This document provides construction drawings for the renovation of the drives, walks, and parking lot at the Robert Cotton Correctional Facility in Jackson, Michigan. The project scope includes replacement of bituminous parking areas, concrete paving, and a staff courtyard area. The project is being managed by the Department of Technology, Management and Budget - State Facilities Administration Design and Construction Division on behalf of the Michigan Department of Corrections. Construction is planned to be completed in three phases, with Phase 1 required to be finished in 2024. The project requires the contractor to provide a detailed phasing and staging plan, and coordinate construction activities to maintain access and operations at the facility.
The construction documents include specifications for demolition, site preparation, paving, grading, utilities, signage, and landscaping. Benchmark information and site survey data are provided. Pricing details and funding sources are not included in the document. The procurement process requires bidder submissions through the SIGMA VSS system, with questions to be directed to the project architect. No set-aside or incumbent contractor information is provided.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
M C
SA
G
R O
U P, I N
C
A rc hi te ct ur e
Pa rk
R ec re at io n Pl an ni ng
L an ds ca pe A rc hi te ct ur e
(6
)4
-3 w w .m cs ag ro up
.c om
G re en w oo d
A ve nu e
S.
E
E as t G ra nd
R ap id s, M I
D ow nt ow n
Pl an
I nt er io r
D es ig n
Sp or ts
F ac ili ty
P la nn in g
D
EP
A R
TM
EN
T O
F
TE
C H
N O
LO
G
Y , M
A N
A G
EM
EN
T A
N D
B U
D G
ET
ST
A
TE
O
F M
IC
H
IG
A
N
A D
A M
P . L
A C
H , R
A , D
IR
EC
TO
R
ST
A
TE
F
A C
IL
IT
IE
S
A D
M
IN
IS
TR
A
TI
O N
D
ES
IG
N
A N
D C
O N
ST
R
U C
TI
O
N D
IV
IS
IO
N
AutoCAD SHX Text
DRIVES, WALKS, PARKING LOT RENO
AutoCAD SHX Text
3500 N ELM AVE JACKSON, MI 49201
AutoCAD SHX Text
ARCHITECT PROJECT#
AutoCAD SHX Text
SHEET
AutoCAD SHX Text
PRELIMINARY
AutoCAD SHX Text
CONSTRUCTION
AutoCAD SHX Text
FINAL RECORD
AutoCAD SHX Text
ISSUED FOR
AutoCAD SHX Text
IDENTIFICATION NO.
AutoCAD SHX Text
DATE
AutoCAD SHX Text
AutoCAD SHX Text
BID SET 03.04.2024
AutoCAD SHX Text THIS DOCUMENT AND CONTENT ARE THE EXCLUSIVE PROPERTY OF MCSAGROUP,INC. AND MAY NOT BE UTILIZED OR REPRODUCED WITHOUT THE WRITTEN PERMISSION OF MCSAGROUP,INC. COPYRIGHT (C) 2021
AutoCAD SHX Text
ROBERT COTTON CORRECTIONAL FACILITY
AutoCAD SHX Text
STATE FILE #
AutoCAD SHX Text
472/20020.RWG
AutoCAD SHX Text X
AutoCAD SHX Text P
AutoCAD SHX Text L
AutoCAD SHX Text U
AutoCAD SHX Text R
AutoCAD SHX Text I
AutoCAD SHX Text B
AutoCAD SHX Text U
AutoCAD SHX Text E
AutoCAD SHX Text S
AutoCAD SHX Text U
AutoCAD SHX Text N
AutoCAD SHX Text U
AutoCAD SHX Text M
AutoCAD SHX Text C
AutoCAD SHX Text I
AutoCAD SHX Text R
AutoCAD SHX Text C
AutoCAD SHX Text U
