About this file
This document contains several forms related to a federal contract opportunity for a Non-Time Critical Removal Action (NTCRA) at the Caneel Bay Resort within the Virgin Islands National Park. The forms provide details on the contract price schedule, additional price details, relevant experience, key personnel experience, and limitations on subcontracting.
The federal contract opportunity is solicitation 140P2124R0017 issued by the National Park Service, Department of the Interior, to conduct a CERCLA removal action. The work includes removing approximately 288 bank cubic yards of contaminated soil and 40 loose cubic yards of contaminated sediment, transporting the materials to appropriate disposal facilities, and performing limited site restoration. This is a best value negotiated procurement set-aside for small businesses, with proposals due approximately 30 days after the solicitation is posted. The contract will use unit-priced items subject to the variation in quantity clause, and require payment and performance bonds as well as liability insurance prior to contract performance.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2. price schedule
| Form 2: Contract Price Schedule. | Solicitation 140P2124R0017 |
| Offerors are required to submit, at minimum, an offer that conforms to the solicitation documents with pricing for base items and all option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. If no specific line item exists for a portion of the work, include the costs in a related item. In case of an error in the calculation of extended prices, the unit price governs. In case of an error in summation, the total of the corrected amounts governs. Complete this form and return with other documents described in Section L. |
| CONTRACT PRICE SCHEDULE | |||
| All work shall be performed in accordance with the attached Statement of Work, referenced documents, and wage determination. Refer to Attachment 1 for line item definitions. | |||
| Contract Line Item (CLIN) | Quantity (1) and Unit | Unit Price | CLIN Price (2) |
| 1: Construction Plan preparation and contract support tasks | 1 lump sum | -- | $0.00 |
| 2: Soil area - Mobilization and Site Preparation | 1 lump sum | -- | $0.00 |
| 3: Drainage Channel - Mobilization and Site Preparation | 1 lump sum | -- | $0.00 |
| 4: Soil and Sediment Removal, Transportation, and Disposal (non-RCRA Hazardous Waste) | 425 tons | $0.00 | $0.00 |
| 5: Soil and Sediment Removal, Transportation, and Disposal (RCRA Hazardous Waste) | 20 ton | $0.00 | $0.00 |
| 6: Site Restoration | 1 lump sum | -- | $0.00 |
| TOTAL PRICE FOR CLINs 1 through 6: | $0.00 |
| (1) Unit-priced CLINs show an estimated quantity; see Paragraph H.7. |
| (2) CLIN Price uses estimated quantities for unit-priced items. |
3. add'l price details
| Form 3: Additional Price Details (will be the basis for post-award Schedule of Values) | Solicitation 140P2124R0017 | ||||
| CLIN | Estimated Quantity | Unit | Unit Price or Sub-CLIN value | CLIN Price | |
| 1 | Contract Support Tasks | LS | - | $0.00 | |
| General contract administration and project oversight (do not include removal action superintendence in this line) | - | LS | - | ||
| Project meetings and conference calls, develop project schedule | - | LS | - | ||
| Construction Plan Document Preparation and Submittal | - | LS | - | ||
| Performance and payment bonds | - | LS | - | ||
| Liability insurance | - | LS | - | ||
| Waste characterization | - | LS | - | ||
| 2 | Soil Area - Mobilization and site preparation | LS | - | $0.00 | |
| Transport equipment and materials to site. | - | LS | - | ||
| Install, maintain, and remove erosion and sedimentation controls. Install stormwater diversion features. | - | LS | - | ||
| Establish support areas, excavation limits, clear brush and trees, chip and stockpile vegetation. | - | LS | - | ||
| 3 | Drainage Channel – Mobilization and Site Preparation | LS | - | $0.00 | |
| Install, maintain, and remove erosion and sedimentation controls. Install stormwater diversion features. | - | LS | - | ||
| Establish support areas, removal limits, clear brush and trees, chip and stockpile. | - | LS | - | ||
| 4 | Soil and Sediment Removal, Transportation, and Disposal (non-RCRA Hazardous Waste) | 425 | TN | $0.00 | $0.00 |
| Soil excavation (from Soil Removal Units A2-Soil1, A2-Soil2, A2-Soil3, and A2-Soil4) | - | - | - | ||
| Sediment removal (from Sediment Removal Units A2-Sed1, A2-Sed2, and A2-Sed3) | - | - | - | ||
| Waste transportation (includes trucking and shipping) | - | - | - | ||
| Disposal of non-RCRA hazardous soils and/or sediment | - | - | - | ||
