Form D - Rate Schedule.xlsx
XLSX spreadsheet 51 KB Posted
- Attached to
- Re-Advertisement for Petroleum Products Corporation Superfund Site Remedial Action Services
- Solicitation number
- RFP-15168
- Issued by
- Leon County, Florida
About this file
Summary of Form D - Rate Schedule
This is a Rate Schedule form prepared by the Florida Department of Environmental Protection for the Petroleum Products Corporation Superfund Site Remedial Action Services contract (RFP 2026010). The schedule establishes fixed unit prices and lump sum rates for comprehensive environmental remediation work at the Pembroke Park site in Broward County, Florida. Services encompass remedial action planning, building demolition of seven structures, soil excavation of approximately 31,890 cubic yards, in-situ soil stabilization/solidification treatment of approximately 93,022 cubic yards, utility management including removal and replacement of stormwater, sanitary, water, gas, electric, and telecommunications systems, transportation and disposal of approximately 102,000 tons of contaminated materials, asphalt paving, geomembrane liner installation, drainage piping networks, well abandonment services, and site restoration including landscaping and seeding. The contract is structured with both Initial Contract Term and Renewal Contract Term sections, with the initial term spanning five years from execution and renewal options available for up to three additional years. Contractors must complete all pricing entries in the designated purple-shaded cells; blank spaces or zero values will result in those services being offered at no cost. The grand total of all base bid items serves as the primary evaluation criterion for contract award.
The rate schedule comprises base bid items organized into 15 primary service categories plus 10 contingency item categories. Pricing is submitted on a fixed unit price basis (identified as "UP") for items with estimated quantities and lump sum basis (identified as "LS") for services with single deliverables. Contingency items address potential needs for ISS revised mixtures, vapor and odor control systems, asbestos and RCRA abatement, lead paint abatement, universal waste disposal, construction and demolition waste, and subtitle C hazardous waste disposal. The instructions prohibit respondents from modifying the rate schedule, adding assumptions, or providing additional terms. All rates submitted constitute ceiling rates that may be quoted lower per individual task assignment. Payment bonds of $3,000,000 are required, and contractors must maintain commercial general liability insurance of $1,000,000 per occurrence/$2,000,000 aggregate and pollution liability insurance of $3,000,000 aggregate. Cost reductions of 1% per day apply for missed deliverable deadlines absent written extensions, and final payment requires submission of a Contractor Certification/Release of Claims Form.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFP 2026010 Re-Ad PPC Superfund Site RAS.pdf | ||
| Addendum No. 2 – Revised RFP 2026010.pdf | ||
| Add 2 - QA for RFP 2026010.pdf | ||
| Add No. 1 - RFP 2026010 Timeline Mod Final.pdf | ||
| Attachment 1 - Draft Contract for RFP 2026010.pdf | ||
| Form D - Rate Schedule.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Instructions State of Florida Department of Environmental Protection Form D - Rate Schedule Instructions The Rate Schedule must contain complete responses to all items. Any blank spaces or zeros (0) added to any of the cells will result in that service being offered at no cost to the State.
Rates contained within are ceiling rates that may be quoted at a lower rate per Task Assignment.
This worksheet must be included in both the electronic proposal (original Excel format) and the hard copy proposal (the print area is already pre-set for this worksheet).
The Respondent shall not modify Rate Schedule.
The Respondent shall not add or provide any assumptions, contingencies, or additional terms to the Rate Schedule.
The Respondent shall enter text in the purple shaded cells as indicated below:
| 1) | Enter Respondent Name in cell B2. |
| 2) | Enter the Fixed Unit Price for each Item in column F. |
| 3) | Review Data entries for accuracy. |
Review the header information, checking for any formula errors and ensure the rates for each pay item price are accurate.
Initial Contract Term State of Florida Department of Environmental Protection Form D - Rate Schedule Initial Contract Term
| Contractor Name: | ||||||||
| Item No. | Item | Basis of | ||||||
| Payment | Estimated | |||||||
| Quantity | Unit | Fixed Unit Price | Total Price | Subtotal | ||||
| BASE BID | ||||||||
| 1 | Remedial Action (RA) Work Plan and Pre-Construction Services | |||||||
| 1.1 | RA Work Plan and Certified/Signed Plans and Specifications1 | |||||||
| (includes pre-construction site survey by a Florida licensed surveyor and pre-construction site visit/photo documentation) | LS | 1 | LS | $0.00 | $0.00 | |||
| 1.2 | Recertification of Construction Drawings and Specifications from Engineer of Record | LS | 1 | LS | $0.00 | $0.00 | ||
| 1.3 | Permitting | LS | 1 | LS | $0.00 | $0.00 | ||
| Subtotal | $0.00 | |||||||
| 2 | Mobilization Services - Pre-Construction Photographic Documentation | LS | 1 | LS | $0.00 | $0.00 | ||
