Final SOW 2025 09 02 Memphis_IRS Service Center_Roof Elect_ Fire Alarm Impro.pdf
PDF 2 MB Posted
- Solicitation number
- 47PE0325R0007
About this file
This Statement of Work (SOW) details a design-build project for the U.S. General Services Administration (GSA) at the Internal Revenue Service Center in Memphis, Tennessee. The project encompasses roof cover replacement, electrical breaker repairs, and fire alarm system replacement across multiple building modules. Key work items include: 1) roof repairs involving membrane replacement, insulation upgrades, and drainage improvements, 2) replacing and refurbishing 26 failed Westinghouse circuit breakers with spare and reconditioned units, and 3) comprehensive fire alarm system replacement meeting UL certification standards. The project requires a 20-year no-dollar-limit warranty, wind resistance up to 140 miles per hour, and must comply with various environmental and energy performance requirements. The total project duration is 1,095 calendar days, with potential for an additional 180 days if an optional roof replacement is awarded. GSA anticipates contract award in the first quarter of 2026, with design phase services beginning soon thereafter.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (REVISED FINAL DRAFT)
Internal Revenue Service Center
PROJECT TYPE: ROOFING, ELECTRICAL BREAKER, & FIRE ALARM SYSTEM
IMPROVEMENT
PROJECT
Design Build Project Delivery
U.S. GENERAL SERVICES ADMINISTRATION (GSA) PUBLIC BUILDINGS SERVICE (PBS)
PROJECT IDENTIFICATION:
PROJECT NAME Roof, Electrical Breaker & Fire Alarm System Improvement
SOLICITATION NUMBER 47PE0325R0007
KAHUA/PCN/ASID NUMBERS Kahua: 13549
DIVISION PBS Project Delivery
BUILDING NAME & NUMBER TN0005ZZ_TN_Memphis_IRS Service Center
BUILDING ADDRESS 5391-5399 Getwell Rd, Memphis, TN 38118
CONTRACTING OFFICER Joseph Ardoin
PROJECT MANAGER Joesph Couch
LAST REVISION 9/2/2025
TABLE OF CONTENTS
SECTION 1 - PROJECT DESCRIPTION 4
A. SUMMARY 4
B. PROJECT GOALS AND OBJECTIVES 5
C. PROJECT REQUIREMENTS 5
1. Work Item # 1 – Roof Repairs and Replacements: 5
2. Work Item # 2 – Electrical Breaker Repairs and Replacements 7
3. Work Item # 3 – Fire Alarm System Replacement
4. Work Item # 4: Option 1: Additional Roof E Replacement & Repairs 8
5. Illustration of Roof Work Locations 8
6. Figure 1 – Breaker Detail – SOW 12
D. PREPROPOSAL CONFERENCE 13
SECTION 2 - GSA PBS GENERAL REQUIREMENTS 14
A. COMPLETION TIMEFRAME AND SCHEDULE 14
B. NOTICES TO PROCEED 14
C. GENERAL PROJECT MANAGEMENT RESPONSIBILITIES 14
1. Design-Builder Project Team 14
2. Communications Plan 14
3. Project Schedules 15
4. Project Progress Meetings/Presentations 15
5. Review Comments and Response 15
6. Coordination with GSA Construction Manager 15
7. Protection 15
D. MECHANICAL AND ELECTRICAL OUTAGES 16
E. GOVERNMENT-FURNISHED SERVICES 16
F. PROHIBITED USE 16
G. DEMOLITION AND REMOVAL 17
H. BUILDING OCCUPATION DURING CONSTRUCTION 17
I. WORK HOURS FOR ON-SITE CONSTRUCTION 17
J. NOISE MANAGEMENT 18
K. SECURITY REVIEWS AND BADGING 18
L. QUALITY CONTROL 18
M. CONTRACTOR-FURNISHED CONSTRUCTION SURVEILLANCE SYSTEM 19
N. PRE-CONSTRUCTION CONFERENCE 19
O. PROGRESS REPORTS 19
P. WARRANTY 19
Q. FINAL INSPECTION 20
R. CLOSE-OUT 20
SECTION 3 - DESIGN AND SUBMITTAL REQUIREMENTS 22
A. SCOPE OF WORK 22
B. DESIGN TEAM 22
C. DESIGN STANDARDS AND CRITERIA 22
D. DRAWINGS AND SPECIFICATIONS 23
E. ELECTRONIC / PRINT MEDIA FORMAT 23
F. TITLE BLOCKS 23
G. TRANSMITTAL REQUIREMENTS 23
H. INVESTIGATIVE REQUIREMENTS 25
I. INVESTIGATIVE REPORT / PRELIMINARY CONCEPT DESIGN (35 PERCENT) 25
1. Management Plan 25
2. Investigative Report 25
3. Architectural and Structural Documentation 25
4. Mechanical and Electrical Documentation 26
5. Construction Schedule 26
6. Meeting Minutes 26
J. DESIGN DEVELOPMENT / INITIAL CONSTRUCTION DOCUMENTS (75 PERCENT)26
1. Architectural and Structural Documentation 26
2. Mechanical and Electrical Documentation 27
3. Samples 28
4. Manufacturer's Product Data 28
5. Indoor Air Quality (IAQ) Management Plan 29
6. Certification Requirements 29
7. Construction Schedule 29
8. Meeting Minutes 29
K. FINAL CONSTRUCTION DOCUMENTS (100 PERCENT) 30
SECTION 4 – ROOFING COVER TECHNICAL PERFORMANCE 31
A. BASIC FUNCTION: 31
B. AMENITY AND COMFORT: 31
C. HEALTH AND SAFETY: 31
D. ROOF LOADS: 31
E. DURABILITY: 31
F. ENERGY AND ENVIRONMENTAL PERFORMANCE 32
G. PERMITTED PRODUCTS: 32
H. PROHIBITED PRODUCTS: 33
I. DELIVERY AND STORAGE OF MATERIALS 33
J. METHODS OF CONSTRUCTION 34
K. FIELD QUALITY CONTROL 34
1. Tests of Sealant Applications: 34
2. Tests of Roofing System Installation: 34
3. Tests of Roof Anchors 35
4. Fire Alarm 35
5. Manufacturer Inspection: 36
L. TRAINING 36
SECTION 5 - RAIN WATER DRAINANGE PERFORMANCE 38
ATTACHMENT 1 39
SECTION 1 - PROJECT DESCRIPTION
A. SUMMARY
1. Roof Cover Replacement and Improvement:
The project involves the design, repair, replacement, and improvement of thermal and moisture protection systems and rainwater drainage systems at roofs of the Internal Revenue Service Center in Memphis, Tennessee. The existing roof covers involve built-up asphalt membrane;
bituminous base flashing; metal counterflashing and parapet copings; rigid insulation over metal decking; internal rain leaders and conductors; and associated materials and components.
