FINAL PLANS CM1530 33.pdf
PDF 13 MB Posted
- Solicitation number
- B27000492
- Issued by
- Hawaii
About this file
This is a final construction document set prepared by SSFM International, Inc. for the State of Hawaii Department of Transportation—Airports Division for the Apron Reconstruction Phase 1 project at Kahului Airport on Maui. The project scope involves repairing deteriorated exterior concrete and concrete masonry unit (CMU) surfaces of Holdroom F and adjacent concrete apron areas. The work includes concrete rehabilitation of spalls, delaminations, and voids; concrete crack repair; CMU crack repair; and reinforcing steel replacement. Estimated quantities include 273 square feet of concrete rehabilitation in Holdroom F, 491 linear feet of concrete crack repair in Holdroom F, 12 linear feet of CMU crack repair in Holdroom F, 410 pounds of reinforcing steel, 15 square feet of concrete rehabilitation on the apron, and 117 linear feet of concrete crack repair on the apron. The project is divided into Phase 1A and Phase 1B, with each phase designated for 30 calendar days, totaling approximately 60 calendar days for combined phases. Construction work hours are restricted to 12:00 AM to 8:00 AM to minimize disruption to airport operations. The document set, dated August 2026 and issued for 100 percent construction documents, includes overall site plans, damage schedules, elevation drawings, repair details, reinforcing bar specifications, and construction safety and phasing plans for restricted haul routes and barricade placement.
Damage quantities were determined during investigation in April 2024 and have been increased by a factor of 1.25 for bidding and cost estimation purposes, with contractors to be paid for actual measured repair quantities upon verification. The contractor must verify all dimensions, quantities, and existing conditions prior to commencing work and immediately notify the State Engineer of any discrepancies. Coordination requirements include weekly construction meetings with airfield users, compliance with FAA Advisory Circular 150/5370-2G regarding operational safety during construction, TSA inspection coordination, and adherence to 2021 International Building Code standards. All work must maintain uninterrupted airport operations, with aircraft always having right-of-way and gates remaining accessible. The project requires special inspections in accordance with IBC 2021 Chapter 17, including reinforcement placement, post-installed anchors in concrete, and reinforcing bar welding. Contractors must provide complete coordination shop drawings, maintain clean haul routes with sweeper trucks on-site at all times, and remove all temporary erosion and sediment control measures within 30 days of final site stabilization.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FINAL SPECIFICATIONS CM1530 33.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AT
KAHULUI AIRPORT
KAHULUI, MAUI, HAWAII
KAHULUI AIRPORT
KAHULUI, MAUI, HAWAII
This work was prepared by me or under my supervision.
Licensed Expiration Date 04/30/2028
DATE
PROJECT TEAM
STRUCTURAL: SSFM
SSFM INTERNATIONAL, INC.
601 SUMNER ST., STE 620
808-531-1308
AIRPORT VICINITY MAP
DEPARTMENT OF TRANSPORTATION
STATE OF HAWAII
APPROVED:
DATEFOR DIRECTOR OF TRANSPORTATION
STATE OF HAWAII
DEPARTMENT OF TRANSPORTATION
AIRPORTS
DSGN. DRWN. CHKD. APPD.
DATE : DWG. NO.
SHEET :
REVISIONSNO. DATE REVISIONS
PROJECT TITLE :
PROJECT NO.:
SHEET TITLE:
HAWAII
MAUI
KAHOOLAWE
LANAI
MOLOKAI
OAHU
KAUAI
NIIHAU
Upolu Airport
Waimea-Kohala Airport
Hilo International Airport
Kalaupapa Airport Molokai Airport
Kahului Airport
Lanai Airport Hana Airport
Dillingham Airfield
Lihue Airport
Port Allen Airport
P a c i f i c O c e a n
Kapalua Airport
Kalaeloa Airport
Daniel K. Inouye International Airport
Ellison Onizuka Kona International Airport At Keahole
P a c i f i c O c e a n
North
South
EastWest
NENW
SESW
DEPARTMENT OF TRANSPORTATION
AIRPORTS
PLANS FOR
ATAT
STATE OF HAWAII
CIVIL: SSFM
SSFM INTERNATIONAL, INC.
601 SUMNER ST., STE 620
808-531-1308
APRON RECONSTRUCTION
PHASE 1
PROJECT NO. CM1530-33
JP AK KW KW
100% CONSTRUCTION
DOCUMENT
August , 2026
APRON RECONSTRUCTION
PHASE 1
CM1530-33
COVER SHEET,
VICINITY MAP,
PROJECT TEAM
08/19/2026
1 OF 23 SHEETS
G-001
W
St ru ct ur al P ro je ct s\
_1
.0
D O
TA
O
G G
A pr on R ep ai rs \C on tra ct D oc s\
W
O R
KI
N
G D
R
AW
IN
G
S
PROJECT AREA
PROJECT LOCATION
KA
T HLEE N Y . W ONG
HA W A II, U.S .A
LICENSED
PROFESSIONAL
ENGINEER
No. 10469-S
KA
T HLEE N Y . W ONG
HA W A II, U.S .A
LICENSED
PROFESSIONAL
ENGINEER
No. 10469-S
Adam Tolentino for 09/04/2026 https://stateofhawaii.na1.adobesign.com/verifier?tx=CBJCHBCAABAA01ctammYSuRTgyIv2JnlYXGm8ArgP_kP
G-002
INDEX TO DRAWINGS
AND QUANTITY
SUMMARY TABLE
SHT NO. DWG NO. SHEET TITLE
1 G-001 COVER SHEET, VICINITY MAP, AND PROJECT TEAM
2 G-002 INDEX TO DRAWINGS AND QUANTITY SUMMARY TABLE
3 G-003 GENERAL NOTES
CIVIL
4 C-001 EROSION CONTROL NOTES AND DETAILS
5 C-101 EROSION CONTROL PLAN - PHASE 1B
6 C-102 EROSION CONTROL PLAN - PHASE 1A
STRUCTURAL
7 S-001 STRUCTURAL GENERAL NOTES AND ABBREVIATIONS
8 S-002 DAMAGE SCHEDULE
9 S-003 DAMAGE SCHEDULE
10 S-101 OVERALL SITE PLAN
11 S-102 APRON DAMAGE PLAN
12 S-103 HOLDROOM F PLAN
13 S-201 EXTERIOR ELEVATIONS HOLDROOM F SERVICE YARD SIDE
14 S-202 EXTERIOR ELEVATIONS HOLDROOM F KAHULUI SIDE
15 S-203 EXTERIOR ELEVATIONS HOLDROOM F KAHULUI AND MAKAI SIDE
16 S-501 HOLDROOM REPAIR DETAILS
17 S-502 APRON REPAIR DETAILS
18 S-503 REINFORCING BAR REPAIR DETAILS
CONSTRUCTION SAFETY AND PHASING PLAN
19 SK-1.0 OVERALL SITE ACCESS AND HAUL ROUTE PLAN (PHASE I)
20 SK-1.1AW GATE 39 ACCESS AND HAUL ROUTE PLAN (PHASE IA) WORKING
AREA
21 SK-1.1AN GATE 39 ACCESS AND HAUL ROUTE PLAN (PHASE IA)
NON-WORKING AREA
22 SK-1.1BW GATE 35 ACCESS AND HAUL ROUTE PLAN (PHASE IB) WORKING
AREA
23 SK-1.1BN GATE 35 ACCESS AND HAUL ROUTE PLAN (PHASE IB)
NON-WORKING AREA
INDEX TO DRAWINGS
ESTIMATED QUANTITIES SUMMARY TABLE
ITEM QTY UNIT
CONCRETE REHABILITATION OF SPALL AND DELAMINATIONS:
HOLDROOM F 273 SQ. FT
CONCRETE CRACK REPAIR: HOLDROOM F 491 LIN. FT
CMU CRACK REPAIR: HOLDROOM F 12 LIN. FT
REINFORCING STEEL FOR CONCRETE REPAIRS 410 LBS
CONCRETE REHABILITATION OF SPALL AND VOID: APRON 15 SQ. FT
CONCRETE CRACK REPAIR: APRON 117 LIN. FT.
NOTES:
1. QUANTITIES LISTED IN DAMAGE SCHEDULE ON S-002 AND S-003 WERE DETERMINED AT
THE TIME OF INVESTIGATION, APRIL 2024. CONTRACTOR MUST VERIFY ALL QUANTITIES
AND LOCATIONS. NOTIFY THE STATE ENGINEER OF ANY DISCREPANCIES.
2. DAMAGE QUANTITIES HAVE BEEN INCREASED BY A FACTOR OF 1.25 FOR BIDDING AND
COST ESTIMATION PURPOSES.
3. FOR BIDDING PURPOSES, IT IS ASSUMED TO REPLACE 1.5 POUNDS OF STEEL
REINFORCEMENT PER SQUARE FOOT OF CONCRETE SPALL IN ALL HOLDROOM AREAS.
IMMEDIATELY NOTIFY THE STATE ENGINEER ON VERIFIED QUANTITIES PRIOR TO
COMMENCING WORK.
AT
KAHULUI AIRPORT
KAHULUI, MAUI, HAWAII
This work was prepared by me or under my supervision.
Licensed Expiration Date 04/30/2028
STATE OF HAWAII
DEPARTMENT OF TRANSPORTATION
AIRPORTS
DSGN. DRWN. CHKD. APPD.
DATE : DWG. NO.
SHEET :
REVISIONSNO. DATE REVISIONS
PROJECT TITLE :
PROJECT NO.:
SHEET TITLE:
DATE
JP AK KW KW
100% CONSTRUCTION
DOCUMENT
August, 2026
APRON RECONSTRUCTION
PHASE 1
CM1530-33
08/19/2026
OF 23 SHEETS
W
St ru ct ur al P ro je ct s\
_1
.0
D O
TA
O
G G
A pr on R ep ai rs \C on tra ct D oc s\
W
O R
KI
N
G D
R
AW
IN
G
S
KA
T HLEE N Y . W ONG
HA W A II, U.S .A
LICENSED
PROFESSIONAL
ENGINEER
No. 10469-S
GENERAL NOTES
A. THE CONTRACTOR SHALL PROVIDE COMPLETE PROJECT SYSTEMS
AND COMPONENTS AND COMPLY WITH ALL REQUIREMENTS
INDICATED ON THE PROJECT DOCUMENTS.
B. WORK WITHIN THE AREA BOUNDARIES INDICATED IN THE PROJECT
DOCUMENTS, AND COMPLY WITH ALL APPLICABLE BUILDING CODE,
REGULATION, & ORDINANCE REQUIREMENTS. OCCUPANTS
ADJACENT TO THE PROJECT AREA BOUNDARIES SHALL CONTINUE
UNINTERRUPTED OCCUPANCY DURING CONSTRUCTION OF THE
PROJECT.
C. VERIFY FIELD CONDITIONS AND COORDINATION WITH THE PROJECT
DOCUMENTS PRIOR TO PROCEEDING WITH THE WORK.
D. COORDINATE THE WORK WITH ALL REQUIREMENTS INDICATED IN
THE PROJECT DOCUMENTS.
E. WORK HOURS SHALL BE PERFORMED AT THE PROJECT SITE
BETWEEN 12AM-6AM, UNLESS OTHERWISE APPROVED BY STATE
PROJECT MANAGER.
F. COORDINATE THE WORK WITH EQUIPMENT, FURNISHINGS, AND
SYSTEMS PROVIDED BY THE OWNER.
G. GENERAL CONTRACTOR SHALL BE SOLELY RESPONSIBLE FOR THE
COORDINATION OF THE VARIOUS TRADES PERFORMING THE WORK.