| Subtotal | $0.00 | |||||||
| 3 | Temporary Facilities and Controls | |||||||
| 3.1 | General (Site Services)2 | LS | 1 | LS | $0.00 | $0.00 | ||
| 3.2 | Fencing and Visual Barrier Fabric | UP | 2,700 | LF | $0.00 | $0.00 | ||
| 3.3 | Erosion and Sedimentation Controls | LS | 1 | LS | $0.00 | $0.00 | ||
| 3.4 | Weekly Air Monitoring Reporting for Daily Odor and Vapor Monitoring | LS | 1 | LS | $0.00 | $0.00 | ||
| 3.5 | Contractor Quality Control Plan (CQCP) and Pre-Construction Survey | LS | 1 | LS | $0.00 | $0.00 | ||
| Subtotal | $0.00 | |||||||
| 4 | Construction Water Management Services | |||||||
| 4.1 | Provision of Construction Water Treatment and Temporary Storage System3 | LS | 1 | LS | $0.00 | $0.00 | ||
| 4.2 | Provision of Underground Injection System (includes permitting) | LS | 1 | LS | $0.00 | $0.00 | ||
| 4.3 | Operation and Verification That System is Meeting Treatment Objectives and Sampling Documentation | LS | 1 | LS | $0.00 | $0.00 | ||
| 4.4 | Operation of Construction Water Management System | UP | 244 | Days | $0.00 | $0.00 | ||
| 4.5 | Reporting - Weekly Construction Water Management System Operation Reporting | LS | 1 | LS | $0.00 | $0.00 | ||
| Subtotal | $0.00 | |||||||
| 5 | Building Demolition Services (see contingency items 20 - 24) | |||||||
| 5.1 | Building D | LS | 1 | LS | $0.00 | $0.00 | ||
| 5.2 | Building E | LS | 1 | LS | $0.00 | $0.00 | ||
| 5.3 | Building G | LS | 1 | LS | $0.00 | $0.00 | ||
| 5.4 | Building H | LS | 1 | LS | $0.00 | $0.00 | ||
| 5.5 | Building I | LS | 1 | LS | $0.00 | $0.00 | ||
| 5.6 | Building J | LS | 1 | LS | $0.00 | $0.00 | ||
| 5.7 | Building L | LS | 1 | LS | $0.00 | $0.00 | ||
| 5.8 | Reporting - Building Demolition Weekly Progress Reporting | LS | 1 | LS | $0.00 | $0.00 | ||
| 5.9 | Reporting - Building Demolition Completion Report | LS | 1 | LS | $0.00 | $0.00 | ||
| Subtotal | $0.00 | |||||||
| 6 | Utility Management Services (locate, removal, and bypass) | |||||||
| 6.1 | Sitewide Utility Locate | LS | 1 | LS | $0.00 | $0.00 | ||
| 6.2 | Termination | |||||||
| 6.2.1 | Storm Water | LS | 1 | LS | $0.00 | $0.00 | ||
| 6.2.2 | Sanitary | LS | 1 | LS | $0.00 | $0.00 | ||
| 6.2.3 | Water | LS | 1 | LS | $0.00 | $0.00 | ||
| 6.2.4 | Gas | UP | 2 | EA | $0.00 | $0.00 | ||
| 6.2.5 | Electric | UP | 2 | EA | $0.00 | $0.00 | ||
| 6.2.6 | Telecommunications | UP | 2 | EA | $0.00 | $0.00 | ||
| 6.3 | Removal | |||||||
| 6.3.1 | Stormwater | |||||||
| 6.3.1.2 | Removal and Disposal of Drain Manholes | UP | 3 | EA | $0.00 | $0.00 | ||
| 6.3.1.3 | Removal and Disposal of Catch Basins | UP | 14 | EA | $0.00 | $0.00 | ||
| 6.3.1.4 | Removal and Disposal of Drainage Piping | UP | 520 | LF | $0.00 | $0.00 | ||
| 6.3.2 | Sanitary | |||||||
| 6.3.2.1 | Removal and Disposal of Sewer Manholes | UP | 4 | EA | $0.00 | $0.00 | ||
| 6.3.2.2 | Removal and Disposal of Gravity Sewer Pipelines | UP | 300 | LF | $0.00 | $0.00 | ||
| 6.3.2.3 | Removal and Disposal of Sewer Force Main Pipelines | UP | 550 | LF | $0.00 | $0.00 | ||
| 6.3.3 | Water | |||||||
| 6.3.3.1 | Removal and Disposal of Water Lines | UP | 660 | LF | $0.00 | $0.00 | ||
| 6.3.3.2 | Remove Water Service | UP | 1 | EA | $0.00 | $0.00 | ||
| 6.3.4 | Gas | |||||||
| 6.3.4.1 | Removal and Disposal of Gas Lines | UP | 150 | LF | $0.00 | $0.00 | ||
| 6.3.5 | Electric | |||||||
| 6.3.5.1 | Removal and Disposal of Electric Lines | UP | 500 | LF | $0.00 | $0.00 | ||
| 6.3.5.2 | Removal and Disposal of Underground Electric Lines | UP | 230 | LF | $0.00 | $0.00 | ||
| 6.3.6 | Communication Cable | |||||||
| 6.3.6.1 | Removal and Disposal of Communication Cable | UP | 160 | LF | $0.00 | $0.00 | ||
| 6.4 | Temporary Bypass | |||||||
| 6.4.1 | Install Temporary Stormwater Bypass Lines | LS | 1 | LS | $0.00 | $0.00 | ||
| 6.4.2 | Install Temporary Sanitary Sewer Bypass Lines | LS | 1 | LS | $0.00 | $0.00 | ||
| 6.4.3 | Install Temporary Water Bypass Lines | LS | 1 | LS | $0.00 | $0.00 | ||
| 6.4.4 | Install Temporary Electric Lines | LS | 1 | LS | $0.00 | $0.00 | ||
| 6.4.5 | Install Temporary Communication Cables | LS | 1 | LS | $0.00 | $0.00 | ||
| 6.5 | Reporting - Utility Abandonment/Utility Relocation Weekly Progress Reporting | LS | 1 | LS | $0.00 | $0.00 | ||
| 6.6 | Reporting - Utility Abandonment/Utility Relocation Completion Report | LS | 1 | LS | $0.00 | $0.00 | ||
| Subtotal | $0.00 | |||||||
| 7 | Utility Management Services - Furnish and Install (F&I) | |||||||
| 7.1 | Storm Water (area shown in drawing R-010 and drawing R-003) | |||||||
| 7.1.1 | F&I Catch Basins | UP | 12 | EA | $0.00 | $0.00 | ||
| 7.1.2 | F&I 6" (or equivalent) Perforated PVC Drain Line | UP | 300 | LF | $0.00 | $0.00 | ||
| 7.1.3 | F&I 12" (or equivalent) Perforated PVC Drain Line | UP | 220 | LF | $0.00 | $0.00 | ||
| 7.1.4 | F&I 18" (or equivalent) PVC Drain Line | UP | 290 | LF | $0.00 | $0.00 | ||
| 7.2 | Sanitary | |||||||
| 7.2.1 | F&I Sewer Manholes | UP | 4 | EA | $0.00 | $0.00 | ||
| 7.2.2 | F&I 12" PVC Sanitary Sewer Line | UP | 280 | LF | $0.00 | $0.00 | ||
| 7.2.3 | F&I 6" PVC Sanitary Sewer Line | UP | 245 | LF | $0.00 | $0.00 | ||
| 7.2.4 | F&I 4" PVC Sanitary Sewer Line | UP | 720 | LF | $0.00 | $0.00 | ||
| 7.3 | Water | |||||||
| 7.3.1 | F&I 6" PVC Water Line | UP | 300 | LF | $0.00 | $0.00 | ||