As-built drawings indicate that the metal deck and structural steel supports provide the roof slope.
The Design-Builder shall design and construct appropriate repairs, replacements, and improvements of roof cover and rainwater drainage systems to this facility. The Design-Builder shall confirm the quantity of roof area prior to submitting a proposal.
In addition, the project requires a web-camera surveillance system to monitor on-site roof work through project completion.
The Design-Builder shall also provide a twenty-year (20-year), no-dollar-limit (NDL) warranty on all areas of roof replacement. The warranties shall include wind riders to cover damage caused by winds speeds up to one-hundred forty (140) miles per hour or up to the design wind speed for the project location, whichever is less.
2. Breaker Repairs:
During PM inspection and testing of Westinghouse POW-R-100 circuit breakers in the Memphis IRS, twenty-six (26) circuit breakers failed. It is the intention of this scope of work to correct these issues and ensure the IRS has an adequate supply of functional breakers as spares.
The Design-Builder shall purchase and provide breakers as listed in Figure 1. Once the purchased breakers arrive and the spare breakers requiring refurbishment are returned, the IRS will have enough spare breakers to allow one switchboard’s breakers to be replaced on a weekend. The breakers will then have to be sent out to be refurbished. Once the refurbished breakers are returned, the next switchboard breakers can be completed.
The Design-Builder shall provide a one-year (1-year) warranty on all replaced breakers, including all parts and labor.
3. Fire Alarm System Replacement:
The work also includes replacement of the fire alarm system, including but not limited to all fire alarm control panels, initiating devices, notification devices, wiring, control modules, monitor modules, NAC panels, tamper switches, flow switches, etc. within the Memphis IRS Service Center Complex. The new Fire Alarm system shall be UL Certified; thus, the installing contractor shall be UL certified. The Design-Builder shall provide UL Certification to GSA upon completion of the project.
The Design-Builder’s registered Fire Protection Engineer (FPE) is required to be a full participant in the Project Delivery Team throughout the Design and Construction Stages of the project and should be thoroughly familiar with current PBS-P100.
4. Common Requirements:
This contract requires construction and demolition (C&D) waste diversion plans, waste diversion monthly reports, and related documentation.
The Design-Builder is responsible for assessing all visible existing conditions that may impact pricing prior to submission of a proposal.
B. PROJECT GOALS AND OBJECTIVES
1. Provide new roof cover at designated areas of the facility that is leak-free for a minimum of twenty years.
2. Repair, upgrade or improve rainwater drainage systems on the designated roofs of the building as required to provide effective and efficient removal of water from the roofs.
3. Provide an up-to-date fire alarm system that meets all the requirements of all applicable
Standards and Criteria, Building Codes, and Life Safety Code.
4. Ensure the adequate supply and operation of functional breakers.
5. Maximize the project's contributions to environmental sustainability and national energy security.
C. PROJECT REQUIREMENTS
1. Work Item # 1: Roof Repairs and Replacements Provide a price proposal to design and construct the following work:
a. Sealant Configuration and Installation:
1) Install new fluid-applied joint sealants in the horizontal joints between the wall panels of the penthouses. Remove gaskets and retainers in all vertical joints between wall panels and install a fluid-applied sealant in these locations. All joint sealants shall consist of silicone material except where incompatible substrates exist (use polyether or polyurethane). Install backer rods, joint fillers, and bond breakers as required for a functional joint system.
b. Expansion Joint Replacement
1) Replace expansion joints between roof areas, including at roofs of canteens and building entrances. New expansion joints must include sheet metal covers with a T-type cleat and an underlayment meeting or exceeding ASTM D1970. Install insulation inside expansion joints with flexible liners. Base flashing at expansion joints should consist of modified bitumen backer and surface sheets applied per NRCA recommendations and manufacturer's guidance (if TPO is used, appropriate base flashing configuration shall be used). Work also includes replacement of wood blocking and nailers; GSA receives credit for unused amounts less than 120 linear feet.
c. Standing Seam Metal Coping Replacement:
1) Replace standing seam metal coping adjacent to exterior walls at canteens for Building
Modules A, and H, and at entrances to Building Modules E North, DF, and GH. New metal coping shall include a self-adhered modified bitumen underlayment per ASTM D1970 and a slip sheet. Copper roofing sheet materials must comply with ASTM B370 and have a minimum weight of 16 ounces per square foot (0.0216-inch thickness).