CONTRACTOR SHALL SUBMIT FOR REVIEW COMPLETE, COMPOSITE
COORDINATION SHOP DRAWINGS ILLUSTRATING THE EXTEND AND
POSITION OF EACH COMPONENT OF THE WORK SO AS TO AVOID
CONFLICT AND TO MAINTAIN REQUIRED SERVICE ACCESS AND
CODE REQUIRED CLEARANCES. NO WORK SHALL BE PERFORMED
UNTIL REFERENCED COORDINATION SHOP DRAWINGS HAVE BEEN
REVIEWED WITH NO EXCEPTION TAKEN.
H. CUTTING, BORING, SAWCUTTING OR DRILLING THROUGH THE NEW
OR EXISTING STRUCTURAL ELEMENTS TO BE DONE ONLY WHEN SO
DETAILED IN THE DRAWINGS OR REVIEWED AND ACCEPTED BY
STATE ENGINEER.
I. THE CONTRACTOR IS TO NOTIFY THE STATE ENGINEER
IMMEDIATELY REGARDING ANY CONFLICTS IN THE DRAWINGS OR
SPECIFICATIONS. FOR BIDDING PURPOSES, THE CONTRACTOR IS TO
NOTE THE FOLLOWING: WHEN INFORMATION IS IN CONFLICT WITHIN
OR BETWEEN THE DRAWING AND SPECIFICATIONS, THE
CONTRACTOR IS TO ASSUME THE MOST STRINGENT CASE.
J. PRIOR TO START OF WORK, THE CONTRACTOR SHALL CAREFULLY
INSPECT AND VERIFY ALL CONDITIONS SHOWN ON THE CONTRACT
DRAWINGS. IF WORK CAN NOT BE PERFORMED AS SHOWN, THE
CONTRACTOR SHALL NOTIFY THE STATE ENGINEER IMMEDIATELY.
WORK PERFORMED AFTER SUCH DISCOVERY UNLESS AUTHORIZED
BY THE STATE ENGINEER, SHALL BE DONE AT THE CONTRACTOR'S
RISK.
K. THE CONTRACTOR SHALL NOT INTERRUPT EXISTING UTILITIES
SERVING EXISTING FACILITIES, EXCEPT WHEN AUTHORIZED IN
WRITING BY THE STATE ENGINEER AND ALL AUTHORITIES HAVING
JURISDICTION. PROVIDE TEMPORARY SERVICES DURING
CONSTRUCTION ACTIVITIES ACCEPTABLE TO OWNER AND
GOVERNING AUTHORITIES.
L. THE CONTRACTOR SHALL KEEP ALL EXITS READILY ACCESSIBLE
AND UNOBSTRUCTED AT ALL TIMES.
M. ALL DETAILS SHOWN ON DRAWINGS ARE TO BE APPLIED, WHETHER
CALLED OUT OR NOT. IN CASE OFF A CONFLICT, THE 'G' SERIES IS
TO GOVERN. NOTIFY THE STATE ENGINEER BEFORE PROCEEDING
WITH THE WORK IN CASE OF A CONFLICT.
N. THE CONTRACTOR SHALL MAINTAIN PROPER ACCESS FOR FIRE
DEPARTMENT VEHICLES AND EQUIPMENT AT ALL TIMES. ANY
CHANGES MADE TO FIRE DEPARTMENT ACCESS ROUTES SHALL BE
REVIEWED AND APPROVED BY FIRE DEPARTMENT AUTHORITIES
HAVING JURISDICTION PRIOR TO CHANGING ACCESS ROUTING.
O. AIRPORT OPERATIONS SHALL BE CLOSED WITHIN THE CURRENT
PHASE LIMITS DURING CONSTRUCTION PERIOD. ALL OTHER
AIRPORT OPERATIONS SHALL BE KEPT IN FULL OPERATION
THROUGHOUT THE CONSTRUCTION PERIOD. ANY WORK THAT WILL
DISRUPT OPERATIONS SHALL BE COORDINATED WITH THE STATE
ENGINEER. NOISY WORK, ACTIVITIES CAUSING VIBRATION AND/OR
SIMILAR DISRUPTIVE ACTIONS SHALL BE SCHEDULED AT TIMES
ACCEPTABLE TO THE STATE ENGINEER.
P. THE CONTRACTOR SHALL PROVIDE SOUND, DUST AND SIGHT
BARRIERS AS REQUIRED AND DESCRIBED IN THE SPECIFICATIONS
TO PROTECT THE EXISTING TERMINAL DURING CONSTRUCTION. IT
IS THE CONTRACTOR'S RESPONSIBILITY TO DETERMINE THE
EXTENT AND LOCATION OF THESE BARRIERS TO LIMIT THE
PASSAGE OF DUST AND NOISE TO THE EXISTING TERMINAL.
Q. IN AREAS REQUIRING REMODELING, THE USE OF 'VISQUEEN' OR
SIMILAR TYPE OF MATERIAL AS TEMPORARY CONSTRUCTION
BARRIER IS NOT PERMITTED. TEMPORARY CONSTRUCTION
BARRIERS SHALL MEET THE SAME FIRE RATING AS THE PERMANENT
PARTITION.
R. CONTRACTOR IS RESPONSIBLE FOR VERIFICATION OF ALL
DIMENSIONS, DETAILS AND (EXISTING) CONDITIONS OF THE
PROJECT. ANY DISCREPANCIES SHALL BE REPORTED TO THE STATE
ENGINEER FOR THE RESOLUTION PRIOR TO FABRICATIONS
INSTALLATION OF AFFECTED BUILDING COMPONENTS.
S. WHERE LOCAL AND COUNTY CODES ARE MORE RESTRICTIVE THAN
2021 IBC REQUIREMENTS THE LOCAL CODES WILL BE ENFORCED BY
THE STATE ENGINEER.
T. ALL CHANGE ORDERS AND/OR ADDITIONS TO THE WORK MUST BE
APPROVED BY THE STATE ENGINEER PRIOR TO CONSTRUCTION.
U. CONTRACTOR IS RESPONSIBLE FOR COORDINATING WITH TSA
INSPECTIONS AS REQUIRED BY THE TRANSPORTATION SECURITY
ADMINISTRATION (TSA).
V. THIS PROJECT SHALL BE PHASED TO PROVIDE UNINTERRUPTED
OPERATION OF THE AIRPORT OPERATIONS. IN PARTICULAR, THE
AIRPORT MUST BE ABLE TO SCREEN PASSENGERS EACH DAY, AND
MAINTAIN EXISTING PASSENGER SERVICE LEVELS.
DEFINITIONS
A. WHEN A DETAIL IS IDENTIFIED AS TYPICAL, THE CONTRACTOR
SHALL APPLY THIS DETAIL TO EVERY LIKE CONDITION WHETHER OR
NOT THE REFERENCE IS REPEATED IN EVERY INSTANCE. WHEN A
NOTE IS A IDENTIFIED AS TYPICAL (TYP), THE CONTRACTOR SHALL
APPLY THIS NOTE TO EVERY LIKE CONDITION (REPRESENTED
GRAPHICALLY OR NOT) WHETHER OR NOT THE REFERENCE IS
REPEATED IN EVERY INSTANCE.
B. "SIMILAR" INDICATES COMPLETE SYSTEM AND COMPONENTS SHALL
BE PROVIDED COMPARABLE TO THE CHARACTERISTICS FOR THE
CONDITION NOTED.
C. "AS REQUIRED" INDICATES COMPONENTS REQUIRED TO COMPLETE
THE NOTED, SYSTEM AS INDICATED IN THE PROJECT DOCUMENTS,
SHALL BE PROVIDED.
D. "ALIGN" INDICATES ACCURATELY PROVIDE FINISH FACES OF
MATERIALS IN STRAIGHT, TRUE, AND PLUMB RELATION TO
ADJACENT MATERIALS.
DIMENSIONS
A. DIMENSIONS ARE INDICATED TO THE CENTERLINE OF THE
STRUCTURAL GRID, FACE OF CONCRETE WALL, NOMINAL FACE OF
CMU WALL, FACE OF PARTITION FINISH, UON.
B. VERTICAL DIMENSIONS ARE INDICATED FROM THE FLOOR
ELEVATION TO FACE OF FINISHED MATERIAL AT THE DIMENSION
POINT, UNLESS NOTED ABOVE FINISH FLOOR - "AFF".
C. DIMENSIONS SHOWN ON THE DRAWINGS SHALL INDICATE THE
REQUIRED SIZE, CLEARANCE, AND DIMENSIONAL RELATIONSHIP
BETWEEN PROJECT SYSTEMS AND COMPONENTS. DIMENSIONS
SHALL NOT BE DETERMINED BY SCALING THE DRAWINGS.
DRAWING SET ORGANIZATION
A. EACH DRAWING SET SHEET IS IDENTIFIED BY THE SHEET NUMBER IN
THE LOWER RIGHT HAND CORNER OF THE DRAWING TITLE BLOCK.
THE SHEET TITLE PROVIDES A GENERAL DESCRIPTION OF THE
CONTENTS OF THE SHEET.
SHEET NUMBER EXAMPLE: A-201
"A" INDICATES THE DISCIPLINE THAT CREATED THE DRAWING
"2" INDICATES THE DRAWING CATEGORY CONTAINED ON THE SHEET
"01" INDICATES THE SHEET NUMBER
B. DRAWING SET INDEX INDICATES THE COMPLETE LIST OF SHEETS
CONTAINED IN THE DRAWING SET, INDEXED BY DISCIPLINE, SHEET
NUMBER AND SHEET TITLE, IN SEQUENTIAL ORDER. NOTE THAT ALL
SEQUENTIAL SHEET NUMBERS MAY BE NOT USED IN THE DRAWING
SET.
C. DISCIPLINE IDENTIFICATION, IN ORDER BOUND IN THE DRAWING
SET. REFER TO THE DRAWING SET INDEX FOR DISCIPLINE
CONTAINED IN THIS DRAWING SET:
T TITLE
G GENERAL INFORMATION
S STRUCTURAL
C CIVIL
SK CONSTRUCTION SAFETY AND PHASING PLAN
D. DRAWING CATEGORY IDENTIFICATION. REFER TO THE DRAWING
SET INDEX FOR DISCIPLINES, CATEGORIES, AND SHEET NUMBERS
CONTAINED IN THIS DRAWING SET.
G-003
GENERAL NOTES
AT
KAHULUI AIRPORT
KAHULUI, MAUI, HAWAII
This work was prepared by me or under my supervision.
Licensed Expiration Date 04/30/2028
STATE OF HAWAII
DEPARTMENT OF TRANSPORTATION
AIRPORTS
DSGN. DRWN. CHKD. APPD.
DATE : DWG. NO.
SHEET :
REVISIONSNO. DATE REVISIONS
PROJECT TITLE :
PROJECT NO.:
SHEET TITLE:
DATE
JP AK KW KW
100% CONSTRUCTION
DOCUMENT
August, 2026
APRON RECONSTRUCTION
PHASE 1
CM1530-33
08/19/2026
OF 23 SHEETS
W
St ru ct ur al P ro je ct s\
_1
.0
D O
TA
O
G G
A pr on R ep ai rs \C on tra ct D oc s\
W
O R
KI
N
G D
R
AW
IN
G
S
KA
T HLEE N Y . W ONG
HA W A II, U.S .A
LICENSED
PROFESSIONAL
ENGINEER
2' -0
PLACE GEOTEXTILE
FABRIC UNDER
ADAPTER SKIRT
RETRIEVAL STRAP
OVERFLOW (TO BYPASS
PEAK STORM VOLUMES)
ADAPTER SKIRT
INLET GRATE
GEOTEXTILE
FABRIC
SEDIMENT
ACCUMULATION NOTE:
3'-0"4'-0"
PROTECTED AREA
WORK AREA
WORK AREA
RUNOFF FLOW
RUNOFF FLOW6" MIN. OVERLAP
OR PER SPEC.
