, NASA Strategic Plan.
e. NPD 7120.4, NASA Engineering and Program/Project Management Policy.
P.4 Applicable Documents and Forms
a. NPR 7120.5, NASA Space Flight Program and Project Management Requirements.
b. NPR 7120.7, NASA Information Technology and Institutional Infrastructure Program and Project Management Requirements.
c. NPR 7120.8, NASA Research and Technology Program and Project Management Requirements.
d. NPR 7150.2, NASA Software Engineering Requirements.
e. NPR 8705.2, Human-Rating Requirements for Space Systems.
f. NASA-STD-3001, NASA Space Flight Human System Standard.
P.5 Measurement/Verification
a. Compliance with this NPR will be documented by Center Directors in the SE NPR Compliance Matrix for Centers (Appendix H.1). Center self-assessment of compliance should be conducted approximately every two years or at the request of the Office of Chief Engineer (OCE). A copy of the Compliance Matrix is forwarded to the Office of the Chief Engineer. In addition, the OCE conducts periodic assessments at the Centers to obtain feedback on the effectiveness of NPR 7123.1 to facilitate updating the NPR.
b. Compliance for programs and projects is documented by appending a completed Compliance Matrix for this NPR (see Appendix H.2) to the Systems Engineering Management Plan (SEMP).
P.6 Cancellation NID 7123-69, NASA Interim Directive (NID) NASA Systems Engineering Processes and Requirements, dated March 13, 2012.
NPR 7123.1A, NASA Systems Engineering Processes and Requirements, w/Change 1 (11/04/09), NPR 7123.1B -- Preface Verify Current version before use at:
http://nodis3.gsfc.nasa.gov/ Page 6 of 157
NPR 7123.1B -- Preface Verify Current version befor use at:
http://nodis3.gsfc.nasa.gov/ Page 6 of 157 dated March 26, 2007.
/S/ Michael Ryschkewitsch Chief Engineer
NPR 7123.1B -- Preface Verify Current version before use at:
http://nodis3.gsfc.nasa.gov/ Page 7 of 157
NPR 7123.1B -- Preface Verify Current version befor use at:
http://nodis3.gsfc.nasa.gov/ Page 7 of 157
Chapter 1. Introduction
1.1 Background
1.1.1 Systems engineering at NASA requires the application of a systematic, disciplined engineering approach that is quantifiable, recursive, iterative, and repeatable for the development, operation, maintenance, and disposal of systems integrated into a whole throughout the life cycle of a project or program. The emphasis of systems engineering is on safely achieving stakeholder functional, physical, and operational performance requirements in the intended use environments over the system's planned life within cost and schedule constraints.
1.1.2 This document establishes the common technical processes for implementing NASA products and systems, as directed by NPD 7120.4, NASA Engineering and Program/Project Management Policy. Additionally, this NPR establishes the common NASA systems engineering technical model.
This document complements the administration, management, and review of all programs and projects, as specified in NPR 7120.5, NASA Space Flight Program and Project Management Requirements, NPR 7120.7, NASA Information Technology and Institutional Infrastructure Program and Project Management Requirements, and NPR 7120.8, NASA Research and Technology Program and Project Management Requirements.
1.1.3 The processes described in this document build upon and apply best practices and lessons learned from NASA, other governmental agencies, and industry to clearly delineate a successful model to complete comprehensive technical work, reduce program and technical risk, and improve mission success. The requirements and practices established in this NPR should be tailored and customized, respectively, per Paragraph 2.2.
1.1.4 Precedence
The order of precedence in case of conflict between requirements is 51 USC 20113(a) (1), National Aeronautics and Space Act of 1958, as amended; NPD 1000.0, NASA Governance and Strategic Management Handbook; NPD 1000.3, The NASA Organization; NPD 7120.4, NASA Engineering and Program/Project Management Policy; and NPR 7123.1, NASA Systems Engineering Processes and Requirements.
