This is a Statement of Work (SOW) for the replacement of the MDF server room cooling system at Kayenta Health Care Center in Kayenta, Arizona. The project period runs from the award date through December 31, 2026. The contractor shall furnish all labor, materials, tools, equipment, supervision, and transportation to remove the existing dual Liebert PFH037A-AH7 precision cooling units and install two new six-ton Vertiv Liebert precision cooling systems configured for N+1 redundancy.
The scope of work includes recovering and removing existing refrigerant per EPA Section 608, furnishing and installing the new cooling systems with outdoor condensing units rated for low-ambient operation down to -20°F, installing indoor ceiling-mounted air handlers with integrated humidifiers and condensate drains, replacing refrigerant piping with pressure testing and evacuation, upgrading electrical disconnects and wiring to NEC standards, and integrating Liebert iCOM controls for environmental monitoring and redundancy coordination. The systems must maintain 20°C ± 2°C and 45% ± 5% relative humidity year-round with both humidification and dehumidification capability. All work must comply with ASHRAE TC 9.9, ASHRAE 90.1, DOE 10 CFR 431, GSA P-100, EPA Section 608, and NEC (NFPA 70). The contractor must provide factory-certified technicians, conduct full startup and commissioning testing, and deliver as-built drawings, operations and maintenance manuals, and training upon completion. Licensed HVAC and electrical contractors with minimum three comparable projects within five years are required, and all technicians must hold valid EPA Section 608 certification. Workmanship warranty is one year minimum with a five-year compressor warranty. Work hours are 8:00 AM to 5:00 PM Monday through Friday, excluding Federal Holidays, coordinated with Facility Maintenance to minimize disruption.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| IHS IEE Representation Form_Jan 2022_508 Compliant.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
TO:
MDF SERVER ROOM COOLING SYSTEM REPLACEMENT
AT:
KAYENTA HEALTH CARE CENTER
KAYENTA, ARIZONA
DATE:
NOVEMBER 19, 2025
PERIOD OF PERFORMANCE:
AWARD DATE – DECEMBER 31, 2026
DRAFT
INTRODUCTION
Kayenta Health Center (KHC) operates a critical Main Distribution Frame (MDF) server room that supports network, telecommunications, and medical data systems essential to healthcare operations. The existing Liebert precision cooling system has reached the end of its service life and no longer meets capacity requirements due to planned IT and server expansions. This project provides for a complete replacement and upgrade of the precision cooling systems to ensure reliable, year-round temperature and humidity control in compliance with federal, ASHRAE, and KHC facility standards.
BACKGROUND
The MDF room relies on dual Liebert PFH037A-AH7 units operating simultaneously to maintain a setpoint temperature of 20°C (68°F). During cold weather, the rooftop condensing units experience low-head pressure issues that reduce cooling performance. These issues, combined with increased server density, necessitate replacement with modern precision cooling systems featuring low-ambient operation and N+1 redundancy.
OBJECTIVE
Replace the existing cooling systems with two (2) new six-ton Vertiv Liebert precision cooling systems, configured for N+1 redundancy and equipped with integrated humidity control, energy-efficient operation, and low-ambient capability rated to -20°F (-29°C).
PERFORMANCE DESCRIPTION
The Contractor shall furnish all labor, materials, tools, equipment, supervision, and transportation to remove the existing systems and install new precision cooling equipment. All work shall be performed in accordance with ASHRAE TC 9.9, ASHRAE 90.1, DOE 10 CFR 431, GSA P-100, EPA Section 608, and NEC (NFPA 70). Work shall be coordinated with Facility Maintenance to minimize disruption.
SCOPE OF WORK
1. Recover refrigerant and remove existing indoor and outdoor units per EPA Section 608.
2. Furnish and install two (2) Vertiv Liebert six-ton precision cooling systems in N+1 configuration.
3. Provide outdoor condensing units rated for low-ambient operation (-20°F minimum) with variable-speed condenser fans.
4. Install indoor ceiling-mounted air handlers with integrated humidifiers and condensate drains.
5. Replace refrigerant piping, insulation, and supports; pressure test and evacuate per manufacturer requirements.
6. Verify and replace electrical disconnects, wiring, and breakers to meet NEC.
7. Integrate Liebert iCOM or approved equal controls for environmental monitoring and redundancy coordination.
8. Conduct full startup, testing, and commissioning with factory-certified technicians.
9. Provide as-built drawings, O&M manuals, and training upon project completion.
COLD WEATHER PERFORMANCE REQUIREMENTS
The system shall include features for reliable operation during low-ambient conditions:
- Low-ambient control package with stable operation to -20°F (-29°C).