Aluminum roofing panels shall comply with ASTM B209 for 3004 alloy aluminum and have a minimum thickness of 0.040 inches.
d. Inaccessible Area Waterproofing:
1) Remove metal panel and jamb flashing adjacent to a steel column at the southwest corner of
Penthouse C mechanical yard (northwest corner of the penthouse). Apply a fully reinforced, fluid-applied silicone waterproofing coating to the roof area currently inaccessible behind these components. Provide fully reinforced, fluid-applied silicone base flashing to vertical elements in this location for a minimum distance of 8 inches from the roof surface. Base flashing should also be applied to door jambs. Acceptable fluid-applied flashing and waterproofing products include Carlisle Seal-Tek Silicone Mastic, Carlisle Seamless SEAL ULTRA Silicone Coating, or equal materials approved by Carlisle to maintain the existing roof warranty. Reinstall metal panel and jamb flashing upon completion.
e. Low-Slope Roof Cover Removal and Replacement:
1) Remove and replace all low-slope roof cover over Building Modules A, D-F, E North, G-H, H.
These areas include the roofs over the canteens and the circular sections between roofs H and D and between D and E. New roof membranes are restricted to 80-mil heat-welded thermoplastic polyolefin (TPO) materials. All roof surfaces shall be highly reflective and meet EPA and DOE Energy Star requirements at minimum. Provide walk pads from roof access points to, around, and beneath all powered equipment on the roof.
f. Metal Decking Repair/Replacement:
1) Replace or repair metal decking as required to provide a suitable substrate for adhesives or fasteners. The Government will receive a credit for any amount less than 700 square feet that is not repaired or replaced.
g. Roof Insulation:
1) Provide new polyisocyanurate roof insulation to meet ASHRAE 90.1 recommendations for this location, except where existing copings, through-wall flashing, door and window sills, or similar components conflict with required insulation heights. Where conflicts occur, provide the maximum thickness achievable without raising these building components, but this exception does not apply to equipment curbs (raise equipment curbs as required to achieve ASHRAE recommendations where no other conflicts exist). Provide tapered insulation or similar products where required to improve roof slopes, prevent ponding, and ensure efficient rainwater flow to existing drains. Minimum roof slope shall be 1/4" per foot. Insulation and cover boards shall not incorporate organic materials, including in facers.
h. h. Roof Flashing Replacement:
1) Remove and replace all roof flashing:
2) Replace all metal flashing and parapet caps with new metal flashing and caps.
3) Replace non-metal flashings and pitch pans at roof penetrations with new reinforced, silicone or similar fluid-applied flashing material. Penetration/pitch pockets are not allowed.
4) Provide goosenecks or weatherheads for cable penetrations.
5) Extend any pipes, ductwork, or similar penetrations that do not allow an 8-inch flashing height.
i. Joint Sealants Associated with Replaced Roofing:
1) Replace all joint sealants associated with replaced roofing components, including at expansion joints, parapets, and copings. New joint sealants are limited to polyether, polyurethane, and silicone sealants.
j. Parapet Face Sealants and Repointing:
1) Replace all joint sealants in the outside faces of parapets, including at masonry, precast concrete panels, and glass spandrel panels. These sealants should be replaced from the top of the parapets down to a distance equal to the underside of the roof deck.
2) Repoint mortar joints at exterior faces of parapets on Building Module I. Repointing must cover an area extending from the top of the parapet to a level equal to the underside of the roof deck (approximately 4 feet), including stone copings. Work shall also include any exposed mortar joints on the interior and exterior sides of the parapets.
k. Equipment Support Repair/Replacement:
1) Repair or replace all existing equipment supports that exhibit deterioration, non-conformance with manufacturer's recommendations, or non-conformance with NRCA recommendations (NRCA recommendations must be met at minimum).
2) Where manufacturer's standards are desired, demonstrate they meet or exceed NRCA recommendations.
3) Where equipment stands are used instead of equipment curbs, provide hurricane-rated equipment stands.
4) Remove abandoned equipment supports.
l. Roof Drain Configuration Improvement:
1) Improve roof drain configurations as required to ensure effective drainage and to prevent ponding and leaks at drains. Ensure drain sumps are installed in accordance with NRCA recommendations and are properly configured in relation to roof saddles and crickets to prevent ponding and leaks.
m. Electrical Conduit and Wiring Rerouting:
1) Remove and reinstall all electrical conduit and wiring on roof surfaces and associated components as required to accomplish roof work, including any lightning protection. Comply with UL, IEEE, and NEC requirements when reinstalling electrical components.
n. Web-Camera Surveillance System:
1) Provide a web-camera surveillance system to monitor on-site work progress through project completion.
o. Drain Line Inspection, Repair and Cleaning:
1) Inspect and clean all existing drain lines servicing roof areas as required to prevent clogging and to ensure efficient movement of water from the roof. Inspect all drain pipes during the design phase and at construction completion. Provide videos of all inspections. Cleaning shall involve hydro-jetting or mechanically routing the pipes as required to clear obstructions and debris. Any drain assemblies with missing, rusted or broken components including bolts, bowls and clamp rings that have rust welded shall be repaired or removed and replaced.
p. Roof Area Dividers:
1) Install four area dividers through the high points of crickets and saddles, perpendicular to adjacent walls, to separate each roof into five sections. Ensure roof drainage is not adversely impacted. Provide foam closures for metal decks to prevent water from flowing under separators.
q. Design Work:
1) The base offer shall also include all design work for all elements of this combined work item.