PROTECTED AREA
LIMITS OF GRADING
AND/OR GRUBBING
SANDBAG
MIN. LENGTH=18"
MIN. WIDTH=12"
MIN. THICKNESS=3"
PLACE EVERY 6' TYP.
SANDBAG TO
SECURE EACH END
PROTECTED AREA
10" SOCK BARRIER
(MULTI-FILAMENT
POLYPROPYLENE)
WORK AREA
RUNOFF FLOW
FILTER SOCK
FILTER SOCK
SANDBAG
MIN. LENGTH=18"
MIN. WIDTH=12"
MIN. THICKNESS=3"
PLACE EVERY 6' TYP.
1. CONTRACTOR SHALL REFER TO THE "CONSTRUCTION ACTIVITIES
BEST MANAGEMENT PRACTICE MANUAL" DATED JUNE 2024, FOR BEST
MANAGEMENT PRACTICES DETAILS AND SPECIFICATIONS.
2. CONSTRUCTION SHALL BE SEQUENCED TO MINIMIZE THE EXPOSURE
TIME OF CLEARED SURFACE AREA.
3. ALL CONTROL MEASURES SHALL BE CHECKED REGULARLY AND
REPAIRED AS NECESSARY.
4. PROVIDE CONSTRUCTION ENTRANCE FOR EACH INGRESS AND
EGRESS.
5. TIMING OF CONTROL MEASURE IMPLEMENTATION SHALL BE IN
ACCORDANCE WITH THE APPROVED EROSION CONTROL PLAN IF
SUCH PLAN IS REQUIRED. AT A MINIMUM, DISTURBED AREAS OF
CONSTRUCTION SITES THAT WILL NOT BE RE-DISTURBED FOR
TWENTY-ONE DAYS OR MORE WILL BE STABILIZED (GRASSES OR
GRAVELED) BY NO LATER THAN THE FOURTEENTH DAY AFTER LAST
DISTURBANCE.
6. STORM WATER FLOWING TOWARD THE CONSTRUCTION AREA SHALL
BE DIVERTED BY USING APPROPRIATE CONTROL MEASURES AS
PRACTICAL.
7. ALL BMPS TO BE COORDINATED WITH CONSTRUCTION SEQUENCING.
8. ADDITIONAL DUST FENCE MAY BE REQUIRED AND SPECIFIC
LOCATIONS SHALL BE DETERMINED AT THE TIME THE
PRE-CONSTRUCTION MEETING IS HELD.
9. CONTRACTOR SHALL PROVIDE TEMPORARY PROTECTION FOR
EXISTING CATCH BASINS, DURING CONSTRUCTION AND UNTIL
CONSTRUCTION AREA IS STABILIZED AND FINAL GRADES ARE
ACHIEVED.
10. DUST CONTROL SHOULD BE APPLIED TO REDUCE DUST EMISSIONS.
CONTRACTOR TO SPRAY WATER AS NECESSARY.
11. ALL STORM DRAIN INLETS ON SITE, AND THOSE OFFSITE WHICH MAY
RECEIVE RUNOFF FROM THE SITE, SHALL USE AN INLET PROTECTION
DEVICE.
12. ALL DISTURBED AREAS SHALL BE PERMANENTLY STABILIZED PRIOR
TO REMOVING EROSION AND SEDIMENT MEASURES. ALL TEMPORARY
EROSION AND SEDIMENT MEASURES SHALL BE REMOVED WITHIN 30
DAYS AFTER FINAL SITE STABILIZATION OR AFTER THE TEMPORARY
MEASURES ARE NO LONGER NEEDED. TRAPPED SEDIMENT AND
AREAS OF DISTURBED SOIL WHICH RESULT FROM THE REMOVAL OF
THE TEMPORARY MEASURES SHALL BE IMMEDIATELY PERMANENTLY
STABILIZED.
13. SAWCUT AND BORING SLURRY GENERATED BY CRACK, VOID/SPALL,
AND MAP CRACKING REPAIR OPERATIONS SHALL BE COLLECTED OR
VACUUMED AND REMOVED FROM THE SITE. STORM DRAINS SHALL BE
COVERED OR BARRICADED DURING SAWCUTTING TO CONTAIN
SLURRY, AND SAWCUTTING SHALL BE AVOIDED DURING WET
WEATHER. SLURRY MAY BE PLACED IN A TEMPORARY PIT OR
CONTAINER TO PROMOTE EVAPORATION AND SHALL BE DISPOSED OF
IN ACCORDANCE WITH SO-3 (MILLING AND PAVING OPERATIONS) AND
WM-8 (CONCRETE WASTE MANAGEMENT) OF THE REFERENCED BMP
MANUAL.
BMPS SEQUENCE OF WORK NOTES:
1. INSTALL DUST BARRIERS, SILT SCREENS, DRAIN INLET PROTECTION,
AND CONSTRUCTION ENTRANCES/EXITS, AND ANY OTHER
PRELIMINARY STRUCTURAL BMPS AS PLANNED OR NEEDED.
2. COMPLETE CONSTRUCTION OF THE FIRST PHASE OR INCREMENT AS
PLANNED. MODIFY BMPS AS NEEDED.
3. REMOVE TEMPORARY STRUCTURAL BMPS ONLY UPON
ESTABLISHMENT OF PERMANENT STABILIZATION MEASURES.
BMPS MAINTENANCE NOTES:
1. DUST CONTROL MEASURES REQUIRED FREQUENT, OFTEN DAILY,
ATTENTION.
2. INSPECT CONSTRUCTION ROADS AND PARKING AREAS PERIODICALLY
FOR CONDITION OF SURFACE. ADD NEW GRAVEL AS NEEDED. CHECK
ROAD DITCHES AND OTHER SEEDED AREAS FOR EROSION AND
SEDIMENTATION WEEKLY AND AFTER EACH RAINFALL EVENT.
MAINTAIN ALL VEGETATION IN A HEALTHY, VIGOROUS CONDITION.
SEDIMENT-PRODUCING AREAS SHOULD BE TREATED IMMEDIATELY.
3. INSPECT SEDIMENT FENCES AT LEAST ONCE A WEEK AND AFTER
EACH RAINFALL EVENT. MAKE ANY REQUIRED REPAIRS IMMEDIATELY.
4. SHOULD THE FABRIC OF A SEDIMENT FENCE COLLAPSE, TEAR,
DECOMPOSE, OR BECOME INEFFECTIVE, REPLACE IT PROMPTLY.
REPLACE BURLAP EVERY 60 DAYS.
5. REMOVE SEDIMENT DEPOSITS AS NECESSARY TO PROVIDE
ADEQUATE STORAGE VOLUME FOR THE NEXT RAIN AND TO REDUCE
PRESSURE ON THE FENCE. AVOID UNDERMINING THE FENCE DURING
CLEANING.
6. REMOVE ALL FENCING MATERIALS AND UNSTABLE SEDIMENT
DEPOSITS AND BRING THE AREA TO GRADE AND STABILIZE IT AFTER
THE CONTRIBUTING DRAINAGE AREA HAS BEEN PROPERLY
STABILIZED.
C-001
EROSION CONTROL
NOTES AND DETAILS
EROSION CONTROL NOTES AND BEST
MANAGEMENT PRACTICES (BMPS):
NOT TO SCALE
FILTER SOCK DETAIL1
C001
NOT TO SCALE
DRAIN INLET PROTECTION DETAIL2
C001
AT
KAHULUI AIRPORT
KAHULUI, MAUI, HAWAII
This work was prepared by me or under my supervision.
Licensed Expiration Date 04/30/2028
STATE OF HAWAII
DEPARTMENT OF TRANSPORTATION
AIRPORTS
DSGN. DRWN. CHKD. APPD.
DATE : DWG. NO.
SHEET :
REVISIONSNO. DATE REVISIONS
PROJECT TITLE :
PROJECT NO.:
SHEET TITLE:
DATE
JP AK KW KW
100% CONSTRUCTION
DOCUMENT
August, 2026
APRON RECONSTRUCTION
PHASE 1
CM1530-33
08/19/2026
OF 23 SHEETS
W
St ru ct ur al P ro je ct s\
_1
.0
D O
TA
O
G G
A pr on R ep ai rs \C on tra ct D oc s\
W
O R
KI
N
G D
R
AW
IN
G
S
FILTER SOCK
SEE DET.
AREA OF WORK TYP.
CRACK REPAIR,
SEE STRUCTURAL DWGS
PHASE WORK
AREA LIMITS
MAP CRACKING,
SEE STRUCTURAL DWGS
VOID/SPALL,
SEE STRUCTURAL DWGS
INLET PROTECTION
SEE DET.
C-101
EROSION CONTROL
PLAN - PHASE 1B
INLET PROTECTION
FILTER SOCK
PLAN
NORTH
FLOW ARROW
PHASE WORK AREA LIMITS
AT
KAHULUI AIRPORT
KAHULUI, MAUI, HAWAII
This work was prepared by me or under my supervision.
Licensed Expiration Date 04/30/2028
STATE OF HAWAII
DEPARTMENT OF TRANSPORTATION
AIRPORTS
DSGN. DRWN. CHKD. APPD.
DATE : DWG. NO.
SHEET :
REVISIONSNO. DATE REVISIONS
PROJECT TITLE :
PROJECT NO.:
SHEET TITLE:
DATE
JP AK KW KW
100% CONSTRUCTION
DOCUMENT
August, 2026
APRON RECONSTRUCTION
PHASE 1
CM1530-33
08/19/2026
OF 23 SHEETS
W
St ru ct ur al P ro je ct s\
_1
.0
D O
TA
O
G G
A pr on R ep ai rs \C on tra ct D oc s\
W
O R
KI
N
G D
R
AW
IN
G
S
PLAN
NORTH
PARK
PARK
PARK
PARK
PARK
PARK PARK
PARK PARKPARK
PARK
PARK
PARKPARK
PARK
PARK
KEY PLAN
C-101
PHASE 1B WORK AREA LIMITS PHASE 1A WORK AREA LIMITS
FILTER SOCK
SEE DET.
AREA OF WORK TYP.
CRACK REPAIR,
SEE STRUCTURAL DWGS
PHASE WORK
AREA LIMITS
INLET PROTECTION
SEE DET.
VOID/SPALL, SEE
STRUCTURAL DWGS
C-102
EROSION CONTROL
PLAN - PHASE 1A
INLET PROTECTION
FILTER SOCK
PLAN
NORTH
FLOW ARROW
PHASE WORK AREA LIMITS
AT
KAHULUI AIRPORT
KAHULUI, MAUI, HAWAII
This work was prepared by me or under my supervision.
Licensed Expiration Date 04/30/2028
STATE OF HAWAII
DEPARTMENT OF TRANSPORTATION
AIRPORTS
DSGN. DRWN. CHKD. APPD.
DATE : DWG. NO.