1.1.5 Figures
1.1.5.1 Figures within this NPR are not intended to be prescriptive but notional.
1.2 Framework for Systems Engineering Procedural
Requirements
1.2.1 Institutional requirements are the responsibility of the institutional authorities. They focus on how NASA does business and are independent of any particular program or project. These requirements are issued by NASA Headquarters and by Center organizations, and are normally documented in NASA Policy Directives (NPDs), NASA Procedural Requirements (NPRs), NASA Standards, Center Policy Directives (CPDs), Center Procedural Requirements (CPRs), and Mission Directorate (MD) requirements. Figure 1-1 shows the flow down from NPD 1000.0, NASA Governance and Strategic Management Handbook, through Program and Project Plans.
1.2.2 This NPR focuses on systems engineering processes and requirements. It is one of several
NPR 7123.1B -- Chapter1 Verify Current version before use at:
http://nodis3.gsfc.nasa.gov/ Page 8 of 157
NPR 7123.1B -- Chapter1 Verify Current version befor use at:
http://nodis3.gsfc.nasa.gov/ Page 8 of 157 related Engineering and Program/Project NPRs that flow down from NPD 7120.4, NASA Engineering and Program/Project Management Policy, as shown in Figure 1-2.
Figure 1-1 - Hierarchy of Related Documents
Figure 1-2 - Documentation Relationships
1.3 Framework for Systems Engineering Capability
1.3.1. The common systems engineering framework consists of three elements that make up NASA systems engineering capability. The relationship of the three elements is illustrated in Figure 1-3.
The integrated implementation of the three elements of the SE Framework is intended to improve the overall capability required for the efficient and effective engineering of NASA systems. The SE processes are one element of the larger context to produce quality products and achieve mission success. This NPR addresses the SE processes. The larger SE framework also includes the workforce
NPR 7123.1B -- Chapter1 Verify Current version before use at:
http://nodis3.gsfc.nasa.gov/ Page 9 of 157
NPR 7123.1B -- Chapter1 Verify Current version befor use at:
http://nodis3.gsfc.nasa.gov/ Page 9 of 157 and tools and methods. Additional initiatives to address these other elements include revision of the NASA handbook on systems engineering and development of tools and an assessment model.
Together, these elements comprise the capability of an organization to perform successful SE. Each element is described below.
Figure 1 3 - SE Framework
1.3.2. Element 1: Common Technical Processes. The common technical processes of this NPR provide what has to be done to engineer system products within a project and why. These processes are applied to the hardware, software, and human systems integration of a system as one integrated whole. In addition to the common technical processes, contributions to improvements of SE capability also come from the inclusion of:
a. Concepts and terminology that are basic to consistent application and communication of the common technical processes Agency wide.
b. A structure for when the common technical processes are applied.
1.3.3. Element 2: Tools and Methods. Tools and methods enable the efficient and effective completion of the activities and tasks of the common technical processes. An essential contribution of this element to SE capability is the improvement of the engineering infrastructure through the three Agency-wide activities listed below:
a. Infusion of advanced methods and tools in the SE processes to achieve greater efficiency, collaboration, and communication among distributed teams.
b. Provision of a NASA handbook on SE methodologies (NASA/SP-2007-6105, NASA Systems Engineering Handbook) that is a source for various methods and procedures that Centers can draw upon to plan implementation of the required processes in their projects.
c. Measurement of the SE capability of projects within NASA and assessment of the improvements of capability resulting from implementation of the SE NPR, use of adopted methods and tools, and workforce engineering training.
1.3.4. Element 3: Workforce. A well-trained, knowledgeable, and experienced technical workforce is essential for improving SE capability. The workforce must be able to apply NASA and Center methods and tools for the completion of the required SE processes within the context of the program or project to which they are assigned. In addition, they must be able to effectively communicate requirements and solutions to customers, other engineers, and management to work efficiently and effectively on a team. Issues of recruitment, retention, and training are aspects included in this element. The OCE will facilitate the training of the NASA workforce on the application of this and associated NPRs.
