Clay County, Florida is seeking bids for Fire Station No. 24 Site Clearing Services through a competitive Request for Bid (RFB) process. The project involves site preparation for a new fire station located at 1075 County Road 226 in Green Cove Springs, with a focus on environmental sensitivity and regulatory compliance. The bid was released on August 21, 2025, with a mandatory pre-bid meeting scheduled for September 4, 2025, and bids due by October 9, 2025, at 4:00 pm. The project requires site clearing in two phases: first, installing erosion and sediment control measures, and second, removing trees and vegetation. The work must be completed between December 15, 2025, and February 15, 2026, to accommodate wildlife protection requirements, particularly for tri-colored bats and Eastern Indigo Snakes. The contract includes specific environmental protection measures and will be awarded to the lowest responsive and responsible bidder.
The bid includes two pricing options: a base bid where gopher tortoises will be relocated prior to clearing by a separate contractor, and an alternate bid where tortoises remain on-site with close monitoring. Bidders must submit a five percent bid bond and provide comprehensive insurance coverage, including commercial general liability, business automobile liability, workers' compensation, and property coverage. The total project cost will be determined through a lump sum pricing structure covering mobilization, erosion control, clearing and grubbing, and final site stabilization. The county reserves the right to reject any bids and engage in value engineering discussions. Additional requirements include compliance with drug-free workplace regulations, licensing certifications, and various legal and ethical standards set by Clay County and the state of Florida.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| Addendum_#1_-_Gopher_Tortoise_Burrow_Locations.pdf | ||
| Fire_Station_No._24_Site_Clearing_Services_(Addendum_#2_Revision).pdf | ||
| Standard_Protection_Measures_-_Eastern_Indigo_Snake_.pdf | ||
| Indigo_Snake_Poster.pdf | ||
| Indigo_Snake_Poster.pdf | ||
| Standard_Protection_Measures_-_Eastern_Indigo_Snake_.pdf | ||
| CC_FS_24_Tree_Clearing_Only_Set.pdf | ||
| CC_FS_24_Tree_Clearing_Only_Set.pdf | ||
| Certificate_of_final_payment.pdf | ||
| EFT_FORM.pdf | ||
| Certificate_of_final_payment.pdf | ||
| Certificate_of_partial_payment.pdf | ||
| Certificate_of_partial_payment.pdf | ||
| Chapter_8_Section_I.pdf | ||
| EFT_FORM.pdf | ||
| Chapter_8_Section_I.pdf | ||
| W-9_(2024).pdf | ||
| W-9_(2024).pdf |
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INVITATION FOR BID
24/25-115
FIRE STATION NO. 24 SITE CLEARING SERVICES
Clay County
477 Houston Street
Green Cove Springs, FL 32043
RELEASE DATE: August 21, 2025
LAST DATE FOR INQUIRIES: October 2, 2025, 4:00 pm
BID DUE: October 9, 2025, 4:00 pm
RESPONSES MUST BE SUBMITTED ELECTRONICALLY TO:
https://secure.procurenow.com/portal/claycounty https://secure.procurenow.com/portal/%7bproject.government.code%7d
Clay County
INVITATION FOR BID
Fire Station No. 24 Site Clearing Services
I. Introduction II. Instructions to Bidders
III. Scope of Work IV. Pricing Proposal V. Supplier Questionnaire
Attachments:
A - Chapter 8
B - EFT FORM
C - W-9 (2024)
D - Certificate of partial payment
E - Certificate of final payment
F - CC FS 24 Tree Clearing Only Set
G - Indigo Snake Poster
H - Standard Protection Measures - Eastern Indigo Snake
I - Addendum #1 - Gopher Tortoise Burrow Locations
Invitation For Bid #24/25-115 Title: Fire Station No. 24 Site Clearing Services
1. Introduction
The mission of the Purchasing Department is to provide fair and equitable treatment of all persons involved in public purchasing by the County, to maximize the purchasing value of public funds in procurement, and to provide safeguards for maintaining a procurement system of quality and integrity.
1.1. Summary
The Clay County Board of County Commissioners (County) is requesting bids from qualified Contractors for the site clearing services at Fire Station 24 located at 1075 County Road 226 Green Cove Springs, FL
32043 per the plans and specifications associated with this Request for Bid (RFB).
Bidders shall submit all inquiries regarding this RFB in the "Question and Answer" tab of the
RFB. See "Inquiries/Questions" in the "Instructions to Bidders" below for more information.
Bidders are prohibited from contacting, by any means, whether orally, telephonically, electronically or in writing, any member of the Board, any County employee, including the
County Manager, the County Attorney or the Commission Auditor, any member of the designated Evaluation Committee or any agent of the County regarding the Request for Bids in any respect during the Request for Bid Period. The Request for Bid Period during which no contact may occur commences from the date of publication of the notice of a Request for Bids and ends upon a Bid Decision becoming final, i.e. after the notice of bid protest period of 72 hours has expired. However, in the event of a notice of protest, the no contact rule continues in place during the Protest Period and does not end until a resolution of the protest has occurred and become final. The following exceptions exist to the no-contact rule:
A. Inquiries may be submitted to the Purchasing Department if specifically provided in the
Request for Bids;
B. Pre-bid conferences provided for in the Request for Bids; and
C. Formal presentations by Bidders to the designated Evaluation Committee or to the
Board or any committee thereof specifically contemplated in the Request for Bids.
The Board reserves the right and power to reject any and all Bids without cause and to waive technical and non-technical or non-material defects in the Request for Bids or submittal of any
Bid, and in its discretion to re-advertise the Request for Bids. The Board reserves the right to award Request for Bids which would be in the Best Interest of the County. Interested vendors are advised that the Clay County Board of County Commissioners has a local preference policy and Buy American policy. The complete policy for both can be viewed at:
https://www.claycountygov.com/government/purchasing/vendor-information.
https://www.claycountygov.com/government/purchasing/vendor-information
FOLLOWING THE BID OPENING AND TABULATION, A “NOTICE OF INTENT TO AWARD BID” OR
A “NOTICE OF REJECTION OF ALL BIDS” WILL BE POSTED ON THE INTERNET
AT:https://procurement.opengov.com/portal/claycounty?status=all.