2. Work Item # 2: Electrical Breaker Repairs and Replacements
Provide a price proposal for the additional cost to Work Item # 1 for the following:
a. The contractor will replace “Fail” circuit breakers that have been identified in Figure 1 with a new or reconditioned circuit breaker from IRS spares. The contractor will ensure all settings are identical to the circuit breaker being replaced.
b. Once the existing “Failed” circuit breakers have been replaced, the contractor shall have the “Failed” circuit breakers sent off be refurbished.
c. The breaker refurbishment at a minimum shall consist of:
1) Disassembly of the existing circuit breakers, as necessary to facilitate performing the reconditioning and conversion.
2) Thorough inspection, cleaning, and lubrication of operating mechanisms for proper operation.
3) Cleaning and inspection of the primary intermediate and arcing contacts for excessive arcing, pitting, and abnormal wear.
4) Cleaning and lubrication of the primary disconnecting device contacts with the contact lubricant.
5) Inspection of secondary disconnects and auxiliary relays for excessive arcing, abnormal wear, and proper operation.
6) Removal of the circuit breaker’s old trip device(s) to allow conversion
7) Conversion of the circuit breakers through installation of AC Pro, EATON, or an Approved equal, solid-state, and tripping device offering true RMS sensing protection.
8) Reassembly and inspection of the circuit breakers for contact alignment and correct measurement of wipe and gap.
9) Confirmation of circuit breaker interlocks, mechanical and electrical for proper operation.
10)Measurement of the primary contact resistance of each phase with a low reading.
11)Performance of phase-to-phase and phase-to-ground insulation resistance tests after cleaning, in accordance with ANSI Standards.
12)High-current tests of circuit breaker trip units to verify calibration.
d. Provide the following spare breakers for utilization during replacement work.
1) Merlin Gerin Model #MP50 H1 5000A CIRCUIT BREAKER/5000A TRIP, (1 each)
2) Westinghouse Model #POW-R-1009.6 3000A CIRCUIT BREAKER/3000A TRIP (1 each)
3) Westinghouse Model #POW-R-100 2000A CIRCUIT BREAKER/2000A TRIP (2 each)
4) Westinghouse Model #POW-R-100 1200A CIRCUIT BREAKER/1200A TRIP (1 each)
5) Westinghouse Model #POW-R-100 400A CIRCUIT BREAKER/400A TRIP (1 each)
3. Work Item # 3: Fire Alarm System Replacement
Provide a price proposal for the following:
1) Provide a fire alarm system for the entire complex that meets current Life Safety Code requirements.
2) Provide a remote Annunciator in the Main Lobby and O&M office.
3) Any new conduit, EMT, or junction boxes installed shall be factory painted red. Any existing junction boxes utilized should have cover plates painted red.
4) Fire alarm and emergency communication systems must be installed in accordance with the requirements in the most current editions of NFPA 72, and the IBC.
5) For remote off-site monitoring, all emergency generators shall be monitored directly by the fire alarm system for generator running condition. In the event the emergency generator starts and for the duration of the generator running, a supervisory signal shall be sent to the fire alarm panel and the fire alarm monitoring off site station.
6) All components shall be furnished by a single manufacturer, shall be of current design and shall be in regular and recurrent production. Provide design, materials and devices for a complete protected premise fire alarm system, conforming to NFPA 72 and all other applicable standards, except as otherwise or additionally specified herein.
7) Provide materials, equipment and devices that have been tested by a nationally recognized testing laboratory such as Underwriters' Laboratories or Factory Mutual Laboratories and listed or approved for fire protection service when so required by NFPA 72 or the GSA Fire Alarm Specifications.
8) The new Fire Alarm system shall be UL Certified, thus the installing contractor shall be UL certified. The Design-Builder shall provide UL Certification to GSA upon completion of the project.
9) Provide standard manufacturer warranties for all materials and a one-year warranty on labor and workmanship
4. Work Item # 4: Option 1 - Roof Repair & Replacement of Main Roof E and Daycare E
Provide a price proposal for the option to award additional roof improvements at Main Roof E and Daycare E:
1) Refer to Work Item # 1 for description of work requirements a - q to price Option 1 accordingly.
2) Reference Roof Work Location Illustration Color Orange for visual identification.
5. Illustration of Roof Work Locations
a. Overview
Solid blue lines indicate penthouses' wall locations. Red lines indicate expansion joint locations. Yellow Shaded areas indicate areas requiring full roof replacements as described in Work Item #1. Orange shaded areas repairing full roof replacement as described in Work Item 4: Option 1. Dashed blue lines indicate approximate locations for roof area separators.
b. Typical Wall Panel at Penthouses
Typical Penthouse Wall Typical Vertical Joint Interior Side of Wall
c. Typical Coping at Canteen Requiring Replacement
d. Inaccessible Area Requiring Repair
6. Figure 1 – Breaker Detail
D. PREPROPOSAL CONFERENCE
On site Pre-Proposal Conference walk through, not to exceed 3 hours (date/time TBD). This will be followed by a video call meeting to recap the walkthrough. Those not able to attend shall join the conference line call. The conference provides an opportunity to discuss and clarify this Request for Proposal (RFP), including design requirements, proposal submission requirements, roles and responsibilities, etc. However, nothing said or represented in the conference shall be deemed to modify RFP requirements unless followed by a written amendment. Offerors are requested to submit questions relative to the RFP at least ten (10) calendar days in advance of the conference so the Contracting Officer may prepare responses. Participation is strongly encouraged. Offerors, who plan to attend, should contact the Contracting Officer to enable a rough count of attendance. Depending on response, the number of attendees from any one offeror may be limited by the Government.
Site Access: Because of the fact that the project is in a fully operating Federal Building, site access for offerors will only be available at the Pre-Proposal conference. Pre-award consultation with GSA Property Management Office staff or involved tenants is not permitted.
All site related questions shall be addressed at the Pre-Proposal Conference or be submitted in writing to the Contracting Officer.
