This is a final specifications document and notice to bidders from the State of Hawaii Department of Transportation, Airports Division for the Apron Reconstruction, Phase 1 project at Kahului Airport, Kahului, Maui, Hawaii (State Project No. CM1530-33). The project consists of repairing deteriorated exterior concrete and concrete masonry unit surfaces of Holdroom F and Walkway EFF, along with concrete repair in adjacent areas. A virtual pre-bid conference is scheduled for October 12, 2026, at 10:00 a.m., HST, with attendance optional but encouraged; interested bidders must contact Jake Shiraki, State Project Manager, at jake.l.shiraki@hawaii.gov no later than two working days prior to the conference. A mandatory site visit is scheduled for October 20, 2026, at 9:00 a.m., HST at Kahului Airport. All Request for Information (RFI) questions and substitution requests must be submitted through HIePRO no later than October 26, 2026, at 2:00 p.m., HST. The HIePRO offer due date and time is November 16, 2026, at 2:00 p.m., HST. Bidders must be registered with HIePRO and submit complete proposals through the platform only; proposals received after the deadline will not be considered.
To be eligible for award, bidders must possess a valid State of Hawaii General Engineering "A" license at the time of bidding. The estimated construction cost is between $2,000,000.00 and $3,000,000.00. Bid security is required in an amount equal to at least five percent of the base bid and additive alternates, available in forms including surety bonds, deposits, or certified checks. A five percent bid adjustment applies to bidders party to apprenticeship agreements pursuant to HRS 103-55.6. Employment of Hawaii residents is required, with a minimum of 80 percent of the bidder's workforce on the project consisting of Hawaii residents, in compliance with HRS 103B-3. Liquidated damages are assessed at $150.00 per calendar day for failure to complete work within the contract duration. The State reserves the right to reject any or all proposals and waive any defects. All contractors performing work within 75 feet of taxiways or 500 feet of runways must comply with strict operational safety requirements, Federal Aviation Administration Advisory Circulars, and Airport Certification Manual requirements, including maintaining constant radio communication and hazard markings.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FINAL PLANS CM1530 33.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF HAWAII
DEPARTMENT OF TRANSPORTATION
AIRPORTS
GENERAL REQUIREMENTS, GENERAL PROVISIONS, TECHNICAL PROVISIONS
FOR
APRON RECONSTRUCTION, PHASE 1
KAHULUI AIRPORT
KAHULUI, MAUI, HAWAII
STATE PROJECT NO. CM1530-33
NTB-1
NOTICE TO BIDDERS
Hawaii Revised Statutes (HRS), Chapter 103D
The receiving of bids for APRON RECONSTRUCTION, PHASE 1, KAHULUI
AIRPORT, KAHULUI, MAUI, HAWAII, STATE PROJECT NO. CM1530-33, will begin as of the HIePRO Release Date. Bidders shall register and submit complete bids through
HIePRO only. Refer to the following HIePRO link for important information on Vendor
Registration: https://hiepro.ehawaii.gov/welcome.html.
The solicitation plans, specifications, proposal, and additional documents designated or incorporated by reference shall be available in HIePRO.
HIePRO OFFER DUE DATE AND TIME is November 16, 2026, at 2:00 p.m., Hawaii
Standard Time (HST). Bidders shall submit and upload the complete proposal to HIePRO prior to the offer due date and time. Proposals received after said due date and time shall not be considered. Any additional support documents explicitly designated as confidential and/or proprietary shall be uploaded as a separate file to HIePRO. Bidders shall not include confidential and/or proprietary documents as part of their proposal. The record of each bidder and their respective proposal shall be open to public inspection. FAILURE
TO UPLOAD THE PROPOSAL TO HIePRO SHALL BE GROUNDS FOR REJECTION.
The scope of work consists of repairing deteriorated exterior concrete and concrete masonry unit surfaces of Holdroom F and Walkway EFF, as well as concrete repair for that respective adjacent area. The estimated cost of construction is between $2,000,000.00 and $3,000,000.00.
To be eligible for award, bidders shall possess a valid State of Hawaii General
Engineering "A" license at the time of bidding.
rmiyasato Sticky Note Completed set by rmiyasato
NTB-2
The Hawaii Department of Transportation, Air and Water Transportation Facilities
Division, 2016 GENERAL PROVISIONS FOR CONSTRUCTION PROJECTS, applicable to this project are available on the internet at: http://hidot.hawaii.gov/administration/con/.
A virtual pre-bid conference is scheduled for October 12, 2026, at 10:00 a.m., HST.
Interested bidders shall contact Jake Shiraki, State Project Manager, directly at jake.l.shiraki@hawaii.gov, no later than two working days prior to the scheduled pre-bid conference to receive the meeting invitation. All prospective bidders and/or their respective representatives are encouraged to attend, however, attendance is not mandatory. All information presented at the pre-bid conference shall be provided for clarification and information only. Any amendments to the solicitation shall be made by formal addendum and posted in HIePRO.
A site visit for Kahului Airport will be scheduled for October 20, 2026, at
9:00 a.m., HST. Prospective bidders must contact the airport representative to indicate they will be planning to attend the site visit and coordinate the meeting place. It is the responsibility of the
Contractor to understand the required scope of work. The work shall be performed and documented in accordance with these specifications.
All Request for Information (RFI) questions and Substitution Requests shall be submitted in HIePRO no later than October 26, 2026, at 2:00 p.m., HST. RFI questions received after the stated deadline shall not be addressed. Substitution Requests received after the stated deadline shall not be considered. Verbal RFI(s) shall not receive a response. All responses to
RFI questions shall be provided for clarification and information only and issued by formal addendum. Any amendments to the solicitation shall be made by formal addendum and posted in HIePRO.
rmiyasato
NTB-3
If there is a conflict between the solicitation and information stated in the pre-bid conference, pre-bid site visit, the meeting minutes, and/or the responses to RFI questions, the solicitation shall govern and control, unless as amended by formal addendum.
