About this file
This is a First Article Test (FAT) Waiver Worksheet template designed for contractors to request waivers or partial waivers from first article testing requirements in federal contracts. The form must be submitted on company letterhead and signed by a company agent, with all submissions directed to the contracting officer.
The worksheet requires contractors to identify the current acquisition using specific data fields including the contracting officer's name, solicitation/contract number, contractor name and CAGE code, NSN, part number, nomenclature, top drawing number, and revision level. Contractors must specify whether they are requesting a full waiver (eliminating all first article testing) or a partial waiver (waiving only specific tests), with detailed reference to the Technical Data Package (TDP) specifications and drawing notes for tests to be waived. The justification section provides five primary grounds for waiver requests: (A) successful completion of a FAT on a recent contract for the same item using identical facilities, equipment, processes, and subcontractors; (B) successful FAT on a similar item tested to the same requirements with documented differences; (C) material in continuous production with documented production run length; (D) successful FAT on a next higher assembly to eliminate duplicative testing; and (E) other justifications with specific supporting documentation. Additional sections require disclosure of quality issues including Product Quality Deficiency Reports (PQDRs) and corrective actions, changes to manufacturing data or subcontractors, and any Material Review Board (MRB) actions or waiver/deviation requests. The submission section requires the signatory to provide printed name, title, company name, address, and phone number, with certification that all statements are true and correct.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment W912CH26BA0100004 SF 30.pdf | ||
| Solicitation Amendment W912CH26BA0100003 SF 30.pdf | ||
| Solicitation Amendment 0002 W912CH26BA0100002.pdf | ||
| Solicitation W912CH26BA010 Amendment 0001.pdf | ||
| QandA W912CH-26-B-A010.docx | DOCX document | |
| QandA W912CH-26-B-A010.docx | DOCX document | |
| QandA W912CH-26-B-A010.docx | DOCX document | |
| IFB - W912CH26BA010.pdf | ||
| Exhibit A_CDRLs.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Version - September 2015
This information/supporting documentation is part of your request.
It must be submitted on company letterhead and signed by an agent of the company.
Contact the Contracting Officer if you have any questions about the acquisition offer/quote requirements.
FIRST ARTICLE - WAIVER WORKSHEET
Request for Information and Supporting Documentation
This is a Sample of a Contractor's Request for First Article Waiver Worksheet. If waivers will be considered by the Government, this form or memorandum similar to this should be an attachment in Section J of the solicitation.
Contracting Officer's Name
1. CURRENT ACQUISITION INFORMATION:
NOUN
PART #
CONTRACTOR NAME
NSN
TOP DRAWING #
SOLICITATION/CONTRACT #
CONTRACTOR CAGE
REVISION LEVEL
2. TYPE OF REQUEST:
Partial Waiver: Includes waiver of only a specific test(s) of the First Article Test requirement as required by the Technical Data Package (TDP), contract and/or solicitation.
Full Waiver: Includes waiver of all First Article Testing as required by the TDP, contract and/or solicitation.
TDP Reference(s) of test(s) to be waived: (Please be specific and reference specification paragraph and/or drawing note as appropriate).
3. JUSTIFICATION TO SUPPORT WAIVER REQUEST: (Check and complete all that apply)
Successful completion of a First Article Test on a recent contract for the same item(s).
Complete the following & attach supporting documentation*.
If NO, please describe the differences in detail below and include any considerations these changes will require for the First Article Test waiver request
DATE OF FIRST ARTICLE TEST APPROVALCONTRACT # ISSUING GOVERNMENT AGENCY
Was the above contract manufactured at the same facilities using the same equipment, processes, procedures, and subcontractors in which the current item will be produced?
A)
Successful completion of a First Article Test on a similar item on a recent contract and the item has been tested per the same requirements as those referenced in the solicitation and/or contract.
Complete the following for the similar item & attach supporting documentation*:
Briefly describe the major differences between the similar item and the item being procured.
NSN
CONTRACT #
DATE OF FIRST ARTICLE TEST APPROVAL
Was the similar item manufactured at the same facilities using similar equipment, processes, and procedures in which the current item will be produced?