NPR 7123.1B -- Chapter1 Verify Current version before use at:
http://nodis3.gsfc.nasa.gov/ Page 10 of 157
NPR 7123.1B -- Chapter1 Verify Current version befor use at:
http://nodis3.gsfc.nasa.gov/ Page 10 of 157
1.4 Document Organization
1.4.1 This SE NPR is organized into the following chapters:
a. The Preface describes items such as the purpose, applicability, authority, and applicable documents of this SE NPR.
b. Chapter 1 (Introduction) describes the SE framework and document organization.
c. Chapter 2 describes the institutional and programmatic requirements, including roles and responsibilities. Tailoring of SE requirements and customization of SE practices are also addressed.
d. Chapter 3 describes the core set of common Agency-level technical processes and requirements for engineering NASA system products throughout the product life cycle. Appendix C contains supplemental amplifying material.
e. Chapter 4 describes the activities and requirements to be accomplished by assigned NASA technical teams or individuals (NASA employees and NASA support contractors) when performing technical oversight of a prime or other external contractor.
f. Chapter 5 describes the life-cycle and technical review requirements throughout the program and project life cycles. Appendix G contains entrance/success criteria guidance for each of the reviews.
g. Chapter 6 describes the Systems Engineering Management Plan, including the SEMP role, functions, and content. Appendix D provides details of a generic SEMP annotated outline.
NPR 7123.1B -- Chapter1 Verify Current version before use at:
http://nodis3.gsfc.nasa.gov/ Page 11 of 157
NPR 7123.1B -- Chapter1 Verify Current version befor use at:
http://nodis3.gsfc.nasa.gov/ Page 11 of 157
Chapter 2. Institutional and Programmatic Requirements
2.1 Roles and Responsibilities
2.1.1 General
The roles and responsibilities of senior management are defined in part in NPD 1000.0, NASA Governance and Strategic Management Handbook, and NPD 7120.4, NASA Engineering and Program/Project Management Policy. NPR 7120.5, NASA Space Flight Program and Project Management Requirements; NPR 7120.7, NASA Information Technology and Institutional Infrastructure Program and Project Management Requirements; NPR 7120.8, NASA Research and Technology Program and Project Management Requirements; and other NASA directives define the responsibilities of program and project managers. This NPR establishes systems engineering processes and responsibilities.
2.1.1.1 For programs and projects involving more than one Center, the lead organization will develop documentation for DGA approval to describe the hierarchy and reconciliation of Center plans implementing this NPR. The governing Mission Directorate or mission support office determines whether a Center executes a project in a lead role or in a supporting role. For Centers in supporting roles, compliance should be jointly negotiated and documented in the lead Center's project SEMP.
2.1.1.2 The roles and responsibilities associated with program and project management and Technical Authority (TA) are defined in the Program and Project Management NPRs (for example, NPR 7120.5 for space flight projects). Specific roles and responsibilities of the program/project manager and the engineering technical authority related to the SEMP are defined in Paragraphs 2.1.6 and 6.2.
2.1.2 Office of the Chief Engineer (OCE)
2.1.2.1 The OCE, under the authority of NPD 7120.4, will ensure compliance with this SE NPR.
2.1.2.2 The OCE will ensure systems engineering policies' compatibility across NASA.
2.1.3 Mission Directorate or Headquarters Program Offices
2.1.3.1 When programs and projects are managed at Headquarters or within Mission Directorates, that Program Office is responsible for the requirements in this NPR that are assigned to the Center Director. Technical teams residing at Headquarters will follow the requirements of this NPR unless specific process requirements have been established to implement this NPR by the governing organization. The technical teams residing at Centers will follow Center level process requirement documents.
2.1.4 Center Directors
2.1.4.1 In this document, the phrase "the Center Directors shall..." means the roles and responsibilities of the Center Directors may be further delegated within the organization to the scope and scale of the system.
2.1.4.2 The Center Director is responsible and accountable for both Institutional Authority responsibilities and the proper planning and execution of programs and projects assigned to the
NPR 7123.1B -- Chapter2 Verify Current version before use at:
http://nodis3.gsfc.nasa.gov/ Page 12 of 157
NPR 7123.1B -- Chapter2 Verify Current version befor use at:
http://nodis3.gsfc.nasa.gov/ Page 12 of 157
Center.
2.1.4.3 Center Directors shall perform the following activities:
a. Establish policies, procedures, and processes to execute the requirements of this SE NPR [SE-01].
b. Assess and take corrective actions to improve the execution of the requirements of this SE NPR
[SE-02].
c. Select appropriate standards applicable to projects under their control [SE-03].
d. Complete the compliance matrix, as tailored, in Appendix H.1 for those requirements owned by the Office of Chief Engineer, and provide to the OCE upon request [SE-04].