Apprenticeship Preference. A five percent bid adjustment for bidders that are party to apprenticeship agreements pursuant to HRS § 103-55.6 is applicable to this project.
Employment of State Residents on Construction Procurement Contracts. Compliance with HRS § 103B-3 is a requirement for this project whereby a minimum of 80 percent of the bidder's work force on this project shall consist of Hawaii residents.
Campaign contributions by State and County Contractors. Contractors are hereby notified of the applicability of HRS § 11-355 which states that campaign contributions are prohibited from specified State or County government contractors during the term of the contract if the contractors are paid with funds appropriated by a legislative body. For more information, contact the Campaign Spending Commission at (808) 586-0285.
Protests. Any protest of this solicitation shall be submitted in writing to the Director of
Transportation, in accordance with HRS § 103D-701 and Hawaii Administrative Rules § 3-126.
Bidders are hereby notified that the Department of Transportation shall affirmatively ensure that contracts entered into pursuant to this advertisement are awarded to the lowest responsible bidder without discrimination on the basis of race, color, national origin, sex, age, disability, or any other protected status recognized under applicable State and federal law.
For additional information, contact Jake Shiraki, State Project Manager, by phone at
(808) 838-8805, or by email at jake.l.shiraki@hawaii.gov.
NTB-4
The State reserves the right to reject any or all proposals and to waive any defects in said proposals in the best interest of the public.
CURT T. OTAGURO
Deputy Director of Transportation for Airports
HIePRO RELEASE DATE: October 2, 2026 rmiyasato
APRON RECONSTRUCTION, PHASE 1
TABLE OF CONTENTS
TOC-1
R08/18/2026STATE PROJECT NO. CM1530-33
TABLE OF CONTENTS
Pages
PART 0 – GENERAL REQUIREMENTS
Instructions for Contractor’s Licensing
Special Provisions ................................................................................................. SP-1 to SP-10
Wage Rate Schedule (Not Physically Included)
PART I – GENERAL PROVISIONS FOR CONSTRUCTION PROJECTS
(Not Physically Included In The Bid Documents)
PART II – TECHNICAL PROVISIONS
DIVISION 1 – GENERAL REQUIREMENTS
DESCRIPTION OF WORK .................................................. 01010-1 to 01010-5
WORK SEQUENCE ............................................................ 01014-1 to 01014-2
ALLOWANCES ................................................................... 01210-1 to 01210-2
SUBMITTALS ..................................................................... 01300-1 to 01300-8
CONTRACTOR’S CONSTRUCTION SCHEDULE
AND REPORTS .................................................................. 01301-1 to 01301-16
CONTRACTOR QUALITY CONTROL PROGRAM ............. 01400-1 to 01400-7
TEMPORARY WATER POLLUTION, DUST,
AND EROSION CONTROL ................................................. 01500-1 to 01500-8
CONSTRUCTION WASTE MANAGEMENT ....................... 01524-1 to 01524-17
BARRICADES ..................................................................... 01533-1 to 01533-2
GENERAL ENVIRONMENTAL HEALTH &
SAFETY CONTROLS ......................................................... 01560-1 to 01560-4
CONSTRUCTION SITE POLLUTION CONTROLS ............. 01561-1 to 01561-13
SECURITY MEASURES ..................................................... 01565-1 to 01565-2
TEMPORARY FACILITIES AND UTILITIES ........................ 01580-1 to 01580-2
MOBILIZATION, DEMOBILIZATION ................................... 01700-1 to 01700-3
SECTION 01010
SECTION 01014
SECTION 01210
SECTION 01300
SECTION 01301
SECTION 01400
SECTION 01500
SECTION 01524
SECTION 01533
SECTION 01560
SECTION 01561
SECTION 01565
SECTION 01580
SECTION 01700
SECTION 01800 SPECIAL REQUIREMENTS FOR CONTRACTORS
ON THE AOA ...................................................................... 01800-1 to 01800-8
DIVISION 2 – SITE CONSTRUCTION
SECTION 02410 SELECTIVE DEMOLITION ................................................. 02410-1 to 02410-7 rmiyasato Sticky Note Completed set by rmiyasato rmiyasato Sticky Note Completed set by rmiyasato rmiyasato Sticky Note Completed set by rmiyasato rmiyasato Sticky Note Completed set by rmiyasato rmiyasato Sticky Note Completed set by rmiyasato rmiyasato
APRON RECONSTRUCTION, PHASE 1 TABLE OF CONTENTS
KAHULUI AIRPORT TOC-2
STATE PROJECT NO. CM1530-33
DIVISION 3 – CONCRETE
SECTION 03740 CONCRETE REHABILITATION .......................................... 03740-1 to 03740-13
DIVISION 4 – MASONRY
SECTION 04012 CONCRETE UNIT MASONRY REPAIR .............................. 04012-1 to 04012-10
DIVISION 5 – METALS (NOT USED)
DIVISION 6 - WOOD AND PLASTICS (NOT USED)
DIVISION 7 - THERMAL AND MOISTURE PROTECTION (NOT USED)
DIVISION 8 - DOORS AND WINDOWS (NOT USED)
DIVISION 9 – FINISHES (NOT USED)
DIVISION 10 – SPECIALTIES (NOT USED)
DIVISION 11 - EQUIPMENT (NOT USED)
DIVISION 12 - FURNISHINGS (NOT USED)
DIVISION 13 - SPECIAL CONSTRUCTION
DIVISION 14 - CONVEYING SYSTEMS (NOT USED)
DIVISION 15 – MECHANICAL (NOT USED)
DIVISION 16 – ELECTRICAL (NOT USED)
Requirements of Chapter 104, HRS, Wager and Hours of Employees on Public Works Law (Rev. 05/24) ...................... 1 to 2
Proposal ................................................................................................................ P-1 to P-8
Proposal Schedule ................................................................................................. P-9 to P-10
Surety Bid Bond ..................................................................................................... BB-1
Forms
SAMPLE CONTRACT .......................................................................................... K-1 to K-3
Performance Bond (Surety) ............................................................................. SPB-1 to SBP-2
Performance Bond ......................................................................................... PB-1 to PB-2 rmiyasato Sticky Note Completed set by rmiyasato rmiyasato Sticky Note Completed set by rmiyasato rmiyasato Sticky Note Completed set by rmiyasato rmiyasato
APRON RECONSTRUCTION, PHASE 1 TABLE OF CONTENTS
KAHULUI AIRPORT TOC-3
STATE PROJECT NO. CM1530-33
Labor and Material Payment Bond (Surety) ...................................................... SLB-1 to SLB-2
Labor and Material Payment Bond ................................................................... LB-1 to LB-2
Chapter 104, HRS Compliance Certificate
Certification of Compliance for Employment of State Residents (ACT 192, SLH 2011) - Provisions to be Included in Construction Procurement Solicitation
STATE PROJECT NO. CM1530-33 Instruction to Contractor’s Licensing
INSTRUCTIONS FOR CONTRACTOR’S LICENSING
"A" general engineering contractors and "B" general building contractors are reminded that due to the Hawaii Supreme Court’s January 28, 2002 decision in Okada Trucking Co., Ltd. v.