| 7.3.2 | F&I 12" PVC Water Line | UP | 230 | LF | $0.00 | $0.00 | ||
| 7.3.3 | F&I 6"x 6" Tap and Sleeve | UP | 2 | EA | $0.00 | $0.00 | ||
| 7.3.4 | F&I 12" x 12" Tap and Sleeve | UP | 2 | EA | $0.00 | $0.00 | ||
| 7.4 | Gas | |||||||
| 7.4.1 | F&I Gas Line | UP | 150 | LF | $0.00 | $0.00 | ||
| 7.5 | Electric | |||||||
| 7.5.1 | F&I Underground Electric | UP | 230 | LF | $0.00 | $0.00 | ||
| 7.5.2 | F&I Overhead Electric | UP | 440 | LF | $0.00 | $0.00 | ||
| 7.6 | Communications | |||||||
| 7.6.1 | F&I Underground Communications | UP | 260 | LF | $0.00 | $0.00 | ||
| 7.6.2 | F&I Overhead Communications | UP | 450 | LF | $0.00 | $0.00 | ||
| 7.7 | Reporting - Utility Replacement Weekly Progress Reporting | LS | 1 | LS | $0.00 | $0.00 | ||
| 7.8 | Reporting - Utility Replacement Completion Report | LS | 1 | LS | $0.00 | $0.00 | ||
| Subtotal | $0.00 | |||||||
| 8 | Soil Excavation Services (Outside of Areas 1 through 4) | |||||||
| 8.1 | Building Slab and Foundation Removal | UP | 4,000 | Tons | $0.00 | $0.00 | ||
| 8.2 | Excavation and Management of Soil, Pavement, Utilities, and Debris | UP | 28,000 | CY | $0.00 | $0.00 | ||
| 8.3 | Reporting - Soil Excavation (Outside of Areas 1 through 4) Weekly Progress Reporting that include the daily material removal status | LS | 1 | LS | $0.00 | $0.00 | ||
| 8.4 | Submittal of the As-Built drawings showing extent of post excavation limits | LS | 1 | LS | $5.00 | $5.00 | ||
| Subtotal | $5.00 | |||||||
| 9 | Excavation Services (Areas 1 through 4) | |||||||
| 9.1 | Area 1 (Excavation and Management of Soil, Pavement, Utilities, and Debris) | UP | 1,380 | CY | $0.00 | $0.00 | ||
| 9.2 | Area 2 (Excavation and Management of Soil, Pavement, Utilities, and Debris) | UP | 400 | CY | $0.00 | $0.00 | ||
| 9.3 | Area 3 (Excavation and Management of Soil, Pavement, Utilities, and Debris) | UP | 810 | CY | $0.00 | $0.00 | ||
| 9.4 | Area 4 (Excavation and Management of Soil, Pavement, Utilities, and Debris) | UP | 1,300 | CY | $0.00 | $0.00 | ||
| 9.5 | Reporting - Soil Excavation (Areas 1 through 4) Weekly Progress Reporting that include the daily material removal status | LS | 1 | LS | $0.00 | $0.00 | ||
| 9.6 | Submittal of the As-Builts drawings showing extent of post excavation limits | LS | 1 | LS | $0.00 | $0.00 | ||
| Subtotal | $0.00 | |||||||
| 10 | ISS Treatment (see contingency items 16, 17, 18, & 19) Services | |||||||
| 10.1 | ISS Mix Design Verification (Test Section - 12 ISS columns) | LS | 1 | LS | $0.00 | $0.00 | ||
| 10.2 | ISS Treatment (Shallow [Less Than or Equal to 8ft BGS]) | UP | 50,147 | CY | $0.00 | $0.00 | ||
| 10.3 | ISS Treatment (Deep [Greater Than 8ft BGS]) | UP | 42,875 | CY | $0.00 | $0.00 | ||
| 10.4 | ISS Column Wall Surrounding four sides of K-2 building4 | UP | 840 | LF | $0.00 | $0.00 | ||
| 10.5 | ISS Swell Management | UP | 52,000 | Tons | $0.00 | $0.00 | ||
| 10.6 | Reporting - ISS Treatments Daily Progress Reporting | LS | 1 | LS | $0.00 | $0.00 | ||
| 10.7 | Submittal of the As-Built drawings showing extent of ISS top and bottom column elevations | LS | 1 | LS | $0.00 | $0.00 | ||
| Subtotal | $0.00 | |||||||
| 11 | Transportation and Disposal Services | |||||||
| 11.1 | Demolition Materials | |||||||
| 11.1.1 | C&D Debris | UP | 5,000 | Tons | $0.00 | $0.00 | ||
| 11.2 | Disposal of Excavated Material | |||||||
| 11.2.1 | Subtitle D Disposal of Material Excavated from Areas 1 - 4 and the ISS Area | UP | 45,000 | Tons | $0.00 | $0.00 | ||
| 11.3 | ISS Swell | |||||||
| 11.3.1 | Subtitle D Disposal of ISS Swell Material | UP | 52,000 | Tons | $0.00 | $0.00 | ||
| 11.4 | Reporting - Transportation and Disposal Weekly Progress Reporting | LS | 1 | LS | $0.00 | $0.00 | ||
| Subtotal | $0.00 | |||||||
| 12 | Backfill / Restoration Services | |||||||
| 12.1 | Utility Corridors (see drawing R-010) | UP | 2,300 | LF | $0.00 | $0.00 | ||
| 12.2 | Fine Aggregate | UP | 300 | CY | $0.00 | $0.00 | ||
| 12.3 | Coarse Aggregate | UP | 13,700 | CY | $0.00 | $0.00 | ||
| 12.4 | Backfill and Compaction of Excavation Areas 1 - 4 and the ISS Area5 | UP | 18,190 | CY | $0.00 | $0.00 | ||
| 12.5 | Landscape Soil | UP | 1,100 | CY | $0.00 | $0.00 | ||
| 12.6 | Geotextile | UP | 29,200 | SY | $0.00 | $0.00 | ||
| 12.7 | Seeding (include 2 weeks of watering) | UP | 1 | AC | $0.00 | $0.00 | ||
| 12.8 | LLDPE Liner | UP | 1,815 | LF | $0.00 | $0.00 | ||
| 12.9 | Piping Network (see drawing R-010) | LS | 1 | LS | $0.00 | $0.00 | ||
| 12.9.1 | F&I Leaching Catch Basins | UP | 7 | EA | $0.00 | $0.00 | ||
| 12.9.2 | F&I Cleanout Catch Basins | UP | 26 | EA | $0.00 | $0.00 | ||
| 12.9.3 | F&I 12" HDPE Trunk/Header Pipe | UP | 600 | LF | $0.00 | $0.00 | ||
| 12.9.4 | F&I 6" HDPE Lateral Pipe | UP | 1850 | LF | $0.00 | $0.00 | ||
| 12.10 | 10,000-gallon Cistern Tank and Lift Station | LS | 1 | LS | $0.00 | $0.00 | ||
| 12.11 | Subtitle D Disposal of Soil and Debris Excavated for the F&I Tank Installation | LS | 1 | LS | $0.00 | $0.00 | ||
| 12.12 | Reporting - Site Restoration Weekly Progress Reporting including quality assurance (QA) testing and verification | LS | 1 | LS | $0.00 | $0.00 | ||
| Subtotal | $0.00 | |||||||
| 13 | Asphalt Paving Services | |||||||
| 13.1 | Soil Excavation Areas 1 and 2 | |||||||