THIS WEBPAGE CAN ALSO BE ACCESSED FROM THE HOMEPAGE OF THE COUNTY’S WEBSITE
AT:https://www.claycountygov.com/government/purchasing/formal-bid-solicitations
PROSPECTIVE BIDDERS ARE NOTIFIED THAT THE FAILURE TO INCLUDE A PROPER BID BOND
OR OTHER SECURITY APPROVED UNDER THE COUNTY’S PURCHASING POLICY, IF REQUIRED
FOR THIS REQUEST, WILL RESULT IN REJECTION OF THE BID AND SHALL, AS WELL AS THE
FAILURE TO FILE A WRITTEN NOTICE OF PROTEST AND TO FILE A WRITTEN PETITION
INITIATING A FORMAL PROTEST PROCEEDING WITHIN THE TIMES AND IN THE MANNER
PRESCRIBED IN CHAPTER 8, SECTION I OF THE COUNTY’S PURCHASING POLICY SHALL,
CONSTITUTE A WAIVER OF THE RIGHT TO PROTEST THE BID REQUEST, ANY ADDENDUM
THERETO, OR THE BID DECISION, AS APPLICABLE, AND TO INITIATE A FORMAL PROTEST
PROCEEDING UNDER THE PURCHASING POLICY. THE COUNTY’S PURCHASING POLICY CAN BE
VIEWED AT THE COUNTY’S WEBSITE BY FOLLOWING THE APPROPRIATE LINKS FROM THE
HOMEPAGE ADDRESS SET FORTH ABOVE.
IF A PROSPECTIVE BIDDER IS IN DOUBT WHETHER THIS REQUEST REQUIRES A BID BOND,
SUCH PROSPECTIVE BIDDER IS SOLELY RESPONSIBLE FOR MAKING APPROPRIATE INQUIRY.
THE BOARD RESERVES THE RIGHT TO REJECT ANY AND ALL BIDS WITHOUT CAUSE AND TO
WAIVE TECHNICAL AND NON- TECHNICAL OR NON-MATERIAL DEFECTS IN THE REQUEST OR
SUBMITTAL OF ANY BIDS.
A PERSON OR AFFILIATE WHO HAS BEEN PLACED ON THE CONVICTED VENDOR LIST
FOLLOWING A CONVICTION FOR A PUBLIC ENTITY CRIME MAY NOT SUBMIT A BID ON A
CONTRACT TO PROVIDE ANY GOODS OR SERVICES TO A PUBLIC ENTITY, MAY NOT SUBMIT A
BID ON A CONTRACT WITH A PUBLIC ENTITY FOR THE CONSTRUCTION OR REPAIR OF A
PUBLIC BUILDING OR PUBLIC WORK, MAY NOT SUBMIT BIDS ON LEASES OF REAL PROPERTY
TO A PUBLIC ENTITY, MAY NOT BE AWARDED OR PERFORM WORK AS A CONTRACTOR,
SUPPLIER, SUBCONTRACTOR, OR CONSULTANT UNDER A CONTRACT WITH ANY PUBLIC
ENTITY, AND MAY NOT TRANSACT BUSINESS WITH ANY PUBLIC ENTITY IN EXCESS OF THE
THRESHOLD AMOUNT PROVIDED IN SECTION 287.017, FLORIDA STATUTES, FOR CATEGORY
TWO FOR A PERIOD OF 36 MONTHS FROM THE DATE OF BEING PLACED ON THE CONVICTED
VENDOR LIST.
1.2. Background
The selected site for Fire Station 24 is currently undeveloped and requires full site preparation before construction can begin. Given the ecological sensitivity of the area, including the presence of protected wildlife species such as native bat populations and the potential for https://procurement.opengov.com/portal/claycounty?status=all.
https://www.claycountygov.com/government/purchasing/formal-bid-solicitations
Eastern Indigo Snakes, the County is requiring specialized environmental clearing in full compliance with Florida Fish and Wildlife Conservation Commission (FWC) regulations.
Although the presence of Gopher Tortoises previously required relocation efforts, that portion of the environmental preparation has already been completed under a separate contract.
However, to prevent re-entry of tortoises into the construction zone, the installation of a properly trenched and secured silt fence barrier around the site perimeter is required.
In addition to serving as a wildlife exclusion barrier, the silt fence will function as a key component of the site’s erosion and sedimentation control system, minimizing offsite impacts during vegetation clearing and ground disturbance. The fence must be installed in accordance with current Florida Stormwater, Erosion, and Sedimentation Control Inspector’s Manual guidelines and maintained throughout the duration of site clearing operations.
1.3. Contact Information
If you need immediate assistance, at any point during the solicitation process, please email the
Purchasing Department at: Purchasing@Claycountygov.com in addition to the Purchasing Department
Staff Member listed below.
The Department information listed below is strictly for visibility. Bidders are not to contact any agent of the County regarding the Request for bids in any respect during the Request for Bid Period.
Inquiries may only be submitted to the Purchasing Department.
Jerry Horton
Strategic Sourcing Analyst II / Purchasing
477 Houston St
P.O. Box 1366
Green Cove Springs, FL 32043
Email: jerry.horton@claycountygov.com
Phone: (904) 946-0155
Department:
Capital Projects
Department Head:
Ed Dendor
Director of Capital Projects
1.4. Timeline
The proposed dates for the Evaluation Committee and Recommendation are subject to change.
It is the responsibility of the Bidder to monitor the County's calendar and Board of County Commissioner
Meeting Agendas for any adjusted dates.