2.1.5 Technical Teams
2.1.5.1 Each technical team executes the Center processes to implement this SE NPR under the oversight of the Center Directors in accordance with the SEMP. The makeup and organization of each technical team is the responsibility of each Center or program and includes the personnel required to implement the project.
2.1.5.2 For those requirements owned by Center Directors, the technical team shall complete the compliance matrix in Appendix H.2 and include it in the SEMP [SE-05].
2.1.5.3 For systems that contain software, the technical team ensures that software developed within NASA or acquired complies with NPR 7150.2, NASA Software Engineering Requirements.
Note 1: NPR 7150.2 elaborates on the requirements in this document and determines the applicability of requirements based on the Agency's software classification. Note 2: NPD
7120.4 contains additional Agency requirements for the acquisition, development, maintenance, and management of software.
2.1.6 Designated Governing Authority
The Designated Governing Authority (DGA) for the technical effort in this SE NPR is the Center Director or the person that has been designated by the Center Director to ensure the appropriate level of technical management oversight. Such designation is made from the technical line so that independence between programmatic and technical authority is maintained. The DGA works with the Program/Project Manager to manage the technical effort. The DGA is assigned primary responsibility for evaluating the technical content of a particular program or project to ensure that it is meeting the commitments specified in the key technical management documents. The DGA shall approve the SEMP, waiver authorizations, and other key technical documents to ensure independent assessment of technical content [SE-06]. The DGA and the program/project manager approve the
SEMP.
Note 1: For large programs/projects, the DGA will typically be the associated independently funded Engineering Technical Authority (ETA). In the case of very small projects, DGA responsibilities are occasionally delegated to line managers or other technical experts who are not independently funded and do not serve in an official ETA capacity. If the DGA is not a recognized ETA, an ETA at the appropriate level will be required to approve the SEMP to ensure compliance with the Agency's technical authority process. Note 2: For NPR 7120.7 projects affecting more than one Center, the NASA Chief Information Officer (CIO) or the person the NASA CIO designates is the DGA.
NPR 7123.1B -- Chapter2 Verify Current version before use at:
http://nodis3.gsfc.nasa.gov/ Page 13 of 157
NPR 7123.1B -- Chapter2 Verify Current version befor use at:
http://nodis3.gsfc.nasa.gov/ Page 13 of 157
2.2 Tailoring and Customization
2.2.1 Tailoring SE Requirements
2.2.1.1 SE requirements tailoring is the process used to seek relief from SE NPR requirements consistent with program or project objectives, acceptable risk, and constraints.
2.2.1.2 The tailoring process (which can occur at any time in the program or project's life cycle) results in deviations or waivers to requirements depending on the timing of the request. Deviations and waivers of the requirements in this NPR can be submitted separately to the requirements owner or via the appropriate compliance matrix in Appendix H.
2.2.1.3 The results of a Center's tailoring of NPR 7123.1 SE requirements will be documented in the Compliance Matrix for Centers (Appendix H.1) and submitted to OCE upon request or as changes to the Center processes occur.
2.2.1.4 The results of the program/project Technical Team tailoring of SE requirements from either NPR 7123.1 or a particular Center's implementation of NPR 7123.1, whichever is applicable, will be documented in the next revision of the SEMP, along with supporting rationale and documented approvals from the requirement owner.
2.2.1.5 The appropriate requirement owner, as described in the compliance matrices (Appendix H) will have responsibility to approve or disapprove any SE NPR requirement that is tailored.
2.2.2 Customization of SE Practices
2.2.2.1 Customization is the modification of recommended SE practices that are used to accomplish the SE requirements. Examples of these practices are in Appendix C or in NASA/SP-2007-6105.
2.2.2.2 Technical teams are encouraged to customize their non-requirement SE practices. The results of this customization do not require waivers or deviations, but significant customization should be documented in the SEMP.