| 13.1.1 | Bituminous Asphalt | UP | 1,580 | Tons | $0.00 | $0.00 | ||
| 13.1.2 | 8" Lime Rock | UP | 23,000 | SY | $0.00 | $0.00 | ||
| 13.1.3 | Type B Stabilization 12" LBR=40 | UP | 23,000 | SY | $0.00 | $0.00 | ||
| 13.2 | Area 4 | |||||||
| 13.2.1 | Bituminous Asphalt | UP | 130 | Tons | $0.00 | $0.00 | ||
| 13.2.2 | 8" Lime Rock | UP | 1,850 | SY | $0.00 | $0.00 | ||
| 13.2.3 | Type B Stabilization 12" LBR=40 | UP | 1,850 | SY | $0.00 | $0.00 | ||
| 13.3 | Area 3 | |||||||
| 13.3.1 | Bituminous Asphalt | UP | 110 | Tons | $0.00 | $0.00 | ||
| 13.3.2 | 8" Lime Rock | UP | 1,600 | SY | $0.00 | $0.00 | ||
| 13.3.3 | Type B Stabilization 12" LBR=40 | UP | 1,600 | SY | $0.00 | $0.00 | ||
| 13.4 | Reporting - Site Restoration Weekly Progress Reporting including QA testing and verification | LS | 1 | LS | $0.00 | $0.00 | ||
| Subtotal | $0.00 | |||||||
| 14 | Well Abandonment Services | |||||||
| 14.1 | Leave in Place, Grout, and Incorporate into ISS Matrix | |||||||
| UP | 51 | EA | $0.00 | $0.00 | ||||
| 14.2 | Overdrill Well Casing/Screen, Remove the Well, and Grout Borehole (for depths of 30 feet and under) | UP | 11 | EA | $0.00 | $0.00 | ||
| 14.3 | Reporting - Well Abandonment Completion Report | LS | 1 | LS | $0.00 | $0.00 | ||
| Subtotal | $0.00 | |||||||
| 15 | Demobilization Services | LS | 1 | LS | $0.00 | $0.00 | ||
| 15.1 | Construction Completion Report | LS | 1 | LS | $0.00 | $0.00 | ||
| Subtotal | $0.00 | |||||||
| GRAND TOTAL | ||||||||
| NOTE: Grand Total will be used as a part of Awarding price points in accordance with Section 5 of the RFP. | $5.00 |
| Item No. | Item | Basis of | ||||
| Payment | Estimated | |||||
| Quantity | Unit | Fixed Unit Price | ||||
| CONTINGENCY ITEMS (FIXED UNIT PRICE REQUIRED) | ||||||
| 16 | ISS Revised Mixture (if needed) | LS | 1 | LS | $0.00 | |
| 16.1 | Portland Cement | UP | 1 | Tons | $0.00 | |
| 16.2 | Ground Blast Granulated Slag | UP | 1 | Tons | $0.00 | |
| 15.3 | Bentonite | UP | 1 | Tons | $0.00 |
| 17 | Contingent Vapor and Odor Control Foam System | ||||
| 17.1 | Provision of Odor Control Foam System | LS | 1 | LS | $0.00 |
| 17.2 | Operation of Odor Control Foam System | UP | 8‐Hour Shift | $0.00 |
| 18 | Contingent Vapor and Odor Control Spray Cover System | ||||
| 18.1 | Provision of Spray Cover System | LS | 1 | LS | $0.00 |
| 18.2 | Operation of Spray Cover System | UP | 8‐Hour Shift | $0.00 |
| 19 | Contingent Auger Shroud and Carbon Capture System | ||||
| 19.1 | Provision of Auger Shroud and Carbon Capture System | LS | 1 | LS | $0.00 |
| 19.2 | Operation of Auger Shroud and Carbon Capture System | UP | 8‐Hour Shift | $0.00 | |
| 19.3 | Carbon Capture System Consumables ‐ Carbon | UP | EA | $0.00 |
| 20 | Asbestos and RCRA Abatement (includes inspection, testing, waste removal, segregation, and disposal) | ||||
| 20.1 | Asbestos - Mastic/Tiles | UP | Per | CY | $0.00 |
| 20.2 | Asbestos - Wrapped Pipe, Etc. | UP | Per | LF | $0.00 |
| 20.3 | RCRA Metals | UP | Per | Tons | $0.00 |
| 20.4 | RCRA Organics | UP | Per | Tons | $0.00 |
| 21 | Lead Abatement (includes inspection, testing, waste removal, segregation, and disposal) | ||||
| 21.1 | Lead Paint | UP | Per | SF | $0.00 |
| 21.2 | Other Potential Lead Abatement (Former Gun Range) | UP | Per | Tons | $0.00 |
| 22 | Universal Waste (includes waste removal, segregation, and disposal) | ||||
| 22.1 | Universal Waste | UP | Per | Tons | $0.00 |
| 23 | Construciton & Demonlition Waste (C & D) (includes office furniture waste removal and disposal)6 | ||||
| 23.1 | C&D Waste | UP | Per | Tons | $0.00 |
| 24 | Subtitle C Disposal | ||||
| 24.1 | Excavated Material Subtitle C | UP | Per | Tons | $0.00 |
| 24.2 | ISS Swell Subtitle C | UP | Per | Tons | $0.00 |
| 25 | Well Abandonment | ||||
| 25.1 | Overdrill Well Casing/Screen, Remove the Well, and Grout Borehole (for depths over 30 feet) | UP | Per | LF | $0.00 |
| UP = Unit Price | Notes: | Notes: |
| LS = Lump Sum | DO NOT FILL IN GREYED OUT CELLS | Do not enter any information in greyed out cells |
| CY = Cubic Yards | 1 RA Work Plan - Contractor should consider incorporation of DEP/EPA comments on draft work plans. The RA Work Plan will include all deliverables included in design specifications (see Section 01 36 00 Technical Specifications). | |
| LF = Linear Feet | ||
| SF = Square Feet | ||
| SY = Square Yard | 2 Site Services - Pricing includes set up of a onsite construction office trailer. | |
| EA = Each | 3 Includes temporary storage and disposal (under 10.2.1) of NAPL collected from the Construction Water Treatment System. | |
| AC = Acre | ||
| ISS= In-situ Soil Stabilization/Solidification | 4 This pricing includes the utility management, removal and replacement of concrete pavement along the east side of K-2 building (see drawings C-013 and C-014). | |
| Day = 10 hours | ||
| 5 This backfill will be the coarse aggregate in the ISS area (Design Drawing R-011). This volume includes the total excavation volume (31,890) less the coarse aggregate volume (13,700). |
6 The office furniture and interior warehouse items shall be removed by the property owner and tenants prior to construction activities. This bid item will be used to address any ancillary items or debris that remain after the warehouses have been vacated.
Renewal Contract Term State of Florida Department of Environmental Protection Form D - Rate Schedule Renewal Contract Term
| Contractor Name: | ||||||||
| Item No. | Item | Basis of | ||||||
| Payment | Estimated | |||||||
| Quantity | Unit | Fixed Unit Price | Total Price | Subtotal | ||||
| BASE BID | ||||||||
| 1 | Remedial Action (RA) Work Plan and Pre-Construction Services | |||||||
| 1.1 | RA Work Plan and Certified/Signed Plans and Specifications1 | |||||||
| (includes pre-construction site survey by a Florida licensed surveyor and pre-construction site visit/photo documentation) | LS | 1 | LS | $0.00 | $0.00 | |||
| 1.2 | Recertification of Construction Drawings and Specifications from Engineer of Record | LS | 1 | LS | $0.00 | $0.00 | ||
| 1.3 | Permitting | LS | 1 | LS | $0.00 | $0.00 | ||
| Subtotal | $0.00 | |||||||
| 2 | Mobilization Services - Pre-Construction Photographic Documentation | LS | 1 | LS | $0.00 | $0.00 | ||
| Subtotal | $0.00 | |||||||
| 3 | Temporary Facilities and Controls | |||||||
| 3.1 | General (Site Services)2 | LS | 1 | LS | $0.00 | $0.00 | ||
| 3.2 | Fencing and Visual Barrier Fabric | UP | 2,700 | LF | $0.00 | $0.00 | ||
| 3.3 | Erosion and Sedimentation Controls | LS | 1 | LS | $0.00 | $0.00 | ||
| 3.4 | Weekly Air Monitoring Reporting for Daily Odor and Vapor Monitoring | LS | 1 | LS | $0.00 | $0.00 | ||
| 3.5 | Contractor Quality Control Plan (CQCP) and Pre-Construction Survey | LS | 1 | LS | $0.00 | $0.00 | ||
| Subtotal | $0.00 | |||||||
| 4 | Construction Water Management Services | |||||||
| 4.1 | Provision of Construction Water Treatment and Temporary Storage System3 | LS | 1 | LS | $0.00 | $0.00 | ||
| 4.2 | Provision of Underground Injection System (includes permitting) | LS | 1 | LS | $0.00 | $0.00 | ||
| 4.3 | Operation and Verification That System is Meeting Treatment Objectives and Sampling Documentation | LS | 1 | LS | $0.00 | $0.00 | ||
| 4.4 | Operation of Construction Water Management System | UP | 244 | Days | $0.00 | $0.00 | ||
| 4.5 | Reporting - Weekly Construction Water Management System Operation Reporting | LS | 1 | LS | $0.00 | $0.00 | ||
| Subtotal | $0.00 | |||||||
| 5 | Building Demolition Services (see contingency items 20 - 24) | |||||||
| 5.1 | Building D | LS | 1 | LS | $0.00 | $0.00 | ||
| 5.2 | Building E | LS | 1 | LS | $0.00 | $0.00 | ||
| 5.3 | Building G | LS | 1 | LS | $0.00 | $0.00 | ||
| 5.4 | Building H | LS | 1 | LS | $0.00 | $0.00 | ||
| 5.5 | Building I | LS | 1 | LS | $0.00 | $0.00 | ||
| 5.6 | Building J | LS | 1 | LS | $0.00 | $0.00 | ||
| 5.7 | Building L | LS | 1 | LS | $0.00 | $0.00 | ||
| 5.8 | Reporting - Building Demolition Weekly Progress Reporting | LS | 1 | LS | $0.00 | $0.00 | ||
| 5.9 | Reporting - Building Demolition Completion Report | LS | 1 | LS | $0.00 | $0.00 | ||
| Subtotal | $0.00 | |||||||
| 6 | Utility Management Services (locate, remove, and bypass) | |||||||
| 6.1 | Sitewide Utility Locate | LS | 1 | LS | $0.00 | $0.00 | ||
| 6.2 | Termination | |||||||
| 6.2.1 | Storm Water | LS | 1 | LS | $0.00 | $0.00 | ||
| 6.2.2 | Sanitary | LS | 1 | LS | $0.00 | $0.00 | ||
| 6.2.3 | Water | LS | 1 | LS | $0.00 | $0.00 | ||
| 6.2.4 | Gas | UP | 2 | EA | $0.00 | $0.00 | ||
| 6.2.5 | Electric | UP | 2 | EA | $0.00 | $0.00 | ||
| 6.2.6 | Telecommunications | UP | 2 | EA | $0.00 | $0.00 | ||
| 6.3 | Removal | |||||||
| 6.3.1 | Stormwater | |||||||
| 6.3.1.2 | Removal and Disposal of Drain Manholes | UP | 3 | EA | $0.00 | $0.00 | ||
| 6.3.1.3 | Removal and Disposal of Catch Basins | UP | 14 | EA | $0.00 | $0.00 | ||
| 6.3.1.4 | Removal and Disposal of Drainage Piping | UP | 520 | LF | $0.00 | $0.00 | ||
| 6.3.2 | Sanitary | |||||||
| 6.3.2.1 | Removal and Disposal of Sewer Manholes | UP | 4 | EA | $0.00 | $0.00 | ||
| 6.3.2.2 | Removal and Disposal of Gravity Sewer Pipelines | UP | 300 | LF | $0.00 | $0.00 | ||
| 6.3.2.3 | Removal and Disposal of Sewer Force Main Pipelines | UP | 550 | LF | $0.00 | $0.00 | ||
| 6.3.3 | Water | |||||||
| 6.3.3.1 | Removal and Disposal of Water Lines | UP | 660 | LF | $0.00 | $0.00 | ||
| 6.3.3.2 | Remove Water Service | UP | 1 | EA | $0.00 | $0.00 | ||
| 6.3.4 | Gas | |||||||
| 6.3.4.1 | Removal and Disposal of Gas Lines | UP | 150 | LF | $0.00 | $0.00 | ||
| 6.3.5 | Electric | |||||||
| 6.3.5.1 | Removal and Disposal of Electric Lines | UP | 500 | LF | $0.00 | $0.00 | ||
| 6.3.5.2 | Removal and Disposal of Underground Electric Lines | UP | 230 | LF | $0.00 | $0.00 | ||
| 6.3.6 | Communication Cable | |||||||
| 6.3.6.1 | Removal and Disposal of Communication Cable | UP | 160 | LF | $0.00 | $0.00 | ||
| 6.4 | Temporary Bypass | |||||||
| 6.4.1 | Install Temporary Stormwater Bypass Lines | LS | 1 | LS | $0.00 | $0.00 | ||
| 6.4.2 | Install Temporary Sanitary Sewer Bypass Lines | LS | 1 | LS | $0.00 | $0.00 | ||
| 6.4.3 | Install Temporary Water Bypass Lines | LS | 1 | LS | $0.00 | $0.00 | ||
| 6.4.4 | Install Temporary Electric Lines | LS | 1 | LS | $0.00 | $0.00 | ||
| 6.4.5 | Install Temporary Communication Cables | LS | 1 | LS | $0.00 | $0.00 | ||
| 6.5 | Reporting - Utility Abandonment/Utility Relocation Weekly Progress Reporting | LS | 1 | LS | $0.00 | $0.00 | ||
| 6.6 | Reporting - Utility Abandonment/Utility Relocation Completion Report | LS | 1 | LS | $0.00 | $0.00 | ||
| Subtotal | $0.00 | |||||||
| 7 | Utility Management Services - Furnish and Install (F&I) | |||||||
| 7.1 | Storm Water (area shown in drawing R-010 and drawing R-003) | |||||||
| 7.1.1 | F&I Catch Basins | UP | 12 | EA | $0.00 | $0.00 | ||
| 7.1.2 | F&I 6" (or equivalent) Perforated PVC Drain Line | UP | 300 | LF | $0.00 | $0.00 | ||
| 7.1.3 | F&I 12" (or equivalent) Perforated PVC Drain Line | UP | 220 | LF | $0.00 | $0.00 | ||
| 7.1.4 | F&I 18" (or equivalent) PVC Drain Line | UP | 290 | LF | $0.00 | $0.00 | ||
| 7.2 | Sanitary | |||||||
| 7.2.1 | F&I Sewer Manholes | UP | 4 | EA | $0.00 | $0.00 | ||
| 7.2.2 | F&I 12" PVC Sanitary Sewer Line | UP | 280 | LF | $0.00 | $0.00 | ||
| 7.2.3 | F&I 6" PVC Sanitary Sewer Line | UP | 245 | LF | $0.00 | $0.00 | ||
| 7.2.4 | F&I 4" PVC Sanitary Sewer Line | UP | 720 | LF | $0.00 | $0.00 | ||
| 7.3 | Water | |||||||
| 7.3.1 | F&I 6" PVC Water Line | UP | 300 | LF | $0.00 | $0.00 | ||
| 7.3.2 | F&I 12" PVC Water Line | UP | 230 | LF | $0.00 | $0.00 | ||
| 7.3.3 | F&I 6"x 6" Tap and Sleeve | UP | 2 | EA | $0.00 | $0.00 | ||
| 7.3.4 | F&I 12" x 12" Tap and Sleeve | UP | 2 | EA | $0.00 | $0.00 | ||
| 7.4 | Gas | |||||||
| 7.4.1 | F&I Gas Line | UP | 150 | LF | $0.00 | $0.00 | ||
| 7.5 | Electric | |||||||
| 7.5.1 | F&I Underground Electric | UP | 230 | LF | $0.00 | $0.00 | ||
| 7.5.2 | F&I Overhead Electric | UP | 440 | LF | $0.00 | $0.00 | ||
| 7.6 | Communications | |||||||
| 7.6.1 | F&I Underground Communications | UP | 260 | LF | $0.00 | $0.00 | ||
| 7.6.2 | F&I Overhead Communications | UP | 450 | LF | $0.00 | $0.00 | ||
| 7.7 | Reporting - Utility Replacement Weekly Progress Reporting | LS | 1 | LS | $0.00 | $0.00 | ||
| 7.8 | Reporting - Utility Replacement Completion Report | LS | 1 | LS | $0.00 | $0.00 | ||
| Subtotal | $0.00 | |||||||
| 8 | Soil Excavation Servies (Outside of Areas 1 through 4) | |||||||
| 8.1 | Building Slab and Foundation Removal | UP | 4,000 | Tons | $0.00 | $0.00 | ||
| 8.2 | Excavation and Management of Soil, Pavement, Utilities, and Debris | UP | 28,000 | CY | $0.00 | $0.00 | ||
| 8.3 | Reporting - Soil Excavation (Outside of Areas 1 through 4) Weekly Progress Reporting that include the daily material removal status | LS | 1 | LS | $0.00 | $0.00 | ||
| 8.4 | Submittal of the As-Built drawings showing extent of post excavation limits | LS | 1 | LS | $0.00 | $0.00 | ||
| Subtotal | $0.00 | |||||||
| 9 | Excavation Services (Areas 1 through 4) | |||||||
| 9.1 | Area 1 (Excavation and Management of Soil, Pavement, Utilities, and Debris) | UP | 1,380 | CY | $0.00 | $0.00 | ||
| 9.2 | Area 2 (Excavation and Management of Soil, Pavement, Utilities, and Debris) | UP | 400 | CY | $0.00 | $0.00 | ||
| 9.3 | Area 3 (Excavation and Management of Soil, Pavement, Utilities, and Debris) | UP | 810 | CY | $0.00 | $0.00 | ||
| 9.4 | Area 4 (Excavation and Management of Soil, Pavement, Utilities, and Debris) | UP | 1,300 | CY | $0.00 | $0.00 | ||
| 9.5 | Reporting - Soil Excavation (Areas 1 through 4) Weekly Progress Reporting that include the daily material removal status | LS | 1 | LS | $0.00 | $0.00 | ||
| 9.6 | Submittal of the As-Builts drawings showing extent of post excavation limits | LS | 1 | LS | $0.00 | $0.00 | ||
| Subtotal | $0.00 | |||||||
| 10 | ISS Treatment (see contingency items 16, 17, 18, & 19) Services | |||||||
| 10.1 | ISS Mix Design Verification (Test Section - 12 ISS columns) | LS | 1 | LS | $0.00 | $0.00 | ||
| 10.2 | ISS Treatment (Shallow [Less Than or Equal to 8ft BGS]) | UP | 50,147 | CY | $0.00 | $0.00 | ||
| 10.3 | ISS Treatment (Deep [Greater Than 8ft BGS]) | UP | 42,875 | CY | $0.00 | $0.00 | ||
| 10.4 | ISS Column Wall Surrounding four sides of K-2 building4 | UP | 840 | LF | $0.00 | $0.00 | ||
| 10.5 | ISS Swell Management | UP | 52,000 | Tons | $0.00 | $0.00 | ||
| 10.6 | Reporting - ISS Treatments Daily Progress Reporting and As-Built drawings | LS | 1 | LS | $0.00 | $0.00 | ||
| 10.7 | Submittal of the As-Built drawings showing extent of ISS top and bottom column elevations | LS | 1 | LS | $0.00 | $0.00 | ||
| Subtotal | $0.00 | |||||||
| 11 | Transportation and Disposal Services | |||||||
| 11.1 | Demolition Materials | |||||||
| 11.1.1 | C&D Debris | UP | 5,000 | Tons | $0.00 | $0.00 | ||
| 11.2 | Disposal of Excavated Material | |||||||
| 11.2.1 | Subtitle D Disposal of Material Excavated from Areas 1 - 4 and the ISS Area | UP | 45,000 | Tons | $0.00 | $0.00 | ||
| 11.3 | ISS Swell | |||||||
| 11.3.1 | Subtitle D Disposal of ISS Swell Material | UP | 52,000 | Tons | $0.00 | $0.00 | ||
| 11.4 | Reporting - Transportation and Disposal Weekly Progress Reporting | LS | 1 | LS | $0.00 | $0.00 | ||
| Subtotal | $0.00 | |||||||
| 12 | Backfill / Restoration Services | |||||||
| 12.1 | Utility Corridors (see drawing R-010) | UP | 2,300 | LF | $0.00 | $0.00 | ||
| 12.2 | Fine Aggregate | UP | 300 | CY | $0.00 | $0.00 | ||
| 12.3 | Coarse Aggregate | UP | 13,700 | CY | $0.00 | $0.00 | ||
| 12.4 | Backfill and Compaction of Excavation Areas 1 - 4 and the ISS Area5 | UP | 18,190 | CY | $0.00 | $0.00 | ||
| 12.5 | Landscape Soil | UP | 1,100 | CY | $0.00 | $0.00 | ||
| 12.6 | Geotextile | UP | 29,200 | SY | $0.00 | $0.00 | ||
| 12.7 | Seeding (include 2 weeks of watering) | UP | 1 | AC | $0.00 | $0.00 | ||
| 12.8 | LLDPE Liner | UP | 1,815 | LF | $0.00 | $0.00 | ||
| 12.9 | Piping Network (see drawing R-010) | LS | 1 | LS | $0.00 | $0.00 | ||
| 12.9.1 | F&I Leaching Catch Basins | UP | 7 | EA | $0.00 | $0.00 | ||
| 12.9.2 | F&I Cleanout Catch Basins | UP | 26 | EA | $0.00 | $0.00 | ||
| 12.9.3 | F&I 12" HDPE Trunk/Header Pipe | UP | 600 | LF | $0.00 | $0.00 | ||
| 12.9.4 | F&I 6" HDPE Lateral Pipe | UP | 1850 | LF | $0.00 | $0.00 | ||
| 12.10 | 10,000-gallon Cistern Tank and Lift Station | LS | 1 | LS | $0.00 | $0.00 | ||
| 12.11 | Subtitle D Disposal of Soil and Debris Excavated for the F&I Tank Installation | LS | 1 | LS | $0.00 | $0.00 | ||
| 12.12 | Reporting - Site Restoration Weekly Progress Reporting including quality assurance (QA) testing and verification | LS | 1 | LS | $0.00 | $0.00 | ||
| Subtotal | $0.00 | |||||||
| 13 | Asphalt Paving Services | |||||||
| 13.1 | Soil Excavation Areas 1 and 2 | |||||||
| 13.1.1 | Bituminous Asphalt | UP | 1,580 | Tons | $0.00 | $0.00 | ||
| 13.1.2 | 8" Lime Rock | UP | 23,000 | SY | $0.00 | $0.00 | ||
| 13.1.3 | Type B Stabilization 12" LBR=40 | UP | 23,000 | SY | $0.00 | $0.00 | ||
| 13.2 | Area 4 | |||||||
| 13.2.1 | Bituminous Asphalt | UP | 130 | Tons | $0.00 | $0.00 | ||
| 13.2.2 | 8" Lime Rock | UP | 1,850 | SY | $0.00 | $0.00 | ||
| 13.2.3 | Type B Stabilization 12" LBR=40 | UP | 1,850 | SY | $0.00 | $0.00 | ||
| 13.3 | Area 3 | |||||||
| 13.3.1 | Bituminous Asphalt | UP | 110 | Tons | $0.00 | $0.00 | ||
| 13.3.2 | 8" Lime Rock | UP | 1,600 | SY | $0.00 | $0.00 | ||
| 13.3.3 | Type B Stabilization 12" LBR=40 | UP | 1,600 | SY | $0.00 | $0.00 | ||
| 13.4 | Reporting - Site Restoration Weekly Progress Reporting including QA testing and verification | LS | 1 | LS | $0.00 | $0.00 | ||
| Subtotal | $0.00 | |||||||
| 14 | Well Abandonment Services | |||||||
| 14.1 | Leave in Place, Grout, and Incorporate into ISS Matrix | |||||||
| UP | 51 | EA | $0.00 | $0.00 | ||||
| 14.2 | Overdrill Well Casing/Screen, Remove the Well, and Grout Borehole (for depths of 30 feet and under) | UP | 11 | EA | $0.00 | $0.00 | ||
| 14.3 | Reporting - Well Abandonment Completion Report | LS | 1 | LS | $0.00 | $0.00 | ||
| Subtotal | $0.00 | |||||||
| 15 | Demobilization Services | LS | 1 | LS | $0.00 | $0.00 | ||
| 15.1 | Construction Completion Report | LS | 1 | LS | $0.00 | $0.00 | ||
| Subtotal | $0.00 | |||||||
| GRAND TOTAL | ||||||||
| NOTE: Grand Total will be used as a part of Awarding price points in accordance with Section 5 of the RFP. | $0.00 |
| Item No. | Item | Basis of | ||||
| Payment | Estimated | |||||
| Quantity | Unit | Fixed Unit Price | ||||
| CONTINGENCY ITEMS (FIXED UNIT PRICE REQUIRED) | ||||||
| 16 | ISS Revised Mixture (if needed) | LS | 1 | LS | $0.00 | |
| 16.1 | Portland Cement | UP | 1 | Tons | $0.00 | |
| 16.2 | Ground Blast Granulated Slag | UP | 1 | Tons | $0.00 | |
| 15.3 | Bentonite | UP | 1 | Tons | $0.00 |
| 17 | Contingent Vapor and Odor Control Foam System | ||||
| 17.1 | Provision of Odor Control Foam System | LS | 1 | LS | $0.00 |
| 17.2 | Operation of Odor Control Foam System | UP | 8‐Hour Shift | $0.00 |
| 18 | Contingent Vapor and Odor Control Spray Cover System | ||||
| 18.1 | Provision of Spray Cover System | LS | 1 | LS | $0.00 |
| 18.2 | Operation of Spray Cover System | UP | 8‐Hour Shift | $0.00 |
| 19 | Contingent Auger Shroud and Carbon Capture System | ||||
| 19.1 | Provision of Auger Shroud and Carbon Capture System | LS | 1 | LS | $0.00 |
| 19.2 | Operation of Auger Shroud and Carbon Capture System | UP | 8‐Hour Shift | $0.00 | |
| 19.3 | Carbon Capture System Consumables ‐ Carbon | UP | EA | $0.00 |
| 20 | Asbestos and RCRA Abatement (includes inspection, testing, waste removal, segregation, and disposal) | ||||
| 20.1 | Asbestos - Mastic/Tiles | UP | Per | CY | $0.00 |
| 20.2 | Asbestos - Wrapped Pipe, Etc. | UP | Per | LF | $0.00 |
| 20.3 | RCRA Metals | UP | Per | Tons | $0.00 |
| 20.4 | RCRA Organics | UP | Per | Tons | $0.00 |
| 21 | Lead Abatement (includes inspection, testing, waste removal, segregation, and disposal) | ||||
| 21.1 | Lead Paint | UP | Per | SF | $0.00 |
| 21.2 | Other Potential Lead Abatement (Former Gun Range) | UP | Per | Tons | $0.00 |
| 22 | Universal Waste (includes waste removal, segregation, and disposal) | ||||
| 22.1 | Universal Waste | UP | Per | Tons | $0.00 |
| 23 | Construction & Demolition Waste (C &D) (includes office furniture waste removal and disposal)6 | ||||
| 23.1 | C&D Waste | UP | Per | Tons | $0.00 |
| 24 | Subtitle C Disposal | ||||
| 24.1 | Excavated Material Subtitle C | UP | Per | Tons | $0.00 |
| 24.2 | ISS Swell Subtitle C | UP | Per | Tons | $0.00 |
| 25 | Well Abandonment | ||||
| 25.1 | Overdrill Well Casing/Screen, Remove the Well, and Grout Borehole (for depths over 30 feet) | UP | Per | LF | $0.00 |
| UP = Unit Price | Notes: | Notes: |
| LS = Lump Sum | DO NOT FILL IN GREYED OUT CELLS | Do not enter any information in greyed out cells |
| CY = Cubic Yards | 1 RA Work Plan - Contractor should consider incorporation of DEP/EPA comments on draft work plans. The RA Work Plan will include all deliverables included in design specifications (see Section 01 36 00 Technical Specifications). | |
| LF = Linear Feet | ||
| SF = Square Feet | ||
| SY = Square Yard | 2 Site Services - Pricing includes set up of a onsite construction office trailer. | |
| EA = Each | 3 Includes temporary storage and disposal (under 10.2.1) of NAPL collected from the Construction Water Treatment System. | |
| AC = Acre | ||
| ISS= In-situ Soil Stabilization/Solidification | 4 This pricing includes the utility management, removal and replacement of concrete pavement along the east side of K-2 building (see drawings C-013 and C-014). | |
| Day = 10 hours | ||
| 5 This backfill will be the coarse aggregate in the ISS area (Design Drawing R-011). This volume includes the total excavation volume (31,890) less the coarse aggregate volume (13,700). |
6 The office furniture and interior warehouse items shall be removed by the property owner and tenants prior to construction activities. This bid item will be used to address any ancillary items or debris that remain after the warehouses have been vacated.
File details come from the government source that posted it. Updated .