The County reserves the right to alter dates as needed.
mailto:Purchasing@Claycountygov.com mailto:jerry.horton@claycountygov.com tel:(904)946-0155 https://www.claycountygov.com/government/calendar-of-events https://www.claycountygov.com/government/agendas-and-minutes https://www.claycountygov.com/government/agendas-and-minutes
Clay Today Advertisement Date August 21, 2025
OpenGov Advertisement Date August 21, 2025
Pre-Bid Meeting (Mandatory) September 4, 2025, 10:00am
1075 County Road 226
Green Cove Springs, FL 32043
Please electronically RSVP to this Mandatory Pre-
Bid by clicking the "Events RSVP" drop down located next to "Draft Response" at the top of this project.
Last Date of Inquiries October 2, 2025, 4:00pm
Final Addendum October 3, 2025, 4:00pm
Bid Due October 9, 2025, 4:00pm
This Bid requires a five (5%) percent Bid Bond.
The Bid Bond is required to be uploaded within the
Supplier Questionnaire.
If submitting a Cashier or Certified Check, it must be uploaded with the Bids Supplier Questionnaire and the Original Cashier or Certified Check must be received by the Purchasing Department no later than two (2) business days after the RFB due date
(Original Cashier or Certified Check due date listed below)
Bid Open October 10, 2025, 9:00am
Clay County Administration Building
Fourth Floor
Green Cove Springs, Florida 32043
Original Cashier or Certified Check: October 13, 2025, 4:30pm
Clay County Administration Building
Fourth Floor
477 Houston Street
Green Cove Springs, Florida 32043
Submittal Review October 14, 2025
Estimated Date for Recommendation to
Board of County Commissioners
October 28, 2025, 4:30pm
Clay County Administration Building
Fourth Floor
Green Cove Springs, Florida 32043
2. Instructions to Bidders
2.1. Instruction to Bidders:
The term 'RFB' (Request for Bids) used throughout this solicitation is intended to be all-inclusive, encompassing competitive processes, such as Request for Bids (RFB), Request for
Proposal (RFP), Request for Qualifications (RFQ), Invitation to Negotiate (ITN), Best Final Offer, or Design-Build, and any similar solicitations. These instructions are derived from Clay County's purchasing policy.
2.2. Response to Request for Bids:
The County posts and distributes information pertaining to its RFB's on the County’s e-
Procurement Portal. In order to submit a Bid to this RFB the Bidder must be registered with the
County’s e-Procurement Portal.
The Bid, containing all required documents, must be received by 4:00 pm on Thursday, October 9, 2025 electronically. Any required uploaded documents should be in PDF format and be labeled correctly, unless the Bid states otherwise. The PDF document should be titled with the Bidders name and RFB number.
THE COUNTY NOR THE PUBLIC PORTAL PLATFORM WILL ACCEPT LATE SUBMITTALS
The Bidder should retain a copy of all Bid documents for future reference.
All Bids should be submitted by an officer or employee having authority to bind the Bidder.
2.3. Addenda:
All Addenda language issued shall become part of the RFB and Contract documents, and receipt of Addenda must be acknowledged by the Bidder. If issued, Bidders will receive addenda notifications to their email once they have followed the RFB. Failure to acknowledge Addenda which have no effect on the competitive nature of the Bidding process may be a waivable deviation at the County’s sole discretion. Ultimately, it is the sole responsibility of each Bidder to periodically check the County’s e-Procurement Portal for any Addenda.
2.4. Addenda Distribution:
All Addenda distributed subsequent to the initial distribution of the RFB shall be posted in the
County’s e-Procurement Portal. It is the responsibility of the Bidder to verify if any
Addendum(s) have been issued prior to submitting a Bid to an RFB. No Addendum shall be issued later than five (5) working days prior to the scheduled Bid Opening date.
https://procurement.opengov.com/portal/claycounty https://procurement.opengov.com/portal/claycounty https://procurement.opengov.com/portal/claycounty
2.5. Additional Evaluation:
The County reserves the right to request any additional information from Bidders after Bid Opening and before award as it may be necessary to assist in review and evaluation of any Bid prior to submittal of a recommendation for award to the Board of County Commissioners.
2.6. Americans with Disabilities Act:
In accordance with the Americans with Disabilities Act, any person needing a special accommodation to participate in this matter should contact the Clay County ADA Coordinator, by mail, at P.O. Box 1366, Green Cove Springs, FL 32043, or by telephone at (904) 269-6300, no later than three (3) days prior to the hearing or proceeding for which this notice has been given.
Hearing impaired persons can access the foregoing telephone number by contacting the Florida
Relay service at 1-800-955-8770 (voice), or 1-800-955-8771 (TDD).
2.7. Award:
Bid Awards for Request for Bids (RFB), where competitive price offer is the only determining factor, shall be awarded based on the lowest responsive and responsible bid. Awards for alternative competitive processes, such as a Request for Proposal (RFP), Request for
Qualification (RFQ), Invitation to Negotiate (ITN), Best Final Offer, or Design-Build, should be based on evaluation criteria specified in the request, in addition to price, to determine what is in the Best Interest of the County.
The term “Lowest Responsive Bid” shall mean the lowest Bid price submitted by a Responsive and Responsible Bidder.
The term “Responsive Bidder” means a Bidder that has submitted a Bid, Proposal or reply that conforms in all material respects to the Request for Bids.
The term “Responsible Bidder” means a Bidder who has the capability in all respects to fully perform the Contract requirements and the integrity and reliability that will assure good faith performance.
The County reserves the right to make an award either in part or completely, and/or to accept the bid that, in its judgment, will be in the best interest of the County; providing best value to the County with price, technical, and other applicable factors considered.
The County Reserves the right to award to multiple Bidders.