2.2.3 Considerations for Tailoring or Customization
2.2.3.1 Considerations for tailoring or customization should include: scope and visibility (e.g., organizations and partnerships involved, international agreements); risk tolerance and failure consequences; system size; system complexity (e.g., human spaceflight vs. flagship science vs.
subscale technology demonstration, number of stages and interfaces, technology readiness level);
impact on other systems; longevity; serviceability (including on-orbit); constraints (including cost, schedule, degree of insight/oversight permitted with partnerships or international agreements, etc.);
safety; technology base; and industrial base.
NPR 7123.1B -- Chapter2 Verify Current version before use at:
http://nodis3.gsfc.nasa.gov/ Page 14 of 157
NPR 7123.1B -- Chapter2 Verify Current version befor use at:
http://nodis3.gsfc.nasa.gov/ Page 14 of 157
Chapter 3. Requirements for Common Technical Processes
3.1 Introduction
3.1.1 This chapter establishes the core set of common technical processes and requirements to be used by NASA projects in engineering system products during all life-cycle phases to meet phase exit criteria and project objectives. The 17 common technical processes are enumerated according to their description in this chapter and their interactions shown in Figure 3-1. This SE common technical processes model illustrates the use of: (1) the system design processes for "top-down" design of each product in the system structure; (2) the product realization processes for "bottom-up" realization of each product in the system structure; and (3) the cross-cutting technical management processes for planning, assessing, and controlling the implementation of the system design and product realization processes and to guide technical decision making (decision analysis). The SE common technical processes model is referred to as an "SE engine" in this SE NPR to stress that these common technical processes are used to drive the development of the system products and associated work products required by management to satisfy the applicable product life-cycle phase exit criteria while meeting stakeholder expectations within cost, schedule, and risk constraints.
3.1.2 This chapter identifies the following for each of the 17 common technical processes:
a. The specific requirement for Center Directors or designees to establish and maintain the process;
b. A brief description of how the process is used as an element of the Systems Engineering Engine;
and
c. A reference to typical practices for the process as identified in Appendix C.
3.1.3 It should be emphasized that the Practices for Common Technical Processes documented in Appendix C do not represent additional requirements that must be implemented by the technical team. Appendix C is provided as a summary of typical best practices associated with the 17 common technical processes. As such, it should be considered in conjunction with other sources of systems engineering guidance such as NASA/SP-2007-6105, NASA Systems Engineering Handbook, as the technical team develops a customized approach for the application of these processes consistent with requirements implemented by Center documentation.
NPR 7123.1B -- Chapter3 Verify Current version before use at:
http://nodis3.gsfc.nasa.gov/ Page 15 of 157
NPR 7123.1B -- Chapter3 Verify Current version befor use at:
http://nodis3.gsfc.nasa.gov/ Page 15 of 157
Figure 3 1 - Systems Engineering (SE) Engine
3.1.4 The context in which the common technical processes are used is provided below:
3.1.4.1 The common technical processes are applied to each product layer to concurrently develop the products that will satisfy the operational or mission functions of the system (end products) and that will satisfy the life-cycle support functions of the system (enabling products). In this document, product layer is defined as the product breakdown hierarchy that includes both the end product and enabling product hierarchy. The enabling products facilitate the activities of system design, product realization, operations and mission support, sustainment, and end-of-product-life disposal or recycling, by having the products and services available when needed.
3.1.4.2 The common technical processes are applied to design a system solution definition for each product layer down and across each level of the system structure and to realize the product layer end products up and across the system structure. Figure 3-2 illustrates how the three major sets of processes of the Systems Engineering (SE) Engine (system design processes, product realization processes, and technical management processes) are applied to each product layer within a system structure.
NPR 7123.1B -- Chapter3 Verify Current version before use at:
http://nodis3.gsfc.nasa.gov/ Page 16 of 157
NPR 7123.1B -- Chapter3 Verify Current version befor use at:
http://nodis3.gsfc.nasa.gov/ Page 16 of 157
Figure 3-2 - Application of SE Engine Common Technical Processes Within System Structure
3.1.4.3 The common technical processes are used to define the product layers of the system structure in each applicable phase of the relevant life cycle to generate work products and system products needed to satisfy the exit criteria of the applicable phase.