Board of Water Supply, et al., 97 Haw. 450 (2002), they are prohibited from undertaking any work, solely or as part of a larger project, which would require the general contractor to act as a specialty contractor in any area where the general contractor has no license. Although the "A" and "B" contractor may still bid on and act as the "prime" contractor on an "A" or "B" project
(See, HRS § 444-7 for the definitions of an "A" and "B" project.), respectively, the "A" and "B" contractor may only perform work in the areas in which they have the appropriate contractor’s license (An "A" or "B" contractor obtains "C" specialty contractor’s licenses either on its own, or automatically under HAR § 16-77-32.). The remaining work must be performed by appropriately licensed entities. It is the sole responsibility of the contractor to review the requirements of this project and determine the appropriate licenses that are required to complete the project.
SPECIAL PROVISIONS
SP-1 R03/13/24
SPECIAL PROVISIONS
The following additional amendments to the General Provisions are applicable to this project:
1.3 DEFINITIONS is amended as follows:
1. The following definition shall be deleted in its entirety and replaced with the following:
“Subcontractor – An individual, partnership, firm, corporation, or joint venture, or other legal entity, as licensed or required to be licensed under Chapter 444, Hawaii Revised Statutes, as amended, which enters into an agreement with the Contractor to perform a portion of the work.”
2. Add the following to 1.3 Definitions.
“HAWAII ePROCUREMENT SYSTEM (HIePRO) - The State of Hawaii eProcurement System for issuing solicitations, receiving proposals and responses, and issuing notices of award.”
2.7 REQUEST FOR SUBSTITUTION OF SPECIFIED MATERIALS AND EQUIPMENT
BEFORE BID OPENING is amended as follows:
1. The last sentence in the first paragraph (line 147 to 152) shall be replaced with the following:
Where a bidder intends to use a material or equipment of an unspecified brand, make, or model, the bidder must submit a request to the Department for review and approval at the earliest date possible. As specified in the Notice to Bidders, all requests shall be posted as a question in HIePRO under the "Question and Answer" tab. Supporting documents for specific request shall be emailed to the Project Manager specified in the Notice to Bidders. Request must be posted in HIePRO and supporting documents received by the Project Manager no later than fourteen (14) calendar days before the bid opening date.
2. The first sentence in the second paragraph (line 154 to 156) shall be replaced with the following:
“It shall be the responsibility of the bidder to submit sufficient evidence based upon which a determination can be made by the Department that the alternate brand is a qualified equivalent.”
2.8 PREPARATION AND DELIVERY OF BID is amended as follows: Last Paragraph (line 189 to 192) shall be replaced with the following:
“Bidders shall submit and upload the complete proposal to HIePRO prior to the bid opening date and time. Proposals received after said due date and time shall not be considered. Any additional support documents explicitly designated as confidential and/or proprietary shall be uploaded as a separate file to HIePRO.
Bidders shall not include confidential and/or proprietary documents with the proposal. The record of each bidder and respective bid shall be open to publicinspection. Original (wet ink, hard copy) proposal documents are not required to be
APRON RECONSTRUCTION, PHASE 1
STATE PROJECT NO. CM1530-33
STATE PROJECT NO. CM1530-33 SP-2 R03/13/24
submitted.
FAILURE TO UPLOAD THE COMPLETE PROPOSAL TO HIePRO SHALL BE
GROUNDS FOR REJECTION OF THE BID.
If there is a conflict between the specification document and the HIePRO solicitation, the specifications shall govern and control, unless otherwise specified.”
2.11 BID SECURITY is amended by deleting (a) and replacing it with:
“(a) Unless directed otherwise in the invitation for bids, each bid shall be accompanied by bid security which is intended to protect the Department against the failure or refusal of a bidder to execute the contract for the work bid or to supply the required performance and payment bonds. Bid security shall be in an amount equal to at least five percent of the base bid and additive alternates. Bid security shall be in one of the following forms:
(1) A deposit of legal tender;
(2) A valid surety bid bond, underwritten by a company licensed to issue bonds in the State of Hawaii, in the form and composed, substantially, with the same language as provided herewith and signed by both parties.