2.8. Bid Bond:
If provided for in the RFB Advertisement, Introduction Timeline, or Supplier Questionnaire
Section; Bids require a five (5%) percent bid bond and may not be withdrawn after the scheduled opening time for a period of thirty (30) days. The term bid bond shall include bonds or cashier or certified checks payable to the County.
Any Cashier or Certified Check must be uploaded with the Bid and the original Cashier or
Certified Check must be received by the Purchasing Department no later than two (2) business days after the RFB due date.
The following are exempt from the Bid Bond requirement:
a. SHIP - Bidders bidding on SHIP rehabilitation projects are exempt from the Bid Bond.
b. Fixed Unit Price - Bidders bidding on Contracts with a fixed price, or any other type of
Contract that does not commit the Board to an actual exchange transaction (purchase) but rather seeks only a Fixed Unit Price Commitment from a Bidder in the event a future purchase decision is made.
A prospective Bidder is solely responsible for determining whether a particular Request for Bids requires a Bid Bond, and for resolving any doubt by making appropriate inquiry.
2.9. Bid Errors:
In case of unit price Bid items, if an error is committed in the extension of an item, the unit price as shown in the Bid response will govern. Errors between any sum, computed by the
Bidder, and the correct sum thereof will be resolved in favor of the correct sum. Bidders are expected to examine the RFB in its entirety. Failure to do so will be at the Bidder's risk.
2.10. Bid Preparation Costs:
By submission of a Bid, the Bidder agrees that all costs associated with the preparation of Bid will be the sole responsibility of the Bidder and shall not be borne by the County. The Bidder also agrees that the County bears no responsibility for any costs associated with the preparation of their Bid and/or any administrative or judicial proceedings resulting from the
RFB process.
2.11. Bid Protests:
Any person who is adversely affected by a RFB, by any Addendum thereto, or by a Bid Decision may file with the County Manager a written notice of Bid Protest no later than 4:30 p.m. on the third Business Day immediately following the date notice is published, with respect to a
Request for Bids; no later than 4:30 p.m. on the third Business Day immediately following the date of issuance, with respect to any Addendum; and within 72 hours after the posting of the notice, exclusive of hours occurring during days that are other than Business Days, with respect to a Bid Decision. Full bid protest procedures can be found in the County Purchasing Policy, Chapter 8 Section (I) which is attached hereto or can be found on the County’s website at:
2.12. Business Registration Requirement:
In accordance with Chapters 605-623, Florida Statutes, in order to do business in the State of
Florida, corporations (and other business designations) are required to be registered and in good standing with the Department of State, Department of Corporations. To be eligible to receive a contract and/or purchase order registration must be accomplished prior to the initial posting indicating intent to award to that Supplier. Failure to be registered may be cause for disqualification. Contact the Department of Corporations at (850) 245-6000. Online-filing is available at: http://dos.myflorida.com/sunbiz
2.13. Cancellation of RFB:
Clay County reserves the right to cancel a RFB at any time prior to approval of the award. The decision to cancel a RFB cannot be the basis for a protest under the Bid Protest Procedures as referenced herein.
2.14. Conflict of Interest:
The award hereunder is subject to Chapter 112, Florida Statutes. All Bidders must disclose with their Bid any personal or organizational conflicts of interest pursuant to Section 112.313, Florida Statutes, the name of any officer, director, or agent who is also an employee of the Clay
County Board of County Commissioners. Further, all Bidders must disclose the name of any Clay
County Board of County Commissioners employee who owns, directly or indirectly, an interest of the Bidder or any of its branches.
2.15. Contractor Qualifications and Requirements:
All Contractors must be certified or registered pursuant to Chapter 489, Florida Statutes, or hold a Clay County certification under Article III of Chapter 7 of the Clay County Code, as applicable, at the time of responding to a RFB and must submit evidence of such at the time of submission of any Bid.
The following licensing requirements shall apply when the applicable Florida statute mandates specific licensing for Contractors engaged in the type of work covered by this solicitation. State of Florida, Department of Professional Regulation, Construction Industries Licensing Board and licensed by other federal, state, regional, county or municipal agencies having jurisdiction over the specified construction work. Said licenses shall be in the Bidder's name as it appears on their Bid. Bidders shall supply a copy of each applicable license showing the appropriate license numbers, with expiration dates as required by the County. Failure to hold and provide proof of proper licensing, certification and registration may be grounds for rejection of the Bid and/or termination of the Contract. Sub-Contractors Contracted by the Prime Contractor shall be licensed in their respective fields to obtain construction permits from the County. Said license must be in the name of the Sub-Contractor.
http://dos.myflorida.com/sunbiz
The following licensing requirements shall apply when applicable (Contractor Prequalification):
Florida Law and Rules of the State of Florida, Department of Transportation, require
Contractors to be prequalified with the Department in order to bid for the performance of road, bridge, or public transportation construction contracts greater than $250,000.00. The
Contractor Prequalification process results in the issuance of a Certificate of Qualification for each successful applicant which lists the approved work classes and the Maximum Capacity
Rating in dollars. It is the responsibility of potential bidders to review the requirement listed on the Pre-Qualification Form and meet the qualifications listed at:
https://www.fdot.gov/contracts/prequal-info/prequalified.shtm
Contractors not meeting the applicable work types associated with the scope of the work may utilize Sub-Contractors to assist with meeting the requirement of all necessary prequalification work classes.
2.16. Copyright Restrictions:
Both the County seal and the County logo are registered for a copyright. Neither the Clay
County seal nor the logo may be used or provided to non-Clay County government users for use on company Bids, presentations, etc.
2.17. Deviations:
Bidders are hereby advised the County will only consider Bids that meet the RFB requirements in its entirety. In instances where a deviation is stated in the Bid, said Bid will be subject to rejection by the County.
