Form D - Rate Schedule.xlsx

XLSX spreadsheet 51 KB Posted

Attached to
Re-Advertisement for Petroleum Products Corporation Superfund Site Remedial Action Services
Solicitation number
RFP-15168
Issued by
Leon County, Florida

About this file

This is a Form D Rate Schedule submitted by the State of Florida Department of Environmental Protection for the Petroleum Products Corporation Superfund Site Remedial Action Services contract. The schedule establishes fixed unit prices for a comprehensive environmental remediation project encompassing building demolition, utility management, soil excavation, in-situ soil stabilization/solidification (ISS) treatment, backfill and restoration, asphalt paving, well abandonment, and waste disposal services. The project involves 15 primary service categories with multiple line items, including demolition of seven buildings (D, E, G, H, I, J, L), excavation of approximately 31,890 cubic yards from designated areas, ISS treatment of approximately 93,022 cubic yards across shallow and deep zones, removal and replacement of utilities (stormwater, sanitary, water, gas, electric, and telecommunications), transportation and disposal of approximately 102,000 tons of materials, and site restoration including asphalt paving and landscaping. The contract includes both initial and renewal term sections with identical pricing structures, along with 10 contingency item categories addressing potential scope variations such as revised ISS mixtures, vapor and odor control systems, asbestos and RCRA abatement, lead abatement, and universal waste disposal.

The rate schedule requires respondents to enter fixed unit prices in purple-shaded cells for each line item; any blank cells or zeros result in those services being offered at no cost to the State. Rates serve as ceiling rates that may be reduced at the State's discretion through task assignments. The contractor must complete both the electronic (Excel format) and hard copy versions of this form without modifications, assumptions, or additional terms. The grand total of all base bid items is used for award scoring in accordance with Section 5 of the RFP. All contingency items require fixed unit price quotations for potential scope variations, including specialized pricing for material quantities (per cubic yard, linear foot, square foot, or ton) or shifts of work (eight-hour shifts for equipment operation). The document emphasizes strict compliance with submission requirements and prohibits any alterations to the pre-formatted schedule structure.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Instructions State of Florida Department of Environmental Protection Form D - Rate Schedule Instructions The Rate Schedule must contain complete responses to all items. Any blank spaces or zeros (0) added to any of the cells will result in that service being offered at no cost to the State.

Rates contained within are ceiling rates that may be quoted at a lower rate per Task Assignment.

This worksheet must be included in both the electronic proposal (original Excel format) and the hard copy proposal (the print area is already pre-set for this worksheet).

The Respondent shall not modify Rate Schedule.

The Respondent shall not add or provide any assumptions, contingencies, or additional terms to the Rate Schedule.

The Respondent shall enter text in the purple shaded cells as indicated below:

1)Enter Respondent Name in cell B2.
2)Enter the Fixed Unit Price for each Item in column F.
3)Review Data entries for accuracy.

Review the header information, checking for any formula errors and ensure the rates for each pay item price are accurate.

Initial Contract Term State of Florida Department of Environmental Protection Form D - Rate Schedule Initial Contract Term