END OF SECTION 1
SECTION 2 - GSA PBS GENERAL REQUIREMENTS
A. COMPLETION TIMEFRAME AND SCHEDULE
1. All design and construction under the Work Items #1 through #3 must be completed within 1095 calendar days of notice to proceed. If Work Item # 4: Option 1 is awarded, 180 calendar days will be granted to complete this work concurrently with other contracted work items and within the total project duration of 1095 days.
2. Fire alarm and electrical breaker work shall be done concurrent with roof work. Note - GSA may be performing a separate arc flash project, and the timing of that project may impact the breaker work portion of this project.
3. Provide an overall project delivery schedule addressing all phases of design and construction.
Coordinate this overall schedule with the schedule of submissions and reviews.
4. The Design-Builder will be granted additional time for inclement weather delays only when the project site experiences rain or freezing temperatures which are above the normals documented at the following website:
https://www.weather.gov/ (Click city location on map. Select Climate and Past Weather option beneath weather office. Select Monthly Weather Summary under Product. Select Location.
Select Archived Data under Timeframe. Select Month. Press Go.)
B. NOTICES TO PROCEED
The Design-Builder may not proceed or initiate any work prior to receipt of an original notice to proceed. Any work done without being directed to do so by the Contracting Officer shall be at the Design-Builder's own risk.
GSA anticipates awarding the contract in the 1st quarter of calendar year 2026 and commencing the design phase services soon thereafter. It is anticipated that the Overall Project will be completed within 1095 calendar days after the initial Notice to Proceed (NTP) for design.
The project phasing will be broken down further as follows:
● Design NTP for all Phases (Estimated Duration 12 Months)
○ Roof Construction
○ Electrical Breaker Replacement
○ Fire Alarm
● Pre-Construction (Estimated Duration 3 Months)
● Independent Construction NTP’s To Be Issued (Estimated Duration 18 Months)
○ Roof Construction (Independent NTP Issued, NTP for Optional roofing work may or may not be issued at the same time. )
○ Electrical Breaker Replacement (Independent NTP Issued)
○ Fire Alarm (Independent NTP Issued)
● Project Closeout (Estimated Duration 3 Months)
C. GENERAL PROJECT MANAGEMENT RESPONSIBILITIES
1. Design-Builder Project Team
The Design-Builder shall provide experts in all applicable disciplines and as otherwise required in this section, with credentials as indicated, as they apply to this project. The DB Contractor shall provide sufficient staff of project managers, field engineers, superintendents, inspection and testing engineers, scheduling specialists, cost engineers, clerical and accounting personnel, etc. to perform the required work.
At a minimum, the Design-Builder’s key team members shall consist of the following: Project Manager / Project Engineer https://www.weather.gov/
Construction Superintendent / Quality Control Superintendent Assistant Superintendent / Quality Control for Roofing Assistant Superintendent / Quality Control for Electrical and Fire Alarm
The Design-Builder’s shall utilize the personnel named in its offer to perform the services required under this contract. If any of the personnel named in the Design-Builder’s accepted proposal (incorporated into this contract by reference) become unavailable, the Design-Builder shall promptly submit a complete written resume for a proposed substitution, any other information necessary for the GSA to approve or disapprove, and a detailed explanation of the circumstances necessitating the proposed substitution.
See also FAR 52.244-4 regarding subcontractors and outside associates and consultants.
2. Communications Plan The Design-Builder’s contractual responsibility is to GSA only and not to tenant agencies or local community interests where the project is located. The Design-Builder shall direct all tenant agencies and local community questions and requests to the GSA Project Manager. Prior to contacting any parties other than GSA regional personnel, the Design-Builder shall confirm all meetings and/or communications with the GSA Project Manager.
3. Project Schedules
a. The Design-Builder shall develop and submit a project schedule in Gantt chart format for review by the GSA Project Manager (PM) showing submittal review and approval tasks, required construction tasks, milestone dates, and the critical path among all tasks. The schedule shall also include provisions to show the amount of work completed for each task as work progresses.
b. The Design-Builder shall develop and submit the schedule in Microsoft Project format.
c. The Design-Builder shall submit the schedule within fourteen (14) calendar days of contract award or of the notice to proceed. The Design-Builder is responsible for maintaining the schedule throughout the course of the project. The Design-Builder shall update the schedule monthly and shall allow sufficient time for the review of submittals by all parties.
The updated schedule must be submitted with all pay requests.The Design-Builder shall notify the GSA Project Manager immediately if schedule slippage is expected. The Design-Builder shall submit a revised project schedule within five (5) working days after the GSA Contracting Officer authorizes the revision.
4. Project Progress Meetings/Presentations
a. A design review meetings between the Design-Builder and Government representatives will be held to resolve any outstanding issues on each design submittal and to verify resolution of all other comments. This meeting will be held within fourteen (14) calendar days of the Government's receipt of the 35% and 90% design submittals. A design review for the final construction documents (100% design submittal) will only be held if the submittal is found to be severely deficient.
b. All design review meetings will be held by phone conference, video conference, or similar remote method.
5. Review Comments and Response
a. In response to each of the project submittals required by this Statement of Work, the GSA will provide written comments within fourteen (14) calendar days of submittal distribution.
The Design-Builder shall respond in writing to the design review comments within seven
(7) calendar days.
b. The Government review and comments shall not be construed to relieve the Design-Builder of responsibility for technically correct and complete documents in compliance with applicable codes and industry standards.
6. Coordination with GSA Construction Manager
a. The GSA may contract with a Construction Management (CMa) firm as GSA’s agent to assist in the management of the Government duties under this contract. The CMa may be given full or partial authority to act on behalf of the GSA for design and construction management activities. The GSA contracting officer, project manager, or contracting officer's representative will identify the CMa's level of authority at the start of the CMa's work activities. The contractor shall interact with the CMa in accordance with the authority designated to it by the GSA.
b. Any inspections conducted by the CMa shall not be construed to represent acceptance of the Design-Builder’s work or to relieve the Design-Builder of responsibility for meeting the quality control requirements of the contract.
7. Protection
a. Traffic Control
1) Where pedestrian and driver safety are endangered near or below the area of work, use traffic barricades with flashing lights.
2) The contractor shall ensure that pedestrian and vehicular access to and from all building exits, reserved parking spaces, and service roads are maintained.
3) This campus style facility is fully occupied by the tenant agency (IRS). The agency will be operating under normal conditions throughout the lifecycle of this project.
Consideration must be given to ensure a safe working environment is maintained for the tenant, including reduction of noise hazards, exhaust/odors, path/parking obstructions and debris removal.
b. Existing Facilities
1) Do not disturb existing construction and building components beyond the extent specified or necessary. Provide temporary covers as required to protect adjacent building elements. Ensure that no elements determined to be unstable are left unsupported, and place and secure bracing, shoring, or other supports as may be required due to any cutting, removal, or demolition work performed under this contract.
2) Provide protective measures to control accumulation and migration of dust and dirt in all work areas. Remove dust, dirt, and debris from work areas daily.
3) Protect heavily traveled roof areas and material lay-down areas, including but not limited to corridors for transporting materials to the working areas, as recommended by the applicable roofing membrane provider.
4) Restore any landscaping that is damaged by roofing operations to original condition.
This includes any curbing, sidewalks and parking surfaces that are impacted by scaffolding, ladders or material storage.
c. Fire Watch In the event that a fire alarm or sprinkler system is to be placed out of service, a fire watch must be established. Whenever a fire protection system or portion of a system is impaired or shut down for any reason, the local fire department and the GSA Regional Fire Protection Engineer shall be notified immediately, and a fire watch shall be established in accordance with the GSA Fire Watch Guidelines (09-2007). In addition, the GSA Project Manager and GSA Building Manager must be included in prior approval notification.
d. Hot Works Welding, cutting and brazing with torches is not recommended and is highly discouraged by GSA. However, if these actions are essential, a GSA "Hot Works" Permit (GSA Form 1755) will be required for any use of a welder or cutting torch on the property. In addition, the GSA Project Manager and GSA Building Manager must be included in prior approval notification.
e. Rooftop Mechanical and Electrical Equipment Maintain existing mechanical and electrical equipment on the roof and protect against damage. Provide approved barricades, temporary covering of exposed areas, and temporary services or connections for electrical and mechanical utilities as required.
Note - Use electric (non-gasoline) powered drying equipment such as leaf blowers.
Protect any HVAC air intakes from sucking in exhaust, odors or fumes.
f. Protection of Personnel Before, during and after performance of the work, the Contractor shall continuously evaluate the condition of the work area and take immediate action to protect all personnel working in and around the work site, including parked vehicles. Follow all federal requirements including OSHA, and notify the GSA Project Manager immediately of any incidents.
D. MECHANICAL AND ELECTRICAL OUTAGES
Any required outages (HVAC, electrical, water, etc.,) shall be requested a minimum of seven (7) calendar days in advance of the desired outage date. Submit outage requests to the GSA project manager. Approval is required before work can proceed.
E. GOVERNMENT-FURNISHED SERVICES
1. All reasonable quantities of government-provided electricity and water shall be made available to the Design-Builder without charge. The Design-Builder shall not tamper with, connect or access any Government communication facility, equipment or cable without express written consent from the Contracting Officer. Any temporary connections or lines that may be required shall be installed, maintained, and removed by the Design-Builder at his expense and in a manner satisfactory to the Contracting Officer. The Design-Builder shall remove all temporary connections and lines prior to final acceptance of the construction.
2. On-site parking and materials storage will be made available for the Design-Builder. The Design-Builder must coordinate with the GSA Project Manager to identify specific locations and areas. This will be discussed at the pre-proposal conference.
F. PROHIBITED USE
1. Design-Builder employees are prohibited from using toilet facilities in the building during the construction phase. The Design-Builder must make other arrangements for toilets needed by employees. Location of any portable toilets is to be discussed at the pre-proposal conference.
2. The Design-Builder is prohibited from using existing dumpsters at the facility for removal and disposal of materials associated with the project. Location of any construction containers or dumpsters is to be discussed at the pre-proposal conference.
3. The Design-Builder’s employees will be allowed to park on site, in an area/parking spots as determined by the GSA Project Manager. Location will be discussed at the pre-proposal conference.
4. Construction materials including palletized items must be stored off site in a climate controlled secure location of the Design-Builder’s choosing. All roofing materials must be stored per the manufacturer’s specifications. (Note - the Government cannot prepay for materials.) Only materials in use will be allowed on site. If roof storage is not possible, then a small area secured by a temporary chain link fence will be permitted. Location TBD by the Government
5. Smoking, vaping, and music players are not allowed.
6. Harassment of any Government employees, such as whistling, etc will not be tolerated. Any workers participating in such behavior will be removed from the project. This included speaking to, questioning, video recording or photographing any Government employees.
G. DEMOLITION AND REMOVAL
1. Any demolition or removal of building components required for completion of the work shall be completed in a safe manner and in accordance with 29 CFR 1926.
2. Demolition of roof cover materials shall comply with 29 CFR 1926.1101(g)(8)(ii) at minimum.
Where requirements of local authorities exceed the cited federal regulation, the local requirements shall govern.