2.18. Drug-Free Workplace
Pursuant to Section 287.087, Florida Statutes, whenever two or more bids, proposals, or replies that are equal with respect to price, quality, and service are received by the state or by any political subdivision for the procurement of commodities or contractual services, a bid, proposal, or reply received from a business that certifies that it has implemented a drug-free workplace program shall be given preference in the award process. In order to have a drug-free workplace program, a business shall:
(1) Publish a statement notifying employees that the unlawful manufacture, distribution, dispensing, possession, or use of a controlled substance is prohibited in the workplace and specifying the actions that will be taken against employees for violations of such prohibition.
(2) Inform employees about the dangers of drug abuse in the workplace, the business’s policy of maintaining a drug-free workplace, any available drug counseling, rehabilitation, and employee assistance programs, and the penalties that may be imposed upon employees for drug abuse violations.
(3) Give each employee engaged in providing the commodities or contractual services that are under bid a copy of the statement specified in subsection (1).
(4) In the statement specified in subsection (1), notify the employees that, as a condition of working on the commodities or contractual services that are under bid, the employee will abide by the terms of the statement and will notify the employer of any conviction of, or plea of guilty or nolo contendere to, any violation of chapter 893 or of any controlled substance law of the https://www.fdot.gov/contracts/prequal-info/prequalified.shtm
United States or any state, for a violation occurring in the workplace no later than 5 days after such conviction.
(5) Impose a sanction on, or require the satisfactory participation in a drug abuse assistance or rehabilitation program if such is available in the employee’s community by, any employee who is so convicted.
(6) Make a good faith effort to continue to maintain a drug-free workplace through implementation of this Florida Statute.
2.19. Execution of Contract:
The awarded Bidder may be required to sign a written Contract. Said Contract will evidence in written form the agreement between the parties. The County permits the use of electronic signatures between the County, Suppliers, other agencies, customers, and members of the public in carrying out transactions by entry into Contracts, memorandums, or other types of agreements. Electronic signatures shall have the same force and effect as manual written signatures. Each person signing on behalf of the parties to a Contract must have full authority to execute the Contract on behalf of such party. The use of electronic signatures does not limit the County’s right or option to conduct a transaction in non-electronic form nor does it affect the obligation to have original hand-written signatures when required.
2.20. Indemnification:
Construction Services (per FS 725.06):
To the fullest extent permitted by law, the Contractor shall indemnify and hold harmless the
County including its officers and employees, from liabilities, damages, losses and costs, including, but not limited to, reasonable attorney’s fees, to the extent caused by the negligence, recklessness or intentional wrongful misconduct of the Contractor and persons employed or utilized by the Contractor in the performance of this Agreement.
Design Services (per FS 725.08):
To the fullest extent permitted by law and in accordance with Section 725.08, Florida Statutes, the Consultant shall indemnify and hold harmless the County, including its officers and employees, from any and all liabilities, damages, losses and costs, including, but not limited to, reasonable attorney’s fees, to the extent caused by the negligence, recklessness, or intentionally wrongful conduct of the Consultant and other persons employed or utilized by the Consultant in the performance of the Agreement.
Non-construction Services:
The Contractor shall promptly defend, indemnify, and hold harmless the County, and its directors, officers, employees, representatives, agents, boards and commissions from and against any and all liabilities, demands, claims, suits, losses, damages, causes of action, fines, orders, and/or judgments, either at law or in equity, including court costs, attorneys’ fees, professional fees, or other expenses, that may hereafter at any time be made or brought by anyone on account of personal or bodily injury, damage to or loss of property, loss of monies, death, or other loss, arising out of, by reason of, or in any manner connected with or related to the Services provided under this Agreement.
2.21. Inquiries/Questions:
Bidders shall submit all inquiries regarding this RFB in the "Question and Answer" Tab of the
RFB via the County’s e-Procurement Portal, located at https://procurement.opengov.com/portal/claycounty. Please note the deadline for submitting inquiries listed in the the RFB’s Timetable. Once issued, Bidders will receive addenda notifications to their email once they have followed the RFB.
For more information/instruction on how to submit an inquiry/question, please visit:
https://opengov.my.site.com/support/s/article/12c62371-147b-45f4-9bcd-cf2ce5f58259
2.22. Insurance Requirements:
Awarded Bidder has 10 days from the execution of the Agreement to provide a Certificate of Insurance that is compliant with the required coverage.
a. Commercial General Liability
Coverage must be afforded under a Commercial General Liability policy with limits not less than:
• $1,000,000 each occurrence and $2,000,000 aggregate for Bodily Injury, Property
Damage, and Personal and Advertising Injury (project specific aggregate may be required for construction projects)
• $1,000,000 each occurrence and $2,000,000 aggregate for Products and Completed
Operations
• $50,000 each occurrence for Damage to Rented Premises
• $5,000 Medical Expenses (any one person)
Commercial and General Liability policy must include coverage for contractual liability and independent contractors.
b. Business Automobile Liability
Coverage must be afforded for all Owned, Hired, Scheduled, and Non-Owned vehicles for Bodily
Injury and Property Damage in an amount not less than $1,000,000 combined single limit each accident. If the Bidder does not own vehicles, the Bidder shall maintain coverage for Hired and
Non-Owned Auto Liability, which may be satisfied by way of endorsement to the Commercial
General Liability policy or separate Business Auto Liability policy.
c. Workers’ Compensation and Employer’s Liability https://opengov.my.site.com/support/s/article/12c62371-147b-45f4-9bcd-cf2ce5f58259
Any person or entity performing work for or on behalf of the County must provide Workers’
Compensation and Employer’s Liability insurance in limits not less than:
● Workers Compensation Statutory limits
● Employers Liability $100,000 Each Accident
$500,000 Disease Policy
$100,000 Disease-Each Employee
Exceptions and exemptions may be allowed by the County Manager, if they are in accordance with Florida Statutes.