B)
NOMENCLATURE
PART NUMBER
If NO, please describe the differences in detail below and include any considerations these changes will require for the First Article Test waiver request
Material has been in continuous production. Complete and attach supporting documentation*:
Remarks (if needed)
LENGTH OF PRODUCTION RUN
C)
APPROVAL DATE OF LAST SUCCESSFUL FIRST ARTICLE TEST
Provide a full explanation justifying why duplicate testing is unnecessary:
Recent and successful performance of a first article test on the next higher assembly. A waiver may be requested in order to eliminate duplication of testing on the lower assembly.
Complete the following for the next higher assembly and attach supporting documentation*:
D)
NSN
CONTRACT #
DATE OF FIRST ARTICLE TEST APPROVAL
NOMENCLATURE
PART NUMBER
Was the next higher assembly manufactured at the same facilities using similar equipment, processes, and procedures in which the current item will be produced?
If NO, please explain:
Other: A waiver or partial waiver of the FAT is being requested based on the following:
Please be specific and attach supporting documentation* as appropriate:E)
4. OTHER PERTINENT INFORMATION
There are or have been quality issues (history) for this or similar items to include Product Quality Deficiency Reports (PQDRs), Corrective Action Request, and/or show-cause letters. Please briefly discuss below:A)
There have been changes to the manufacturing data (e.g. drawing revisions that change materials, dimensions, processes, inspection or testing requirements) or subcontractors used to manufacture the items successfully in the past.
Please describe below.
B)
There have been Requests for Waiver/Deviation submitted or Material Review Board (MRB) actions related to manufacture of this item. Please describe below. C)
5. ATTACH SUPPORTING DOCUMENTATION
6. SUBMISSION
The submitter, by signing the below certifies that the above statements are true and correct.
Please provide printed name, signature, company address, and phone number where you can be reached. Again, the signer must be an agent of the company.
PRINTED NAME
COMPANY NAME
PHONE NUMBER
TITLE
COMPANY ADDRESS
Signature
*See the solicitation/contract for information on submitting supporting documentation as well as additional requirements regarding First Article Test Waiver requests.
This information/supporting documentation is part of your request.
It must be submitted on company letterhead and signed by an agent of the company.
Contact the Contracting Officer if you have any questions about the acquisition offer/quote requirements.
FIRST ARTICLE - WAIVER WORKSHEET
Request for Information and Supporting Documentation This is a Sample of a Contractor's Request for First Article Waiver Worksheet. If waivers will be considered by the Government, this form or memorandum similar to this should be an attachment in Section J of the solicitation.
1. CURRENT ACQUISITION INFORMATION:
2. TYPE OF REQUEST:
3. JUSTIFICATION TO SUPPORT WAIVER REQUEST: (Check and complete all that apply) Was the above contract manufactured at the same facilities using the same equipment, processes, procedures, and subcontractors in which the current item will be produced?
Page of A) Was the similar item manufactured at the same facilities using similar equipment, processes, and procedures in which the current item will be produced?
B) C) D) Was the next higher assembly manufactured at the same facilities using similar equipment, processes, and procedures in which the current item will be produced?
Page of Page of E)
4. OTHER PERTINENT INFORMATION
A) B) C)
5. ATTACH SUPPORTING DOCUMENTATION
6. SUBMISSION
The submitter, by signing the below certifies that the above statements are true and correct. Please provide printed name, signature, company address, and phone number where you can be reached. Again, the signer must be an agent of the company.
*See the solicitation/contract for information on submitting supporting documentation as well as additional requirements regarding First Article Test Waiver requests.
8.2.1.4029.1.523496.503679
| TextField7: |
| : |
| DateTimeField1: |
| TextField8: |
| DropDownList1: |
| CurrentPage: 1.00000000 |
| CurrentPage: 2.00000000 |
| CurrentPage: 3.00000000 |
| PageCount: 3.00000000 |
| PageCount: 3.00000000 |
| PageCount: 3.00000000 |
| ResetButton1: |
| TextField9: |
| DateTimeField2: |
| TextField10: |
| NumericField1: 0 |
| SignatureField1: |
| Button1: |
| Button2: |
| ListBox1: |
| Button3: |
File details come from the government source that posted it. Updated .