3.1.4.4 The common technical processes are applied by assigned technical teams and individuals trained in the requirements of this SE NPR.
3.1.4.5 The assigned technical teams and individuals are using the appropriate and available sets of tools and methods to accomplish required common technical process activities. This includes the use of modeling and simulation as applicable to the product phase, location of the product layer in the system structure, and the applicable phase exit criteria.
3.2 Requirements for the Common Technical Processes
3.2.1 For this section, "establish" means developing policy, work instructions, or procedures to implement process activities. "Maintain" includes planning the process, providing resources, assigning responsibilities, training people, managing configurations, identifying and involving stakeholders, and monitoring and controlling the process. The technical team is responsible for the execution of these 17 required processes per Paragraph 2.1.5.
3.2.2 Stakeholder Expectations Definition Process
3.2.2.1 Center Directors or designees shall establish and maintain a Stakeholder Expectations Definition process to include activities, requirements, guidelines, and documentation for the definition of stakeholder expectations for the applicable product layer [SE-07].
3.2.2.2 The stakeholder expectations definition process is used to elicit and define use cases, scenarios, concept of operations, and stakeholder expectations for the applicable product life- cycle phases and product layer. This includes expectations such as: (a) operational end products and
NPR 7123.1B -- Chapter3 Verify Current version before use at:
http://nodis3.gsfc.nasa.gov/ Page 17 of 157
NPR 7123.1B -- Chapter3 Verify Current version befor use at:
http://nodis3.gsfc.nasa.gov/ Page 17 of 157 life-cycle-enabling products of the product layer; (b) affordability; (c) operator or user interfaces; (d) expected skills and capabilities of operators or users; (e) expected number of simultaneous users; (f) system and human performance criteria; (g) technical authority, standards, regulations, and laws; (h) factors such as health and safety, planetary protection, orbital debris, quality, security, context of use by humans, reliability, availability, maintainability, electromagnetic compatibility, interoperability, testability, transportability, supportability, usability, and disposability; and (i) local management constraints on how work will be done (e.g., operating procedures). The baselined stakeholder expectations are used for validation of the product layer end product during product realization. At this point, Measures of Effectiveness (MOEs) are defined.
3.2.2.3 Typical practices of this process are defined in Appendix C.1.1.
3.2.3 Technical Requirements Definition Process
3.2.3.1 Center Directors or designees shall establish and maintain a Technical Requirements Definition process to include activities, requirements, guidelines, and documentation for the definition of technical requirements from the set of agreed upon stakeholder expectations for the applicable product layer [SE-08].
3.2.3.2 The technical requirements definition process is used to transform the baselined stakeholder expectations into unique, quantitative, and measurable technical requirements expressed as "shall" statements that can be used for defining a design solution for the product layer end product and related enabling products. This process also includes validation of the requirements to ensure that the requirements are well-formed (clear and unambiguous), complete (agrees with customer and stakeholder needs and expectations), consistent (conflict free), and individually verifiable and traceable to a higher level requirement or goal. As part of this process, Measures of Performance (MOPs) and Technical Performance Measures (TPMs) are defined.
3.2.3.3 Typical practices of this process are defined in Appendix C.1.2.
3.2.4 Logical Decomposition Process
3.2.4.1 Center Directors or designees shall establish and maintain a Logical Decomposition process to include activities, requirements, guidelines, and documentation for logical decomposition of the validated technical requirements of the applicable product layer [SE-09].
3.2.4.2 The logical decomposition process is used to improve understanding of the defined technical requirements and the relationships among the requirements (e.g., functional, behavioral, performance, and temporal) and to transform the defined set of technical requirements into a set of logical decomposition models and their associated set of derived technical requirements for lower levels of the system and for input to the design solution definition process.
3.2.4.3 Typical practices of this process are defined in Appendix C.1.3.
3.2.5 Design Solution Definition Process
3.2.5.1 Center Directors or designees shall establish and maintain a Design Solution Definition process to include activities, requirements, guidelines, and documentation for designing product solution definitions within the applicable product layer that satisfy the derived technical requirements [SE-10].
