FNWZ 17-0021A Demolish BLDG 6142 LibraryEduc Ctr Bid Schedule (11-6-2025).pdf
PDF 86 KB Posted
- Attached to
- Demo B6142
- Solicitation number
- FA46612526Q0006
About this file
This document is an Independent Government Estimate (IGE) for the demolition of Building 6142, identified under project number FNWZ 17-0021A. The scope of work includes comprehensive demolition services encompassing design, survey, layout, plant, labor, supplies, equipment, hauling, permits, abatement, materials, supervision, and associated incidentals required to fully demolish the existing building in compliance with specified drawings and specifications. The contract performance timeline is set at 180 calendar days, which includes 5 working days allocated for anticipated weather delays, and encompasses activities such as mobilization, submittal approval, abatement, actual demolition work, system testing, and close-out documentation. No specific pricing or cost estimates are provided in this document, with blank spaces left for the total construction cost and line item pricing.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B6142_RFQ_COMBO_V4.pdf | ||
| B6142_RFQ_COMBO_V3.pdf | ||
| FNWZ 17-0021A B6142 RFIs - Final (12-10-2025)V2.xlsx | XLSX spreadsheet | |
| 55-0597 - Original Construction.zip | ZIP file | |
| FNWZ 17-0021A Demo BLDG 6142 SoW (11-6-2025) 2.pdf | ||
| FNWZ 17-0021A - Att E - AF Form 3064.xlsx | XLSX spreadsheet | |
| FNWZ 17-0021A - Attachment E - Pricing Worksheet - Contractor.xlsx | XLSX spreadsheet | |
| FNWZ 17-0021A Demo BLDG 6142 DWGs.pdf | ||
| B6142_RFQ_COMBO.pdf | ||
| FNWZ 17-0021A - Att E - AF Form 3065.xlsx | XLSX spreadsheet | |
| Wage Determinations_2025.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment D Independent Government Estimate: Demo Buildings
0001 Base Bid - Item 1 – FNWZ 17-0021A – Demo Building 6142
This Item includes all design, survey, layout, plant, labor, supplies, equipment, hauling, permits, abatement, materials, supervision and incidentals required to complete all work to demolish the existing Building6142, in compliance with the drawings & specifications for FNWZ 17-0021A.
1 LS: $
Total Construction Cost: $
CONTRACT PERFORMANCE TIME:
1. Total of 180 calendar days to complete the work.
2. Performance time includes 5 working days of anticipated weather. No additional time weather related delays will be granted until these 5 anticipated weather days have been exceeded and approved by the Contracting Officer.
3. Performance time includes mobilization, submittal approval, abatement, actual demolition work, perform system testing, and close out documents.
END NARRATIVE