SHEET :
REVISIONSNO. DATE REVISIONS
PROJECT TITLE :
PROJECT NO.:
SHEET TITLE:
DATE
JP AK KW KW
100% CONSTRUCTION
DOCUMENT
August, 2026
APRON RECONSTRUCTION
PHASE 1
CM1530-33
08/19/2026
OF 23 SHEETS
W
St ru ct ur al P ro je ct s\
_1
.0
D O
TA
O
G G
A pr on R ep ai rs \C on tra ct D oc s\
W
O R
KI
N
G D
R
AW
IN
G
S
PLAN
NORTH
PARK
PARK
PARK
PARK
PARK
PARK PARK
PARK PARKPARK
PARK
PARK
PARKPARK
PARK
PARK
KEY PLAN
C-102
PHASE 1B WORK AREA LIMITS PHASE 1A WORK AREA LIMITS
STRUCTURAL GENERAL NOTES
A. SEE SPECIFICATIONS, SPECIAL NOTES ON DRAWINGS, AND
OTHER CONTRACT DOCUMENTS.
B. DISCREPANCIES - CONTRACTOR SHALL VERIFY ALL DIMENSIONS
AND CONDITIONS AND SHALL REPORT ANY DISCREPANCIES IN
WRITING TO THE STATE ENGINEER BEFORE COMMENCING WORK
OR ORDERING MATERIALS.
C. MATERIALS AND WORKMANSHIP SHALL CONFORM TO THE 2021
INTERNATIONAL BUILDING CODE.
D. DETAILS SHOWN ON THE DRAWINGS SHALL BE TYPICAL FOR ALL
SIMILAR CONDITIONS. MODIFY DETAILS FOR SPECIAL
CONDITIONS AS DIRECTED BY THE STATE ENGINEER. IF
CONDITIONS ARE NOT AS SHOWN ON DRAWINGS, CONTRACTOR
SHALL NOTIFY STATE ENGINEER IMMEDIATELY.
E. SCOPE OF WORK: REPAIR DETERIORATED EXTERIOR CONCRETE
AND CONCRETE MASONRY UNIT SURFACES OF HOLDROOM F AS
WELL AS CONCRETE APRON REPAIR FOR THAT RESPECTIVE
ADJACENT AREA.
F. PROVIDE SPECIAL INSPECTIONS IN ACCORDANCE WITH IBC 2021,
CHAPTER 17. THIS INCLUDES PERIODIC INSPECTION OF:
1. REINFORCEMENT PLACEMENT
2. INSPECT ANCHORS POST-INSTALLED IN CONCRETE
3. REINFORCING BAR WELDING
CONSTRUCTION NOTES
A. NEITHER THE PROFESSIONAL ACTIVITIES OF SSFM
INTERNATIONAL, INC. (SSFM), NOR THE PRESENCE OF SSFM OR
SSFM'S EMPLOYEES AT A CONSTRUCTION SITE, SHALL RELIEVE
THE GENERAL CONTRACTOR AND ANY OTHER ENTITY OF THEIR
OBLIGATIONS, DUTIES, AND RESPONSIBILITIES INCLUDING, BUT
NOT LIMITED TO, CONSTRUCTION MEANS, METHODS,
SEQUENCES, TECHNIQUES, OR PROCEDURES NECESSARY FOR
PERFORMING, SUPERINTENDING, OR COORDINATING ALL
PORTIONS OF THE WORK OF CONSTRUCTION IN ACCORDANCE
WITH THE CONTRACT DOCUMENTS AND ANY HEALTH OR SAFETY
PRECAUTIONS REQUIRED BY ANY REGULATORY AGENCIES. SSFM
AND SSFM'S PERSONNEL HAVE NO AUTHORITY TO EXERCISE
ANY CONTROL OVER ANY CONSTRUCTION CONTRACTOR OR
OTHER ENTITY OR THEIR EMPLOYEES IN CONNECTION WITH
THEIR WORK OR ANY HEALTH OR SAFETY PRECAUTIONS.
B. THE CONTRACTOR SHALL NOTIFY THE STATE ENGINEER AT
LEAST 48 HOURS IN ADVANCE FOR REVIEW AND OBSERVATION
OF REINFORCING AND CONCRETE POURS.
C. THE CONTRACTOR SHALL FAMILIARIZE HIMSELF/HERSELF AND
VERIFY THE ACTUAL EXISTING CONDITIONS OF HOLDROOM F
AND ITS ADJACENT APRON PRIOR TO COMMENCING WORK.
D. CERTAIN WORK, INCLUDING BUT NOT LIMITED TO UTILITY
SHUT-DOWNS AND WORK OUTSIDE THE CONSTRUCTION FENCE
LIMITS, SHALL BE PERFORMED AT NIGHT. NIGHT WORK SHALL BE
PERFORMED BETWEEN THE HOURS OF 12:00AM TO 5:00AM. ANY
WORK PERFORMED DURING HOLIDAYS MUST BE PRESENTED TO
THE AIRPORT 3 WEEKS PRIOR TO APPROVAL. COVER TRENCHES
WITH STEEL PLATES EACH DAY.
E. THIS IS AN OPERATING AIRPORT. THE CONTRACTOR SHALL
CONDUCT ALL OPERATIONS IN A MANNER THAT WILL CAUSE NO
INTERFERENCE WITH AIRPLANE TRAFFIC OR NORMAL
OPERATION OF THE AIRPORT. IN ALL OPERATIONS, THE
CONTRACTOR SHALL BE GOVERNED BY THE REGULATIONS AND
RULES OF KAHULUI AIRPORT, AND SHALL COOPERATE FULLY
WITH THE STATE ENGINEER AND AIRPORT OPERATIONS.
F. AIRPORT OPERATIONS WILL NOTIFY THE CONTRACTOR OF ANY
UNSCHEDULED FLIGHTS THAT WILL BE ARRIVING OR DEPARTING.
THE CONTRACTOR SHALL TEMPORARILY STOP WORK IN
SPECIFIC AREAS THAT WOULD AFFECT THE FLIGHT AND
PASSENGER OPERATIONS AT THE AIRPORT OR TERMINAL. WHEN
THE OPERATIONS HAVE BEEN COMPLETED, AIRPORT
OPERATIONS WILL NOTIFY THE CONTRACTOR TO RESUME THE
WORK. NOTICE TO THE CONTRACTOR WILL BE ISSUED AT LEAST 1
HOUR PRIOR TO REQUIRED WORK STOPPAGE.
G. ALL EQUIPMENT AND MATERIALS SHALL BE STORED OFF
AIRPORT PROPERTY, OR IN DESIGNATED LAY-DOWN AREAS ON
THE AIRPORT PROPERTY UNTIL THEY ARE TO BE USED IN THE
WORK. EQUIPMENT AND MATERIALS LOCATED ON AIRPORT
PROPERTY, BUT NOT BEING USED, SHALL BE LEFT AT LOCATIONS
TO BE APPROVED BY THE STATE ENGINEER AND AIRPORT
OPERATIONS. ALL OTHER OPERATIONS OF THE CONTRACTOR
SHALL BE CONFINED TO THE AREAS SHOWN ON THESE
DOCUMENTS, OR AUTHORIZED BY THE STATE ENGINEER.
H. THE AIRPORT HAS OTHER CONSTRUCTION PROJECTS WHICH
MAY OCCUR AT THE SAME TIME AS THIS PROJECT. THE
CONTRACTOR SHALL COOPERATE WITH OTHER CONTRACTORS
ON THE SITE AND SHALL CAUSE NO DISRUPTION TO ANY OF THE
CONSTRUCTION WORK.
I. THE CONTRACTOR SHALL ABIDE BY FAA ADVISORY CIRCULAR
150/5370-2G "OPERATIONAL SAFETY ON AIRPORTS DURING
CONSTRUCTION".
J. ALL WORK IN THE SECURE AREAS OF THE AIRPORT REQUIRE
BADGES OR ESCORTED WORKERS.
K. CONTRACTOR SHALL SUBMIT A SINGLE COMPATIBLE REPAIR
SYSTEM FOR EACH TYPE OF REPAIR RATHER THAN MIXING
MANUFACTURERS.
STANDARDS AND REFERENCES
A. INTERNATIONAL BUILDING CODE, INTERNATIONAL CODE
COUNCIL, 2021 EDITION
B. IEBC 2021, INTERNATIONAL EXISTING BUILDING CODE,
INTERNATIONAL CODE COUNCIL, 2021 EDITION
C. ACI 318-19, AMERICAN CONCRETE INSTITUTE, BUILDING CODE
REQUIREMENTS FOR STRUCTURAL CONCRETE
D. TMS 402/602, THE MASONRY SOCIETY, BUILDING CODE
REQUIREMENTS AND SPECIFICATIONS FOR MASONRY
STRUCTURES (FORMERLY ACI 530/530.1), 2016 EDITION
E. ACI 311, AMERICAN CONCRETE INSTITUTE, MANUAL FOR
CONCRETE INSPECTION
F. ACI 546R, AMERICAN CONCRETE INSTITUTE, GUIDE TO
CONCRETE REPAIR, 2014 EDITION
G. ICRI 310.2R, INTERNATIONAL CONCRETE REPAIR INSTITUTE,
SELECTING AND SPECIFYING CONCRETE SURFACE
PREPARATION FOR SEALERS, COATINGS, POLYMER OVERLAYS,
AND CONCRETE REPAIR, 2013 EDITION
H. ICRI 320.1R, INTERNATIONAL CONCRETE REPAIR INSTITUTE,
GUIDELINE FOR SELECTING APPLICATION METHODS FOR THE
REPAIR OF CONCRETE SURFACES
REINFORCING STEEL NOTES
A. ALL REINFORCING BARS USED IN CONSTRUCTION AND
CONCRETE REPAIRS SHALL BE ASTM A706, GRADE 60.
B. SPLICES SHALL BE IN ACCORDANCE WITH ACI 318-14. SPLICE
LENGTH SHALL NOT BE LESS THAN 48 BAR DIAMETERS OR 2'-0",
WHICHEVER IS GREATER. FOR REPAIRS WHERE THE TYPICAL
SPLICE CANNOT BE PERFORMED, SEE DETAILS SHEET S-503 FOR
ALTERNATE SPLICES.
G. MINIMUM CONCRETE CLEAR COVER MUST CONFORM TO ACI 318
SECTION 20.6.1.3.
H. BAR BENDS, HOOKS, AND OFFSETS MUST BE IN ACCORDANCE
WITH ACI RECOMMENDATIONS.
I. WELDING OF REINFORCING BARS SHALL BE IN ACCORDANCE
WITH THE "STRUCTURAL WELDING CODE-REINFORCING STEEL"
(AWS D1.4).
J. BAR SUPPORTS: BOLSTERS, CHAIRS, SPACERS, AND OTHER
DEVICES FOR SPACING, SUPPORTING, AND FASTENING
REINFORCING BARS AND WELDED WIRE FABRIC IN PLACE. USE
BLACK ANNEALED IRON WIRE TO SECURE REINFORCING.
K. MANUFACTURE BAR SUPPORTS ACCORDING TO CRSI'S “MANUAL
OF STANDARD PRACTICE” FROM STEEL WIRE, PLASTIC, OR
PRECAST CONCRETE OR FIBER-REINFORCED CONCRETE OF
GREATER COMPRESSIVE STRENGTH THAN CONCRETE.
L. CLEAN REINFORCEMENT OF LOOSE RUST AND MILL SCALE,
EARTH, AND OTHER FOREIGN MATERIALS.
M. ACCURATELY POSITION, SUPPORT, AND SECURE
REINFORCEMENT AGAINST DISPLACEMENT. LOCATE AND
SUPPORT REINFORCEMENT WITH BAR SUPPORTS TO MAINTAIN
MINIMUM CONCRETE COVER.
N. SET WIRE TIES WITH ENDS DIRECTED INTO CONCRETE, NOT
TOWARD EXPOSED CONCRETE SURFACES.