Contractor Name:
Item No.ItemBasis of
PaymentEstimated
QuantityUnitFixed Unit PriceTotal PriceSubtotal
BASE BID
1Remedial Action (RA) Work Plan and Pre-Construction Services
1.1RA Work Plan and Certified/Signed Plans and Specifications1
(includes pre-construction site survey by a Florida licensed surveyor and pre-construction site visit/photo documentation)LS1LS$0.00$0.00
1.2Recertification of Construction Drawings and Specifications from Engineer of RecordLS1LS$0.00$0.00
1.3PermittingLS1LS$0.00$0.00
Subtotal$0.00
2Mobilization Services - Pre-Construction Photographic DocumentationLS1LS$0.00$0.00
Subtotal$0.00
3Temporary Facilities and Controls
3.1General (Site Services)2LS1LS$0.00$0.00
3.2Fencing and Visual Barrier FabricUP2,700LF$0.00$0.00
3.3Erosion and Sedimentation ControlsLS1LS$0.00$0.00
3.4Weekly Air Monitoring Reporting for Daily Odor and Vapor MonitoringLS1LS$0.00$0.00
3.5Contractor Quality Control Plan (CQCP) and Pre-Construction SurveyLS1LS$0.00$0.00
Subtotal$0.00
4Construction Water Management Services
4.1Provision of Construction Water Treatment and Temporary Storage System3LS1LS$0.00$0.00
4.2Provision of Underground Injection System (includes permitting)LS1LS$0.00$0.00
4.3Operation and Verification That System is Meeting Treatment Objectives and Sampling DocumentationLS1LS$0.00$0.00
4.4Operation of Construction Water Management SystemUP244Days$0.00$0.00
4.5Reporting - Weekly Construction Water Management System Operation ReportingLS1LS$0.00$0.00
Subtotal$0.00
5Building Demolition Services (see contingency items 20 - 24)
5.1Building DLS1LS$0.00$0.00
5.2Building ELS1LS$0.00$0.00
5.3Building GLS1LS$0.00$0.00
5.4Building HLS1LS$0.00$0.00
5.5Building ILS1LS$0.00$0.00
5.6Building JLS1LS$0.00$0.00
5.7Building LLS1LS$0.00$0.00
5.8Reporting - Building Demolition Weekly Progress ReportingLS1LS$0.00$0.00
5.9Reporting - Building Demolition Completion ReportLS1LS$0.00$0.00
Subtotal$0.00
6Utility Management Services (locate, removal, and bypass)
6.1Sitewide Utility LocateLS1LS$0.00$0.00
6.2Termination
6.2.1Storm WaterLS1LS$0.00$0.00
6.2.2SanitaryLS1LS$0.00$0.00
6.2.3WaterLS1LS$0.00$0.00
6.2.4GasUP2EA$0.00$0.00
6.2.5ElectricUP2EA$0.00$0.00
6.2.6TelecommunicationsUP2EA$0.00$0.00
6.3Removal
6.3.1Stormwater
6.3.1.2Removal and Disposal of Drain ManholesUP3EA$0.00$0.00
6.3.1.3Removal and Disposal of Catch BasinsUP14EA$0.00$0.00
6.3.1.4Removal and Disposal of Drainage PipingUP520LF$0.00$0.00
6.3.2Sanitary
6.3.2.1Removal and Disposal of Sewer ManholesUP4EA$0.00$0.00
6.3.2.2Removal and Disposal of Gravity Sewer PipelinesUP300LF$0.00$0.00
6.3.2.3Removal and Disposal of Sewer Force Main PipelinesUP550LF$0.00$0.00
6.3.3Water
6.3.3.1Removal and Disposal of Water LinesUP660LF$0.00$0.00
6.3.3.2Remove Water ServiceUP1EA$0.00$0.00
6.3.4Gas
6.3.4.1Removal and Disposal of Gas LinesUP150LF$0.00$0.00
6.3.5Electric
6.3.5.1Removal and Disposal of Electric LinesUP500LF$0.00$0.00
6.3.5.2Removal and Disposal of Underground Electric LinesUP230LF$0.00$0.00
6.3.6Communication Cable
6.3.6.1Removal and Disposal of Communication CableUP160LF$0.00$0.00
6.4Temporary Bypass
6.4.1Install Temporary Stormwater Bypass LinesLS1LS$0.00$0.00
6.4.2Install Temporary Sanitary Sewer Bypass LinesLS1LS$0.00$0.00
6.4.3Install Temporary Water Bypass LinesLS1LS$0.00$0.00
6.4.4Install Temporary Electric LinesLS1LS$0.00$0.00
6.4.5Install Temporary Communication CablesLS1LS$0.00$0.00
6.5Reporting - Utility Abandonment/Utility Relocation Weekly Progress ReportingLS1LS$0.00$0.00
6.6Reporting - Utility Abandonment/Utility Relocation Completion ReportLS1LS$0.00$0.00
Subtotal$0.00
7Utility Management Services - Furnish and Install (F&I)
7.1Storm Water (area shown in drawing R-010 and drawing R-003)
7.1.1F&I Catch BasinsUP12EA$0.00$0.00
7.1.2F&I 6" (or equivalent) Perforated PVC Drain LineUP300LF$0.00$0.00
7.1.3F&I 12" (or equivalent) Perforated PVC Drain LineUP220LF$0.00$0.00
7.1.4F&I 18" (or equivalent) PVC Drain LineUP290LF$0.00$0.00
7.2Sanitary
7.2.1F&I Sewer ManholesUP4EA$0.00$0.00
7.2.2F&I 12" PVC Sanitary Sewer LineUP280LF$0.00$0.00
7.2.3F&I 6" PVC Sanitary Sewer LineUP245LF$0.00$0.00
7.2.4F&I 4" PVC Sanitary Sewer LineUP720LF$0.00$0.00
7.3Water
7.3.1F&I 6" PVC Water LineUP300LF$0.00$0.00
7.3.2F&I 12" PVC Water LineUP230LF$0.00$0.00
7.3.3F&I 6"x 6" Tap and SleeveUP2EA$0.00$0.00
7.3.4F&I 12" x 12" Tap and SleeveUP2EA$0.00$0.00
7.4Gas
7.4.1F&I Gas LineUP150LF$0.00$0.00
7.5Electric
7.5.1F&I Underground ElectricUP230LF$0.00$0.00
7.5.2F&I Overhead ElectricUP440LF$0.00$0.00
7.6Communications
7.6.1F&I Underground CommunicationsUP260LF$0.00$0.00
7.6.2F&I Overhead CommunicationsUP450LF$0.00$0.00
7.7Reporting - Utility Replacement Weekly Progress ReportingLS1LS$0.00$0.00
7.8Reporting - Utility Replacement Completion ReportLS1LS$0.00$0.00
Subtotal$0.00
8Soil Excavation Services (Outside of Areas 1 through 4)
8.1Building Slab and Foundation RemovalUP4,000Tons$0.00$0.00
8.2Excavation and Management of Soil, Pavement, Utilities, and DebrisUP28,000CY$0.00$0.00
8.3Reporting - Soil Excavation (Outside of Areas 1 through 4) Weekly Progress Reporting that include the daily material removal statusLS1LS$0.00$0.00
8.4Submittal of the As-Built drawings showing extent of post excavation limitsLS1LS$5.00$5.00
Subtotal$5.00
9Excavation Services (Areas 1 through 4)
9.1Area 1 (Excavation and Management of Soil, Pavement, Utilities, and Debris)UP1,380CY$0.00$0.00
9.2Area 2 (Excavation and Management of Soil, Pavement, Utilities, and Debris)UP400CY$0.00$0.00
9.3Area 3 (Excavation and Management of Soil, Pavement, Utilities, and Debris)UP810CY$0.00$0.00
9.4Area 4 (Excavation and Management of Soil, Pavement, Utilities, and Debris)UP1,300CY$0.00$0.00
9.5Reporting - Soil Excavation (Areas 1 through 4) Weekly Progress Reporting that include the daily material removal statusLS1LS$0.00$0.00
9.6Submittal of the As-Builts drawings showing extent of post excavation limitsLS1LS$0.00$0.00
Subtotal$0.00
10ISS Treatment (see contingency items 16, 17, 18, & 19) Services
10.1ISS Mix Design Verification (Test Section - 12 ISS columns)LS1LS$0.00$0.00
10.2ISS Treatment (Shallow [Less Than or Equal to 8ft BGS])UP50,147CY$0.00$0.00
10.3ISS Treatment (Deep [Greater Than 8ft BGS])UP42,875CY$0.00$0.00
10.4ISS Column Wall Surrounding four sides of K-2 building4UP840LF$0.00$0.00
10.5ISS Swell ManagementUP52,000Tons$0.00$0.00
10.6Reporting - ISS Treatments Daily Progress ReportingLS1LS$0.00$0.00
10.7Submittal of the As-Built drawings showing extent of ISS top and bottom column elevationsLS1LS$0.00$0.00
Subtotal$0.00
11Transportation and Disposal Services
11.1Demolition Materials
11.1.1C&D DebrisUP5,000Tons$0.00$0.00
11.2Disposal of Excavated Material
11.2.1Subtitle D Disposal of Material Excavated from Areas 1 - 4 and the ISS AreaUP45,000Tons$0.00$0.00
11.3ISS Swell
11.3.1Subtitle D Disposal of ISS Swell MaterialUP52,000Tons$0.00$0.00
11.4Reporting - Transportation and Disposal Weekly Progress ReportingLS1LS$0.00$0.00
Subtotal$0.00
12Backfill / Restoration Services
12.1Utility Corridors (see drawing R-010)UP2,300LF$0.00$0.00
12.2Fine AggregateUP300CY$0.00$0.00
12.3Coarse AggregateUP13,700CY$0.00$0.00
12.4Backfill and Compaction of Excavation Areas 1 - 4 and the ISS Area5UP18,190CY$0.00$0.00
12.5Landscape SoilUP1,100CY$0.00$0.00
12.6GeotextileUP29,200SY$0.00$0.00
12.7Seeding (include 2 weeks of watering)UP1AC$0.00$0.00
12.8LLDPE LinerUP1,815LF$0.00$0.00
12.9Piping Network (see drawing R-010)LS1LS$0.00$0.00
12.9.1F&I Leaching Catch BasinsUP7EA$0.00$0.00
12.9.2F&I Cleanout Catch BasinsUP26EA$0.00$0.00
12.9.3F&I 12" HDPE Trunk/Header PipeUP600LF$0.00$0.00
12.9.4F&I 6" HDPE Lateral PipeUP1850LF$0.00$0.00
12.1010,000-gallon Cistern Tank and Lift StationLS1LS$0.00$0.00
12.11Subtitle D Disposal of Soil and Debris Excavated for the F&I Tank InstallationLS1LS$0.00$0.00
12.12Reporting - Site Restoration Weekly Progress Reporting including quality assurance (QA) testing and verificationLS1LS$0.00$0.00
Subtotal$0.00
13Asphalt Paving Services
13.1Soil Excavation Areas 1 and 2
13.1.1Bituminous AsphaltUP1,580Tons$0.00$0.00
13.1.28" Lime RockUP23,000SY$0.00$0.00
13.1.3Type B Stabilization 12" LBR=40UP23,000SY$0.00$0.00
13.2Area 4
13.2.1Bituminous AsphaltUP130Tons$0.00$0.00
13.2.28" Lime RockUP1,850SY$0.00$0.00
13.2.3Type B Stabilization 12" LBR=40UP1,850SY$0.00$0.00
13.3Area 3
13.3.1Bituminous AsphaltUP110Tons$0.00$0.00
13.3.28" Lime RockUP1,600SY$0.00$0.00
13.3.3Type B Stabilization 12" LBR=40UP1,600SY$0.00$0.00
13.4Reporting - Site Restoration Weekly Progress Reporting including QA testing and verificationLS1LS$0.00$0.00
Subtotal$0.00
14Well Abandonment Services
14.1Leave in Place, Grout, and Incorporate into ISS Matrix
UP51EA$0.00$0.00
14.2Overdrill Well Casing/Screen, Remove the Well, and Grout Borehole (for depths of 30 feet and under)UP11EA$0.00$0.00
14.3Reporting - Well Abandonment Completion ReportLS1LS$0.00$0.00
Subtotal$0.00
15Demobilization ServicesLS1LS$0.00$0.00
15.1Construction Completion ReportLS1LS$0.00$0.00
Subtotal$0.00
GRAND TOTAL
NOTE: Grand Total will be used as a part of Awarding price points in accordance with Section 5 of the RFP.$5.00
Item No.ItemBasis of
PaymentEstimated
QuantityUnitFixed Unit Price
CONTINGENCY ITEMS (FIXED UNIT PRICE REQUIRED)
16ISS Revised Mixture (if needed)LS1LS$0.00
16.1Portland CementUP1Tons$0.00
16.2Ground Blast Granulated SlagUP1Tons$0.00
15.3BentoniteUP1Tons$0.00
17Contingent Vapor and Odor Control Foam System
17.1Provision of Odor Control Foam SystemLS1LS$0.00
17.2Operation of Odor Control Foam SystemUP8‐Hour Shift$0.00
18Contingent Vapor and Odor Control Spray Cover System
18.1Provision of Spray Cover SystemLS1LS$0.00
18.2Operation of Spray Cover SystemUP8‐Hour Shift$0.00
19Contingent Auger Shroud and Carbon Capture System
19.1Provision of Auger Shroud and Carbon Capture SystemLS1LS$0.00
19.2Operation of Auger Shroud and Carbon Capture SystemUP8‐Hour Shift$0.00
19.3Carbon Capture System Consumables ‐ CarbonUPEA$0.00
20Asbestos and RCRA Abatement (includes inspection, testing, waste removal, segregation, and disposal)
20.1Asbestos - Mastic/TilesUPPerCY$0.00
20.2Asbestos - Wrapped Pipe, Etc.UPPerLF$0.00
20.3RCRA MetalsUPPerTons$0.00
20.4RCRA OrganicsUPPerTons$0.00
21Lead Abatement (includes inspection, testing, waste removal, segregation, and disposal)
21.1Lead PaintUPPerSF$0.00
21.2Other Potential Lead Abatement (Former Gun Range)UPPerTons$0.00
22Universal Waste (includes waste removal, segregation, and disposal)
22.1Universal WasteUPPerTons$0.00
23Construciton & Demonlition Waste (C & D) (includes office furniture waste removal and disposal)6
23.1C&D WasteUPPerTons$0.00
24Subtitle C Disposal
24.1Excavated Material Subtitle CUPPerTons$0.00
24.2ISS Swell Subtitle CUPPerTons$0.00
25Well Abandonment
25.1Overdrill Well Casing/Screen, Remove the Well, and Grout Borehole (for depths over 30 feet)UPPerLF$0.00
UP = Unit PriceNotes:Notes:
LS = Lump SumDO NOT FILL IN GREYED OUT CELLSDo not enter any information in greyed out cells
CY = Cubic Yards1 RA Work Plan - Contractor should consider incorporation of DEP/EPA comments on draft work plans. The RA Work Plan will include all deliverables included in design specifications (see Section 01 36 00 Technical Specifications).
LF = Linear Feet
SF = Square Feet
SY = Square Yard2 Site Services - Pricing includes set up of a onsite construction office trailer.
EA = Each3 Includes temporary storage and disposal (under 10.2.1) of NAPL collected from the Construction Water Treatment System.
AC = Acre
ISS= In-situ Soil Stabilization/Solidification4 This pricing includes the utility management, removal and replacement of concrete pavement along the east side of K-2 building (see drawings C-013 and C-014).
Day = 10 hours
5 This backfill will be the coarse aggregate in the ISS area (Design Drawing R-011). This volume includes the total excavation volume (31,890) less the coarse aggregate volume (13,700).

6 The office furniture and interior warehouse items shall be removed by the property owner and tenants prior to construction activities. This bid item will be used to address any ancillary items or debris that remain after the warehouses have been vacated.

Renewal Contract Term State of Florida Department of Environmental Protection Form D - Rate Schedule Renewal Contract Term

Contractor Name:
Item No.ItemBasis of
PaymentEstimated
QuantityUnitFixed Unit PriceTotal PriceSubtotal
BASE BID
1Remedial Action (RA) Work Plan and Pre-Construction Services
1.1RA Work Plan and Certified/Signed Plans and Specifications1
(includes pre-construction site survey by a Florida licensed surveyor and pre-construction site visit/photo documentation)LS1LS$0.00$0.00
1.2Recertification of Construction Drawings and Specifications from Engineer of RecordLS1LS$0.00$0.00
1.3PermittingLS1LS$0.00$0.00
Subtotal$0.00
2Mobilization Services - Pre-Construction Photographic DocumentationLS1LS$0.00$0.00
Subtotal$0.00
3Temporary Facilities and Controls
3.1General (Site Services)2LS1LS$0.00$0.00
3.2Fencing and Visual Barrier FabricUP2,700LF$0.00$0.00
3.3Erosion and Sedimentation ControlsLS1LS$0.00$0.00
3.4Weekly Air Monitoring Reporting for Daily Odor and Vapor MonitoringLS1LS$0.00$0.00
3.5Contractor Quality Control Plan (CQCP) and Pre-Construction SurveyLS1LS$0.00$0.00
Subtotal$0.00
4Construction Water Management Services
4.1Provision of Construction Water Treatment and Temporary Storage System3LS1LS$0.00$0.00
4.2Provision of Underground Injection System (includes permitting)LS1LS$0.00$0.00
4.3Operation and Verification That System is Meeting Treatment Objectives and Sampling DocumentationLS1LS$0.00$0.00
4.4Operation of Construction Water Management SystemUP244Days$0.00$0.00
4.5Reporting - Weekly Construction Water Management System Operation ReportingLS1LS$0.00$0.00
Subtotal$0.00
5Building Demolition Services (see contingency items 20 - 24)
5.1Building DLS1LS$0.00$0.00
5.2Building ELS1LS$0.00$0.00
5.3Building GLS1LS$0.00$0.00
5.4Building HLS1LS$0.00$0.00
5.5Building ILS1LS$0.00$0.00
5.6Building JLS1LS$0.00$0.00
5.7Building LLS1LS$0.00$0.00
5.8Reporting - Building Demolition Weekly Progress ReportingLS1LS$0.00$0.00
5.9Reporting - Building Demolition Completion ReportLS1LS$0.00$0.00
Subtotal$0.00
6Utility Management Services (locate, remove, and bypass)
6.1Sitewide Utility LocateLS1LS$0.00$0.00
6.2Termination
6.2.1Storm WaterLS1LS$0.00$0.00
6.2.2SanitaryLS1LS$0.00$0.00
6.2.3WaterLS1LS$0.00$0.00
6.2.4GasUP2EA$0.00$0.00
6.2.5ElectricUP2EA$0.00$0.00
6.2.6TelecommunicationsUP2EA$0.00$0.00
6.3Removal
6.3.1Stormwater
6.3.1.2Removal and Disposal of Drain ManholesUP3EA$0.00$0.00
6.3.1.3Removal and Disposal of Catch BasinsUP14EA$0.00$0.00
6.3.1.4Removal and Disposal of Drainage PipingUP520LF$0.00$0.00
6.3.2Sanitary
6.3.2.1Removal and Disposal of Sewer ManholesUP4EA$0.00$0.00
6.3.2.2Removal and Disposal of Gravity Sewer PipelinesUP300LF$0.00$0.00
6.3.2.3Removal and Disposal of Sewer Force Main PipelinesUP550LF$0.00$0.00
6.3.3Water
6.3.3.1Removal and Disposal of Water LinesUP660LF$0.00$0.00
6.3.3.2Remove Water ServiceUP1EA$0.00$0.00
6.3.4Gas
6.3.4.1Removal and Disposal of Gas LinesUP150LF$0.00$0.00
6.3.5Electric
6.3.5.1Removal and Disposal of Electric LinesUP500LF$0.00$0.00
6.3.5.2Removal and Disposal of Underground Electric LinesUP230LF$0.00$0.00
6.3.6Communication Cable
6.3.6.1Removal and Disposal of Communication CableUP160LF$0.00$0.00
6.4Temporary Bypass
6.4.1Install Temporary Stormwater Bypass LinesLS1LS$0.00$0.00
6.4.2Install Temporary Sanitary Sewer Bypass LinesLS1LS$0.00$0.00
6.4.3Install Temporary Water Bypass LinesLS1LS$0.00$0.00
6.4.4Install Temporary Electric LinesLS1LS$0.00$0.00
6.4.5Install Temporary Communication CablesLS1LS$0.00$0.00
6.5Reporting - Utility Abandonment/Utility Relocation Weekly Progress ReportingLS1LS$0.00$0.00
6.6Reporting - Utility Abandonment/Utility Relocation Completion ReportLS1LS$0.00$0.00
Subtotal$0.00
7Utility Management Services - Furnish and Install (F&I)
7.1Storm Water (area shown in drawing R-010 and drawing R-003)
7.1.1F&I Catch BasinsUP12EA$0.00$0.00
7.1.2F&I 6" (or equivalent) Perforated PVC Drain LineUP300LF$0.00$0.00
7.1.3F&I 12" (or equivalent) Perforated PVC Drain LineUP220LF$0.00$0.00
7.1.4F&I 18" (or equivalent) PVC Drain LineUP290LF$0.00$0.00
7.2Sanitary
7.2.1F&I Sewer ManholesUP4EA$0.00$0.00
7.2.2F&I 12" PVC Sanitary Sewer LineUP280LF$0.00$0.00
7.2.3F&I 6" PVC Sanitary Sewer LineUP245LF$0.00$0.00
7.2.4F&I 4" PVC Sanitary Sewer LineUP720LF$0.00$0.00
7.3Water
7.3.1F&I 6" PVC Water LineUP300LF$0.00$0.00
7.3.2F&I 12" PVC Water LineUP230LF$0.00$0.00
7.3.3F&I 6"x 6" Tap and SleeveUP2EA$0.00$0.00
7.3.4F&I 12" x 12" Tap and SleeveUP2EA$0.00$0.00
7.4Gas
7.4.1F&I Gas LineUP150LF$0.00$0.00
7.5Electric
7.5.1F&I Underground ElectricUP230LF$0.00$0.00
7.5.2F&I Overhead ElectricUP440LF$0.00$0.00
7.6Communications
7.6.1F&I Underground CommunicationsUP260LF$0.00$0.00
7.6.2F&I Overhead CommunicationsUP450LF$0.00$0.00
7.7Reporting - Utility Replacement Weekly Progress ReportingLS1LS$0.00$0.00
7.8Reporting - Utility Replacement Completion ReportLS1LS$0.00$0.00
Subtotal$0.00
8Soil Excavation Servies (Outside of Areas 1 through 4)
8.1Building Slab and Foundation RemovalUP4,000Tons$0.00$0.00
8.2Excavation and Management of Soil, Pavement, Utilities, and DebrisUP28,000CY$0.00$0.00
8.3Reporting - Soil Excavation (Outside of Areas 1 through 4) Weekly Progress Reporting that include the daily material removal statusLS1LS$0.00$0.00
8.4Submittal of the As-Built drawings showing extent of post excavation limitsLS1LS$0.00$0.00
Subtotal$0.00
9Excavation Services (Areas 1 through 4)
9.1Area 1 (Excavation and Management of Soil, Pavement, Utilities, and Debris)UP1,380CY$0.00$0.00
9.2Area 2 (Excavation and Management of Soil, Pavement, Utilities, and Debris)UP400CY$0.00$0.00
9.3Area 3 (Excavation and Management of Soil, Pavement, Utilities, and Debris)UP810CY$0.00$0.00
9.4Area 4 (Excavation and Management of Soil, Pavement, Utilities, and Debris)UP1,300CY$0.00$0.00
9.5Reporting - Soil Excavation (Areas 1 through 4) Weekly Progress Reporting that include the daily material removal statusLS1LS$0.00$0.00
9.6Submittal of the As-Builts drawings showing extent of post excavation limitsLS1LS$0.00$0.00
Subtotal$0.00
10ISS Treatment (see contingency items 16, 17, 18, & 19) Services
10.1ISS Mix Design Verification (Test Section - 12 ISS columns)LS1LS$0.00$0.00
10.2ISS Treatment (Shallow [Less Than or Equal to 8ft BGS])UP50,147CY$0.00$0.00
10.3ISS Treatment (Deep [Greater Than 8ft BGS])UP42,875CY$0.00$0.00
10.4ISS Column Wall Surrounding four sides of K-2 building4UP840LF$0.00$0.00
10.5ISS Swell ManagementUP52,000Tons$0.00$0.00
10.6Reporting - ISS Treatments Daily Progress Reporting and As-Built drawingsLS1LS$0.00$0.00
10.7Submittal of the As-Built drawings showing extent of ISS top and bottom column elevationsLS1LS$0.00$0.00
Subtotal$0.00
11Transportation and Disposal Services
11.1Demolition Materials
11.1.1C&D DebrisUP5,000Tons$0.00$0.00
11.2Disposal of Excavated Material
11.2.1Subtitle D Disposal of Material Excavated from Areas 1 - 4 and the ISS AreaUP45,000Tons$0.00$0.00
11.3ISS Swell
11.3.1Subtitle D Disposal of ISS Swell MaterialUP52,000Tons$0.00$0.00
11.4Reporting - Transportation and Disposal Weekly Progress ReportingLS1LS$0.00$0.00
Subtotal$0.00
12Backfill / Restoration Services
12.1Utility Corridors (see drawing R-010)UP2,300LF$0.00$0.00
12.2Fine AggregateUP300CY$0.00$0.00
12.3Coarse AggregateUP13,700CY$0.00$0.00
12.4Backfill and Compaction of Excavation Areas 1 - 4 and the ISS Area5UP18,190CY$0.00$0.00
12.5Landscape SoilUP1,100CY$0.00$0.00
12.6GeotextileUP29,200SY$0.00$0.00
12.7Seeding (include 2 weeks of watering)UP1AC$0.00$0.00
12.8LLDPE LinerUP1,815LF$0.00$0.00
12.9Piping Network (see drawing R-010)LS1LS$0.00$0.00
12.9.1F&I Leaching Catch BasinsUP7EA$0.00$0.00
12.9.2F&I Cleanout Catch BasinsUP26EA$0.00$0.00
12.9.3F&I 12" HDPE Trunk/Header PipeUP600LF$0.00$0.00
12.9.4F&I 6" HDPE Lateral PipeUP1850LF$0.00$0.00
12.1010,000-gallon Cistern Tank and Lift StationLS1LS$0.00$0.00
12.11Subtitle D Disposal of Soil and Debris Excavated for the F&I Tank InstallationLS1LS$0.00$0.00
12.12Reporting - Site Restoration Weekly Progress Reporting including quality assurance (QA) testing and verificationLS1LS$0.00$0.00
Subtotal$0.00
13Asphalt Paving Services
13.1Soil Excavation Areas 1 and 2
13.1.1Bituminous AsphaltUP1,580Tons$0.00$0.00
13.1.28" Lime RockUP23,000SY$0.00$0.00
13.1.3Type B Stabilization 12" LBR=40UP23,000SY$0.00$0.00
13.2Area 4
13.2.1Bituminous AsphaltUP130Tons$0.00$0.00
13.2.28" Lime RockUP1,850SY$0.00$0.00
13.2.3Type B Stabilization 12" LBR=40UP1,850SY$0.00$0.00
13.3Area 3
13.3.1Bituminous AsphaltUP110Tons$0.00$0.00
13.3.28" Lime RockUP1,600SY$0.00$0.00
13.3.3Type B Stabilization 12" LBR=40UP1,600SY$0.00$0.00
13.4Reporting - Site Restoration Weekly Progress Reporting including QA testing and verificationLS1LS$0.00$0.00
Subtotal$0.00
14Well Abandonment Services
14.1Leave in Place, Grout, and Incorporate into ISS Matrix
UP51EA$0.00$0.00
14.2Overdrill Well Casing/Screen, Remove the Well, and Grout Borehole (for depths of 30 feet and under)UP11EA$0.00$0.00
14.3Reporting - Well Abandonment Completion ReportLS1LS$0.00$0.00
Subtotal$0.00
15Demobilization ServicesLS1LS$0.00$0.00
15.1Construction Completion ReportLS1LS$0.00$0.00
Subtotal$0.00
GRAND TOTAL
NOTE: Grand Total will be used as a part of Awarding price points in accordance with Section 5 of the RFP.$0.00
Item No.ItemBasis of
PaymentEstimated
QuantityUnitFixed Unit Price
CONTINGENCY ITEMS (FIXED UNIT PRICE REQUIRED)
16ISS Revised Mixture (if needed)LS1LS$0.00
16.1Portland CementUP1Tons$0.00
16.2Ground Blast Granulated SlagUP1Tons$0.00
15.3BentoniteUP1Tons$0.00
17Contingent Vapor and Odor Control Foam System
17.1Provision of Odor Control Foam SystemLS1LS$0.00
17.2Operation of Odor Control Foam SystemUP8‐Hour Shift$0.00
18Contingent Vapor and Odor Control Spray Cover System
18.1Provision of Spray Cover SystemLS1LS$0.00
18.2Operation of Spray Cover SystemUP8‐Hour Shift$0.00
19Contingent Auger Shroud and Carbon Capture System
19.1Provision of Auger Shroud and Carbon Capture SystemLS1LS$0.00
19.2Operation of Auger Shroud and Carbon Capture SystemUP8‐Hour Shift$0.00
19.3Carbon Capture System Consumables ‐ CarbonUPEA$0.00
20Asbestos and RCRA Abatement (includes inspection, testing, waste removal, segregation, and disposal)
20.1Asbestos - Mastic/TilesUPPerCY$0.00
20.2Asbestos - Wrapped Pipe, Etc.UPPerLF$0.00
20.3RCRA MetalsUPPerTons$0.00
20.4RCRA OrganicsUPPerTons$0.00
21Lead Abatement (includes inspection, testing, waste removal, segregation, and disposal)
21.1Lead PaintUPPerSF$0.00
21.2Other Potential Lead Abatement (Former Gun Range)UPPerTons$0.00
22Universal Waste (includes waste removal, segregation, and disposal)
22.1Universal WasteUPPerTons$0.00
23Construction & Demolition Waste (C &D) (includes office furniture waste removal and disposal)6
23.1C&D WasteUPPerTons$0.00
24Subtitle C Disposal
24.1Excavated Material Subtitle CUPPerTons$0.00
24.2ISS Swell Subtitle CUPPerTons$0.00
25Well Abandonment
25.1Overdrill Well Casing/Screen, Remove the Well, and Grout Borehole (for depths over 30 feet)UPPerLF$0.00
UP = Unit PriceNotes:Notes:
LS = Lump SumDO NOT FILL IN GREYED OUT CELLSDo not enter any information in greyed out cells
CY = Cubic Yards1 RA Work Plan - Contractor should consider incorporation of DEP/EPA comments on draft work plans. The RA Work Plan will include all deliverables included in design specifications (see Section 01 36 00 Technical Specifications).
LF = Linear Feet
SF = Square Feet
SY = Square Yard2 Site Services - Pricing includes set up of a onsite construction office trailer.
EA = Each3 Includes temporary storage and disposal (under 10.2.1) of NAPL collected from the Construction Water Treatment System.
AC = Acre
ISS= In-situ Soil Stabilization/Solidification4 This pricing includes the utility management, removal and replacement of concrete pavement along the east side of K-2 building (see drawings C-013 and C-014).
Day = 10 hours
5 This backfill will be the coarse aggregate in the ISS area (Design Drawing R-011). This volume includes the total excavation volume (31,890) less the coarse aggregate volume (13,700).

6 The office furniture and interior warehouse items shall be removed by the property owner and tenants prior to construction activities. This bid item will be used to address any ancillary items or debris that remain after the warehouses have been vacated.

File details come from the government source that posted it. Updated .