3. Construction and Demolition (C&D) Waste Progress Report: After the start of construction, submit monthly waste diversion progress reports. The reports shall include the following information at minimum:
a. Material category
b. Generation point of waste (Building address)
c. Total quantity of waste in tons. Include waste hauler receipts for materials disposed and diverted during project performance.
d. Landfill and incinerator disposal records indicating receipt and acceptance of waste by licensed landfills and incineration facilities. Include manifests, weight tickets, receipts and invoices.
e. Quantity of waste salvaged, both estimated and actual tons.
f. Quantity of waste recycled, both estimated and actual tons. Data should also include recycling and processing facility records indicating receipt and acceptance of recyclable waste by a licensed facility. Include manifests, weight tickets, receipts and invoices.
g. Total quantity of waste recovered (salvaged plus recycled) as a percentage of total waste.
h. Pay requests will not be processed without the proper waste diversion documentation.
4. When actual weights are not known, the Design-Builder must use volume-to-weight conversion factors such as:
a. California State CalRecycle Conversion Factors at http://www.calrecycle.ca.gov/LGCentral/Library/DSG/ICandD.htm
b. U.S. EPA WasteWise Update “The Measure of Success---Calculating Waste Reduction at http://www3.epa.gov/epawaste/conserve/smm/wastewise/pubs/conversions.pdf
H. BUILDING OCCUPATION DURING CONSTRUCTION
The building will remain fully occupied during the entire construction period. Cooperate with the Building Manager during construction operations to minimize conflicts and facilitate Owner usage. Perform the work so as not to interfere with day- to-day operations of building occupants.
Comply with all guidance in the Noise Management paragraphs of this Statement of Work.
Maintain existing exits unless authorized by GSA.
I. WORK HOURS FOR ON-SITE CONSTRUCTION
1. The normal work hours for the performance of all work under this contract will be from 7:00 a.m.
to 4:30 p.m. The workdays will be Monday through Friday, with Federal holidays excluded. Work which disrupts the operations of building occupants or causes them unreasonable discomfort shall be performed outside of normal work hours and/or normal work days. The Design-Builder must identify and execute these requirements at no additional cost to the Government. At minimum, the Design-Builder shall comply with the criteria specified in the following paragraph entitled Noise Management.
2. Alternate work hours and workdays require written permission of the Contracting Officer. The Design-Builder must submit a written request for permission to work outside of normal work hours and workdays to the Contracting Officer at least three (3) working days in advance of the date when the Design-Builder desires to deviate from the normal hours and days. Permission to deviate will be predicated on complete justification for the request after due consideration to a larger work force and more equipment during normal hours, and providing the contractor defrays the additional costs to the Government including, but not limited to, inspection computed in accordance with existing Government regulations.
J. NOISE MANAGEMENT
1. Noise Control: Perform construction and repair operations to minimize noise. Work which exceeds 80dB for more than 3 minutes in any hour, 70 dB for more than 12 minutes in any hour, or 65 dB for any longer duration in any hour when measured at any occupied location must be performed outside of normal working hours.
2. In the event the existing local ambient noise level exceeds the maximum allowable receiving noise level (dB), the noise level from construction operations shall be adjusted by a maximum 5 additional dB above the local ambient.
3. Provide equipment, sound-deadening devices, and take noise abatement measures that are necessary for compliance.
http://www.calrecycle.ca.gov/LGCentral/Library/DSG/ICandD.htm http://www3.epa.gov/epawaste/conserve/smm/wastewise/pubs/conversions.pdf
4. When compliance with these criteria is in question, the Design-Builder shall monitor noise produced from applicable construction operations in accordance with ASTM E 1780.
K. SECURITY REVIEWS AND BADGING
1. All personnel performing work on the project site must obtain an Enter on Duty (EOD) determination before they will be granted site access. This process is lengthy and can take up to 3 months. The GSA Project Manager is the security clearance sponsor. The Design-Builder is to designate one administrative employee to be their point of contact. It is the DB’s responsibility to take the free training and understand the process, what is required of them for contractor clearances and to return all badges to GSA for the Homeland Security Presidential Directive 12 (HSPD-12). Requirements and procedures for obtaining these security clearances are set forth in Article III.N of the contract. Additional information can be found at:
http://www.gsa.gov/portal/category/26757.
2. All subcontractors will be listed on the Design-Builder’s ROCAL spreadsheet. This includes full legal names and company.
3. All workers needing interior building access will be required to get a Tier 2 HSPD12 badge.
4. The Government is not responsible for any schedule delays caused by the Design-Builder not completing the security clearance process in a timely manner.
5. The IRS may have separate security requirements, such as escort by an IRS staff member.
6. The Design-Builder will be responsible for providing easily recognizable means for identifying their staff / workers at all times while on site. This may be accomplished by a company issued ID badge, company logo t-shirt worn while on site, etc.
L. QUALITY CONTROL
1. The Design-Builder shall provide a quality control program encompassing: selection of construction materials and sources; suppliers; subcontractors; on-site and off-site fabrication of contractor-furnished assemblies; on-site and off-site assembly; erection; work procedures;
workmanship; inspection; and testing. The Design-Builder's program shall provide document systems ensuring that quality provisions of contract schedule, specifications, and drawings have been performed. The program shall include, but not be limited to, the specific quality control requirements as specified in this scope of work.
2. The Design-Builder shall complete the attached daily inspection report for roofing and submit copies to the GSA Project Manager in pdf format at the end of each week. (The attachments are provided for reference. An Excel spreadsheet version will be provided to the Design-Builder upon contract award.) The Design-Builder shall supplement the report with any additional information required by the roof cover manufacturer.