| 5 | Soil and Sediment Removal, Transportation, and Disposal (RCRA Hazardous Waste) | 20 | TN | $0.00 | $0.00 |
| Soil excavation (from Soil Removal Units A2-Soil1, A2-Soil2, A2-Soil3, and A2-Soil4) | - | - | - | ||
| Sediment removal (from Sediment Removal Units A2-Sed1, A2-Sed2, and A2-Sed3) | - | - | - | ||
| Waste transportation (includes trucking and shipping) | - | - | - | ||
| Disposal of RCRA hazardous soils and/or sediment | - | - | - | ||
| 6 | Site Restoration | LS | - | $0.00 | |
| Measure and record final extents of excavation. | - | LS | - | ||
| Backfill excavations with topsoil. | - | LS | - | ||
| Restore disturbed areas, seed, maintain erosion and sedimentation controls and seeded areas until final inspection. Remove erosion and sedimentation controls | - | LS | - | ||
| TOTAL PRICE FOR CLINs 1 through 6: | $0.00 |
| Info | Identify the wage determination number, modification number, and date for work to be performed in the continental US and used to develop these prices (eg FL2024xxxx, Modification Y, dated xx/yy/zz): |
| Info | Identify the waste disposal facility for non-RCRA hazardous waste (name and location): |
| Info | Identify the waste disposal facility for RCRA hazardous waste (name and location): |
Page &P
4. experience summary
| Form 4: Relevant Experience - Comparability to current project | #1 | #2 | #3 | #4 | #5 |
| Project Title (with location) | |||||
| Client (eg name of federal or state agency, city, private) | |||||
| Area of Comparability: | Instructions: Enter an X in the project's column if it included the listed area of comparability; leave blank if not relevant. | ||||
| NTCRAs under CERCLA conducted at similarly complex sites. | |||||
| NTCRAs under CERCLA with similar contaminants. | |||||
| NTCRAs under CERCLA with similar affected media. | |||||
| Projects that included a similar magnitude of soil removal. | |||||
| Projects that included working on sloped terrain. | |||||
| NTCRAs under CERCLA at sites with potential migration pathways from impacted soils to surface water, sediment, and groundwater. | |||||
| Performed waste characterization for landfill acceptance. | |||||
| Required preparation of planning documents similar to this contract | |||||
| Performed in challenging environments with limited services, such as electricity, cell phone coverage, grocery or hardware store, etc. | |||||
| Performed in public, highly visible locations. | |||||
| Performed in a US territory or similarly remote location. | |||||
| Conducted soil investigations that used Incremental Sampling Methodology (ISM) procedures. | |||||
| Required interpreting ISM results. | |||||
| Similar work performed at a site with similarly complicated logistics, particularly related to transport of contaminated materials between the site (origin) and the landfill(s) (destination). | |||||
| Required obtaining and complying with a soil import permit (PPQ Form 525-A, Application for Permit to Receive Soil) from the United States Department of Agriculture (USDA) Animal and Plant Health Inspection Service (APHIS) (7 CFR 330). | |||||
| NTCRAs under CERCLA for federal government customers. |
5. key personnel experience
| Form 5: Key Personnel Relevant Experience - Comparability to current project | Contractor's Project Manager | Site Supt - Candidate 1 | Site Supt - Candidate 2 | Site Supt - Candidate 3 |
| Name | ||||
| Overall years of similar experience | ||||
| Area of Comparability: | Instructions: Enter an X in the individual's column if they have relevant experience in the listed area of comparability; leave blank if not relevant. | |||
| NTCRAs under CERCLA conducted at similarly complex sites. | ||||
| NTCRAs under CERCLA with similar contaminants. | ||||
| NTCRAs under CERCLA with similar affected media. | ||||
| Projects that included a similar magnitude of soil removal. | ||||
| Projects that included working on sloped terrain. | ||||
| NTCRAs under CERCLA at sites with potential migration pathways from impacted soils to surface water, sediment, and groundwater. | ||||
| Performed waste characterization for landfill acceptance. | ||||
| Required preparation of planning documents similar to this contract | ||||
| Performed in challenging environments with limited services, such as electricity, cell phone coverage, grocery or hardware store, etc. | ||||
| Performed in public, highly visible locations. | ||||
| Performed in a US territory or similarly remote location. | ||||
| Conducted soil investigations that used Incremental Sampling Methodology (ISM) procedures. | ||||
| Required interpreting ISM results. | ||||
