Contractor Pricing Template_Memphis IRS.xlsx

XLSX spreadsheet 76 KB Posted

Attached to
IRS Memphis, TN Design/Build Replacement of Roofs, Electrical Breakers and Fire Alarm System Construction Project
Solicitation number
47PE0325R0007
Issued by

About this file

This document is a Contractor Pricing Template for a Design-Build project at the Memphis IRS Service Center, involving roofing, electrical breaker, and fire alarm system repairs and replacements. The pricing template breaks down potential costs across multiple divisions including general requirements, existing conditions, metals, wood/plastics, thermal/moisture protection, electrical, communications, and electronic safety systems. The project involves three primary work items: roof repairs/replacements, electrical breaker repair/replacement, and fire alarm system replacement, with an additional optional fourth work item for roof replacement. The template provides a comprehensive cost breakdown structure that includes direct costs, contractor contingency, prime contractor markup, developer fees, escalation, and owner contingency, allowing detailed financial modeling for the proposed construction project. Specific component cost breakdowns are included for roof replacement (membrane, copings, flashings) and fire alarm system components (control panels, detectors, pull stations, wiring).

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contractor Pricing Template

Page1.0of1
Contractor Pricing Template
Project:MEMPHIS IRS SERVICE CENTER
ROOFING, ELECTRICAL BREAKER, & FIRE ALARM SYSTEM REPAIR & REPLACEMENTSubject of Negotiation:Above Prospectus Design Build Procurement
Basic or Other Services:
Design Build ServicesCONTRACTOR PROPOSAL
Project Stage:
Date of Proposal:
Contractor:
DIRECT COST BREAKDOWN BY DIVISION WORK TYPE
%ShellTITotal
1Division 01 - General Requirements
2Division 02 - Existing Conditions
3Division 05 - Metals
4Division 06 - Wood, Plastics, & Composites
5Division 07 - Thermal & Moisture Protection
6Division 26 - Electrical
7Division 27 - Communications
8Division 28 - Electronic Safety & Security
9DIRECT SUBTOTAL BY DIVISION WORK TYPE
TOTAL COST SUMMARY
COST ELEMENTSUnitShellTITotal
10Direct Costs
11Contractor Contingency
12Subtotal
13Prime Contractor Markup

Includes:

- Home Office Overhead - Jobsite Overhead for General Conditions

- Profit - Bond & Insurance - Professional Services

14CECA (Current Estimated Cost of Acquisition)
15Developer Fee
16Subtotal - Developer
17Additional Market Escalation
18ECCA (Escalated Current Cost of Acquisition)
19Owner Contingency
20ECC (Estimated Construction Cost)

21 Design

22 ETPC (Estimated Total Project Cost)

TOTAL COST BREAKDOWN BY WORK ITEM
%ShellTITotal
23Work Item #1:Roof Repairs and Replacements
24Work Item #2:Electrical Breaker Repair & Replacement
25Work Item #3:Fire Alarm System Replacement
26SUBTOTAL BY WORK TYPE COSTS
24Option Not Included in Total Cost Summary
25Work Item #4:Option 1 - Additional Roof E Replacement
COST BREAKDOWN BY COMPONENT
ROOF REPLACEMENT COMPONENTSUnitQuantityRateAmt. ($)
Roof Membrane ReplacementSF
Base/Thermal/Moisture ProtectionLS
Metal Copings & FlashingsLF
Expansion JointsLF
Joint SealantsLF
Demolition & DisposalLS
SUBTOTAL OF COMPONENT COSTS
FIRE ALARM COMPONENTSUnitQuantityRateAmt. ($)
Fire Alarm Control PanelsEA
Addressable Smoke DetectorsEA
Duct Smoke DetectorsEA
Heat DetectorsEA
Pull StationsEA
NAC Devices & WiringLF
Communications WiringCLF
Labor & InstallationHRS
SUBTOTAL OF COMPONENT COSTS

SUBTOTAL OF ALL COMPONENT COSTS

ESTIMATE ASSUMPTIONS & NOTES
26
28Note:
29
30Prepared By:
GENERAL SERVICES ADMINISTRATION SOUTHEAST SUNBELT REGION

File details come from the government source that posted it. Updated .