CONCRETE CRACK REPAIR NOTES
A. REFER TO THE SPECIFICATIONS, CONCRETE REPAIR NOTES, AND
REPAIR DETAILS FOR CONCRETE CRACK REPAIR MATERIALS AND
ADDITIONAL INFORMATION.
B. LOCATIONS OF DAMAGES SHOWN ON THE PLANS ARE
APPROXIMATIONS ONLY. THE CONTRACTOR MUST VERIFY AND
IDENTIFY THE DAMAGES. IMMEDIATELY NOTIFY THE STATE
ENGINEER OF DISCREPANCIES.
C. CLEAN ALL CRACKS IN ACCORDANCE WITH MANUFACTURER'S
RECOMMENDATIONS.
D. DO NOT APPLY ADHESIVE IF THE TEMPERATURE OF THE
CONCRETE IS NOT WITHIN THE RANGE OF APPLICATION
TEMPERATURES RECOMMENDED BY THE MANUFACTURER OF
THE ADHESIVE.
CONCRETE SPALL REPAIR NOTES
A. REFER TO SPECIFICATIONS FOR CONCRETE REPAIR MATERIALS
AND ADDITIONAL INFORMATION NOT SHOWN ON THE DRAWINGS.
B. LOCATE DAMAGED AREA, REMOVING ALL PAINT AND LOOSE
MATERIAL TO SOUND CONCRETE. AREA TO BE REPAIRED MUST
BE CLEAN, SOUND, AND FREE OF CONTAMINANTS.
C. MAKE SQUARED OFF SAW CUT TO THE DEPTH INDICATED ON THE
PLANS, MINIMUM 1" BEYOND EDGE OF DAMAGED AREA OR
SPALL, INTO SOUND CONCRETE.
D. CHIP CONCRETE SUBSTRATE TO OBTAIN A SURFACE PROFILE OF
-1/8" IN DEPTH WITH A NEW FRACTURED AGGREGATE SURFACE.
E. CHIP OUT EXISTING CONCRETE TO A DEPTH OF 1/2" MINIMUM
BELOW AND AROUND THE EXPOSED REINFORCING STEEL INTO
SOUND CONCRETE.
F. FULLY EXPOSE AND REMOVE ALL CORROSION ON REINFORCING
STEEL BY POWER TOOL CLEANING (SSPC-SP3). COAT WITH
CORROSION INHIBITOR.
G. WHEN THE CROSS-SECTIONAL AREA OF THE REBAR LOST DUE
TO CORROSION EXCEEDS 25% OF THE ORIGINAL AREA,
CONTRACTOR SHALL NOTIFY THE STATE ENGINEER
IMMEDIATELY, PRIOR TO COMMENCEMENT OF REPAIR WORK.
SEE ALSO DETAIL 4/S-503 FOR ALLOWABLE BAR SIZES.
H. SUBSTRATE SHOULD BE SATURATED SURFACE DRY (SSD) WITH
NO STANDING WATER.
I. APPLY 2 COMPONENT CORROSION-INHIBITING EPOXY ADHESIVE
TO REINFORCING STEEL AND CONCRETE.
J. COMPLETELY FILL CHIPPED AREAS WITH CERTIFIED POLYMER
MODIFIED CEMENTITIOUS MORTAR. IF MORE THAN 1" IN DEPTH,
ADD A 3/8" COARSE AGGREGATE PER MANUFACTURER'S
INSTRUCTIONS. FINISH TO EXISTING LINES. MATCH EXISTING
ADJACENT SURFACE FINISH.
K. THE REPAIR MORTAR SHALL HAVE A MINIMUM 28 DAY
COMPRESSIVE STRENGTH OF 6000 PSI.
L. SEE STRUCTURAL DRAWINGS FOR ADDITIONAL SPALL
PREPARATION AND REPAIR PROCEDURES.
CMU CRACK / SPALL REPAIR NOTES
A. REFER TO THE SPECIFICATIONS, QTY SUMMARY TABLE FOR
QUANTITIES AND CMU CRACK AND SPALL REPAIR DETAILS FOR
MATERIALS AND ADDITIONAL INFORMATION.
B. LOCATIONS OF DAMAGES SHOWN ON THE PLANS ARE
APPROXIMATIONS ONLY. THE CONTRACTOR MUST CONFIRM IF
WALL IS PARTIALLY GROUTED. VERIFY AND IDENTIFY THE
DAMAGES AND IMMEDIATELY NOTIFY THE STATE ENGINEER.
C. REPAIR CRACKS IN THE MORTAR JOINTS BY REMOVING OLD
MORTAR AND APPLYING NEW POLYMER MODIFIED
CEMENTITIOUS REPAIR MATERIAL.
D. REPLACING A DAMAGED UNIT SHALL BE ACCOMPLISHED BY
CAREFULLY CHISELING OR SAWING OUT THE BROKEN UNIT AND
ALL THE SURROUNDING MORTAR.
E. ONCE ALL THE OLD MORTAR, DUST, AND DEBRIS ARE REMOVED,
REFER TO THE REPAIR DETAILS.
F. THE POLYMER MODIFIED CEMENTITIOUS REPAIR MATERIAL MUST
BE TOOLED TO MATCH THE ORIGINAL PROFILE ONCE THE
MATERIAL BECOMES THUMBPRINT HARD.
STRUCTURAL ABBREVIATIONS
APPROX. - APPROXIMATE
ARCH. - ARCHITECTURAL
BOT. - BOTTOM
C.J. - CONSTRUCTION JOINT
COL. - COLUMN
CONC. - CONCRETE
CONT. - CONTINUOUS
DIA(M). - DIAMETER
DWGS. - DRAWINGS
E.F. - EACH FACE
ELEV./EL - ELEVATION
E.S. - EACH SIDE
E.W. - EACH WAY
ELEV. - EXISTING
EXP. - EXPANSION
HOR. - HORIZONTAL
JT. - JOINT
MAX - MAXIMUM
MECH - MECHANICAL
MIN. - MINIMUM
NTS - NOT TO SCALE
O.C. - ON CENTER
O.H. - OPPOSITE HAND
QTY - QUANTITY
REINF. - REINFORCEMENT
SIM. - SIMILAR
S.J. - SAWCUT JOINT
SL - SLOPE
SQ. - SQUARE
T&B - TOP AND BOTTOM
t/THK. - THICK(NESS)
TEMP. - TEMPERATURE
TYP. - TYPICAL
TOC - TOP OF CONCRETE
TOF - TOP OF FOOTING
TOS - TOP OF STEEL
U.N.O. - UNLESS NOTED OTHERWISE
VERT. - VERTICAL
V.I.F. - VERIFY IN FIELD
S-001
STRUCTURAL GENERAL
NOTES AND
ABBREVIATIONS
AT
KAHULUI AIRPORT
KAHULUI, MAUI, HAWAII
This work was prepared by me or under my supervision.
Licensed Expiration Date 04/30/2028
STATE OF HAWAII
DEPARTMENT OF TRANSPORTATION
AIRPORTS
DSGN. DRWN. CHKD. APPD.
DATE : DWG. NO.
SHEET :
REVISIONSNO. DATE REVISIONS
PROJECT TITLE :
PROJECT NO.:
SHEET TITLE:
DATE
JP AK KW KW
100% CONSTRUCTION
DOCUMENT
August, 2026
APRON RECONSTRUCTION
PHASE 1
CM1530-33
08/19/2026
OF 23 SHEETS
W
St ru ct ur al P ro je ct s\
_1
.0
D O
TA
O
G G
A pr on R ep ai rs \C on tra ct D oc s\
W
O R
KI
N
G D
R
AW
IN
G
S
KA
T HLEE N Y . W ONG
HA W A II, U.S .A
LICENSED
PROFESSIONAL
ENGINEER
HOLDROOM DAMAGE SCHEDULE
DAMAGE
MARK
SPALL AREA
(SQ. FT.)
CRACK
LENGTH
(LIN. FT.)
SHEET
NUMBER REMARKS
DM15 - 5.0 S-201 CRACK ON CONCRETE BEAM
DM16 - 3.5 S-201 CRACK ON CONCRETE BEAM
DM17 - 3.5 S-201 CRACK ON CONCRETE BEAM
DM18 - 12.0 S-201 CRACK ON CMU SPLIT RIBBED WALL
DM19 - 9.0 S-201 5 CRACKS ON CONCRETE BEAM
DM20 - 4.0 S-201 CRACK ON CONCRETE BEAM
DM21 - 2.5 S-201 CRACK ON CONCRETE BEAM
DM22 - 5.0 S-201 CRACK ON CONCRETE BEAM
DM23 - 4.5 S-201 CRACK ON CONCRETE BEAM
DM24 - 5.0 S-201 CRACK ON CONCRETE BEAM
DM25 - 5.0 S-201 CRACK ON CONCRETE BEAM
DM26 - 5.0 S-201 CRACK ON CONCRETE BEAM
DM27 - 4.0 S-201 2 HORIZONTAL CRACKS ON CONCRETE BEAM
DM28 - 5.0 S-201 CRACK ON CONCRETE BEAM
DM29 - 5.0 S-201 CRACK ON CONCRETE BEAM
DM30 - 5.0 S-201 CRACK ON CONCRETE BEAM
DM31 - 2.0 S-201 CRACK ON UNDERSIDE OF CONCRETE BEAM
DM32 - 9.0 S-201 2 CRACKS ON CONCRETE BEAM
DM33 - 5.0 S-201 CRACK ON CONCRETE BEAM
DM34 - 5.0 S-201 CRACK ON CONCRETE BEAM
DM35 - 11.5 S-201 CRACK ON CONCRETE WALL
DM36 - 7.5 S-201 CRACK ON CONCRETE WALL
DM37 - 6.0 S-201 CRACK ON CONCRETE WALL
DM38 - 8.5 S-201 CRACK ON CONCRETE WALL
DM39 - 10.0 S-201 CRACK ON CONCRETE WALL
DM40 - 5.0 S-201 CRACK ON CONCRETE WALL
DM41 7.5 - S-202 SPALL ON SIDE OF CONCRETE BEAM
DM42 - 9.0 S-202 3 CRACKS ON CONCRETE BEAM
DM43 - 6.0 S-202 2 CRACKS ON CONCRETE BEAM
NOTES:
1. QUANTITIES LISTED IN THE SCHEDULE ABOVE WERE DETERMINED AT THE TIME OF INVESTIGATION, APRIL 2024.
CONTRACTOR MUST VERIFY ALL QUANTITIES AND LOCATIONS. NOTIFY THE STATE ENGINEER OF ANY DISCREPANCIES.
2. DAMAGE QUANTITIES HAVE BEEN INCREASED BY A FACTOR OF 1.25 FOR BIDDING AND COST ESTIMATION PURPOSES. THE
CONTRACTOR SHALL BE PAID FOR ACTUAL MEASURED REPAIR QUANTITIES.
3. FOR BIDDING PURPOSES, IT IS ASSUMED TO REPLACE 1.5 POUNDS OF STEEL REINFORCEMENT PER SQUARE FOOT OF CONCRETE SPALL IN ALL HOLDROOM AREAS. IMMEDIATELY NOTIFY THE STATE ENGINEER OF VERIFIED QUANTITIES PRIOR
TO COMMENCING WORK.
4. DELAMINATIONS, VOIDS, AND CONCRETE PATCH FAILURES TO BE REPAIRED SAME AS SPALLS.
5. BLOCKOUTS AND CRACKS ON SHEET S-102 AND S-201 THROUGH S-204 ARE ONLY INTENDED TO PROVIDE THE CONTRACTOR WITH GENERAL LOCATION OF THE DEFECTS. DO NOT SCALE THE BLOCKOUTS AND CRACKS SHOWN ON THE
DRAWINGS TO CALCULATE DAMAGE QUANTITIES.