3.2.5.2 The design solution definition process is used to translate the outputs of the logical decomposition process into a design solution definition that is in a form consistent with the product life-cycle phase and product layer location in the system structure and that will satisfy phase exit criteria. This includes transforming the defined logical decomposition models and their associated
NPR 7123.1B -- Chapter3 Verify Current version before use at:
http://nodis3.gsfc.nasa.gov/ Page 18 of 157
NPR 7123.1B -- Chapter3 Verify Current version befor use at:
http://nodis3.gsfc.nasa.gov/ Page 18 of 157 sets of derived technical requirements into alternative solutions, then analyzing each alternative to be able to select a preferred alternative, and fully defining that alternative into a final design solution definition that will satisfy the requirements.
3.2.5.3 These design solution definitions will be used for generating end products either by using the product implementation process or product integration process as a function of the position of the product layer in the system structure and whether there are additional subsystems of the end product that need to be defined. The output definitions from the design solution (end product specifications) will be used for conducting product verification.
3.2.5.4 Typical practices of this process are defined in Appendix C.1.4.
3.2.6 Product Implementation Process
3.2.6.1 Center Directors or designees shall establish and maintain a Product Implementation process to include activities, requirements, guidelines, and documentation for implementation of a design solution definition by making, buying, or reusing an end product of the applicable product layer
[SE-11].
3.2.6.2 The product implementation process is used to generate a specified product of a product layer through buying, making, or reusing in a form consistent with the product life-cycle phase exit criteria and that satisfies the design solution definition (e.g., drawings, specifications).
3.2.6.3 Typical practices of this process are defined in Appendix C.2.1.
3.2.7 Product Integration Process
3.2.7.1 Center Directors or designees shall establish and maintain a Product Integration process to include activities, requirements, guidelines, and documentation for the integration of lower level products into an end product of the applicable product layer in accordance with its design solution definition [SE-12].
3.2.7.2 The product integration process is used to transform lower level, validated end products into the desired end product of the higher level product layer through assembly and integration.
3.2.7.3 Typical practices of this process are defined in Appendix C.2.2.
3.2.8 Product Verification Process
3.2.8.1 Center Directors or designees shall establish and maintain a Product Verification process to include activities, requirements/specifications, guidelines, and documentation for verification of end products generated by the product implementation process or product integration process against their design solution definitions [SE-13].
3.2.8.2 The product verification process is used to demonstrate that an end product generated from product implementation or product integration conforms to its design solution definition requirements as a function of the product life-cycle phase and the location of the product layer end product in the system structure. Special attention is given to demonstrating satisfaction of the MOPs defined for each MOE during conduct of the technical requirements definition process.
3.2.8.3 Typical practices of this process are defined in Appendix C.2.3.
3.2.9 Product Validation Process
3.2.9.1 Center Directors or designees shall establish and maintain a Product Validation process to include activities, requirements, guidelines, and documentation for validation of end products generated by the product implementation process or product integration process against their
NPR 7123.1B -- Chapter3 Verify Current version before use at:
http://nodis3.gsfc.nasa.gov/ Page 19 of 157
NPR 7123.1B -- Chapter3 Verify Current version befor use at:
http://nodis3.gsfc.nasa.gov/ Page 19 of 157 stakeholder expectations [SE-14].
3.2.9.2 The product validation process is used to confirm that a verified end product generated by product implementation or product integration fulfills (satisfies) its intended use when placed in its intended environment and to ensure that any anomalies discovered during validation are appropriately resolved prior to delivery of the product (if validation is done by the supplier of the product) or prior to integration with other products into a higher level assembled product (if validation is done by the receiver of the product). The validation is done against the set of baselined stakeholder expectations. Special attention should be given to demonstrating satisfaction of the MOEs identified during conduct of the stakeholder expectations definition process. The type of product validation is a function of the form of the product and product life-cycle phase and in accordance with an applicable customer agreement.
3.2.9.3 Typical practices of this process are defined in Appendix C.2.4.
3.2.10 Product Transition Process
3.2.10.1 Center Directors or designees shall establish and maintain a Product Transition process to include activities, requirements, guidelines, and documentation for transitioning end products to the next higher level product layer customer or user [SE-15].
