SOW Indoor Play Area - 6 Aug 12.pdf
PDF 220 KB Posted
- Attached to
- FA4690-12-INDOORPLAYAREA Federal contract opportunity
- Solicitation number
- FY12_Indoor_Playground_Equip
About this file
Attachment 1 - Statement of Work 6 Aug 12
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 3 Response to question - 28 Aug 12.pdf | ||
| Photo 2 - Play room Door to be replaced with Double door.jpg | JPG image | |
| Photo 3 - View from corridor.jpg | JPG image | |
| Photo 1 - North and East walls.jpg | JPG image | |
| Amendment 2 Photographs - 27 Aug 12.pdf | ||
| Photo 4 - West wall sink removed pipes to be also.jpg | JPG image | |
| Amendment 1 Responses to Questions - 24 Aug 12.pdf | ||
| SOW Indoor Play Area - 24 Aug 12.pdf | ||
| SOW Indoor Play Area - 13 Aug 12.pdf | ||
| Indoor Play Area Floor Plan - 13 Aug 12.pdf | ||
| Indoor Play Area Floor Plan - 6 Aug 12.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
Indoor Play Area Library (Bldg 3910)
Project Number: FXBM 12-1048 6 Aug 2012
Summary
1. This project consists of installation of a new indoor play area in the Ellsworth AFB Library Bldg
3910. The target age group will be children 1 to 6 years old.
Description of Services
1. The Contractor shall perform design, provide, deliver, assemble, install, and certify an indoor play area in the Library on Ellsworth AFB, SD. All work shall be in accordance with federal, state, local laws, and regulations & guidelines established by the U.S. the American Society for Testing Materials (ASTM) for playground equipment (F1292, F1487, and F1951), the International Playground Equipment Manufacturing Association (IPEMA), the Consumer Product Safety Commission (CPSC), ADAAG, Public Playground Safety Handbook and this document.
General Information and Requirements
1. Project Title: Indoor Play Area – Library Bldg 3910
2. Project Number: FXBM 12-1048
a. Award Method: RFQ; Best Value; Award will be made to the Best Value offer meeting or exceeding the acceptability standards for non-cost evaluation factor(s). The non-cost evaluation factor for this award shall be the proposed submittal. The proposal must include the following:
1) Contractor’s written certification that his proposal includes all work identified in the statement of work, bid schedule and attachments.
2) Technical data: contractor is responsible for floors, walls, wall safety protection for a total integrated play environment. The play environment consist of a wide range of play elements, impact absorbing flooring, impact absorbing wall padding, interactive panels, and rules signage, that can fit the area (see Attachment 1 Room Layout) and are all tied together by a general room theme.
a) Have at minimum a 1 year warrantee
b) Play elements: Brand Name or Equal to Playtime, LLC.’s sculpted foam soft play elements, e.g., fiberglass shell, closed cell low density foam, flexible elastomer base, elastomer paint.
c) Impact absorbing flooring: Brand Name or Equal to Playtime DuraSoft Safety Flooring System, e.g., soft and flexible surface that is extremely durable
d) Impact absorbing wall padding specifications I. At a minimum the North and East brick walls need to have an impact absorbing padding
e) 1.5” rating at 5 foot fall height (ASTM F1292)
3) Project timeline
a) The latest completion date that will be accepted is 5 Jan 13 which included ordering, delivery, assembly, and complete installation.
4) Room design(s)/layout(s)
a) Provide layouts/designs for 3 room themes each with equal cost: 1 jungle theme, 1 ocean theme, & 1 contractors choice theme I. All themes must have a parent seating area, shoe storage area, and rules signage
b) Maximum Height: 8ft ceilings, For Library layout, room dimensions, and square footages see attachment 1
b. Best Value evaluation criteria are as follows:
1) Shorter schedules will result in a more favorable evaluation.
2) A greater number of play elements, diversity of play elements and appearance of play elements will result in a more favorable evaluation.
3) Room layout and appearance of play elements will result in a more favorable evaluation.
Best Value criteria 1, 2, & 3 are of equal importance and constitute 100% of the evaluation;
price is not an evaluation criteria.
3. Project Budget: Not to Exceed $100,000.00
4. Proposal Acceptance Period: Contractors must honor proposal until 30 Sep 12.
5. A site visit will be scheduled. Contractor(s) are strongly encouraged to attend the site visit to verify existing conditions. If additional information is needed or the contractor needs to visit the project site again, arrangements can be made by contacting the Contracting Officer.
6. Proposals due date will be stated on the Request for Quote.
7. Electronic copies of existing floor plans attached. Drawings are not guaranteed to be updated, and therefore, the contractor shall verify all measurements at the site and shall be responsible for dimensions and proper calculations
8. Restrooms are available for contractor use near area of work.
9. Conduct activities to minimize disruptions to Library.
10. South Dakota has a use and excise tax that must be included when contractor is preparing quote. The guide and information concerning the use and excise tax can be obtained at http://www.state.sd.us/drr2/businesstax/publications/cet/cetguide.pdf
Scope of Work
1. Installation of Play Area
a. The contractor shall install the play elements, flooring, and wall padding in accordance with the manufacturer’s specific instructions. This will include, but is not limited to uncrating, assembly, anchoring and/or bolting the structure to the facility floor and removal of all shipping materials.
2. Site condition
a. If during play structure installation, and before the condition is disturbed, contact the
Contracting Officer in writing of any physical condition at the site of an unusual nature from those normally encountered in performance of this type of work.
3. All work shall be performed in a skillful and workmanlike manner.
4. The contractor shall ensure that the worksite is secure at all times. All debris shall be removed and properly disposed of daily (contractor is responsible for providing/maintaining dumpsters if needed).
5. The contractor shall provide a signed report, upon completion of work, stating that all work performed and all material installed was done in accordance with federal, state, local laws, and regulations & guidelines established by the U.S. the American Society for Testing Materials (ASTM) for playground equipment (F1292, F1487, and F1951), the International Playground Equipment Manufacturing Association (IPEMA), the Consumer Product Safety Commission (CPSC), ADAAG, Public Playground Safety Handbook and this document.
6. The contractor is responsible for providing documentation stating that after project completion the play area was inspected and approved by a certified safety inspector.
7. The contractor shall provide the Ellsworth Library staff with 2 copies of any manufacturer installation and care manuals at project completion.
Government Furnished Property and Services
1. The government will provide access to inside electrical outlets for contractor use.
2. The contractor shall keep the area secure and clean at all times.
General Information
1. Library Hours of Operations and contractor work hours
a. Normal hours of operation are Monday-Friday 0700-1630 and Saturday 0930-1700 excluding Federal holidays listed below:
1) Labor Day – 3 September
2) Columbus Day – 8 October
3) Veterans Day – 12 November
4) Thanksgiving – 22 November
5) Christmas – 25 December
6) New Years – 1 January
b. If work hours outside of normal hours of operation are required, a written request shall be submitted to the Contracting Officer for approval.
Attachment
1. Attachment 1 – Library (Bldg 3910) Floor Plan
File details come from the government source that posted it. Updated .