Fire Suppression System specs.doc
DOC document 31 KB Posted
- Attached to
- Fire Suppression System
- Solicitation number
- RFQ - 17D - 11061000000000001255
- Issued by
- Kennebec County, Maine
About this file
This specification document pertains to a fire suppression system installation project for Maine Department of Transportation (Maine DOT) Fleet Services located at 105 Capitol Street, Augusta, Maine. The project involves the installation of a dry chemical fire suppression system for a COL-MET truck and equipment paint booth, model TSC 1813-40 PSB, with dimensions of 19 feet wide by 15 feet 2 inches tall by 40 feet 6 inches long. The system must meet all applicable Federal, State, local, and OSHA regulations and be inspected and certified by the local regulating authority. The paint booth package includes a paint mixing room (PMR-0810), a Titan Heat and Cure Air Make-Up Unit Model TA-220 LG VRH-H.O.T, thirty-two four-foot UL-listed fluorescent light fixtures, two 24-inch vaneaxial exhaust fans, and three bi-folding product doors. The air make-up unit features a 2,500,000 BTU LP gas direct-fired burner with a 15-horsepower fan motor capable of producing 160-degree hot air for paint curing and requires 460V, 3-phase, 3-wire power at 60Hz.
Bid proposals must include all shipping, delivery, and installation costs to the specified Maine DOT location. Maine DOT reserves the right to pre-inspect equipment before delivery, and upon delivery, all necessary documentation including invoices, layout diagrams, drawings, and maintenance and inspection schedules must accompany the unit. Bids will be evaluated based on price, warranty, manufacturer performance data, delivery schedule, parts availability, and other factors deemed appropriate. The specifications represent minimum requirements, and vendors must submit all questions through the Question and Answer link on the Solicitation Details View page, with responses posted for all vendors to access. The document revision date is June 11, and all vendor communications regarding the RFQ must occur through the designated online platform to ensure validity.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation_terms.doc | DOC document | |
| PAYMENT METHOD (2).doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FIRE SUPPRESSION SYSTEM
Specifications
The following specifications are intended to describe an area where a dry chemical fire suppression system is required to be installed. The completed system must meet all applicable Federal, State, local and OSHA regulations. The system must be well designed, tested for reliable performance, inspected and certified by the local regulating authority.
1. COL-MET TRUCK and EQUIPMENT PAINT BOOTH
1. COL-MET truck and equipment, modified down-flow, pressurized paint and bake booth, model TSC 1813-40 PSB. With paint mixing room and a Titan Heat and Cure, Air Make-Up Unit attached.
2. Dimensions and Accessories of Paint Booth
2.1 Out-side dimensions 19ft. wide x 15ft. 2” tall x 40ft 6” long.
2.2 Inside dimensions 18ft x 13 ft. x 40 ft. long.
2.3 Two 24” Vaneaxial exhaust fans with intake air and exhaust pipes.
2.4 Thirty two (32) four (4) ft. UL listed four tube fluorescent light fixtures.
2.5 Three bi-folding product doors 16ft. wide x 1ft high (approximate)
3. Paint Mixing Room (PMR-0810)
3.1 Dimensions are 8ft x 8ft x 10ft (approximate).
3.2 Two personnel access doors 30in. wide x 7ft. tall (approximate).
3.3 One open light fixture.
3.4 Exhaust stack 12in diameter x 15ft. high.
3.5 One 12in.exhaust fan with a 1-1/4hp.motor to provide exhaust at 1700 scfm.
4. TITAN HEAT AND CURE AIR MAKE-UP UNIT
4.1 Titan Outdoor Vertical Air Make-up Unit Model TA-220 LG VRH-H.O.T with Bake Mode.
4.2 AMU has a LP Gas Direct-Fired 2,500,000 BTU burner with a 15 hp.fan motor.
4.3 AMU is capable of 160° hot air for paint curing.
4.4 AMU will replace exhausted paint booth air at normal requirements.
4.5 AMU requires 460V, 3ph, 3 wire and 60Hz power source.
5. GENERAL INFORMATION:
5.1 Engineer drawings, manufacturer brochures and related information will be issued upon request to bidding vendors.
5.2 All bid proposals will include shipping, delivery and installation costs at:
Maine DOT Fleet Services, 105 Capitol St. Augusta, Maine 04333.
5.3 Maine DOT reserves the right to pre-inspect the equipment before delivery.
5.4 Upon delivery of unit all necessary paper work such as invoices, lay-out diagrams, drawings and maintenance and/or inspection schedules shall accompany unit
5.7 Be it known that these specifications are a minimum and
that bids will be valuated based on price, warranty, manufacturer’s performance data, delivery schedule, parts availability and other items deemed appropriate.
If you have a question regarding this RFQ, you must submit your questions thru the Question and Answer link on the Solicitation Details View page. Your answer will appear there as well. It is the vendor’s responsibility to log in to view all questions and answers posted there. Questions and Answers obtained any other way will not be valid for this RFQ.
REV. 6/11 ESB