AutoCAD SHX Text M
AutoCAD SHX Text S
AutoCAD SHX Text P
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text E
AutoCAD SHX Text S
AutoCAD SHX Text I
AutoCAD SHX Text Q
AutoCAD SHX Text U
AutoCAD SHX Text E
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text I
AutoCAD SHX Text S
AutoCAD SHX Text P
AutoCAD SHX Text E
AutoCAD SHX Text N
AutoCAD SHX Text I
AutoCAD SHX Text N
AutoCAD SHX Text S
AutoCAD SHX Text U
AutoCAD SHX Text L
AutoCAD SHX Text A
AutoCAD SHX Text M
AutoCAD SHX Text A
AutoCAD SHX Text M
AutoCAD SHX Text O
AutoCAD SHX Text E
AutoCAD SHX Text N
AutoCAD SHX Text A
AutoCAD SHX Text M
AutoCAD SHX Text Architect:
AutoCAD SHX Text Owner:
AutoCAD SHX Text Arch. Project No. 2192
AutoCAD SHX Text Date: March 4, 2024
AutoCAD SHX Text T1 TITLE SHEET TITLE SHEET C1.1-C1.2 OVERALL SITE, PHASING AND STAGING PLANS OVERALL SITE, PHASING AND STAGING PLANS C2.1-C2.4 SITE PLAN ENLARGEMENT SITE PLAN ENLARGEMENT C3.1-C3.3 EXISTING CONDITIONS AND REMOVALS EXISTING CONDITIONS AND REMOVALS C4.1- C4.10 LAYOUT PLANS C4.10 LAYOUT PLANS LAYOUT PLANS C5.1-C5.10 GRADING, UTILITY AND SESC PLANS GRADING, UTILITY AND SESC PLANS C6.1 STAFF COURTYARD PLANTING PLAN STAFF COURTYARD PLANTING PLAN C7.1 STRIPING AND SIGNAGE PLAN STRIPING AND SIGNAGE PLAN C8.1- C8.7 CONSTRUCTION DETAILS C8.7 CONSTRUCTION DETAILS CONSTRUCTION DETAILS C9.1- C9.4 SITE SURVEYC9.4 SITE SURVEYSITE SURVEY
AutoCAD SHX Text N
AutoCAD SHX Text
NTS
AutoCAD SHX Text
%%UROBERT COTTON CORRECTIONAL CAMPUS MAP
AutoCAD SHX Text 3500 N Elm Ave, Jackson, MI 49201
AutoCAD SHX Text
PROJECT DESCRIPTION
AutoCAD SHX Text THE PROJECT SCOPE INCLUDES REPLACEMENT OF BITUMINOUS PARKING AREAS, CONCRETE PAVING AND STAFF COURTYARD AREA.
AutoCAD SHX Text
APPLICABLE CODES
AutoCAD SHX Text MDTMB/MDOC- G. ROBERT COTTON CORRECTIONAL DRIVES, WALKS AND PARKING LOT RENOVATIONS
AutoCAD SHX Text
MCSA GROUP, INC
AutoCAD SHX Text
MDTMB - STATE OF MICHIGAN
AutoCAD SHX Text State Facilities Administration Design and Construction Division 3111 W. St. Joseph Street Lansing, Michigan 48917
AutoCAD SHX Text Sheet Index:
AutoCAD SHX Text State File No.
AutoCAD SHX Text
472/20020.RWG
AutoCAD SHX Text T1
AutoCAD SHX Text 529 Greenwood Avenue SE East Grand Rapids, Michigan 49506 616-451-3346
AutoCAD SHX Text Bid Set
AutoCAD SHX Text
2015 MICHIGAN BUILDING CODE
AutoCAD SHX Text Surveying and
AutoCAD SHX Text
LRE
AutoCAD SHX Text 2121 3 Mile Rd. NW. Walker, MI 49544 616-301-7888
AutoCAD SHX Text Civil Engineer:
AutoCAD SHX Text Geotechnical and
AutoCAD SHX Text
SOILS + STRUCTURES
AutoCAD SHX Text 6480 Grand Haven Road Muskegon, MI 49441 800-933-3959
AutoCAD SHX Text Structural Engineer:
N.
E
LM
A
VE
NU
E
E. PARNALL ROAD
BENCHMARK INFORMATION
M C
SA
G
R O
U P, I N
C
A rc hi te ct
R ec re at io n Pl an ds ca pe A rc hi te ct ur e
(6
)4
-3 w .m cs ag ro up
.c om
G re en w oo d
A ve nu e
S.