APRON DAMAGE SCHEDULE
DAMAGE
MARK
SPALL AREA
(SQ. FT.)
CRACK
LENGTH
(LIN. FT.)
SHEET
NUMBER REMARKS
DM01 6.5 - S-102 VOID/SPALL ON APRON SLAB, 1" DEEP
DM02 1.0 - S-102 VOID/SPALL ON APRON SLAB, 2" DEEP
DM03 - 10.5 S-102 2 CRACKS ON APRON SLAB
DM04 - 8.0 S-102 MAP CRACKING ON ENTIRE APRON SLAB
DM05 1.5 - S-102 VOID/SPALL ON APRON SLAB, 1" DEEP
DM06 - 3.5 S-102 2 CRACKS ON APRON SLAB
DM07 - 1.5 S-102 2 CRACKS ON APRON SLAB
DM08 - 13.0 S-102 2 CRACKS ON APRON SLAB
DM09 - 4.5 S-102 3 CRACKS ON APRON SLAB
DM10 6.0 - S-102 VOID/SPALL ON APRON SLAB, 1" DEEP
DM11 - 50.0 S-102 13 CRACKS ON 2 APRON SLABS
DM12 - 1.5 S-102 2 CRACKS ON APRON SLAB
DM13 - 15.0 S-102 6 CRACKS ON APRON SLAB
DM14 - 9.0 S-102 1 CRACK ON APRON SLAB
HOLDROOM DAMAGE SCHEDULE
DAMAGE
MARK
SPALL AREA
(SQ. FT.)
CRACK
LENGTH
(LIN. FT.)
SHEET
NUMBER REMARKS
DM44 - 2.5 S-202 CRACK ON CONCRETE WALL
DM45 - 7.5 S-202 CRACK ON CONCRETE WALL
DM46 - 1.5 S-202 CRACK ON CONCRETE WALL
DM47 - 10.5 S-202 2 CRACKS ON CONCRETE WALL
DM48 - 3.5 S-202 CRACK ON CONCRETE WALL
DM49 - 3.0 S-202 CRACK ON CONCRETE WALL
DM50 - 2.5 S-202 CRACK ON CONCRETE WALL
DM51 - 3.0 S-202 CRACK ON CONCRETE WALL
DM52 - 2.0 S-202 CRACK ON CONCRETE WALL
DM53 - 7.5 S-202 3 CRACKS ON CONCRETE WALL ABOVE BEAM
DM54 - 5.0 S-202 2 CRACKS ON CONCRETE WALL ABOVE BEAM
DM55 - 2.5 S-202 CRACK ON CONCRETE WALL ABOVE BEAM
DM56 5.0 - S-202 DELAMINATION ON SIDE OF CONCRETE BEAM
DM57 2.0 - S-202 DELAMINATION ON CONCRETE COLUMN
DM58 2.0 - S-202 DELAMINATION ON CONCRETE COLUMN
DM59 2.0 - S-202 DELAMINATION ON CONCRETE COLUMN
DM60 - 5.0 S-202 2 CRACKS ON CONCRETE WALL ABOVE BEAM
DM61 - 5.0 S-202 2 CRACKS ON CONCRETE WALL ABOVE BEAM
DM62 - 5.0 S-202 CRACK ON CONCRETE BEAM
DM63 - 5.0 S-202 2 CRACKS ON CONCRETE WALL ABOVE BEAM
DM64 - 5.0 S-202 CRACK ON CONCRETE BEAM
DM65 - 4.5 S-202 3 CRACKS ON CONCRETE WALL ABOVE BEAM
DM66 - 7.5 S-202 CRACK ON CONCRETE BEAM
DM67 - 5.0 S-202 3 CRACKS ON CONCRETE WALL ABOVE BEAM
DM68 - 7.5 S-202 CRACK ON UNDERSIDE OF CONCRETE BEAM
DM69 - 2.0 S-202 CRACK ON CONCRETE BEAM
DM70 - 5.0 S-202 CRACK ON CONCRETE BEAM
DM71 - 5.5 S-202 2 CRACKS ON CONCRETE BEAM
DM72 - 10.0 S-202 CRACK ON CONCRETE BEAM
DM73 2.5 5.0 S-202 SPALL ON SIDE OF CONCRETE BEAM
DM74 2.0 - S-202 DELAMINATION ON CONCRETE COLUMN
DM75 - - S-202 CRACK ON CONCRETE BEAM
DM76 - 5.0 S-202 CRACK ON CONCRETE BEAM
DM77 - 3.0 S-202 CRACK ON CONCRETE WALL ABOVE BEAM
DM78 - 2.5 S-202 2 CRACKS ON CONCRETE WALL ABOVE BEAM
DM79 - 5.0 S-202 2 CRACKS ON CONCRETE BEAM
DM80 - 8.0 S-202 CRACK ON CONCRETE WALL ABOVE BEAM
DM81 - 2.5 S-202 CRACK ON CONCRETE BEAM
DM82 - 4.0 S-202 2 CRACKS ON CONCRETE WALL ABOVE BEAM
DM83 - 5.0 S-202 2 CRACKS ON CONCRETE BEAM
DM84 - 8.5 S-202 2 CRACKS ON CONCRETE WALL ABOVE BEAM
DM85 - 5.0 S-202 2 CRACKS ON CONCRETE BEAM
DM86 - 10.0 S-202 CRACK ON CONCRETE WALL ABOVE BEAM
DM87 - 2.5 S-202 CRACK ON CONCRETE BEAM
DM88 2.0 7.0 S-202 DELAMINATION ON CONCRETE COLUMN
DM89 2.0 - S-202 DELAMINATION ON CONCRETE COLUMN
DM90 - - S-202 CRACK ON CONCRETE WALL ABOVE BEAM
DM91 - 2.5 S-202 CRACK ON CONCRETE BEAM S-002
DAMAGE SCHEDULE
AT
KAHULUI AIRPORT
KAHULUI, MAUI, HAWAII
This work was prepared by me or under my supervision.
Licensed Expiration Date 04/30/2028
STATE OF HAWAII
DEPARTMENT OF TRANSPORTATION
AIRPORTS
DSGN. DRWN. CHKD. APPD.
DATE : DWG. NO.
SHEET :
REVISIONSNO. DATE REVISIONS
PROJECT TITLE :
PROJECT NO.:
SHEET TITLE:
DATE
JP AK KW KW
100% CONSTRUCTION
DOCUMENT
August, 2026
APRON RECONSTRUCTION
PHASE 1
CM1530-33
08/19/2026
OF 23 SHEETS
W
St ru ct ur al P ro je ct s\
_1
.0
D O
TA
O
G G
A pr on R ep ai rs \C on tra ct D oc s\
W
O R
KI
N
G D
R
AW
IN
G
S
KA
T HLEE N Y . W ONG
HA W A II, U.S .A
LICENSED
PROFESSIONAL
ENGINEER
QTY SUMMARY TABLE
LOCATION
TOTAL CONCRETE
SPALLS, VOIDS, AND
DELAMINATIONS
(SQ. FT.)
TOTAL CONCRETE
CRACKS
(LIN. FT.)
TOTAL CMU
CRACKS
(LIN. FT.)
TOTAL REBAR
(LBS)
HOLDROOM F 273 491 12 410
APRON 15 117 - -
NOTES:
1. QUANTITIES LISTED IN THE SCHEDULE ABOVE WERE DETERMINED AT THE TIME OF INVESTIGATION, APRIL 2024.
CONTRACTOR MUST VERIFY ALL QUANTITIES AND LOCATIONS. NOTIFY THE STATE ENGINEER OF ANY DISCREPANCIES.
2. DAMAGE QUANTITIES HAVE BEEN INCREASED BY A FACTOR OF 1.25 FOR BIDDING AND COST ESTIMATION PURPOSES. THE
CONTRACTOR SHALL BE PAID FOR ACTUAL MEASURED REPAIR QUANTITIES.
3. FOR BIDDING PURPOSES, IT IS ASSUMED TO REPLACE 1.5 POUNDS OF STEEL REINFORCEMENT PER SQUARE FOOT OF CONCRETE SPALL IN ALL HOLDROOM AREAS. IMMEDIATELY NOTIFY THE STATE ENGINEER OF VERIFIED QUANTITIES PRIOR
TO COMMENCING WORK.
4. DELAMINATIONS, VOIDS, AND CONCRETE PATCH FAILURES TO BE REPAIRED SAME AS SPALLS.
5. BLOCKOUTS AND CRACKS ON SHEET S-102 AND S-201 THROUGH S-204 ARE ONLY INTENDED TO PROVIDE THE CONTRACTOR WITH GENERAL LOCATION OF THE DEFECTS. DO NOT SCALE THE BLOCKOUTS AND CRACKS SHOWN ON THE
DRAWINGS TO CALCULATE DAMAGE QUANTITIES.
HOLDROOM DAMAGE SCHEDULE
DAMAGE
MARK
SPALL AREA
(SQ. FT.)
CRACK
LENGTH
(LIN. FT.)
SHEET
NUMBER REMARKS
DM92 - 23.5 S-202 CRACK ON CONCRETE WALL ABOVE BEAM
DM93 - 2.5 S-202 CRACK ON CONCRETE WALL ABOVE BEAM
DM94 - 2.5 S-202 3 CRACKS ON CONCRETE BEAM
DM95 1.0 15.0 S-202 CRACK ON CONCRETE BEAM, SPALLING
DM96 - 4.5 S-202 CRACK ON CONCRETE WALL ABOVE BEAM
DM97 - 6.5 S-202 CRACK ON CONCRETE BEAM
DM98 - 5.0 S-202 CRACK ON CONCRETE WALL ABOVE BEAM
DM99 4.0 S-202 SPALL ON SIDE OF CONCRETE BEAM
DM100 2.0 - S-202 SPALL ON CONCRETE COLUMN
DM101 2.0 - S-203 SPALL ON SIDE OF CONCRETE BEAM
DM102 3.0 - S-203 SPALL ON SIDE OF CONCRETE BEAM
DM103 - - S-203 CRACK ON CONCRETE WALL ADJACENT TO DOOR
DM104 8.0 - S-203 SPALL ON SIDE OF CONCRETE BEAM
DM105 15.5 - S-203 SPALL ON CONCRETE COLUMN
DM106 1.5 - S-203 SPALL ON CONCRETE COLUMN
DM107 4.0 - S-203 SPALL ON CONCRETE BEAM
DM108 1.5 - S-203 SPALL ON CONCRETE COLUMN
DM109 8.0 - S-203 DELAMINATION ON CONCRETE BEAM
DM110 - 6.5 S-203 3 CRACKS ON CONCRETE WALL ADJACENT TO
DOOR
DM111 - 17.0 S-203 2 CRACKS ON CONCRETE WALL ADJACENT TO
DOOR
DM112 2.5 - S-203 SPALL ON CONCRETE COLUMN
DM113 - 1.5 S-203 CRACK ON CONCRETE COLUMN
DM114 1.5 - S-203 SPALL ON CONCRETE COLUMN
DM115 - 2.5 S-203 CRACK ON CONCRETE BEAM
DM116 - 5.0 S-203 CRACK ON CONCRETE COLUMN
DM117 - 8.0 S-203 CRACK ON CONCRETE COLUMN
HOLDROOM DAMAGE SCHEDULE
DAMAGE
MARK
SPALL AREA
(SQ. FT.)
CRACK
LENGTH
(LIN. FT.)