The Bidder waives, and the Bidder shall ensure that its insurance carrier waives, all subrogation rights against the County, its employees, agents, boards, and commissions, for all losses or damages. The County requires the policy to be endorsed with WC 00 03 13 Waiver of our Right to Recover from Others or equivalent.
The Bidder must be in compliance with all applicable State and federal workers’ compensation laws, including the U.S. Longshore Harbor Workers’ Act and the Jones Act, if applicable.
For any Bidder who has exempt status as an individual, the County requires proof of Workers’
Compensation insurance coverage for that Bidder’s employees, leased employees, volunteers, and any workers performing work.
d. Property Coverage (Builder’s Risk) – Applies to Construction related Projects
Coverage must be afforded in an amount not less than 100% of the total Project value, including soft costs, with a deductible of no more than $25,000 each claim. Named Windstorm
Deductibles, if any, must be disclosed to the County.
Coverage form shall include, but not be limited to:
• All Risk Coverage including Flood and Windstorm with no coinsurance clause
• Waiver of Occupancy Clause Endorsement, which will enable the County to occupy the property/structure under construction/renovation during the activity
• Storage and transport of materials, equipment, supplies of any kind whatsoever to be used on or incidental to the project
• Equipment Breakdown for cold testing of all mechanized, pressurized, or electrical equipment
• LEG2 Coverage or equivalent
For installation of property and/or equipment, Builder’s Risk Installation insurance must be provided to include coverage for materials or equipment stored at the Project site, while in transit, or while stored at a temporary location. Coverage limit must be no less than replacement cost.
The Property Coverage (Builder’s Risk) policy shall insure the interests of the owner, contractor, and subcontractors in the property against all risk of physical loss and damage, and name the
County as a loss payee. Additionally, the County shall be named as an Additional Insured for its interest in the property/structure and for any materials purchased directly by the County. This insurance shall remain in effect until the work is completed and the property has been accepted by the County.
e. Professional Liability and/or Errors and Omissions – Applies to Projects involving
Professional Services
Coverage must be afforded for Wrongful Acts in an amount not less than $1,000,000 each claim and $1,000,000 aggregate.
Insurance must be kept in force until the third anniversary of the expiration or termination of any Contract that may be entered into between the parties.
f. Umbrella/Excess Insurance
If the Bidder’s primary insurance policy/policies do not meet the minimum requirements, the
Bidder may provide an Umbrella/Excess insurance policy to comply with the insurance requirements.
Providing and maintaining adequate insurance coverage is a material obligation of the Bidder.
Upon being awarded the Bid and prior to commencement of the Services, the successful Bidder must deliver valid certificates of insurance for the required insurance coverage to the County’s
Purchasing Department.
The certificates of insurance for the required coverages, with the exception of Workers’
Compensation, Employer’s Liability, and Professional Liability, shall name “Clay County, a political subdivision of the State of Florida, and The Board of County Commissioners, Clay
County, Florida, its employees, agents, boards and commissions, as their interests may appear” as “Additional Insureds”. The coverage shall contain no special limitation on the scope of protection afforded to the County, its employees, agents, officials, boards, and commissions.
The certificates of insurance shall indicate if coverage is provided under a claims-made or occurrence form. If any coverage is provided on a claimsmade form, the certificates of insurance will show a retroactive date, which should be the same date of the initial Contract or prior. The Contract number, Bid number, event dates, or other identifying reference must be listed on the certificates of insurance.
The Certificate Holder on the certificates of insurance should read as follows: “Clay County
Board of County Commissioners, P.O. Box 1366, Green Cove Springs, FL 32043” or as otherwise designated by the County’s Purchasing Department.
The certificates of insurance shall be provided to the County with a thirty (30) day notice of cancellation; ten (10) days’ notice if cancellation is for nonpayment of premium. In the event that the insurer is unable to accommodate the cancellation notice requirement, it shall be the responsibility of the Bidder to provide the proper notice. Such notification will be in writing by registered mail, return receipt requested, and addressed to the Certificate Holder. In the event the Contract term goes beyond the expiration date of any insurance policy, the Bidder shall provide the County’s Purchasing Department with an updated certificate of insurance no later than ten (10) days prior to the expiration of the insurance currently in effect. The County reserves the right to suspend the Contract until this requirement is met. If any required insurance coverage is canceled, terminated, or revoked, the Bidder agrees to immediately suspend its operations until replacement insurance is obtained and verified.
Any exclusions or provisions in the insurance maintained by the Bidder that excludes coverage for work or services contemplated under the Bid shall be deemed unacceptable, a material violation of the County’s Bidding requirements, and shall be considered a breach of any
Contract entered into after a Bid Award.
It is the successful Bidder’s responsibility to ensure that all independent and subcontractors comply with the insurance requirements. All coverages for independent and subcontractors shall be subject to all of the requirements stated herein. Any and all deficiencies are the responsibility of the Bidder.
The County Manager may modify the insurance requirements for particular projects and/or
Services.
2.23. Laws and Regulations:
The Bidder shall comply with all laws and regulations applicable to provide the goods and/or services specified in this RFB. The Bidder shall be familiar with all federal, state and local laws that may affect the goods and/or services offered. All applicable Federal and State laws, municipal and Clay County ordinances, and the rules and regulations of all authorities having jurisdiction over any part of the project shall apply to the entire project and Contract.
2.24. No Bid:
Each Bidder not intending to Bid should select the "No-Bid" button on the main screen of the posted RFB.
For more information/instruction on how to submit a "No-Bid", please visit:
https://opengov.my.site.com/support/s/article/c529de59-be0a-458f-82b0-9aaa0e3dfac1 https://opengov.my.site.com/support/s/article/c529de59-be0a-458f-82b0-9aaa0e3dfac1
2.25. No Contact Period:
Bidders are prohibited from contacting, by any means, whether orally, telephonically, electronically or in writing, any member of the Board, any County employee, including the
County Manager, the County Attorney or the Commission Auditor, any member of the designated Evaluation Committee or any agent of the County regarding the Request for bids in any respect during the Request for Bid Period.