(3) A certificate of deposit; credit union share certificate; or cashier’s, treasurer’s, teller’s, or official check drawn by or a certified check accepted by a bank, savings institution, or credit union insured by the Federal Deposit Insurance Corporation (FDIC) or the National Credit Union Administration (NCUA) and payable at sight or unconditionally assigned to the Department.
These instruments may be utilized only to a maximum of one hundred thousand dollars ($100,000.00). If the required amount totals over one hundred thousand dollars ($100,000.00), more than one instrument not exceeding one hundred thousand dollars ($100,000.00) each and issued by different financial institutions shall be accepted.
If bidder elects options (1) or (3) above for its bid security, said bid security shall be in its original form and shall be submitted before the bid deadline to the Contract Office, Department of Transportation, Aliiaimoku Hale, 869 Punchbowl Street, Room 103, Honolulu, Hawaii 96813. Original surety bid bonds do not need to be submitted to the Contracts Office. Bidders are reminded that a copy of its surety bid bond shall be included with its bid submitted and uploaded to HIePRO.”
2.12 PRE-OPENING MODIFICATION OR WITHDRAWAL OF BIDS is amended by deleting 2.12 PRE-OPENING MODIFICATION OR WITHDRAWAL OF BIDS in its entirety and replacing with the following:
2.12 PRE-OPENING MODIFICATION OF WITHDRAWAL OF BIDS. Bids may be modified or withdrawn prior to the bid opening date and time. Withdrawal or revision of proposal shall be completed, and submitted and uploaded to HIePRO prior to the bid opening date and time.
rmiyasato
STATE PROJECT NO. CM1530-33 SP-3 R03/13/24
2.14 PUBLIC OPENING OF BIDS is amended by deleting 2.14 PUBLIC OPENING OF BIDS in its entirety.
4.12 UTILITIES AND SERVICES is amended as follows:
Add the following after the last paragraph:
“(e) Repairs and Outages.
(1) The Contractor shall have available on 24-hour call sufficient specialty contractors, such as electrical and plumbing contractors, to repair any damage to existing facilities that might occur as a result of construction operations regardless of when the damage might occur.
(2) Outage: Written requests for power outage, communication changes, and water and sewer connection outages shall be submitted to the Engineer at least seven (7) days in advance or as specified in other sections of these specifications. Outages will be restricted to non-peak operational hours between midnight and 6:00 a.m."
7.21 PUBLIC CONVENIENCE AND SAFETY - is hereby added to the General Provisions:
“It shall be especially noted by the Contractor that the area directly adjacent to the existing in use runways and taxiways, is an extremely hazardous area and that very strict controls will apply throughout the entire period required to complete all work within 500 feet from the edge of an in use runway and 180 feet from the edge of an in use taxiway.
The Contractor shall familiarize himself with the Airport Certification Manual available for review at the Airport Manager's Office and shall comply with its requirements.
The Contractor is responsible for the security of access points to the Airport Operational Area that are located within the limits of construction and will be fined $1,000 per incident for any breach of security at these locations. All gates leading into the AOA shall be kept locked and if required to be open, the Contractor shall provide professional security guards to attend gates. The guards must be approved by the Director and shall be required to attend a training session conducted by the Airport Manager prior to gate assignment.”
8.8 LIQUIDATED DAMAGES FOR FAILURE TO COMPLETE THE WORK OR
PORTIONS OF THE WORK ON TIME: The General Provisions is hereby amended to include the following:
The schedule of liquidated damages provided in Section 8.8 of the General Provisions in these specifications shall be amended to include the following:
ONE HUNDRED FIFTY DOLLARS ($150.00) per calendar day for failure to complete the work within the duration (calendar days) noted on Proposal Schedule page P-1.
8.20 LIMITATION OF OPERATIONS: is hereby added to the General Provisions:
"The following limitations shall be observed by the Contractor when operating within 75 feet from the edge of any taxiway.
rmiyasato
STATE PROJECT NO. CM1530-33 SP-4 R03/13/24
General - The Contractor shall schedule his operations to minimize interference with the movement of aircraft or passengers as may be required by the Engineer. The Contractor shall be responsible to alert all of his personnel to the location of power and signal cables installed for the operation of the airport. The Contractor shall control his operations in a manner to preclude any possible damage to those cables. Utility companies shall be notified by the Contractor one week before commencement of work.
The Contractor shall give notice to the Engineer in writing, at least 168 hours before operating within 75 feet from the edge of any taxiway and the Engineer will assure himself that the Airport Management personnel are notified in sufficient time to publish the warning (NOTAM). The Contractor shall immediately repair any damages to the existing perimeter fence to prevent inadvertent entry to the Airport Operation Area
(AOA).
Work in Vicinity of Runways and Taxiways in Use - Under the terms of this contract, it is intended that work shall be completed without disturbing the paved surface of existing runways and taxiways, unless shown otherwise on the plans. Aircraft traffic shall not be interrupted. The Contractor shall schedule to work within 75 feet of the taxiway as directed by the Airport Management. No ruts, holes, or open trenches of 3 inches or more in depth and no objects or material 3 inches or more in height shall be permitted within the safety area when the airfield is in operation in conformance to Federal Aviation Regulation Part 139. The Contractor is also informed that Airport Zoning Regulations dictate that a 'clear zone' be maintained 500 feet on each side of an active runway, to be known as a hazardous area. The Contractor shall comply with all regulations governing ground operations within hazardous areas. The following FAA Advisory Circulars or later versions and FAA Regulations specify these requirements:
AC 150/5210-5C Painting, Marking, and Lighting Vehicles Used on an Airport, dated August 2007
AC 150/5340-1J Standards for Airport Markings
AC 150/5370-2E Operational Safety on Airports During Construction, dated 1/17/03
FAA Regulations Objects Affecting Navigable Airspace Part 77
The Contractor shall keep all personnel and equipment off the areas not specifically designated for work under this Contract. At all times when the Contractor's equipment is not in use, the equipment shall be moved outside the hazardous areas to an area designated by the Engineer. Under no condition shall equipment be parked or material stored within the hazardous areas.
Failure on the part of the Contractor to abide by the above will result in suspension of work.
Authority of Control Tower Personnel - With the exception of actual construction methods, the airport control tower personnel will have full authority to control the Contractor's movements within the existing taxiway. When required, the Contractor shall maintain a constant radio vigil within all work areas and in addition shall keep at least one flagman on duty with the radio man. When notified by the control tower to temporarily halt operations, it shall be the duty of the flagman, through the use of appropriate methods (lighted flares shall not be used under any circumstances), to notify all operators of equipment and other personnel to cease work and move men and
STATE PROJECT NO. CM1530-33 SP-5 R03/13/24
equipment off of hazardous areas.
Contractor shall provide, at his own expense, the necessary radio and equipment including a radio equipped mobile vehicle to maintain contact with control tower personnel at all times during job performance. A transceiver operating at a frequency designated by the Engineer to communicate with the Control Tower.
Marking of Hazardous Areas - The Engineer will designate areas that are hazardous for aircraft. The Contractor shall provide red blinker lights spaced not more than 50 feet apart around all hazardous areas and areas of work within 75 feet of any taxiway. Such systems shall be subject to approval by the Engineer. The Contractor shall have personnel on call 24 hours per day for the emergency maintenance of hazard markings.
The Contractor shall provide red flags not less than 20 inches square in addition to the red blinker lights. When danger flags are made of fabric, a wire stiffener shall be used to hold the flags in an extended position. Flags shall be so mounted that they do not produce a hazard. The red danger flags shall be spaced not more than 50 feet apart around all areas of work within 75 feet of any taxiway.
All systems proposed by the Contractor for lighting and barricading shall be submitted to the Engineer for review prior to installation. The Contractor shall install all flags, lighting and barricades as required by the Engineer. Such systems shall be subject to approval by the Engineer.
Storage of Equipment and Materials - At the end of each working shift, all of the Contractor's equipment shall be withdrawn to an area designated by the Engineer. The Contractor shall park all equipment in an orderly fashion and place a sufficient number of red flasher lights to identify these areas. Materials stored within the airport shall be so placed and the work shall, at all times, be so conducted as to cause no greater obstruction to the air and ground traffic than is considered necessary by the Engineer.
No runways, taxiways or roadways shall be closed or opened, except by permission of the Engineer.
Blasting Operations - The Contractor shall notify the Engineer at least three (3) days before performing blasting operations as to the extent and timing of such operations, so that the Control Tower and other concerned parties can be informed.
Utilities - The Contractor shall provide for the protection of all utilities from damages in areas to be traversed by his vehicles and equipment. If required, buried cables and utility lines shall be protected by mounding earth over the cables or by any other method approved by the Engineer.
The Contractor shall notify representatives of the owner, agencies, and other affected organizations at least 48 hours prior to working in any area containing the facilities of these organizations.
Failure to notify the owning organization will prevent authorization to work in a specific area.
Archaeological Features - Any archaeological features such as petroglyphs, burial sites, and artifacts discovered or unearthed during the performance of the work shall immediately be brought to the attention of the Engineer and all work that would damage or destroy these features shall be discontinued. The Engineer will decide, after
STATE PROJECT NO. CM1530-33 SP-6 R03/13/24
proper investigation, to salvage or abandon such artifacts."
8.21 OPERATION OF CONTRACTOR'S MOTOR VEHICLE AND PERSONNEL IN
RESTRICTED AIR OPERATIONS AND MOVEMENT AREAS is hereby added to the General Provisions:
"The Contractor shall conform with the all sections of the "State of Hawaii, Department of Transportation, Airports , Contractor's Training Guide" pertaining to access and operation in the Airport Operation Area (AOA) hereinafter described as follows:
A. Motor Vehicles in Airport Operation Area
For safety reasons, the operation of motor vehicles in the AOA must conform with all applicable State Airport rules and regulations."
B. Motor Vehicle Access Permit
Each motor vehicle operated in the AOA is required to:
1. Meet all State licensing registration and safety requirements and be specifically licensed for operation in the AOA.
2. Meet all insurance requirements.
3. Be restricted to operation by those persons qualified to drive the vehicle and in possession of a current Ramp Driver's License and applicable Motor Vehicle Operator's License.
C. The operators of motor vehicles in the AOA shall be responsible for meeting the following insurance requirements.
1. Licensed Vehicles
As a condition for authorization to enter the AOA, the Contractor shall provide evidence of vehicle liability insurance in the form of a Certificate of Insurance issued by an authorized insurance carrier.
Automobile Liability and general Liability (combined single limit, Bodily Injury and Property Damage, per occurrence) shall be required in the applicable minimum limits specified below:
a. Daniel K. Inouye International Airport
(1) Standard AOA clearance ..... $5,000,000
(2) Limited AOA clearance ..... $1,000,000 Limited AOA clearance is defined as operations restricted to Diamond head and Ewa Concourses second level roadways and connecting third level main terminal roadway only, with entry and exit via Security Access Point "C" (Primary) and Access Point "A" (Secondary)
b. Other Airports
Standard AOA clearance......... $1,000,000
STATE PROJECT NO. CM1530-33 SP-7 R03/13/24
Standard AOA clearance is defined as any portion of a public Airport from which the public is restricted by fences or appropriate signs and not leased or demised to anyone for exclusive use and shall include runways, taxiways, all ramp and apron areas, aircraft parking and storage areas, fuel storage areas, maintenance areas, and any other area of a public Airport used or intended to be used for landing, takeoff, or surface maneuvering of aircraft or used for embarkation or debarkation of passengers.
2. Unlicensed Vehicles
Airport Liability (or General Liability) shall be required in the applicable minimum limits specified below:
a. Daniel K. Inouye International Airport, Kahului Airport and Kona International Airport at Keahole
AOA clearance .................. $5,000,000
b. All other Airports
AOA clearance .................. $1,000,000
3. Specifically name the State of Hawaii as additionally insured.
4. Indicate that the Airport Engineer will be provided with a 30-day written prior notice of policy cancellation or material change in coverage or conditions.
D. Operator's Permit
1. No person shall operate a motor vehicle on the AOA unless he holds and carries on his person a current Airport Motor Vehicle operator's permit issued by the State of Hawaii, Department of Transportation, Airports .
2. Operator's permits will only be issued to persons who apply through the Airport District Security Office and pass a written exam covering those portions of the Airport Rules and Regulation relating to the operation of vehicles in Airport Operations Areas.
E. Authorized Vehicles
1. Only vehicles considered operationally safe and necessary for the performance of this contract may be allowed to operate in the AOA.
2. All motor vehicles must be painted in such a manner so as to be easily identifiable and must carry the Contractor's name on each side. These signs may be of a temporary nature applied to the side windows or doors.
The lettering shall be in bold characters of a minimum of four (4) inches in height and one and one-half (1-1/2) inches in widths, the height of logos should be a minimum of six (6) inches.
3. The Contractor's operations on, over, across, and/or immediately
STATE PROJECT NO. CM1530-33 SP-8 R03/13/24
adjacent to any runway and/or taxiway at a towered airport shall require the use of two-way radio communication. The Contractor shall obtain the necessary equipment at his own expense.
4. No person shall operate a motor vehicle on the AOA unless he holds and carries on his person a current Motor Vehicle Operator's Permit issued by the Airport Manager.
a. The Motor Vehicle Operator's Permit will be issued only to persons who apply through the Airport Security Section and pass a written exam covering those portions of the Airport Rules and Regulations relating to the operation of vehicles in the AOA.
b. Permits issued may be suspended or revoked for cause at any time by the Airports .
F. Airport Operation Area Construction Pass
1. Issuance of Airport Operation Area (AOA) Construction Passes shall be limited to contractors, subcontractors, companies, organizations, individuals engaged in authorized and approved construction activity which requires a continuing need for entry into the AOA or Airfield Movement Areas. Request letters for such passes must be made to the Airport District Manager's Office in accordance with the Contractors Training Guide or applicable District requirements.
2. As a condition for security area clearance, applicants must comply with Transportation Security Regulation 1542 which requires a ten-year background Criminal History Records Check for those individuals employed under this contract.
G. Access to Movement Areas
1. Movement areas shall mean all of the runways and taxiways of the Airport which are utilized for taxiing, takeoff, and landing of aircraft.
a. Any vehicle which requires access to the movement area shall be equipped with operational radio equipment capable of positive two-way contact with Tower/Ground Control.
b. Operators of vehicles in movement areas must possess knowledge and familiarity with restricted and airfield movement areas, operational rules, regulations, and procedures, or be under direct escort by individuals meeting all of the above requirements.
2. Vehicle Operations on Movement Areas
a. No vehicle shall proceed across any runway unless specifically cleared by Tower/Ground Control.
b. The operator of a vehicle in the movement area shall not leave his vehicle unless continuous radio contact is maintained with the Tower/ Ground Control while he is away from his vehicle.
c. Any vehicle proceeding onto the movement area between the hours of sunset and sunrise shall be equipped with an overhead flashing light which is visible for one (1) mile, unless such vehicle
STATE PROJECT NO. CM1530-33 SP-9 R03/13/24
is being escorted by another vehicle so equipped.
d. All vehicles operated on the movement area between sunrise and sunset except those being escorted, shall operate an overhead amber or red flashing beacon visible for at least one (1) mile; or display a flag at least three (3) feet square with orange and white checkered squares of not less than one (1) foot on each side.
H. Runway and Taxiway Closure
1. Requests for runway or taxiway closures, or for any work which affect operational conditions at the airport must be made in writing through the Airport Engineering Branch.
2. Temporarily closed runways require placement of yellow "X" markings (constructed of material such as fabric or plywood or other acceptable material) on top of the runway identification numerals at both ends of the closed runway.
3. Taxiway closures require placement of barricades with alternate orange and white markings at each end of the closed taxiway segment.
Barricades must be supplemented with flashing red lights. The intensity of the lights and spacing for barricades, and lights must adequately define and delineate the hazardous area.
I. Gate Guards Furnished by Contractors
1. If a contractor is permitted by the airport to maintain operational control of an AOA Access Gate, entry through such gate shall be controlled by the posting of a gate guard.
a. Written instruction will be provided, outlining the guard's duties to enforce those requirements and provisions prescribed by the airport's security program to include all personnel and vehicle entry and access requirements.
b. Procedures will be established to identify the actions which will be undertaken by the guard in calling for assistance.
c. An approved emergency communications procedure will be established.
J. Compliance
1. The contractor shall comply with all regulations and rules governing the Air Operations Areas during construction, as specified in the following or later versions:
a. Hawaii Revised Statutes, Title 19, Administrative Rules for Public Airports.
b. Federal Aviation Administration Advisory Circular AC 150/5340 1J
c. Marking of Paved Areas on Airport; AC 150/5370-2E, Operational Safety on Airports During Constructions.
STATE PROJECT NO. CM1530-33 SP-10 R03/13/24
K. Enforcement Authorization
Act 21, Section 1, Section 261-17(a), HRS; Federal Aviation Administration Regulations, Part 139, Part 107.
L. Right of Rejection or Revocation
The State of Hawaii, Airports , reserves the right to withhold, deny or revoke any airport security clearance, licenses or permits to any individual or organization who fails to meet the prescribed or required access area clearance criteria to include background investigation information, or fails to observe or comply with established rules, regulations, and directives.
It should be clearly understood that such denial or revocation is based solely on airport security or safety considerations and does not in any way constitute a determination by the State with regard to private employment by any individual or organization."
- END OF SECTION -
PART I - GENERAL PROVISIONS FOR CONSTRUCTION PROJECT
(NOT PHYSICALLY INCLUDED)
The General Provisions are available at http://hidot.hawaii.gov/administration/con/
PART II - TECHNICAL PROVISIONS
KAHULUI AIRPORT Description of Work
STATE PROJECT NO. CM1530-33 01010-1
DIVISION 1 - GENERAL REQUIREMENTS
SECTION 01010 - DESCRIPTION OF WORK
PART I - GENERAL
1.01 RELATED DOCUMENTS
The General Provisions for Construction Projects (2016), Special Provisions and General Requirements of the Specifications, apply to the work specified this Section.
1.02 SUMMARY
A. Section Includes:
1. Location of the work
2. Hours of work
3. Safety
4. Operation of airport facilities during construction
5. Construction stakes, lines and grades
6. Special project requirements
1.03 VEHICLE PARKING
Parking passes may be purchased at a monthly rate of $175.00 plus a one-time fee of $25.00 for parking access card. These passes are subject to approval by the Airport Manager and availability of parking spaces. All costs associated with obtaining parking passes shall be the responsibility of the Contractor.
1.04 PROVISIONS FOR FIELD OFFICE/STORAGE SPACE
Pending the availability of space on airport property, the State will issue Revocable Permit(s) to the Contractor for the use of the space, assessed at a monthly fee of $25 for each Revocable Permit issued. The space(s) may be used for a field office, staging of materials and equipment, vehicle parking or other uses subject to the approval of the State. All spaces shall be subject to the requirements of Section 01561 - CONSTRUCTION SITE POLLUTION
CONTROL.
Since space on airport property is extremely limited, the State does not guarantee that space(s) provided to the Contractor will be in close proximity to the project site. The State will make every effort to provide the Contractor with space on airport property, however, should the State determine that no space is available for such use(s), the responsibility shall then be on the Contractor to find space outside of airport property.
STATE PROJECT NO. CM1530-33 01010-2
1.05 LOCATION OF THE WORK
A. The work to be performed under this contract is located at Kahului Airport, Kahului, Maui, Hawaii.
B. Conditions:
1. The Main Terminal and airport roadways shall remain operational at all times. Any damages to existing areas caused by the Contractor shall be repaired by the Contractor at no cost to the State.
2. Upon execution of the contract, the Contractor, at their cost, shall obtain all permits required for this project.
1.06 HOURS OF WORK
A. Work can be performed at the construction site at any time over a 24-hour period without considerable disruption to airport operations or other adjacent tenants. The Contractor shall coordinate their schedule with the Engineer if rescheduling of work or intermittent work is required, such work shall be performed at no extra cost to the State. If the Contractor elects to work overtime, compensation for State employees and for construction management consultant as authorized by the State shall be the Contractor's obligation to pay in accordance with Section 7.6 – “Overtime and Night Payment for State Inspection Services” of the General Provisions of Construction Projects (2016).
B. Contractor shall clean work areas at the end of each working shift.
Rubbish, loose materials, etc. shall be disposed of daily. Tools and equipment shall not be left unattended during work hours. This includes tools left in unlocked vehicles, in the bed of pickup trucks, or in unlocked job sites. TSA citations may result in fines in excess of $13,000 per violation and the confiscation of AOA badges. Materials shall be safely secured and stored in an area designated by the Airport Manager.
1.07 SAFETY
A. The Contractor shall take the necessary precautions to protect his workers and other personnel from injuries. The rules and regulations promulgated by the Occupational Safety and Health Acts are applicable and made a part of these specifications.
B. Barricades and warning signs shall be erected by the Contractor in the work area to properly protect all personnel in the area.
C. During the progress of the work debris, empty crates, waste, material drippings, etc., shall be removed by the Contractor at the end of each workday, and the work area shall be left clean and orderly.
STATE PROJECT NO. CM1530-33 01010-3
D. Based on the impacts of the project to airport operations, participation and attendance at meetings with various airport stakeholders may be required to fulfill the project’s adherence to Safety Management System (SMS) requirements.
E. As applicable, the contractor will be required to file a Safety Plan
Compliance Document (SPCD) with the Federal Aviation Administration’s (FAA) OE/AAA website (https://oeaaa.faa.gov/oeaaa/external/portal.jsp).
1.08 OPERATION OF AIRPORT FACILITIES DURING CONSTRUCTION
A. The Contractor shall coordinate the phases of work under this contract with the Engineer to permit the continuing operation of existing Airport facilities and to minimize disruption to pedestrian and vehicular traffic.
B. Utility Maintenance: During the construction of this contract, existing utility services serving occupied or used facilities shall not be disrupted except where authorized in writing by authorities having jurisdiction. Contractor shall provide temporary services during interruptions to existing utilities, as acceptable to the Engineer. Damages to the existing utility facilities by the Contractor will be repaired at the Contractors expense.
C. Outages for water, power, communications, air conditioning or any other utility, if necessary, shall be kept to a minimum and scheduled for off-peak hours, generally from 12:00 a.m. to 6:00 a.m. The Contractor shall submit written requests to the Engineer for such outages no later than fourteen (14) calendar days in advance. The request shall include a description of work and the duration of the outage. The Contractor shall not proceed with such outages until written approval is received from the State.