- Variable-speed fans or fan cycling for head pressure control.
- Flooded condenser or equivalent head pressure management.
- Crankcase heaters and coil guards for rooftop applications.
- Field verification of head pressure stabilization during cold-weather commissioning.
HUMIDITY CONTROL AND DEHUMIDIFICATION
The precision cooling systems shall include integrated humidity control capable of both humidification and dehumidification to maintain 40–60% RH. Dehumidification shall occur via the cooling coil and reheat process, while humidification shall be achieved through electrode steam or infrared systems. Control shall be automatic via the Liebert iCOM to maintain 20°C ± 2°C and 45% ± 5% RH year-round.
COMPLIANCE REQUIREMENTS
- ASHRAE TC 9.9 – Thermal Guidelines for Data Processing Environments
- ASHRAE 90.1 and 62.1 – Energy and Ventilation Standards
- DOE 10 CFR 431 – Federal Energy Efficiency Standards
- GSA P-100 – Facilities Standards for Public Buildings
- Joint Commission EC.02.01.01, EC.02.05.01, and EC.02.05.07
- NEC (NFPA 70), EPA Section 608, and OSHA 29 CFR 1910
CONTRACTOR QUALIFICATIONS
All work shall be performed by licensed HVAC and electrical contractors with a minimum of three (3) comparable projects within the last five (5) years. All technicians shall hold valid EPA Section 608 certification for refrigerant handling.
REPORTING AND DOCUMENTATION
Contractor shall provide submittals for review and approval, daily construction logs, a safety plan, as-built drawings, and final testing reports.
TESTING AND COMMISSIONING
Final commissioning shall confirm temperature, humidity, and redundancy performance under supervision of the Facility Representative. The contractor shall submit signed verification reports prior to acceptance.
QUALITY CONTROL AND SAFETY
The Contractor shall follow KHC safety and infection control protocols, maintain a site-specific quality plan, and ensure all personnel carry visible identification and PPE. Work shall be coordinated to minimize patient and staff disruption.
ENVIRONMENTAL AND SITE RESTORATION
All disturbed areas, including roof penetrations, shall be restored to equal or better condition. Any roofing cuts or penetrations for piping or conduit shall be properly sealed and flashed per manufacturer specifications. All debris shall be removed daily.
GENERAL REQUIREMENTS
Work hours: 8:00 AM – 5:00 PM, Monday through Friday, excluding Federal Holidays. Alternate hours require Facility Representative approval. All areas shall be kept clean and restored after work completion.
PROJECT CLOSEOUT
Provide training for maintenance staff, warranty documentation, performance data, and commissioning results upon completion.
CONTACT INFORMATION
Desmond Jones – Supervisory General Engineer – (928) 697-5192 Vernon Begay – Maintenance Mechanic Supervisor – (928) 697-5194 Kendall Tanner – Maintenance Mechanic Supervisor – (928) 697-5193
WARRANTY
Workmanship Warranty: One (1) year or better.
Equipment Warranty: One (1) year minimum, five (5) years compressor warranty. Contractor shall guarantee full operational functionality and compliance upon final acceptance.
| STATEMENT OF WORK |
| INTRODUCTION |
| BACKGROUND |
| OBJECTIVE |
| PERFORMANCE DESCRIPTION |
| SCOPE OF WORK |
| COLD WEATHER PERFORMANCE REQUIREMENTS |
| HUMIDITY CONTROL AND DEHUMIDIFICATION |
| COMPLIANCE REQUIREMENTS |
| CONTRACTOR QUALIFICATIONS |
| REPORTING AND DOCUMENTATION |
| TESTING AND COMMISSIONING |
| QUALITY CONTROL AND SAFETY |
| ENVIRONMENTAL AND SITE RESTORATION |
| GENERAL REQUIREMENTS |
| PROJECT CLOSEOUT |
| CONTACT INFORMATION |
| WARRANTY |