The Request for Bid Period during which no contact may occur commences from the date of publication of the notice of a Request for Bids and ends upon a Bid Decision becoming final, i.e.
after the notice of bid protest period of 72 hours has expired. However, in the event of a notice of protest, the no contact rule continues in place during the Protest Period and does not end until a resolution of the protest has occurred and become final.
The following exceptions exist to the no-contact rule:
A. Inquiries may be submitted to the Purchasing Department if specifically provided in the
Request for Bids;
B. Pre-bid conferences provided for in the Request for Bids; and
C. Formal presentations by Bidders to the designated Evaluation Committee or to the
Board or any committee thereof specifically contemplated in the Request for Bids.
2.26. Payments:
All payments will be made in accordance with the Local Government Prompt Payment Act;
related to non-construction services and construction services, as it may apply.
2.27. Performance and Payment Bond Requirements:
Awarded Bidder has 10 days from the execution of the Agreement to provide a compliant Performance and Payment Bond.
Performance and Payment Bonds are not required for projects of $200,000.00 or less. Prior to commencement of a project exceeding $200,000.00, in accordance with F.S. 255.05, the awarded Bidder shall file a 100% Performance Bond and Payment Bond (using Clay County’s
Standard Form) in the Public Record of Clay County, Florida, Recording Dept./Room 130, 825
North Orange Avenue, Green Cove Springs, Florida 32043. The recorded Performance and
Payment Bonds shall be provided prior to the commencement of construction to Clay County
Purchasing Department, PO Box 1366, Green Cove Springs, Florida 32043. Performance and
Payment Bonds must be increased in accordance with any change order increases on the project.
2.28. Public Entity Crimes:
Pursuant to Section 287.133(2)(a) of the Florida Statutes, a person or affiliate who has been placed on the convicted supplier list following a conviction for a public entity crime may not submit a Bid for a Contract to provide any goods or services to a public entity, may not submit a
Bid for a Contract with a public entity for the construction or repair of a public building or public work, may not submit Bids on leases of real property to a public entity, may not be awarded or perform work as a Contractor, supplier, Sub-Contractor, or consultant under a Contract with any public entity, and may not transact business with any public entity in excess of the threshold amount provided in Section 287.017 of the Florida Statutes, for CATEGORY TWO for a period of 36 months from the date of being placed on the convicted supplier list. By submitting a Bid - Bidder attests that they have not been placed on the Convicted Supplier List.
2.29. Public Records:
In accordance with Chapter 119 of the Florida Statutes (Public Records Law) and except as may be provided by other applicable State and Federal Law, all Bidders should be aware that Bids are public record. If the Bidder considers any portion of the documents, data or records within their Bid to be confidential and/or proprietary and which they believe to be exempt from disclosure, the Bidder must mark the document/response as “Confidential” in the applicable section, citing specifically the applicable exempting law and provide the County with a separate redacted copy of its Bid. Each RFB will provide a submittal section for a separate redacted copy.
In the event of a request for public records that is in accordance with the above mentioned authority, to which documents that are marked as confidential are responsive, the County will provide the Redacted Copy to the requestor. The Bidder acknowledges that if the Bidder fails to submit a redacted copy of information it claims is confidential, the County is authorized to produce the entire documents, data or records submitted to the County in answer to a public records request for these records.
2.30. Qualification:
The County shall have the right to review the references, experience of assigned personnel, and qualifications of the Bidder in order to make the final determination of acceptability of the
Bidder.
At the sole discretion of the County, such determination may result in the Bidder being deemed non-responsive.
2.31. Rejection:
The Board reserves the right to reject any and all Bids without cause and to waive technical and nontechnical or non-material defects in the request or submittals of any Bids.
2.32. Scrutinized Companies Certification:
In compliance with subsection (5) of Section 287.135(5), Florida Statutes the Bidder certifies that the company is not participating in a boycott of Israel as defined in subsection (1) of the
Statute; is not on the Scrutinized Companies with Activities in Sudan List or the Scrutinized
Companies with Activities in the Iran Petroleum Energy Sector List as referred to in subsection
(2) of the Statute; and is not engaged in business operations in Cuba or Syria as defined in subsection (1) of the Statute. The included Scrutinized Companies Certification Form must be completed and returned as part of the Bid.
2.33. Sub-Contractors:
The County reserves the right to approve all Sub-Contractors. If Sub-Contractors are to be utilized, their names and references must be included within this Bid. Responsibility for the performance of the Contract remains with the main Contractor exclusively. After the commencement of the project, Sub-Contractors may be added or modified during the Contract period only with prior written permission from the County, and only for reasonable cause, as judged by the County.
2.34. Supplier Debarment:
By submitting a Bid, the Bidder certifies that it is not currently debarred from submitting Bids for contracts issued by any political subdivision or agency of the State of Florida and that it is not an agent of a person or entity that is currently debarred from submitting Bids for contracts issued by any subdivision or agency of the State of Florida.
2.35. Use of Contract by other Government Agencies:
At the option of the Bidder, the use of the Contract resulting from this solicitation may be extended to other governmental agencies, including the State of Florida, its agencies, political subdivision, counties, and cities.
Each governmental agency permitted by the Bidder to utilize this Contract must operate autonomously from other governmental entities. Each agency is accountable for its own procurement and is only liable for the goods or services it orders, receives, and accepts. No agency assumes liability solely by participating in this bid and subsequent contract award.
2.36. Value Engineering
The County reserves the right to engage in value engineering discussions prior to the award of the RFB.
The County will give the lowest qualified Bidder the opportunity to determine if viable options exist to meet the budget threshold without substantially reducing the scope of the project as designed and solicited.