1.09 CONSTRUCTION STAKES, LINES AND GRADES
A. The Contractor shall perform all construction layout and reference staking necessary for the proper control and satisfactory completion of all structures, grading, paving, drainage, sewer, water, and all other appurtenances required for the completion of the work.
B. Existing horizontal and vertical survey control points for the project are shown on the plans. The Contractor shall verify the location of all control points prior to the start of construction.
C. The Department will not be responsible for delays in setting stakes and marks.
D. All control points and stakes or marks which the Engineer may set shall be preserved by the Contractor. If such control points, stakes or marks are destroyed or disturbed by the Contractor, the cost of replacing such stakes or marks will be charged against the Contractor and deducted from payments due the Contractor.
STATE PROJECT NO. CM1530-33 01010-4
E. The Contractor shall be responsible for the placement and preservation of adequate ties to all control points whether established by the Contractor or by the Engineer.
F. All original, additional or replacement stakes, marks, references and batter-boards which may be required for the construction operations, shall be furnished, set and properly referenced by the Contractor. The Contractor shall be solely and completely responsible for the accuracy of the line and grade of all features of the work. Any errors or apparent discrepancies found in previous surveys, the plans and specifications shall be called to the Engineer's attention by the Contractor for correction or interpretation prior to proceeding with the work.
G. Before construction is started on any structure which is referenced to an existing structure or topographical feature, the Contractor shall check the pertinent locations and grades of the existing structures or topographical features to determine whether the locations and grades shown on the plans are correct.
H. All construction staking shall be performed by qualified personnel under the direct supervision of a person with an engineering background who is experienced in the direction of such work and is acceptable to the Engineer.
I. All stakes and markers used for control staking shall be of the same quality as used by the Department for this purpose. For slope limits, pavement edges, gutter lines, et cetera, where so called "working" stakes are commonly used, stakes of different quality may be acceptable.
J. The Department may check the Contractor's control of the work at any times as the work progresses. The Contractor will be informed of the results of these checks, but the Department by doing so will in no way relieve the Contractor of his responsibility for the accuracy of the layout work. The Contractor shall at his expense correct or replace any deficient or inaccurate layout and construction work. If, as a result of these deficiencies or inaccuracies, the Department is required to make further studies, redesign, or both, all expenses incurred by the Department due to such deficiencies or inaccuracies, will be deducted from any payments due the Contractor.
K. The Contractor shall furnish all necessary personnel, engineering equipment and supplies, materials, and transportation incidental to the accurate and satisfactory completion of this work.
Unless otherwise provided, all requirements imposed by this section and performed by the Contractor shall be considered incidental to the various contract items and not separate or additional payment will be made thereof.
STATE PROJECT NO. CM1530-33 01010-5
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
PART 4 - MEASUREMENT AND PAYMENT
4.01 BASIS OF MEASUREMENT AND PAYMENT
A. Work under this Section will no be measured for payment but will be paid for at the contract Lump Sum Price.
Item No. Description Unit Price
01010.1 Construction Work Lump Sum
END OF SECTION
KAHULUI AIRPORT Work Sequence
STATE PROJECT NO. CM1530-33 01014-1
SECTION 01014 – WORK SEQUENCE
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
The General Provisions, Special Provisions, and General Requirements of the
Specifications, apply to the work specified in this Section.
1.02 TENANTS ADJACENT TO CONSTRUCTION AREA
A. The User Agencies and their operations will be adjacent to the construction area throughout the construction period. The Contractor shall minimize inconvenience to them and their clientele and shall continue to provide the following for these occupants:
1. Continuity of utility services.
2. Means of ingress and egress.
3. All measures to ensure their safety and health.
4. All measures to ensure the required security in the secure areas.
B. Official communications and coordination with the User Agencies and operations shall be made through the State Engineer.
1.03 SEQUENCE OF WORK
A. Work under the entire project shall be completed within specified calendar days from the date indicated in the Notice to Proceed from the State.
B. Work shall proceed in tasks of construction to facilitate and ensure the continued operations and functions of the existing terminal facilities. Work to be accomplished within each task of construction is described and the areas affected are shown on drawings.
Each task of the work shall be completed within the specified number of calendar days. Specific language relating to the sequence of work is defined below.
1. Scheduled Start Day: The day designated as the beginning of a particular task; the number listed is the number of calendar days from which work for that particular task is to be completed.
2. Completion Day: The day designated as the end of a given task with completion and acceptance of work as assigned and shown in the drawings.
3. The total number of calendar days for all stages of work shall equal the number of calendar days established for the entire project.
1.04 OPERATION OF AIRPORT FACILITIES DURING CONSTRUCTION
A. The Contractor shall coordinate all tasks of work under this contract with the Engineer to permit the continuing operation of existing airport facilities.
KAHULUI AIRPORT Work Sequence
STATE PROJECT NO. CM1530-33 01014-2
B. The Contractor shall take precaution to protect people and property from injury and damage. Construction, including barricades as specified in Section 01533 - BARRICADES shall be sequenced to minimize the duration of disruption and appropriate signing be provided to aid the public and airport pedestrian and vehicular traffic around his work areas.
C. The Contractor shall limit the delivery of materials and equipment and hauling of debris material during non-peak Airport operational hours. Contractor shall obtain prior approval of planned schedule of delivery of material and hauling of debris from the State Engineer.
Work under this Section will not be measured for payment but will be paid for at the contract Lump Sum Price.
KAHULUI AIRPORT Allowance
STATE PROJECT NO. CM1530-33 01210-1
SECTION 01210 - ALLOWANCES
PART 1 - GENERAL
The General Provisions, Special Provisions, and General Requirements of the Specifications, apply to the work specified in this section.
1.02 GENERAL REQUIREMENTS
A. This Section includes administrative and procedural requirements governing allowances. Certain materials, equipment, and services are specified in the Contract Documents by allowances.