3.2.10.2 The product transition process is used to transition a verified and validated end product that has been generated by product implementation or product integration to the customer at the next level in the system structure for integration into an end product or, for the top level end product, transitioned to the intended end user. The form of the product transitioned will be a function of the product life-cycle phase and the location within the system structure of the product layer in which the end product exists.
3.2.10.3 Typical practices of this process are defined in Appendix C.2.5.
3.2.11 Technical Planning Process
3.2.11.1 Center Directors or designees shall establish and maintain a Technical Planning process to include activities, requirements, guidelines, and documentation for planning the technical effort
[SE-16].
3.2.11.2 The technical planning process is used to plan for the application and management of each common technical process. It is also used to identify, define, and plan the technical effort applicable to the product life-cycle phase for product layer location within the system structure and to meet project objectives and product life-cycle phase exit criteria. A key document generated by this process is the SEMP (See Chapter 6).
3.2.11.3 Typical practices of this process are defined in Appendix C.3.1.
3.2.12 Requirements Management Process
3.2.12.1 Center Directors or designees shall establish and maintain a Requirements Management process to include activities, requirements, guidelines, and documentation for management of requirements throughout the system life cycle [SE-17].
3.2.12.2 The requirements management process is used to: (a) manage the product requirements identified, baselined, and used in the definition of the product layer products during system design;
(b) provide bidirectional traceability back to the top product layer requirements; and (c) manage the changes to established requirement baselines over the life cycle of the system products.
3.2.12.3 Typical practices of this process are defined in Appendix C.3.2.
NPR 7123.1B -- Chapter3 Verify Current version before use at:
http://nodis3.gsfc.nasa.gov/ Page 20 of 157
NPR 7123.1B -- Chapter3 Verify Current version befor use at:
http://nodis3.gsfc.nasa.gov/ Page 20 of 157
3.2.13 Interface Management Process
3.2.13.1 Center Directors or designees shall establish and maintain an Interface Management process to include activities, requirements, guidelines, and documentation for management of the interfaces defined and generated during the application of the system design processes [SE-18].
3.2.13.2 The interface management process is used to: (a) establish and use formal interface management to assist in controlling system product development efforts when the efforts are divided between Government programs, contractors, and/or geographically diverse technical teams within the same program or project; and (b) maintain interface definition and compliance among the end products and enabling products that compose the system, as well as with other systems with which the end products and enabling products must interoperate.
3.2.13.3 Typical practices of this process are defined in Appendix C.3.3.
3.2.14 Technical Risk Management Process
3.2.14.1 Center Directors or designees shall establish and maintain a Technical Risk Management process to include activities, requirements, guidelines, and documentation for management of the risk identified during the technical effort [SE-19].
3.2.14.2 The technical risk management process is used to make risk-informed decisions and examine, on a continuing basis, the potential for deviations from the project plan and the consequences that could result should they occur. This enables risk-handling activities to be planned and invoked as needed across the life of the product or project to mitigate impacts on achieving product life-cycle phase exit criteria and meeting technical objectives. The technical team supports the development of potential health and safety, cost, and schedule impacts for identified technical risks and any associated mitigation strategies. NPR 8000.4, Agency Risk Management Procedural Requirements, is to be used as a source document for defining this process and NPR 8705.5, Technical Probabilistic Risk Assessment (PRA) Procedures for Safety and Mission Success for NASA Programs and Projects, provides one means of identifying and assessing technical risk. While the focus of this requirement is the management of technical risk, the process applies to the management of programmatic risks as well. The highly interdependent nature of health and safety, technical, cost, and schedule risks require the broader program/project team to consistently address risk management with an integrated approach. NASA/SP-2011-3422, NASA Risk Management Handbook, provides guidance for managing risk in an integrated fashion.
3.2.14.3 Typical practices of this process are defined in Appendix C.3.4.
3.2.15 Configuration Management Process
3.2.15.1 Center Directors or designees shall establish and maintain a Configuration Management process to include activities, requirements, guidelines, and documentation for configuration management [SE-20].
3.2.15.2 The configuration management process for end products, enabling products, and other work products placed under configuration control is used to: (a) identify the…
This is the start of the file's text. The full file is on GovTribe.