2.37. Waiver of Formalities/Rejection of Bids:
The County reserves the right to waive formalities in any Bid, to reject any or all Bids with or without cause, to waive irregularities, and waive technical and non-technical or non-material defects in the Bid document or submittal of any Bid. Bids in which the prices obviously are unbalanced will be rejected. The County reserves the right to reject any and all Bids and to re-advertise for all or any part of this solicitation as deemed in its best interest.
2.38. Withdrawal of Bid:
Bids may be withdrawn by selecting "Unsubmit Proposal" at the bottom of the Bidders
"OpenGov Proposal" screen before the date and time for receiving Bids has expired. Negligence on the part of the Bidder in preparing a Bid is not grounds for withdrawal or modification of a
Bid after such Bid has been opened by the County. Bidders may not withdraw or modify a Bid after the appointed Bid Opening, and Bids will be in force for a minimum of One Hundred and
Twenty (120) days after the Bid Opening. Bidders may not assign or otherwise transfer their
Bids.
For more information/instruction on how to Withdrawal a Bid, please visit:
https://opengov.my.site.com/support/s/article/4f4218bf-7da6-4fc6-b0c3-7eade0776ebe https://opengov.my.site.com/support/s/article/4f4218bf-7da6-4fc6-b0c3-7eade0776ebe
3. Scope of Work
3.1. Purpose
The Clay County Board of County Commissioners (County) is requesting bids from qualified
Contractors for the site clearing services at Fire Station 24 located at 1075 County Road 226
Green Cove Springs, FL 32043 per the plans and specifications associated with this Request for
Bid (RFB).
The selected site is currently undeveloped and must undergo full site preparation to enable construction activities. This project will be executed in a phased approach to ensure that environmental sensitivities and regulatory compliance are prioritized throughout the process.
Site disturbance shall not commence until all required pre-clearing inspections, permits, and regulatory approvals are completed and accepted by Clay County Project Manager or designee.
The phased scope includes:
• Phase I – Erosion and Sedimentation Control: Installation of erosion control measures to prevent soil displacement and protect surrounding natural resources during and after site disturbance.
• Phase II – Tree Removal and Grubbing: Clearing of designated trees and vegetation to prepare the site for construction access and subsequent environmental work.
3.2. Scope
The Contractor shall provide all labor, equipment, materials, permitting, supervision, and coordination necessary to perform phased site clearing and environmental mitigation services for the development of Fire Station 24 in Clay County, Florida.
The work shall be performed in phases defined below, beginning with installation and maintenance of erosion and sedimentation control measures and followed with tree removal and grubbing. All work shall be completed in accordance with applicable Clay County regulations, as well as environmental compliance requirements set forth by the Florida Fish and
Wildlife Conservation Commission (FWC) and the U.S. Fish and Wildlife Service (USFWS).
The site has known protected species of Tri-Colored Bats and Eastern Indigo Snakes.
Implementation of species protection measures in accordance with applicable wildlife regulations shall be required.
Protected Species (Eastern Indigo Snakes and Tri-Colored Bats)
The awarded Contractor shall implement the following protective measures to avoid harm to state and federally protected species during site clearing and preparation. These activities must be coordinated with qualified environmental professionals and conducted in accordance with
Florida Fish and Wildlife Conservation Commission (FWC) and U.S. Fish and Wildlife Service
(USFWS) guidelines.
A. Eastern Indigo Snake Measures
1. The Contractor shall conduct daily visual inspections of the work area prior to clearing. All personnel must receive a Species Protection Plan briefing covering snake identification and avoidance protocols. Signage shall be visibly posted on-site outlining steps to take if an Eastern Indigo Snake is observed. If a snake is encountered:
a. Immediately stop work in the vicinity
b. Do not touch or move the snake. Allow it to leave the area on its own.
c. Notify FWC in accordance with permit or agency requirements.
3.3. Base Bid
Base Bid: Gopher tortoises shall be relocated prior to clearing and grubbing activities. The County has contracted with WGI, Inc. to relocate gopher tortoises.
Phase I – Erosion and Sedimentation Control
The Contractor shall:
• Install and maintain erosion and sediment control measures prior to or immediately following vegetation removal, as necessary to prevent offsite sedimentation.
• Maintain all erosion control features throughout the duration of the project or until permanent stabilization is achieved.
• Inspect erosion control devices regularly and after rain events.
• Immediately repair or replace damaged devices as needed to maintain effectiveness.
• Remove temporary erosion control measures upon final site stabilization, unless otherwise directed by the County.
• Prevent sediment tracking onto public roadways.
• Coordinate with County staff or environmental monitors for erosion control inspections prior to progressing to subsequent phases of construction.
Phase II – Tree Removal and Grubbing
The Contractor shall:
• Secure all necessary permits for clearing activities.
• Dispose of clearing debris by either open burning with an air curtain incinerator or grinding and removing off-site. Contractor shall be responsible for verifying the site meets all required site conditions to obtain a burn permit. Contractor shall abide by all local and state environmental regulations for each method.
• Maintain all necessary records, permits, inspection reports, and species mitigation documentation onsite and make them available for County review upon request.
• Remove all trees identified in the associated plans, along with brush and surface vegetation, within the project limits. The County shall identify and flag all trees designated for removal.
• Conduct mechanical grubbing of stumps, root systems, and invasive undergrowth to prepare the site for grading and development.
• Prior to removing trees, ensure a pre-clearing inspection is completed.
• Coordinate with the County Project Manager or designee before removing any tree potentially protected by local ordinance. Do not remove any protected tree without prior written authorization.
• Utilize existing site access and is responsible for clean truck and tires prior to entering public road systems.
• Installing and maintaining clear signage, fencing or flagging where necessary.
• Be responsible for the coordination and maintenance of all pedestrian and vehicle traffic as needed for construction following FDOT and County MOT guidelines.
• Maintain the silt fence in its designed alignment, or as otherwise directed to ensure sedimentation and turbidity control, in accordance with Phase I…