fwc 22-23-02 Addendum 2 FINAL.docx
DOCX document 424 KB Posted
- Attached to
- Desalination Equipment Update/Replace REBID
- Solicitation number
- ITB-02180
- Issued by
- Brevard County, Florida
About this file
This document is an Addendum to a Solicitation issued by the Florida Fish and Wildlife Conservation Commission (FWC) for Desalination Equipment Update/Replace. The Addendum provides clarification and answers to questions related to the Solicitation. It confirms that the equipment to be supplied must be similar in function and quality to the existing on-site equipment, with a product water capacity of 5,000 gallons per day. The existing well pumps can provide adequate flow and pressure for this system, and the existing shed can be used to house the new equipment. The Addendum also states that the standard 1-year warranty is acceptable, and that 3 references are required, which cannot be passed through via subcontractors. Regarding payment terms, the Addendum directs bidders to the Purchase Order Terms and Conditions in the original Solicitation.
The related State and Local Contract Opportunity is for the Desalination Equipment Update/Replace REBID in the state of Florida, specifically within the jurisdictions of Leon County and the City of Tallahassee. The Solicitation is open to competitive bidding, and vendors must be registered in the MyFloridaMarketPlace system and with SunBiz prior to the bid opening.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FWC 22-23-02 Addendum 1.docx | DOCX document | |
| FWC 22-23-02 FINAL.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Fish and Wildlife Conservation Commission
Commissioners Rodney Barreto Chairman Coral Gables
Steven Hudson Vice Chairman Fort Lauderdale
Gary Lester Oxford
Albert Maury Coral Gables
Gary Nicklaus Jupiter
Sonya Rood St. Augustine
Robert A. Spottswood Key West
Office of the Executive Director Eric Sutton Executive Director
Thomas H. Eason, Ph.D.
Assistant Executive Director
Jennifer Fitzwater Chief of Staff
850-487-3796
850-921-5786 FAX
Finance and Budget Office
(850) 488-6551
Managing fish and wildlife resources for their long-term well-being and the benefit of people.
620 South Meridian Street Tallahassee, Florida 32399-1600 Voice: 850-488-4676
Hearing/speech-impaired:
800-955-8771 (T) 800 955-8770 (V)
MyFWC.com
| DATE: | August 30, 2022 |
| ADDENDUM NO.: | 2 |
| BID NO.: | FWC 21/22-02 |
| BID TITLE: | Desalination Equipment Update/replace |
| UPDATE: | questions and answers. |
The enclosed addendum has been issued for consideration in the preparation of your response to the Florida Fish and Wildlife Conservation Commission’s (FWC) Solicitation No. FWC 21/22-02, “Desalination Equipment Update/Replace”.
All responses to the subject solicitation must be received no later than 10:30 AM (ET) on Tuesday, September 6, 2022.
A response received after the exact time specified will not be considered. Failure to file a protest within the time prescribed in Section 120.57(3), Florida Statutes (F.S.), or failure to post the bond or other security required by law within the time allowed for filing a bond shall constitute a waiver of proceedings under Chapter 120, Florida Statutes. Written notices, formal requests and proceedings must conform with the requirements set forth in Chapter 28-110, Florida Administrative Code (F.A.C.). Protests must be filed with the Purchasing Office, Fish and Wildlife Conservation Commission, 1875 Orange Avenue East, Tallahassee, Florida 32311-6160 within the time prescribed in Section 120.57(3), F.S. and Chapter 28-110, F.A.C.
Sincerely, Christopher Melkun, FWC Procurement Manager
BEGIN ADDENDUM
Due to the lack of feed water information, there are no guarantees for product water quality. Equipment supply will be similar to existing on site equipment.
Equipment shall be similar to function and quality of the existing on-site equipment in accordance with the scope of work.
Supplier assumes System will be sized for a 5000 gallon per day product water capacity.
Yes, the well pumps can provide adequate flow and pressure for a 5000 gallon per day system.
Supplier assumes Existing shed will be used to house equipment. Suppliers will remove existing equipment and install new equipment on site.
Yes. The shed can be used to house equipment. The existing equipment for replacement per the scope of work will need to be removed, and new equipment will need to be installed on-site.
Supplier assumes that existing well pumps can provide adequate flow and pressure for a 5000 gallon per day system.
Yes, the well pumps can provide adequate flow and pressure for a 5000 gallon per day system
Carver Water will provide our standard 1 year warranty
Standard warranty is okay.
2. Can CW provide less than 3 references? Can references also be passed through via sub vendors?
3 references are required for this bid. References cannot be passed through via sub vendors.
3. CW desires more favorable payment terms than those presented in Section 3, Paragraph A. Suggested terms are as follows:
50% down payment 30% upon equipment delivery 20% 10 days after commissioning.
Please see Section 3(A), of the Purchase Order Terms and Conditions in ITB 22/23-02, for appropriate payment guidelines.
END ADDENDUM