| Similar work performed at a site with similarly complicated logistics, particularly related to transport of contaminated materials between the site (origin) and the landfill(s) (destination). | ||||
| Required obtaining and complying with a soil import permit (PPQ Form 525-A, Application for Permit to Receive Soil) from the United States Department of Agriculture (USDA) Animal and Plant Health Inspection Service (APHIS) (7 CFR 330). | ||||
| NTCRAs under CERCLA for federal government customers. |
6 limitations on subcontracting Form 6: Report on Limitations on Subcontracting [based on DSC template 7/25/19]
| This report is required for small business, 8(a) or other socio-economic set-aside service contracts (including construction) to demonstrate compliance with limitations on subcontracting as implemented by DOI policy. | |
| Solicitation Number: | 140P2124R0017 |
| Prime Contractor: | |
| Total Offered Price | |
| Type of Set Aside and implementing clauses: | Small Business per 52.219-14, Limitations on Subcontracting (OCT 2022) (DEVIATION OCT 2022) and 52.219-6 Notice of Small Business Set-Aside (NOV 2020). |
| Type of Service and Required Participation: | Services; 50% threshold applies (see clause excerpt below). |
| Participartion Calculation | |||
| Amounts shown below shall represent offerered prices. | |||
| 1) Total offered price from the Prime Contractor for contract performance: | $0 | ||
| 2) Total amount projected to be paid to all Similarly Situated* First-Tier Subcontractors (SSS, in this case SMALL BUSINESSES, as measured by <1,000 employees, the standard for NAICS 562910 Exception), excluding the cost of materials. | $0 | ||
| Amount to be paid to: | [Insert SSS company name] | $0 | |
| Amount to be paid to: | [Insert SSS company name] | $0 | |
| Amount to be paid to: | [Insert SSS company name] | $0 | |
| Amount to be paid to: | [Insert SSS company name] | $0 | |
| Amount to be paid to: | [Insert SSS company name] | $0 | Add rows if more than 5 SSS |
| 3) Total amount to be paid to all Non-Similarly Situated Subcontractors (NSS), excluding the cost of materials | $0 | ||
| Amount to be paid to: | [Insert NSS company name] | $0 | |
| Amount to be paid to: | [Insert NSS company name] | $0 | |
| Amount to be paid to: | [Insert NSS company name] | $0 | |
| Amount to be paid to: | [Insert NSS company name] | $0 | |
| Amount to be paid to: | [Insert NSS company name] | $0 | Add rows if more than 5 NSS |
| 4) Prime & SSS Participation % | ERROR:#DIV/0! | Modify formula if rows added above | |
| 5) NSS Participation % | ERROR:#DIV/0! | Modify formula if rows added above |
| FAR 52.219-14 (OCT 2022) (DEVIATION OCT 2022) excerpt: (e) Limitations on subcontracting. By submission of an offer and execution of a contract, the Contractor agrees that in performance of a contract assigned a North American Industry Classification System (NAICS) code for—(1) Services (except construction). It will not pay more than 50 percent of the amount paid by the Government for contract performance, excluding certain other direct costs and certain work performed outside the United States (see paragraph (e)(1)(i)), to subcontractors that are not similarly situated entities. [...] (i) The following services may be excluded from the 50 percent limitation: (A) Other direct costs, to the extent they are not the principal purpose of the acquisition and small business concerns do not provide the service. Examples include airline travel, work performed by a transportation or disposal entity under a contract assigned the environmental remediation NAICS code (562910), cloud computing services, or mass media purchases. (B) Work performed outside the United States on awards made pursuant to the Foreign Assistance Act of 1961, or work performed outside the United States required to be performed by a local contractor. Note that the definition of United States in FAR 2 and 19 is "the 50 States and the District of Columbia." |
| * Similarly situated entity, as used in this clause, means a first-tier subcontractor, including an independent contractor, that— |
(1) Has the same small business program status as that which qualified the prime contractor for the award (e.g., for a small business set-aside contract, any small business concern, without regard to its socioeconomic status); and
(2) Is considered small for the size standard under the North American Industry Classification System (NAICS) code the prime contractor assigned to the subcontract.
| Prepared by: | |
| Name and Title |
Prepared on:
File details come from the government source that posted it. Updated .