E
E as t G ra nd
R ap id s, M I
D ow nt ow n
Pl an er io r
D es ts
F ac ili ty
P la nn in g
D
EP
A R
TM
EN
T O
F
TE
C H
N O
LO
G
Y , M
A N
A G
EM
EN
T A
N D
B U
D G
ET
ST
A
TE
O
F M
IC
H
IG
A
N
A D
A M
P . L
A C
H , R
A , D
IR
EC
TO
R
ST
A
TE
F
A C
IL
IT
IE
S
A D
M
IN
IS
TR
A
TI
O N
D
ES
IG
N
A N
D C
O N
ST
R
U C
TI
O
N D
IV
IS
IO
N
AutoCAD SHX Text D8
AutoCAD SHX Text
AutoCAD SHX Text 938.15
AutoCAD SHX Text
DUMPSTER
AutoCAD SHX Text
BIT.
AutoCAD SHX Text
ALARM POLE
AutoCAD SHX Text
BM#1
AutoCAD SHX Text
BM#4
AutoCAD SHX Text
BM#3
AutoCAD SHX Text
BM#5
AutoCAD SHX Text
BM#6
AutoCAD SHX Text
BM#10
AutoCAD SHX Text
BM#9
AutoCAD SHX Text
BM#8
AutoCAD SHX Text
BM#7
AutoCAD SHX Text
BM#2
AutoCAD SHX Text cbs
AutoCAD SHX Text
AutoCAD SHX Text 0.00
AutoCAD SHX Text
BM#11
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
#700 BLDG.
AutoCAD SHX Text
#400 BLDG.
AutoCAD SHX Text
#300 BLDG.
AutoCAD SHX Text
#200 BLDG.
AutoCAD SHX Text
#600 BLDG.
AutoCAD SHX Text
#500 BLDG.
AutoCAD SHX Text #T100
AutoCAD SHX Text
EXISTING BLDG.
AutoCAD SHX Text
#100 BLDG.
AutoCAD SHX Text SALLY PORT CONCRETE REPLACEMENT SHALL BE COMPLETED BEGINNING FRIDAY AT 12 NOON TO MONDAY AT 7 AM. REMOVALS MAY OCCUR OUTSIDE OF THIS WINDOW PROVIDED THERE IS ADEQUATE BASE MATERIAL TO ALLOW FOR DELIVERIES. HALF OF THE FENCED AREA SHALL BE COMPLETED AT A TIME WITH THE SAME COMPLETION SCHEDULE TRAFFIC SHALL BE MAINTAINED ON THE SALLY PORT AT HALF DURING CONTRUCTION
AutoCAD SHX Text
1/2 OF SEGREGATION YARD TO BE COMPLETED AT A TIME.
AutoCAD SHX Text BM#1) ELEVATION: 934.92 SE BOLT ON LIGHT POST ALONG SOUTH SIDE OF ENTRY DRIVE FROM N. ELM AVE. BM#2) ELEVATION: 937.93 NE. FLANGE BOLT UNDER "E" ON HYDRANT NE. OF BLDG. #700 BM#3) ELEVATION: 936.47 NE. FLANGE BOLT UNDER "E" ON HYDRANT EAST OF BLDG. #700 BY PARKING LOT BM#4) ELEVATION: 937.94 NE. FLANGE BOLT UNDER "E" ON HYDRANT SOUTH OF BLDG. #700 BM#5) ELEVATION: 938.73 SE. FLANGE BOLT UNDER "E" ON HYDRANT NE. OF BLDG. #400 BM#6) ELEVATION: 934.01 NE. FLANGE BOLT UNDER "E" ON HYDRANT NW. OF BLDG. #500 BM#7) ELEVATION: 935.14 NE. FLANGE BOLT ON TOP BOLT OF HYDRANT NW. OF BLDG. #600 BM#8) ELEVATION: 936.02 NE. FLANGE BOLT UNDER "E" ON HYDRANT N. OF BLDG. #200 BM#9) ELEVATION: 937.12 NE. FLANGE BOLT UNDER "E" ON HYDRANT NE. OF BLDG. #100 BM#10) ELEVATION: 937.76 NE. FLANGE BOLT UNDER "E" ON HYDRANT S. OF BLDG. #200 BM#11) ELEVATION: 937.63 NE. FLANGE BOLT UNDER "E" ON HYDRANT W. OF BLDG. #400 THE ELEVATIONS ARE BASED ON NAVD 88
AutoCAD SHX Text
DRIVES, WALKS, PARKING LOT RENO
AutoCAD SHX Text
3500 N ELM AVE JACKSON, MI 49201
AutoCAD SHX Text
ARCHITECT PROJECT#
AutoCAD SHX Text
SHEET
AutoCAD SHX Text
PRELIMINARY
AutoCAD SHX Text
CONSTRUCTION
AutoCAD SHX Text
FINAL RECORD
AutoCAD SHX Text
ISSUED FOR
AutoCAD SHX Text
IDENTIFICATION NO.
AutoCAD SHX Text
DATE
AutoCAD SHX Text
AutoCAD SHX Text
BID SET 03.04.2024
AutoCAD SHX Text THIS DOCUMENT AND CONTENT ARE THE EXCLUSIVE PROPERTY OF MCSAGROUP,INC. AND MAY NOT BE UTILIZED OR REPRODUCED WITHOUT THE WRITTEN PERMISSION OF MCSAGROUP,INC. COPYRIGHT (C) 2021
AutoCAD SHX Text
ROBERT COTTON CORRECTIONAL FACILITY
AutoCAD SHX Text
STATE FILE #
AutoCAD SHX Text
472/20020.RWG
AutoCAD SHX Text X
AutoCAD SHX Text P
AutoCAD SHX Text L
AutoCAD SHX Text U
AutoCAD SHX Text R
AutoCAD SHX Text I
AutoCAD SHX Text B
AutoCAD SHX Text U
AutoCAD SHX Text E
AutoCAD SHX Text S
AutoCAD SHX Text U
AutoCAD SHX Text N
AutoCAD SHX Text U
AutoCAD SHX Text M
AutoCAD SHX Text C
AutoCAD SHX Text I
AutoCAD SHX Text R
AutoCAD SHX Text C
AutoCAD SHX Text U
AutoCAD SHX Text M
AutoCAD SHX Text S
AutoCAD SHX Text P
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text E
AutoCAD SHX Text S
AutoCAD SHX Text I
AutoCAD SHX Text Q
AutoCAD SHX Text U
AutoCAD SHX Text E
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text I
AutoCAD SHX Text S
AutoCAD SHX Text P
AutoCAD SHX Text E
AutoCAD SHX Text N
AutoCAD SHX Text I
AutoCAD SHX Text N
AutoCAD SHX Text S
AutoCAD SHX Text U
AutoCAD SHX Text L
AutoCAD SHX Text A
AutoCAD SHX Text M
AutoCAD SHX Text A
AutoCAD SHX Text M
AutoCAD SHX Text O
AutoCAD SHX Text E
AutoCAD SHX Text N
AutoCAD SHX Text A
AutoCAD SHX Text M
AutoCAD SHX Text N
AutoCAD SHX Text
SCALE: 1" = 80'
AutoCAD SHX Text
OVERALL SITE PLAN/ SHEET KEY REFRENCE
AutoCAD SHX Text
OVERALL SITE PLAN/ SHEET KEY REFERENCE
AutoCAD SHX Text C1.1
AutoCAD SHX Text OVERALL SITE PLAN NOTES 1. SEE SHEET KEY REFERENCE PLANS ON EACH SHEET FOR MATCH LINES. 2. SEE SHEET C4.1 AND C5.1 FOR KEY PLANS AND REFERENCE PLANS FOR LAYOUT AND GRADING. 3. SEE DETAIL 3 OF SHEET C8.7 FOR SEALCOAT AREA PLAN.
AutoCAD SHX Text
SITE PLAN 2.1
AutoCAD SHX Text
SITE PLAN 2.2
AutoCAD SHX Text
SITE PLAN 2.3
COURTYARD PLANTING PLAN 6.1
N.
E
LM
A
VE
NU
E
E. PARNALL ROAD
M C
SA
G
R O
U P, I N
C
A rc hi te ct
R ec re at io n Pl an ds ca pe A rc hi te ct ur e
(6
)4
-3 w .m cs ag ro up
.c om
G re en w oo d
A ve nu e
S.
E
E as t G ra nd
R ap id s, M I
D ow nt ow n
Pl an er io r
D es ts
F ac ili ty
P la nn in g
D
EP
A R
TM
EN
T O
F
TE
C H
N O
LO
G
Y , M
A N
A G
EM
EN
T A
N D
B U
D G
ET
ST
A
TE
O
F M
IC
H
IG
A
N
A D
A M
P . L
A C
H , R
A , D
IR
EC
TO
R
ST
A
TE
F
A C
IL
IT
IE
S
A D
M
IN
IS
TR
A
TI
O N
D
ES
IG
N
A N
D C
O N
ST
R
U C
TI
O
N D
IV
IS
IO
N
AutoCAD SHX Text D8
AutoCAD SHX Text
AutoCAD SHX Text 938.15
AutoCAD SHX Text
DUMPSTER
AutoCAD SHX Text
BIT.
AutoCAD SHX Text
ALARM POLE
AutoCAD SHX Text
BM#1
AutoCAD SHX Text
BM#4
AutoCAD SHX Text
BM#3
AutoCAD SHX Text
BM#5
AutoCAD SHX Text
BM#6
AutoCAD SHX Text
BM#10
AutoCAD SHX Text
BM#9
AutoCAD SHX Text
BM#8
AutoCAD SHX Text
BM#7
AutoCAD SHX Text
BM#2
AutoCAD SHX Text cbs
AutoCAD SHX Text
AutoCAD SHX Text 0.00
AutoCAD SHX Text
BM#11
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
PHASE 1 AREA
AutoCAD SHX Text
PHASE 1 AND 2 STAGING AREA
AutoCAD SHX Text
PHASE 3 STAGING AREA
AutoCAD SHX Text
PHASE 3 AREA
AutoCAD SHX Text
PHASE 2 AREA
AutoCAD SHX Text
#700 BLDG.
AutoCAD SHX Text
#400 BLDG.
AutoCAD SHX Text
#300 BLDG.
AutoCAD SHX Text
#200 BLDG.
AutoCAD SHX Text
#600 BLDG.
AutoCAD SHX Text
#500 BLDG.
AutoCAD SHX Text #T100
AutoCAD SHX Text
EXISTING BLDG.
AutoCAD SHX Text
#100 BLDG.
AutoCAD SHX Text CONCRETE WORK SHALL BE COMPLETED DURING THE HOURS OF 8 PM AND 4 AM SO THAT ACCESS TO ACTIVITIES AND EDUCATION REMAINS AT ALL TIMES.
AutoCAD SHX Text
ACTIVITY AND EDUCATION BUILDING
AutoCAD SHX Text
ACTIVITY AND EDUCATION BUILDING
AutoCAD SHX Text
STAFF COURTYARD
AutoCAD SHX Text SALLY PORT CONCRETE REPLACEMENT SHALL BE COMPLETED BEGINNING FRIDAY AT 12 NOON TO MONDAY AT 7 AM. REMOVALS MAY OCCUR OUTSIDE OF THIS WINDOW PROVIDED THERE IS ADEQUATE BASE MATERIAL TO ALLOW FOR DELIVERIES. HALF OF THE FENCED AREA SHALL BE COMPLETED AT A TIME WITH THE SAME COMPLETION SCHEDULE TRAFFIC SHALL BE MAINTAINED ON THE SALLY PORT AT HALF DURING CONTRUCTION
AutoCAD SHX Text
1/2 OF SEGREGATION YARD TO BE COMPLETED AT A TIME.
AutoCAD SHX Text
E PARNALL ROAD
AutoCAD SHX Text
ALTERNATE STAGING AREA
AutoCAD SHX Text
DRIVES, WALKS, PARKING LOT RENO
AutoCAD SHX Text
3500 N ELM AVE JACKSON, MI 49201
AutoCAD SHX Text
ARCHITECT PROJECT#
AutoCAD SHX Text
SHEET
AutoCAD SHX Text
PRELIMINARY
AutoCAD SHX Text
CONSTRUCTION
AutoCAD SHX Text
FINAL RECORD
AutoCAD SHX Text
ISSUED FOR
AutoCAD SHX Text
IDENTIFICATION NO.
AutoCAD SHX Text
DATE
AutoCAD SHX Text
AutoCAD SHX Text
BID SET 03.04.2024
AutoCAD SHX Text THIS DOCUMENT AND CONTENT ARE THE EXCLUSIVE PROPERTY OF MCSAGROUP,INC. AND MAY NOT BE UTILIZED OR REPRODUCED WITHOUT THE WRITTEN PERMISSION OF MCSAGROUP,INC. COPYRIGHT (C) 2021
AutoCAD SHX Text
ROBERT COTTON CORRECTIONAL FACILITY
AutoCAD SHX Text
STATE FILE #
AutoCAD SHX Text
472/20020.RWG
AutoCAD SHX Text X
AutoCAD SHX Text P
AutoCAD SHX Text L
AutoCAD SHX Text U
AutoCAD SHX Text R
AutoCAD SHX Text I
AutoCAD SHX Text B
AutoCAD SHX Text U
AutoCAD SHX Text E
AutoCAD SHX Text S
AutoCAD SHX Text U
AutoCAD SHX Text N
AutoCAD SHX Text U
AutoCAD SHX Text M
AutoCAD SHX Text C
AutoCAD SHX Text I
AutoCAD SHX Text R
AutoCAD SHX Text C
AutoCAD SHX Text U
AutoCAD SHX Text M
AutoCAD SHX Text S
AutoCAD SHX Text P
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text E
AutoCAD SHX Text S
AutoCAD SHX Text I
AutoCAD SHX Text Q
AutoCAD SHX Text U
AutoCAD SHX Text E
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text I
AutoCAD SHX Text S
AutoCAD SHX Text P
AutoCAD SHX Text E
AutoCAD SHX Text N
AutoCAD SHX Text I
AutoCAD SHX Text N
AutoCAD SHX Text S
AutoCAD SHX Text U
AutoCAD SHX Text L
AutoCAD SHX Text A
AutoCAD SHX Text M
AutoCAD SHX Text A
AutoCAD SHX Text M
AutoCAD SHX Text O
AutoCAD SHX Text E
AutoCAD SHX Text N
AutoCAD SHX Text A
AutoCAD SHX Text M
AutoCAD SHX Text N
AutoCAD SHX Text
SCALE: 1" = 80'
AutoCAD SHX Text
PHASING AND STAGING PLAN
AutoCAD SHX Text
OVERALL SITE, PLAN
AutoCAD SHX Text C1.2
AutoCAD SHX Text PHASING AND STAGING PLAN NOTES 1. EACH PHASE MUST BE COMPLETED WITH EACH PHASE MUST BE COMPLETED WITH NO OUTSTANDING CONSTRUCTION ITEMS PRIOR TO BEGINNING REMOVALS ON THE SUBSEQUENT PHASES. 2. PHASE 1 MUST BE COMPLETED IN 2024. PHASE 1 MUST BE COMPLETED IN 2024. EXTERIOR PAVING (EAST SIDE OF BUILDING #700 AND WEST SIDE OF BUILDING #400) MUST BE COMPLETED PRIOR TO INTERIOR PAVING (PAVING INSIDE FENCED AREA BETWEEN BUILDING #400 AND #700). 3. STAFF COURTYARD WORK MAY BE STAFF COURTYARD WORK MAY BE COMPLETED IN ANY PHASE. 4. STAGING AREAS AS SUGGESTED MAY STAGING AREAS AS SUGGESTED MAY BE MODIFIED WITH PERMISSION FROM DTMB AND DOL STAFF. 5. CONTRACTOR TO PROVIDE COMPLETE CONTRACTOR TO PROVIDE COMPLETE PHASING AND STAGING PLAN PRIOR TO RECEIPT OF FINAL CONTRACT. 6. DURING PHASE 2 AND 3, ACCESS TO DURING PHASE 2 AND 3, ACCESS TO PARKING (INCLUDING BARRIER FREE) SHALL BE MADE AVAILABLE TO STAFF AND VISITORS AT ALL TIMES. 7. CONCRETE WORK SHALL BE CONCRETE WORK SHALL BE COMPLETED DURING THE HOURS OF 8 PM AND 4 AM SO THAT ACCESS DOORS TO ACTIVITIES AND EDUCATION BUILDINGS (#200 AND #300) REMAINS AT ALL TIMES. 8. IN THE EVENT OF AN EMERGENCY, IN THE EVENT OF AN EMERGENCY, CONTRACTOR SHALL HAVE ON HAND MATERIALS TO ALLOW ACCESS FOR TRANSPORTATION FROM THE DORMITORIES.
AutoCAD SHX Text N
AutoCAD SHX Text
SCALE: 1" = 50'
AutoCAD SHX Text
ALTERNATE STAGING AREA
NOTE: ALTERNATE STAGING FOR USE IF NECESSARY. RESTORE AT COMPLETION OF PROJECT.