3. Any inspections or monitoring of the Design-Builder’s work by Government personnel shall not be construed as acceptance of the work or to relieve the design-builder of responsibility for meeting all of the quality control requirements of the contract. This included inspection by a CMa.
4. It is the Design-Builder’s responsibility to verify weather conditions prior to each day's work start and record the temperature high/lows, humidity and forecast on the daily log.
5. The Design-Builder will be liable for any damage caused by water intrusion that is a result of removing the existing roof and leaving the area unfinished/unprotected.
6. It is the Design-Builder’s responsibility to protect any drains, pipes, scuppers, etc from construction debris, screws/bolts, hand tools or trash.
http://www.gsa.gov/portal/category/26757
M. CONTRACTOR-FURNISHED CONSTRUCTION SURVEILLANCE SYSTEM
1. The Design-Builder shall provide an internet-based web-camera system to allow surveillance of all activities on the roofs required for project completion. The Design-Builder shall be responsible for installing web cameras and related equipment, setting up web service for the cameras, and maintaining the service through project completion.
2. The web-cameras shall automatically take high-resolution digital color pictures of 3.0 megapixels or greater at 15-minute intervals or less. The web cameras must take these pictures from at least two opposite vantage points for each area where work is performed. The images shall be available 24-hours every day of the week through a web service. The web service shall provide software allowing the Government to view pictures based on camera, date, and time of picture. The software shall also allow the Government to zoom in on any area of the picture and enlarge it by 500 percent or more. In addition, the software shall allow the Government to print and save pictures on the computers of Government users.
3. The website shall require password log-in to view the images of project progress.
4. Upon completion of the project, the Design-Builder shall furnish the Government with all pictures on flash drives, compact discs (CDs), digital video discs (DVDs), or similar digital storage media.
N. PRE-CONSTRUCTION CONFERENCE
1. Prior to the start of any on-site work, the Design-Builder and the Government shall meet via video conference to confirm that the Design-Builder has properly planned and coordinated construction activities and clearly comprehends the construction administration requirements of the contract. During this conference, the Design-Builder may discuss any issues affecting the prosecution and completion of the work. The following items will be discussed at minimum:
a. Drawings, specifications, and other submittals related to the work;
b. Removal and installation of materials;
c. Contractor's plan for coordination of the work by the various trades involved in the project;
d. Quality control; and
e. Safety requirements.
f. Security requirements.
g. Schedule.
2. Before beginning any work, provide a copy of meeting notes and action items to all parties attending the conference. Note action items requiring resolution prior to start of roof work.
O. PROGRESS REPORTS
1. The Design-Builder shall submit to the GSA project Manager a roof progress report every week, at minimum, that includes a drawing illustrating the areas and locations of completed work with photographs. A report must be submitted in conjunction with each payment application. However, a report is required every week regardless of whether a payment application is submitted. The report must contain a 2 week planned look ahead.
2. A progress report will also be required for the remainder of the scope of work, every two weeks.
3. All progress will be discussed at the project progress meetings via video conference, at a minimum every two weeks. Date/time TBD.
P. WARRANTY
1. Upon completion of work in which an entire roof section is replaced, the Design-Builder shall provide a twenty-year (20-year) No-Dollar-Limit (NDL) warranty on both materials and workmanship. The warranties shall include wind riders to cover damage caused by wind up to the design wind speed or up to 140 miles per hour, whichever is less.
2. The warranties shall include wind riders to cover damage caused by wind speeds up to one-hundred forty (140) miles per hour or up to the design wind speed for the location, whichever is less. The warranties shall also include removal and re-installation of any equipment or building components that are required to complete warranty repairs. The warranties shall be issued directly to the U.S. General Services Administration.
3. If non-destructive surveys by the Government indicate the presence of wet roof components beneath roof membranes during the first two years after acceptance of the work, the Design-Builder shall verify the presence and extent of moisture and shall replace wet insulation and wet cover boards. The Design-Builder shall also repair or replace defective membrane areas at no cost to the Government.
4. Standard manufacturer's or contractor's warranties of not less than two (2) years shall be provided for other materials and components installed under this project.
5. Place a copy of each roof warranty in a transparent document holder and mount on the access door to the applicable roof area.
6. Provide written warranty documents for the remainder of the scope of work. These items are considered close out documents. The final payment will not be processed until receipt.
Q. FINAL INSPECTION
1. A final onsite inspection shall be conducted by Government and contractor personnel prior to acceptance of the work by the Government. The design-builder shall notify the Government when the project is within ten (10) workdays of completion. The notice shall indicate the desired date for the final inspection. The notice shall also include documentation from a separate pre-final inspection conducted solely by Design-Builder personnel identifying the deficiencies discovered during this inspection, their current status, and actions that will be taken to correct any remaining punchlist items prior to the desired final inspection date with the Government.
2. The Design-Builder shall also provide GSA the following documents prior to the final roofing system inspection:
a. Roofing system manufacturer's inspection report.
b. Sealant manufacturer's inspection report.
c. A copy of the sealant field-adhesion-test log.
d. Report with results of tests on roof anchors.
3. The Government will coordinate and schedule the final inspection upon receipt of the notice and supporting documentation.
R. CLOSE-OUT
Submit the following in Adobe Acrobat “pdf” format prior to application for final payment. Warranty documents shall be submitted in both “pdf” and hardcopy formats:
1. Maintenance Manuals: Assemble operation and maintenance data and copies of warranties into manuals, organized by system components as appropriate and using specification numbers where applicable. Place all documentation in 3-ring binders. Provide two (2) separate binders for roof system, electrical breakers, and fire alarm system. (Six (6) binders total.) Include the following in each manual at minimum.
a. Directory: Names, addresses,…
This is the start of the file's text. The full file is on GovTribe.