SHEET
NUMBER REMARKS
DM118 3.5 - S-203 SPALL ON CONCRETE COLUMN
DM119 27.0 - S-203 SPALL ON CONCRETE BEAM WITH EXPOSED
REBAR
DM120 - 2.0 S-203 CRACK ON CONCRETE BEAM
DM121 38.0 - S-203 SPALLING AND DELAMINATION ON CONCRETE
RAMP WALL
DM122 29.0 - S-203 SPALLING AND DELAMINATION ON CONCRETE
RAMP WALL
DM123 - 2.0 S-203 CRACK ON CONCRETE BEAM
DM124 - 2.5 S-203 CRACK ON CONCRETE BEAM
DM125 - 8.0 S-203 2 CRACKS ON CONCRETE BEAM
DM126 2.5 - S-203 SPALL ON CONCRETE BEAM WITH EXPOSED
REBAR
DM127 8.0 - S-203 SPALL ON CONCRETE BEAM WITH EXPOSED
REBAR
DM128 1.5 - S-203 DELAMINATION ON CONCRETE BEAM
DM129 - 1.0 S-203 CRACK ON CONCRETE BEAM
DM130 10.0 - S-203 DELAMINATION ON CONCRETE BEAM
DM131 1.0 - S-203 SPALL ON CONCRETE BEAM WITH EXPOSED
REBAR
DM132 - 2.0 S-203 CRACK ON CONCRETE BEAM
DM133 12.0 - S-203 DELAMINATION AND CRACKING ON CONCRETE
COLUMN
DM134 2.0 - S-203 SPALL ON CONCRETE COLUMN
DM135 1.0 - S-203 DELAMINATION ON CONCRETE BEAM
DM136 8.0 - S-203 DELAMINATION ON CONCRETE BEAM
DM137 5.0 - S-203 SPALL ON CONCRETE BEAM WITH EXPOSED
REBAR
DM138 1.0 - S-203 SPALL ON CONCRETE BEAM
DM139 38.5 - S-203 DELAMINATION ON CONCRETE BEAM
DM140 7.0 - S-203 SPALL ON CONCRETE COLUMN WITH EXPOSED
REBAR
DM141 - 9.0 S-203 CRACK ON CONCRETE COLUMN
DM142 - 6.5 S-203 CRACK ON CONCRETE COLUMN
S-003
DAMAGE SCHEDULE
AT
KAHULUI AIRPORT
KAHULUI, MAUI, HAWAII
This work was prepared by me or under my supervision.
Licensed Expiration Date 04/30/2028
STATE OF HAWAII
DEPARTMENT OF TRANSPORTATION
AIRPORTS
DSGN. DRWN. CHKD. APPD.
DATE : DWG. NO.
SHEET :
REVISIONSNO. DATE REVISIONS
PROJECT TITLE :
PROJECT NO.:
SHEET TITLE:
DATE
JP AK KW KW
100% CONSTRUCTION
DOCUMENT
August, 2026
APRON RECONSTRUCTION
PHASE 1
CM1530-33
08/19/2026
OF 23 SHEETS
W
St ru ct ur al P ro je ct s\
_1
.0
D O
TA
O
G G
A pr on R ep ai rs \C on tra ct D oc s\
W
O R
KI
N
G D
R
AW
IN
G
S
KA
T HLEE N Y . W ONG
HA W A II, U.S .A
LICENSED
PROFESSIONAL
ENGINEER
SEGMENT Q
212'-6"'
GATE 39
SEGMENT P
225''
GATE 35
SEGMENT O
225''
GATE 33
SEGMENT N
175''
GATE 29
SEGMENT M
112'-6"'
GATE 27
SEGMENT L
112'-6"'
GATE 25
SEGMENT K
150''
GATE 23
SEGMENT J
150''
GATE 21
SEGMENT I
137'-6"'
GATE 19
SEGMENT H
162'-6"'
GATE 17
SEGMENT E
125''
GATE 11
SEGMENT D
162'-6"'
GATE 9
SEGMENT C
200''
GATE 7
SEGMENT B
187'-6"'
GATE 5
SEGMENT A
200''
GATE 1
S-102
SEGMENT F
125''
GATE 13
SEGMENT G
187'-6"'
GATE 15
S10
S6.5
K36 K28 K20 K6 P6 P13 P20 P22P14 P29 P32 P37
LIMITS OF PHASE 1
APRON REPAIR
S-103
LIMITS OF PHASE 1
TERMINAL REPAIR
HOLDROOM E HOLDROOM F
S10
S6.5
YARD SIDE
AIR SIDE
K36 K28 K20 K6 P6 P13 P20 P22P14 P29 P32 P37
HOLDROOM C
CENTRAL
ROTUNDAHOLDROOM BHOLDROOM A HOLDROOM D
NOTE:
APRON PLAN VIEW DIMENSIONS, LAYOUT, AND INLET GRATE
LOCATIONS ARE DETERMINED USING RECORD DRAWINGS AND
SURVEYING PERFORMED IN JANUARY 2026.
THE CONTRACTOR MUST VERIFY ALL LOCATIONS AND
DIMENSIONS OF APRON EXISTING CONDITIONS PRIOR TO
COMMENCEMENT OF WORK OR ORDERING MATERIALS.
IMMEDIATELY NOTIFY STATE ENGINEER OF ANY DISCREPANCIES.
S-101
SCALE: 1" = 125'S-101
1 OGG APRON PLAN
OVERALL SITE PLAN
0 250'62.5' 125'
GRAPHIC SCALE
SCALE: 1" = 125'-0"
N
SCALE: 1" = 125'S-101
2 OGG TERMINAL PLAN
AT
KAHULUI AIRPORT
KAHULUI, MAUI, HAWAII
This work was prepared by me or under my supervision.
Licensed Expiration Date 04/30/2028
STATE OF HAWAII
DEPARTMENT OF TRANSPORTATION
AIRPORTS
DSGN. DRWN. CHKD. APPD.
DATE : DWG. NO.
SHEET :
REVISIONSNO. DATE REVISIONS
PROJECT TITLE :
PROJECT NO.:
SHEET TITLE:
DATE
JP AK KW KW
100% CONSTRUCTION
DOCUMENT
August, 2026
APRON RECONSTRUCTION
PHASE 1
CM1530-33
08/19/2026
OF 23 SHEETS
W
St ru ct ur al P ro je ct s\
_1
.0
D O
TA
O
G G
A pr on R ep ai rs \C on tra ct D oc s\
W
O R
KI
N
G D
R
AW
IN
G
S
KA
T HLEE N Y . W ONG
HA W A II, U.S .A
LICENSED
PROFESSIONAL
ENGINEER
SEGMENT Q
212'-6"'
GATE 39
SEGMENT P
225''
GATE 35
SEGMENT O
225''
GATE 33
P29 P32 P37
DM12
DM11
DM10
DM13
DM14DM01
DM03
DM04 DM07
DM08
DM09
DM05
DM06
DM02
12'-6"'±
'-6
'-8
INLET GRATES, TYP.
SLAB UNDER A.C.
NOTE:
APRON PLAN VIEW DIMENSIONS, LAYOUT, AND
INLET GRATE LOCATIONS ARE DETERMINED USING
RECORD DRAWINGS AND SURVEYING PERFORMED
IN JANUARY 2026.
THE CONTRACTOR MUST VERIFY ALL LOCATIONS
AND DIMENSIONS OF APRON EXISTING
CONDITIONS PRIOR TO COMMENCEMENT OF WORK
OR ORDERING MATERIALS. IMMEDIATELY NOTIFY
STATE ENGINEER OF ANY DISCREPANCIES.
S-102 11S-102
1 APRON DAMAGE PLAN
APRON DAMAGE PLAN
SCALE: 1/32" = 1'-0"
N
CRACK ON APRON SLAB
VOID / SPALL ON APRON SLAB
MAP CRACKING ON APRON SLAB
LEGEND
AT
KAHULUI AIRPORT
KAHULUI, MAUI, HAWAII
This work was prepared by me or under my supervision.
Licensed Expiration Date 04/30/2028
STATE OF HAWAII
DEPARTMENT OF TRANSPORTATION
AIRPORTS
DSGN. DRWN. CHKD. APPD.
DATE : DWG. NO.
SHEET :
REVISIONSNO. DATE REVISIONS
PROJECT TITLE :
PROJECT NO.:
SHEET TITLE:
DATE
JP AK KW KW
100% CONSTRUCTION
DOCUMENT
August, 2026
APRON RECONSTRUCTION
PHASE 1
CM1530-33
08/19/2026
OF 23 SHEETS
W
St ru ct ur al P ro je ct s\
_1
.0
D O
TA
O
G G
A pr on R ep ai rs \C on tra ct D oc s\
W
O R
KI
N
G D
R
AW
IN
G
S
KA
T HLEE N Y . W ONG
HA W A II, U.S .A
LICENSED
PROFESSIONAL
ENGINEER
HOLDROOM F
S-201
S-202
S-203
S-203
S-202
S-201
P32 P37
S6.5
S10
YARD SIDE
AIR SIDE
KAHULUI SIDE
MAKAI SIDE
S-103 12S-103
1 HOLDROOM F PLAN
HOLDROOM F PLAN
SCALE: 1/16" = 1'-0"
0 32'8' 16'
GRAPHIC SCALE
SCALE: 1/16" = 1'-0"
4'
N
AT
KAHULUI AIRPORT
KAHULUI, MAUI, HAWAII
This work was prepared by me or under my supervision.
Licensed Expiration Date 04/30/2028
STATE OF HAWAII
DEPARTMENT OF TRANSPORTATION
AIRPORTS
DSGN. DRWN. CHKD. APPD.
DATE : DWG. NO.
SHEET :
REVISIONSNO. DATE REVISIONS
PROJECT TITLE :
PROJECT NO.:
SHEET TITLE:
DATE
JP AK KW KW
100% CONSTRUCTION
DOCUMENT
August, 2026
APRON RECONSTRUCTION
PHASE 1
CM1530-33
08/19/2026
OF 23 SHEETS
W
St ru ct ur al P ro je ct s\
_1
.0
D O
TA
O
G G
A pr on R ep ai rs \C on tra ct D oc s\
W
O R
KI
N
G D
R
AW
IN
G
S
KA
T HLEE N Y . W ONG
HA W A II, U.S .A
LICENSED
PROFESSIONAL
ENGINEER
P37 P36 P35 P34
P34 P33 P32
METAL FASCIA
METAL ROOF
CONCRETE BEAM
METAL GUTTER
CMU SPLIT RIBBED
SCORED (TYP.)
METAL FASCIA
METAL GUTTER
CONCRETE BEAM SPLIT RIBBED
SCORED CMU
DM15
DM16 DM17
DM18
DM19
DM20
DM21
DM22
DM23
DM24 DM25 DM26
DM27
DM28
DM29
DM30
DM32
DM31
DM33 DM34
DM35
DM37
DM38
DM36 DM39 DM40
SCALE: 1/8" = 1'-0"S-201
2 HOLDROOM BUILDING F SERVICE YARD ELEVATION
S-201
EXTERIOR ELEVATIONS
HOLDROOM F SERVICE
YARD SIDE
0 16'4 8'
GRAPHIC SCALE
SCALE: 1/8" = 1'-0"
SCALE: 1/8" = 1'-0"S-201
1 HOLDROOM BUILDING F SERVICE YARD SIDE ELEVATION
CRACK DAMAGE
SPALL ON CONCRETE
ROOFING
CONCRETE
CMU SPLIT RIB
LEGEND
AT
KAHULUI AIRPORT
KAHULUI, MAUI, HAWAII
This work was prepared by me or under my supervision.
