This document is a Contractor Pricing Template for a Design-Build project at the Memphis IRS Service Center, involving roofing, electrical breaker, and fire alarm system repairs and replacements. The pricing template breaks down potential costs across multiple divisions including general requirements, existing conditions, metals, wood/plastics, thermal/moisture protection, electrical, communications, and electronic safety systems. The project involves three primary work items: roof repairs/replacements, electrical breaker repair/replacement, and fire alarm system replacement, with an additional optional fourth work item for roof replacement. The template provides a comprehensive cost breakdown structure that includes direct costs, contractor contingency, prime contractor markup, developer fees, escalation, and owner contingency, allowing detailed financial modeling for the proposed construction project. Specific component cost breakdowns are included for roof replacement (membrane, copings, flashings) and fire alarm system components (control panels, detectors, pull stations, wiring).
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contractor Pricing Template
| Page | 1.0 | of | 1 | |||||
| Contractor Pricing Template | ||||||||
| Project: | MEMPHIS IRS SERVICE CENTER | |||||||
| ROOFING, ELECTRICAL BREAKER, & FIRE ALARM SYSTEM REPAIR & REPLACEMENT | Subject of Negotiation: | Above Prospectus Design Build Procurement | ||||||
| Basic or Other Services: | ||||||||
| Design Build Services | CONTRACTOR PROPOSAL | |||||||
| Project Stage: | ||||||||
| Date of Proposal: | ||||||||
| Contractor: |
| DIRECT COST BREAKDOWN BY DIVISION WORK TYPE | |||||
| % | Shell | TI | Total | ||
| 1 | Division 01 - General Requirements | ||||
| 2 | Division 02 - Existing Conditions | ||||
| 3 | Division 05 - Metals | ||||
| 4 | Division 06 - Wood, Plastics, & Composites | ||||
| 5 | Division 07 - Thermal & Moisture Protection | ||||
| 6 | Division 26 - Electrical | ||||
| 7 | Division 27 - Communications | ||||
| 8 | Division 28 - Electronic Safety & Security | ||||
| 9 | DIRECT SUBTOTAL BY DIVISION WORK TYPE |
| TOTAL COST SUMMARY | |||||
| COST ELEMENTS | Unit | Shell | TI | Total | |
| 10 | Direct Costs | ||||
| 11 | Contractor Contingency | ||||
| 12 | Subtotal | ||||
| 13 | Prime Contractor Markup |
Includes:
- Home Office Overhead - Jobsite Overhead for General Conditions
- Profit - Bond & Insurance - Professional Services
| 14 | CECA (Current Estimated Cost of Acquisition) |
| 15 | Developer Fee |
| 16 | Subtotal - Developer |
| 17 | Additional Market Escalation |
| 18 | ECCA (Escalated Current Cost of Acquisition) |
| 19 | Owner Contingency |
| 20 | ECC (Estimated Construction Cost) |
21 Design
22 ETPC (Estimated Total Project Cost)
| TOTAL COST BREAKDOWN BY WORK ITEM | ||||||
| % | Shell | TI | Total | |||
| 23 | Work Item #1: | Roof Repairs and Replacements | ||||
| 24 | Work Item #2: | Electrical Breaker Repair & Replacement | ||||
| 25 | Work Item #3: | Fire Alarm System Replacement | ||||
| 26 | SUBTOTAL BY WORK TYPE COSTS |
| 24 | Option Not Included in Total Cost Summary | |
| 25 | Work Item #4: | Option 1 - Additional Roof E Replacement |
| COST BREAKDOWN BY COMPONENT | |||||
| ROOF REPLACEMENT COMPONENTS | Unit | Quantity | Rate | Amt. ($) | |
| Roof Membrane Replacement | SF | ||||
| Base/Thermal/Moisture Protection | LS | ||||
| Metal Copings & Flashings | LF | ||||
| Expansion Joints | LF | ||||
| Joint Sealants | LF | ||||
| Demolition & Disposal | LS | ||||
| SUBTOTAL OF COMPONENT COSTS | |||||
| FIRE ALARM COMPONENTS | Unit | Quantity | Rate | Amt. ($) | |
| Fire Alarm Control Panels | EA | ||||
| Addressable Smoke Detectors | EA | ||||
| Duct Smoke Detectors | EA | ||||
| Heat Detectors | EA | ||||
| Pull Stations | EA | ||||
| NAC Devices & Wiring | LF | ||||
| Communications Wiring | CLF | ||||
| Labor & Installation | HRS | ||||
| SUBTOTAL OF COMPONENT COSTS |
SUBTOTAL OF ALL COMPONENT COSTS
| ESTIMATE ASSUMPTIONS & NOTES |
| 26 |
| 28 | Note: |
| 29 | |
| 30 | Prepared By: |
| GENERAL SERVICES ADMINISTRATION SOUTHEAST SUNBELT REGION |