Licensed Expiration Date 04/30/2028
STATE OF HAWAII
DEPARTMENT OF TRANSPORTATION
AIRPORTS
DSGN. DRWN. CHKD. APPD.
DATE : DWG. NO.
SHEET :
REVISIONSNO. DATE REVISIONS
PROJECT TITLE :
PROJECT NO.:
SHEET TITLE:
DATE
JP AK KW KW
100% CONSTRUCTION
DOCUMENT
August, 2026
APRON RECONSTRUCTION
PHASE 1
CM1530-33
08/19/2026
OF 23 SHEETS
W
St ru ct ur al P ro je ct s\
_1
.0
D O
TA
O
G G
A pr on R ep ai rs \C on tra ct D oc s\
W
O R
KI
N
G D
R
AW
IN
G
S
KA
T HLEE N Y . W ONG
HA W A II, U.S .A
LICENSED
PROFESSIONAL
ENGINEER
P33P32 P34 P35
P36 P37P35
METAL ROOF
SMOOTH CONCRETE
PAINTED, TYP.
METAL GUTTER
CONCRETE BEAM
CMU SPLIT RIBBED
SCORED (TYP.)
METAL ROOF
SMOOTH CONCRETE
PAINTED, TYP.
METAL GUTTER
CONCRETE BEAM
CMU SPLIT RIBBED
SCORED (TYP.)
DM41
DM42
DM43
DM44
DM45
DM46
DM47
DM48
DM49
DM50
DM51
DM52
DM53 DM54
DM55
DM59
DM58
DM57
DM56
DM60
DM62
DM61 DM63 DM65 DM67
DM64 DM66
DM68
DM69
DM70
DM71 DM72
DM73
DM74
DM77 DM78 DM80 DM82 DM84 DM86
DM88
DM89
DM90 DM92 DM93 DM96
DM98
DM99
DM100
DM75
DM76 DM79
DM81 DM83 DM85 DM87 DM91 DM94 DM95 DM97
SCALE: 1/8" = 1'-0"S-202
2 HOLDROOM BUILDING F - AIR SIDE ELEVATION
S-202
EXTERIOR ELEVATIONS
HOLDROOM F
KAHULUI SIDE
0 16'4 8'
GRAPHIC SCALE
SCALE: 1/8" = 1'-0"
SCALE: 1/8" = 1'-0"S-202
1 HOLDROOM BUILDING F - AIR SIDE ELEVATION
CRACK DAMAGE
SPALL ON CONCRETE
ROOFING
CONCRETE
CMU SPLIT RIB
LEGEND
AT
KAHULUI AIRPORT
KAHULUI, MAUI, HAWAII
This work was prepared by me or under my supervision.
Licensed Expiration Date 04/30/2028
STATE OF HAWAII
DEPARTMENT OF TRANSPORTATION
AIRPORTS
DSGN. DRWN. CHKD. APPD.
DATE : DWG. NO.
SHEET :
REVISIONSNO. DATE REVISIONS
PROJECT TITLE :
PROJECT NO.:
SHEET TITLE:
DATE
JP AK KW KW
100% CONSTRUCTION
DOCUMENT
August, 2026
APRON RECONSTRUCTION
PHASE 1
CM1530-33
08/19/2026
OF 23 SHEETS
W
St ru ct ur al P ro je ct s\
_1
.0
D O
TA
O
G G
A pr on R ep ai rs \C on tra ct D oc s\
W
O R
KI
N
G D
R
AW
IN
G
S
KA
T HLEE N Y . W ONG
HA W A II, U.S .A
LICENSED
PROFESSIONAL
ENGINEER
S10S9S7.5S6.5
S10 S9 S7.5 S6.5
CONCRETE BEAM
CONCRETE BEAM
METAL ROOF
CMU SPLIT RIBBED
SCORED (TYP.)
METAL ROOFCONCRETE BEAM
CMU SPLIT RIBBED
SCORED (TYP.)
CONCRETE BEAM
DM101
DM104 DM115
DM112
DM113
DM114
DM123 DM124
DM125
DM126
DM133
DM142
DM134
DM135
DM141
DM140
DM139
DM136
DM137
DM138
DM130
DM131DM128
DM129
DM120
DM119
DM122DM121
DM118DM109
DM105
DM106
DM107
DM108
DM127
DM110 DM111
DM102
DM103
DM116
DM117
DM132
NOTE:
DM103 IS PARTLY ON THE OUT OF PLANE
CONCRETE WALL, SPANNING FROM THE
DOORWAY WALL TO CMU WALL.
NOTE:
DM110 AND DM111 IS PARTLY ON THE OUT
OF PLANE CONCRETE WALL, SPANNING
FROM THE DOORWAY WALL TO CMU WALL.
SCALE: 1/8" = 1'-0"S-203
2 KAHULUI ELEVATION, HOLDROOM F AT P32
S-203
EXTERIOR ELEVATIONS
HOLDROOM F
KAHULUI AND
MAKAI SIDE
0 16'4 8'
GRAPHIC SCALE
SCALE: 1/8" = 1'-0"
SCALE: 1/8" = 1'-0"S-203
1 MAKAI ELEVATION, HOLDROOM F AT P37
CRACK DAMAGE
SPALL ON CONCRETE
ROOFING
CONCRETE
CMU SPLIT RIB
LEGEND
AT
KAHULUI AIRPORT
KAHULUI, MAUI, HAWAII
This work was prepared by me or under my supervision.
Licensed Expiration Date 04/30/2028
STATE OF HAWAII
DEPARTMENT OF TRANSPORTATION
AIRPORTS
DSGN. DRWN. CHKD. APPD.
DATE : DWG. NO.
SHEET :
REVISIONSNO. DATE REVISIONS
PROJECT TITLE :
PROJECT NO.:
SHEET TITLE:
DATE
JP AK KW KW
100% CONSTRUCTION
DOCUMENT
August, 2026
APRON RECONSTRUCTION
PHASE 1
CM1530-33
08/19/2026
OF 23 SHEETS
W
St ru ct ur al P ro je ct s\
_1
.0
D O
TA
O
G G
A pr on R ep ai rs \C on tra ct D oc s\
W
O R
KI
N
G D
R
AW
IN
G
S
KA
T HLEE N Y . W ONG
HA W A II, U.S .A
LICENSED
PROFESSIONAL
ENGINEER
WALL SECTION
REPAIR METHOD FOR CRACKS WIDER THAN "HAIRLINE" (0.02") WIDE
1. WATER BLAST CRACK TO REMOVE DIRT AND OTHER CONTAMINANTS.
2. APPLY TEMPORARY SEAL TO THE CRACK FACE. CRACKS EXTENDING
THROUGH THE WALL SHALL BE SEALED ON BOTH FACES.
3. PLACE ENTRY PORTS FOR INJECTION OF EPOXY ADHESIVE IN THE
SEALS ALONG THE CRACK PLANE.
4. INJECT EPOXY ADHESIVE THROUGH ENTRY PORTS FOR FULL DEPTH
PENETRATION INTO THE CRACKS (START AT LOW END).
5. AFTER THE EPOXY HAS CURED, REMOVE THE TEMPORARY SURFACE
SEALS AND ENTRY PORTS AND FINISH SURFACE TO MATCH EXISTING.
CRACK (WIDER THAN 0.02")
EXISTING CONC. WALL
"A
"A
REPAIR METHOD
1. CHIP CONTINUOUS GROOVE TO THE SOURCE OF CORROSION STAINS AND
TO DIMENSIONS SHOWN.
2. WIRE BRUSH REINFORCING TO REMOVE ALL CORROSION.
3. PATCH THE CONCRETE WITH POLYMER MODIFIED CEMENTITIOUS MORTAR
TO THE ORIGINAL LINES. APPLY CORROSION INHIBITOR TO THE
REINFORCING AND BONDING AGENT TO THE CONCRETE SURFACE TO
RECEIVE THE MORTAR.
CRACKS WITH
RUST STAINS
CHIP CONT.
GROOVE
NEW MORTAR
PATCH
EXTERIOR FACE
OF EXIST. CONC.
EXIST. CONC. WALL
EXIST. REINF.
1/2" CLR.
FROM REBARPARTIAL WALL
ELEVATION
SECTION "A"-"A"
2" M
IN
TY
P. SECTION "B"-"B"PARTIAL WALL ELEVATION
"B
"B
1/2" CLR.
REPAIR METHOD
1. REFER TO S-001 FOR ADDITIONAL INFORMATION.
2. CHIP TO EXPOSE CORRODED REINFORCING AND TO DIMENSIONS SHOWN.
3. CLEAN EXPOSED REINFORCING BY WIRE BRUSH OR WATER BLASTING. CONCRETE SURFACE SHALL BE
SATURATED SURFACE-DRY (SSD) BEFORE INSTALLATION OF REPAIR MORTAR.
4. WHEN CROSS-SECTIONAL AREA OF REBAR IS LESS THAN THE MINIMUM ALLOWABLE SIZE FROM CORROSION, SPLICE CORRODED REBAR WITH SAME EXISTING SIZE. REFER TO DETAIL 4/503 FOR ALLOWABLE BAR SIZE AND
REINFORCING SPLICE DETAILS.
5. INSTALL CONCRETE STAINLESS STEEL PINS INTO EXISTING CONCRETE.
6. APPLY FIRST COAT OF CORROSION INHIBITING ON THE REINFORCING BAR TO 3.0-4.0 MILS (DRY FILM THICKNESS)
AND ALLOW TO CURE FOR ONE HOUR, OR PER MANUFACTURER'S WRITTEN INSTRUCTIONS.
7. APPLY SECOND COAT OF CORROSION INHIBITING TO THE REINFORCING AND BONDING AGENT TO THE CONCRETE SURFACE TO RECEIVE THE REPAIR MORTAR, OR PER MANUFACTURER'S WRITTEN INSTRUCTIONS.
8. PATCH THE CONCRETE WITH POLYMER MODIFIED CEMENTITIOUS MORTAR TO THE ORIGINAL LINES, OR PER
MANUFACTURER'S WRITTEN INSTRUCTIONS.
9. CONTRACTOR TO PAINT OVER POLYMER MORTAR REPAIR TO MATCH SURROUNDING PAINTED SURFACES. THE
CONTRACTOR IS TO ALLOW FOR MANUFACTURER RECOMMENDED CURE TIME PRIOR TO COATING.
1/2" BEYOND FACE OF
REBAR (TYP. ALL AROUND) 1/2" MIN. DEPTH AT
SAW CUT EDGE LINE
6" T
YP
EXIST. CONC. WALL
NEW MORTAR
PATCH
SPALLED AREA
EXIST. REINF.
EXIST. REINF.
EXTERIOR FACE
OF CONC.
SAW CUT EDGE LINE CHIP CONC. SURFACE
INSTALL 1/4" DIA. x 3"
316 STAINLESS STEEL
CONC. PINS (SUCH AS
DEWALT MUSHROOM
HEAD SPIKE ANCHOR)
AT 6" O.C., E.W., EMBED
1 1/4" MIN. INTO CONC.
2" M
IN
TY
P.
1" MIN. TYP.
4"
CMU REPAIR NOTES:
1. REFER TO S-001 AND SPECIFICATIONS FOR ADDITIONAL INFORMATION.
2. REMOVE LOOSE CMU AT IDENTIFIED CRACKS. (SEE PLAN AND ELEVATIONS)
3. IF CRACK IS AT MORTAR JOINT, REMOVE EXISTING MORTAR. VERIFY THAT CRACK DOES NOT PROPAGATE THROUGH CMU SHELL. IF NO DAMAGE
TO CMU, PROCEED TO STEP 12.
4. DETERMINE IF CRACKS CAUSED BY…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .