10 - Soliciation RFI Questions and Responses Log Memphis IRS Design Build 2026 02 02.pdf

PDF 138 KB Posted

Attached to
IRS Memphis, TN Design/Build Replacement of Roofs, Electrical Breakers and Fire Alarm System Construction Project
Solicitation number
47PE0325R0007
Issued by

About this file

This is a Request for Information (RFI) document containing 179 numbered questions and government responses regarding a Design-Build Solicitation for the IRS Service Center in Memphis, Tennessee (GSA Building #TN0005ZZ, Solicitation #47PE0325R0007). The solicitation closes on January 16, 2026, with responses issued on February 2, 2026.

The project encompasses three primary scopes: roofing system replacement across multiple building modules (A, D-F, E, G-H, and I), fire alarm system replacement and upgrade, and electrical breaker refurbishment and replacement. For roofing work, contractors must replace standing seam metal roofs on designated areas with 80-mil TPO systems per ASHRAE 90.1, replace metal coping with new standing seam copper (16 oz minimum) or aluminum (0.040-inch minimum), improve roof drain configurations, and perform pre- and post-project drain video inspections. The fire alarm system replacement involves a full system replacement with emergency voice evacuation capability (not horn/strobe only), parallel installation with the existing Simplex 4100 addressable system until new system acceptance, 3/4-inch conduit requirements for all cabling, and integration with fire suppression systems, HVAC, security/access controls, and emergency generators. For electrical work, the contractor must procure new breakers, perform breaker reconditioning following a 12-step process, complete coordination studies, and provide NETA-certified acceptance testing. The total suggested project duration is 1095 calendar days, though contractors may propose reduced schedules. All work must maintain the facility in a watertight condition daily, coordinate with occupants for overhead work, and comply with Core Building Standards guidance and most current code editions at contract award. Restricted areas (Data Center J & K modules, Childcare E Module) require prior coordination and escorts, available at no cost during normal business hours (7:00 a.m. to 4:00 p.m., Monday through Friday) or at $40.76 per hour for after-hours access. The government will provide all necessary escorts during standard duty hours and provide monitoring service for the fire alarm system upon completion.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2/2/2026 4:31:02 PM

IRS SERVICE CENTER MEMPHIS, TN

Design Build Solicitation Memphis, TN

Close Date: 1/16/2026 Response Date 02/02/2026

GSA Building # TN0005ZZ Solicitation #: 47PE0325R0007

Number of Items: 179

Request For Information (RFI)

Number Document/ Section Additional Data Request for Information GSA Team Response

Have any roof cores been taken of the current roofing system? Is so, can you please provide?

No.

Has hazardous material testing been done for the existing roofing and flashing system? If so, can you please provide?

No, there has not been any "Hazardous material testing" to the existing roof.

IRS

Has an infrared survey been done on the proposed roof areas? If so, can you please provide?

No, there has not been any Infrared survey done to the existing roof.

IRS

Can we obtain copies of the previous reroofing project drawings and specifications?

All drawings that can be provided have been uploaded to the contractor files folder

Will cad or revit files be available of the current facility site, floor, ceiling ad roof plans for our use on this project?

The successful contractor will have access to the existing as-builts to scan and use as the basis for the necessary design.

Can the staging area and route for construction be illustrated and clarified on a site plan? This will include routes from roof areas E, H and A to the allocated staging area.

See staging/route map attached to the Contractor Files Folder.

IRS

Will the lightining protection system replacement/renovation for the designated roof areas be included in the project's scope?

See SOW Section 1, C, M, 1:

Remove and reinstall all electrical conduit and wiring on roof surfaces and associated components as required to accomplish roof work, including any lightning protection. Comply with UL, IEEE, and NEC requirements when reinstalling electrical components

RSME

Are standing seam metal roofs on G-H and D-f to be replaced in the scope of work?

Yes.

RSME

Will the roofing assembly be required to meet an FM Global Roof Nav Assemble?

If so can this be provided. Recent changes to this area by FM Global has designated this area to be Very Severe Hail (VSH) and a higher wind speed requirement since the previous roofing project was done.

The roofing assembly shall meet the most recent standards and requirements.

RSME

10 SOW Section 1.B.3. Applicable Criteria

Are the requirements of all applicable codes, standards, criteria, and policy limited to those within the Core Buildings Standards Memo dated 24FEB2025 by C.

Hardy? If not, can a comprehensive list of such applicable codes, standards, criteria, and policy be provided prior to bidding?

Further guidance has been provided regarding FA requirements in the document titled: REV-[28 3176][28 3164] - [FIRE ALARM AND VOICE EVACUATION SYSTEM][FIRE DETECTION AND FIRE ALARM SYSTEM] - FINAL 231110.docx

11 SOW Section 1.C.

3.7

Specification Applicability

GSA Fire Alarm Specifications have not been included in the SOW documents, and have a significant number of cost impacting requirements beyond that contained within this SOW. If this document is applicable, will the GSA Fire Alarm Specification be provided prior to bidding?

GSA Fire Alarm Specs will be provided prior to bidding for review. Please note these are template specifications which has items in brackets [ ] which need to be edited to be project specific by the selected DB contractor. JDW

12 SOW Section 3.G.

2.b Drawing Updates

No drawings were provided electronically in order to verify prior to bid.

Additionally, the drawings provided for viewing were over 30 years old, and may have been superseded by other projects, whose drawings were not provided. Is the DB Contractor responsible for updating all drawings for which they were not provided? If the DB Contactor is only responsible for the update of the drawings within their scope, what are the drawings to be updated? Can reference drawings be released on SAM.gov or the Project Shared Drive for bidding purposes?

The intention of this paragraph is to forewarn the contractor to field verify any information that has been provided by the government. The contractor is only required to provide accurate drawings that pertain to the contracted SOW.

13 SOW Sections 3.H.

3.a and 3.H.4.a.

Drawing Updates No electronic copies of the existing plans to be updated have been provided prior to bid. Which items expressly identified in the SOW will need to be updated on the existing drawings required to be updated?

The contractor is only required to update/provide accurate drawings that pertain to the contracted SOW. The successfull contractor will be provided physical copies of as-built drawings to digitize and use as a starting point for this effort.

14 SOW Section 3.H.4.

a.

Drawing Updates At the Site Visit, it was noted that the existing fire alarm system could not be replaced in a phased manner, but rather in a parallel manner. What updates for existing drawings are required to update drawings for a new system?

The new design documents should acurately show the new fire alarm system as it interacts with the existing space and building components. Teh design should also show a demolition plan for the old system.

SOW Section 3.I.6.

f.

Warranty Start Date

This section requires the warranty documents to be delivered during the design development stage. If the warranty documents must be delivered at the design development stage, prior to the final design, and prior to construction beginning, Is this the start of the one year warranty period?

Warranty period starts after sustantial completion and acceptance by the client.

JAIII

SOW Section 3.I.8

Potential Typo This section states 75% submittal, but the subject phase is identified as 95%. Is this a typo that should read 95%?

This is a typo that should read 95%

SOW Section 3.J.8

Potential Typo This section states 90% submittal, but Design Development/Initial Construction Document phase is identified as 95% is this a typo that should read 95%?

This is a typo that should read 95%

SOW Section 4.

Ambiguous Section Title

This section is noted as roof covering performance, but contains fire alarm field quality control elements. Should the fire alarm be listed in a separate section or considered as part of the roof cover technical requirements?

A separate section for Fire Alarm Quality control would be most appropriate, however the testing requirements do not change.

SOW Section 4.K.4.

Ambiguous Section Title

The fire alarm tests are included with the the tests of the roof components.

Should the fire alarm be listed in a separate section or considered as part of the roof cover technical requirements?

A separate section for Fire Alarm Quality control would be most appropriate, however the testing requirements do not change.

SOW Section 4.K.4.

a.

Supervisor ID

The DB FPE and the Supervisor are required to be in attendance at the preliminary testing and sign off on the Certification letter. To which Supervisor does this requirement refer?

Typically this is the site Supervisor/Foreman.

JDW

21 SOW Section 4.K.4.

e.12.

Trouble Condition Testing

What are the trouble conditions specified? Which wiring Classification is specified for which circuit pathways? Also, is there a typo for a separate requirement to visually inspect the wiring?

Test trouble conditions specified in NFPA 72 Table 14.4.3.2 including but not limited to disconnect/isolating switches, ground faults, short circuits, battery failure, AC power failure, etc.

JDW

22 Contractor Files Attachment 05

CBS vs P100 Applicability

Attachment 05 refers to the P100 Project Delivery Matrix, and is expressly noted as being part of P100. Does this requirement still apply in light of the 24 Feb 2025 C. Hardy CBS Memo?

The CBS Memo will take precedence.

FIRE ALARM SYSTEM

As built drawings and device schedules – Are detailed as built floor plans available for the existing fire alarm system showing device locations, circuit loops, control panels, remote annunciators, and notification appliance circuits? If so, can we obtain a copy under secure conditions?

All available fire alarm as-builts were made accessible during the pre-proposal site visit and on a subsequest date during the following week.

FIRE ALARM SYSTEM

System type and technology – What is the make/model and addressability of the existing fire alarm control panels? Does the current system use voice evacuation, horns, and strobes, or speaker strobes? Are there special detection systems (e.g., beam detectors, aspirating detectors) in critical spaces such as the computer room or raised floors?

Simplex 4100. System is addressable and voice evac system. See points list for list of initiating devices.

JDW

FIRE ALARM SYSTEM

Zoning criteria – How are zones/loops currently defined (e.g., by building module, floor, or hazard type)? Will the new system maintain the same zoning configuration, or are revisions expected? Please provide a zone list with area names, approximate square footage, and occupancy type so we can estimate conductor lengths and power loads.

Sprinkler and FA system are zoned by building. Changes to the FA zoning is not anticipated.

JDW

FIRE ALARM SYSTEM

Device counts per area – Please provide approximate counts of each device type (smoke detectors, duct detectors, beam or spot detectors, heat detectors, manual pull stations, monitor modules, control modules, speaker strobes, strobes only, horn strobes, sounder bases, tamper/supervisory switches, power supplies, battery cabinets, remote annunciators). If counts are unavailable, can we schedule an escorted survey to collect this information before proposal submission?

Existing system points list will be provided. Please note that exact device count of the new system may differ based on newer code requirements or defeciencies with the existing system.

JDW

FIRE ALARM SYSTEM

Special hazard areas – Are there clean agent suppression systems or pre-action sprinkler systems serving the computer room, warehouse, or processing areas that require integration with the fire alarm system? Are there high air flow raised floors or return plenums that demand duct detectors or aspirating detection?

Any specialty suppression systems with releasing panels to be monitored by the new FA system. Duct detectors to be provided in accordance with IMC and NFPA 90A. Typically raised floor or above ceiling return air plenums are not required to have detection. Duct detectors may be required at the plenum opening or return air unit per IMC and/or NFPA 90A.

JDW

FIRE ALARM SYSTEM

Integration with other systems – Does the fire alarm panel interface with security systems, access control, elevator recall, HVAC shutdown, smoke dampers, or emergency power systems? Are there existing control modules that must be replaced and reprogrammed? Please provide a list of required interconnections and monitored functions.

FA interfaces with security/access controls, HVAC, and generator. There are no elevators.

JDW

FIRE ALARM SYSTEM

Cable installation method – In spaces with drop ceilings, can plenum rated cable be installed free air above the ceiling tiles, or is EMT conduit required for all fire alarm cabling? Are there specific areas (e.g., secure rooms, rated corridors, or high traffic areas) where conduit is mandatory regardless of cable rating?

Conduit required for all fire alarm cabling. May use EMT or RMC. Flex conduit may be used for short "whips" to ceiling mounted devices. See FA specs for more information. JDW

FIRE ALARM SYSTEM

Conduit sizes and pathways – When conduit is required, what minimum size should be used (¾ in. vs. ½ in.)? Are there existing conduit sleeves, raceways, or cable trays that can be reused, or will new pathways need to be routed through rated walls and floors? Are there restrictions on drilling or penetrating structural elements due to building security or asbestos abatement?

3/4-inch, see FA specs for more information.

Existing conduit sleeves, reaceways, or cable trays may be reused as long as conduit fill is in accordance with NFPA 70. Existing wiring to remain until the new system is fully comissioned/accepted.

JDW

FIRE ALARM SYSTEM

Use of raised floor plenums – In the areas with raised floors, are we permitted to run fire alarm cabling beneath the floor or within the ducted cavities? Are the hatches large enough for access, and will we need to remove floor tiles or coordinate with IT/operations staff to access cables?

Fire alarm cabling may only be routed beneath raised floor for devices located in raised floor. Wiring serving all other devices to be routed above ceiling. JDW

FIRE ALARM SYSTEM

Ceiling construction and mounting heights – For each area, please clarify the ceiling type (lay in acoustical tile, gypsum board, hard lid, open structure) and the approximate height so we can determine lift/scaffolding requirements and estimate conductor runs. We observed drop ceiling heights of 8′, 10′, 12′, and 15′ during the walk through.

All available fire alarm and architectural as-builts were made accessible during the pre-proposal site visit and on a subsequest date during the following week.

GENERAL

Work area accessibility – Are there restricted zones requiring escorts (e.g., data centers, secure storage, IRS operations)? Will escorts be available during normal work hours, and how must we schedule access? Are there times when work in specific areas is prohibited due to mission critical operations or tax payer data processing?

Yes, there are restricted areas (Data Center J & K modules, Childcare E Module). Proper scheduling and coordination needed for secured area access. Escorts will be available witth prior planning and coordination. IRS

GENERAL

Temporary facilities – We understand that the Design Builder may not use existing restrooms or dumpsters and must provide portable toilets and waste containers. Can we locate these near the laydown area? Are there any restrictions on bringing water or power onto the site for temporary trailers or equipment?

Dumpsters/Porta potties can be stationed at the staging area. There are no restrictions for bringing water and power onsite.

IRS

GENERAL

Occupant coordination – What are the procedures for notifying occupants when work will occur in their areas? Will occupants need to vacate rooms while devices are replaced, or can work occur overhead with shielding? How much notice is required before interrupting operations?

Proper scheduling is necessary for the relocation of employees during overhead work.

Employees will be moved during overhead work. A schedule of work should be provided at the beginning of the project to provide adequate time for coordination. IRS

FIRE ALARM SYSTEM

Parallel installation – The scope indicates that the new system will be installed in parallel with the existing system until completion. Will we be required to energise and test circuits as they are installed or wait until final cutover? Should we plan for dual devices (existing and new) to remain in place temporarily, and will ceiling tiles need to be removed and reinstalled twice?

Final means/methods for energizing and testing the new system is up to DB contractor. The existing system needs to be maintained in its entirety until the new system is fully comissioned/accepted. Dual devices will be in place until the new system is accepted and demolition can start on the existing system. The GSA FPE will not witness final testing until the entirety of the new system is pretested with appropriate documentation submitted for review.

JDW

FIRE ALARM SYSTEM

Interim monitoring – During the installation phase, who will monitor and respond to alarms from the existing system? Will the new panel need to monitor the old system or vice versa to maintain life safety coverage? Are there concerns about nuisance alarms or cross talk between systems?

Systems should be completely separate with little to no cross talk. The existing system will be monitored by the existing monitoring company.

DB Contractor will be responsible for confirming monitoring capabilities of the new panel (i.e., POTS vs cell vs IP). GSA to provide monitoring service and connection.

JDW

FIRE ALARM SYSTEM

Cutover sequence – How will the final cutover be scheduled? How will testing and acceptance be conducted to minimize disruption to the IRS operations? The quality control section indicates that a complete (100%) final test must be performed and documented; please confirm who must witness each test and whether after hours testing will be required.

This is a full system replacement. The existing and new systems will be installed in parallel so there should not be much, if any, final cutovers required. Final means/methods for testing is up to the DB contractor. As long as the GSA FPE receives proper documentation from the pretest it does not necessarily have to happen concurrently.

JDW

FIRE ALARM SYSTEM

Authority Having Jurisdiction (AHJ) – The documents state that the GSA Region 6 Fire Protection Engineer will serve as the AHJ. Will local Memphis Fire Department officials also review and approve the design, or does GSA approval supersede local jurisdiction? Should the system conform strictly to NFPA 72/70/local codes, or will federal/GSA criteria trump local requirements?

GSA FPE approval will supersede local jurisdiction. Local Memphis Fire Department will be give a courtesy review and will be invited to participate in an on-site walkthrough if requested. Final approval from Memphis FD is not required.

Local requirements above and beyond federal/GSA criteria will be considered on a case by case basis with final determination by GSA FPE.

JDW

FIRE ALARM SYSTEM

Code version and standards – Which edition years of NFPA 70 (National Electrical Code), NFPA 72 (National Fire Alarm and Signaling Code), NFPA 101 (Life Safety Code), IBC, IFC and related standards should be used for the design? The design criteria require using the current versions at contract award— please confirm the edition adopted by the AHJ.

Use most current editions at time of award.

JDW

GENERAL

Hazardous materials – Has the pre demolition hazardous materials survey been performed? Are asbestos containing materials, lead paint, or PCB containing light ballasts present above ceilings or in cable trays that could impede installation?

Who will be responsible for abatement or encapsulation if hazardous materials are encountered?

No "Pre-demolition hazardous material survey" has been performed. All hazardous materials encountered will be he responsibility of the contractor.

IRS

GENERAL

UL/Manufacturer approvals – Do all new devices and materials need to be listed/approved for use by GSA or a specific UL listing? The specification prohibits certain products such as CFC containing insulation, adhesives containing neoprene, asbestos or lead-based materials; please confirm whether there are equivalent prohibitions for fire alarm cable (e.g., halogen free) or equipment enclosures.

For fire alarm cable - as long as the cable complies with NFPA 70 (NEC) and NFPA 72, which requires specific marking based on nationally recognized testing labs, it will be acceptable. JDW

FIRE ALARM SYSTEM

Acceptance testing – The quality control program requires independent preliminary and final testing of each device and circuit. Will the government provide test scripts or checklists? How many representatives from GSA, IRS, the fire marshal, and the design builder must witness the 100% final test, and what lead time is required to schedule them?

A checklist/template can be provided if needed. Acceptance testing to follow NFPA 72 Section 14.4.3.

At minimum, GSA FPE or authorized 3rd party must witness the 100% final test.

Any additional representatives will be coordinated when nearing project completion. Must give 2 weeks lead time for scheduling purposes.

JDW

FIRE ALARM SYSTEM

Training requirements – What level of operator training is expected for IRS facility staff? Is classroom training acceptable, or is hands on training at the panel required? How many training sessions are anticipated, and must they be recorded or documented?

See GSA FA Specification Section 3.9 for typical training requirements.

JDW

GENERAL

Record documentation – Please clarify the format and quantity of close out documents: CAD (.dwg) files, PDF record drawings, equipment warranties, operation and maintenance manuals, video or photo documentation, and other deliverables listed in the close out requirements. How many hard copy binders and electronic copies will be required, and what security protocols govern electronic data transfer?

See GSA FA Specification for typical submittal requirements.

JDW

GENERAL

RFI and communication channels – The procurement schedule notes that RFIs must be submitted via a provided spreadsheet by 13 Jan 2026, with responses by 20 Jan 2026, and that site visits are not planned nor anticipated. Are follow up RFIs after 20 Jan allowed, especially if additional information emerges during the escort survey? What is the protocol for questions arising during design that require clarification from the government?

All questions were due on 1-16-26 and a response is provided to each question via this document on 2-2-26. Additional questions after 2-2-26 can be submitted to the CO for consideration by GSA. If the CO determines a response to the question is critical to the solicitation, additional communication will be provided via amendment to the solicitation. RFIs arising during the project will be handled through a predetermined RFI process to be discussed after contract award.

GENERAL

Badging and security clearance – Security and badging can be a lengthy process.

Are background checks required for all subcontractors and vendor personnel on site, and will escorts be needed for the duration or will some badges be issued?

Will work being performed on the exterior of the facility require escorts?

We will cover HSPD12 requirements after contract award. Some personnal can be escorted or the majority will need to have passed a Background Investigation. JAIII

GENERAL

Allowances for after hours work – The noise management paragraph stipulates that work exceeding certain decibel thresholds must occur outside normal working hours. Should we include an allowance for overtime or off hour shifts in our estimate? How should we account for escort overtime and security costs outside the normal 7:00 a.m. – 4:00 p.m. window?

Most work will take place during normal business hours. Some testing and electrical shut downs may occur after hours in which case the contractor will pay the escorting service directly at a rate of $40.76/ hr JAIII

GENERAL

Material storage and staging – Since construction materials must be stored off site or in designated Laydown area, should we include rental costs for off site warehouse space and daily transport? If the government provides temporary storage space inside the building, what is its size and accessibility (freight elevator, loading dock, etc.)?

Materials do not neccesarily need to be stored off site. If the contractor chooses to store materials off site it will be at the cost of said contractor. The lay down area and size of freight elevator, loading dock were discussed and made available during the pre-proposal meeting.

GENERAL

Testing equipment and specialized tools – Will the government furnish any testing apparatus (e.g., calibrated sound level meters for noise monitoring, duct detector test pumps, NFPA 72 acceptance test equipment), or should we include the purchase/rental of such equipment in our estimate?

Contractor to provide testing equipment and specialized tools. Using the same tools used for the pretest and final test reduce the chances of differing results based on device calibrations. JDW

FIRE ALARM SYSTEM

Device mounting for pendant strobes – We observed pendant mounted strobes approximately 12 inches below the drop ceiling. Is this mounting method preferred for replacements, or will ceiling mounted or wall mounted notification appliances be acceptable? Are there ceiling structural supports or plenum obstructions that dictate pendant drops?

Ceiling/wall mounted are preferred but pendant mounting is acceptable as well in case there are ceiling obstructions that would prohibit a ceiling mount.

JDW

FIRE ALARM SYSTEM

Raised floor detection – For the raised floor areas, is under floor smoke detection required, and if so, must cable be run in metal conduit within the floor? Are there water or data lines in the raised floor that could impede installation or require shielding?

Raised floor areas to be protected based on existing devices.

JDW

FIRE ALARM SYSTEM

Fire alarm panel location – Will the new fire alarm control panel and power supplies be installed in the same room as the existing panel, or will a new equipment room be provided? Are there UPS or generator circuits available for secondary power, or must we include battery back up sized for the full 24 hour stand by and 5 minute alarm operation per NFPA 72?

DB contractor is responsible for design. GSA prefers new panels to be in the same rooms as existing panels if enough space is provided. If there are space issues DB contractor to propose alternate location. Fire rating/survivability of circuits crossing evac zones to be in accordance with NFPA 72

JDW

ELECTRICAL

BREAKERS

Figure 1 lists several “purchase for spare” and “purchase to replace existing” breakers (frames from 5,000 A down to 400 A) and shows six spare breakers already available for rotation. Please confirm the exact quantity of new breakers to be procured versus the number of IRS supplied spares that will be provided to the contractor, and provide manufacturer/model numbers, frame sizes, trip unit ratings, and plug sizes for each required breaker.

Contractor shall do site survey, part of owner requirements, to verify model/manufacture. frame, sizes,etc. Based upon figure 1, there are six breakers that shall be purchased. Please re-read owner requirements which state how the breakers will be roatated while other breakers are being refurbished from one switchgear to another.

ESME

ELECTRICAL

BREAKERS

The scope calls for supplying specific spare breakers during the rotation process (e.g., Merlin Gerin MPSF 501 5,000 A/5,000 A, Westinghouse #POW R 1009 5,000 A/3,000 A trip, #POW R 100 2,000 A/2,000 A, #POW R 100 1,200 A/1 200 A, and #POW R 100 400 A/400 A). Please confirm if these units are already owned by IRS or if the contractor must purchase them new.

Contractor must purchase

ESME

ELECTRICAL

BREAKERS

The RFP states that failed breakers shall be “reconditioned” and describes a 12 step process including disassembly, inspection, installation of new solid state trip devices (AC PRO, Eaton, or approved equal), reassembly, and primary and insulation resistance testing. Please confirm whether the contractor is to perform this reconditioning or if IRS will send the breakers to a designated service facility.

If reconditioning is to be included in the contractor’s scope, please provide the preferred refurbishment vendor(s), quality standards (e.g., NETA MTS, ANSI C37), and any required certifications.

Contractor shall provide reconditoning

ESME

ELECTRICAL

BREAKERS

Breaker replacement requires de energizing each switchboard section. Please provide the desired phasing schedule (order of modules A–H), allowable outage windows (e.g., after hours, weekends, or specific IRS blackout dates), and maximum duration per outage. Are multiple modules allowed to be out of service simultaneously?

Phasing schedule windows, and outage duration will be discussed with the awarded contractor at pre-construction because these dates and time will vary depending on the award time of the year. If needed for estimation, I would assume most outages shall be done on the weekend or holidays

ESME

ELECTRICAL

BREAKERS

Are there critical loads (servers, HVAC, security systems, etc.) that cannot be interrupted? If temporary power is required, please specify whether IRS will provide generators or if the contractor should include rental generators and cabling in the proposal.

There are systems that may not be interrupted. However, that shall be coordinated after post-award. Contractor should not include rental generators for temporary power. There is a parallell EPS system on site. ESME

ELECTRICAL

BREAKERS

To size and price the work correctly, please provide current switchgear single line drawings, bus bar layouts, and cell dimensions for each breaker position. Are there any non standard bussing arrangements, mechanical interlocks, or shutters that might require field modifications, or retrofits to accept new breakers?

One-line may be provided. However all field conditions shall be verified by contractor

ESME

ELECTRICAL

BREAKERS

Are secondary control wiring harnesses and rating plugs to be furnished by IRS or by the contractor? Should the price include new control wiring for each breaker?

No material will be provided. If the control wiring is not operational, then it shall be replaced (CDB) ESME

ELECTRICAL

BREAKERS

Many of the failed breakers were noted as “LT out of spec,” “ST out of spec,” “GF out of spec,” or “trip unit bad”. Please provide the desired long time, short time, instantaneous, and ground fault settings for each breaker after replacement or reconditioning so that new trip units can be calibrated at the factory. Is a coordination/arc flash study required as part of this scope?

A new coordination study shall be done by the awarded contractor. The EOR shall provide breaker settings.(CDB)

ESME

ELECTRICAL

BREAKERS

The SOW requires high current or static trip unit tests to verify calibration and insulation resistance tests after cleaning. Please confirm whether a third party, NETA certified firm must perform acceptance testing. What test reports and documentation are required with project closeout?

Contractor shall provide a certified NETA firm to perfom acceptance testting. A simple " PASSED" test report is sufficient on all of the tested breakers (CDB)

ESME

ELECTRICAL

BREAKERS

The summary notes that the design builder shall provide a one year warranty on all replaced breakers, including parts and labor. Are extended warranties on newly purchased breakers also required? Should the warranty period restart on refurbished breakers once they are returned and reinstalled?

no, the manufacture warranty is sufficient on newly purchased breakers, Yes the warranty period should start once the refubrished breakers a tested and operational in its original location.(CDB)

ESME

ELECTRICAL

BREAKERS

Please provide information on loading dock access, floor loading limits, path of travel from the dock to the switchgear rooms, and whether lift trucks or rigging equipment can be used within the facility. Are there working hours or security restrictions (escort requirements, badging) that must be accounted for?

You can not use a forklift in that route. However a pallet jack is acceptable.

Securtity is 24/7 and every worker has to be escorted and accounted

ESME

ELECTRICAL

BREAKERS

Are there environmental or hazardous materials (e.g., PCB oil, asbestos insulating boards) associated with the existing switchgear that the contractor should be aware of when removing and shipping breakers?

There are no enviromental hazards

ESME

ELECTRICAL

BREAKERS

After reconditioned breakers are installed, should the contractor retain or dispose of any breakers deemed non repairable? If disposal is required, please specify whether IRS will take possession of scrap metal or whether the contractor should include haul off and recycling.

Yes, the contractor shall dispose of any breakers deemed non-repairable. The IRS will expect the contractor to haul off and recycle

ESME

ELECTRICAL

BREAKERS

In addition to shop drawings and product data, are there specific drawing formats, 3D models, or coordination reviews (BIM) required? Should the contractor include updated one line diagrams and arc flash labels reflecting the new breakers?

no BIM required. However, the contractor shall included updated one-lines, arc flash, and coordination studies(CDB)

ESME

ELECTRICAL

BREAKERS

Do any of the existing breakers interface with building automation systems or protective relays? If so, please provide communication protocol requirements (e.

g., Modbus, IEC 61850) and specify whether integration programming is in scope.

No breakers interface with the BAS. The contractor shall verify any protective relays that are incorporated into the switchgear as part ot the construction pre-bid and survey. If it is verfied that there are protective realys, communication protocols shall be provided ESME

ELECTRICAL

BREAKERS

Are external accessories (bell alarms, undervoltage trips, shunt trips, auxiliary contacts) required on the new breakers?

No, replace breakers refurbished one to one, UNLESS, code requires that any external accesories be put in place(CDB) ESME

FIRE ALARM SYSTEM Some companies utilize sub labor to install fire alarm cable and device installation. Requirements for this project are that all technicians are to be UL certified, that would mean that the installing technicians have to be employed by a UL certified company and cannot be sub labor from a company that does not carry a UL certification. Is that correct?

Typically wiring and device installation is done by an electrical contractor with final terminations and programming done by a fire alarm contractor. As long as the electrical contractor has appropriate state/local certifications they may be used for general wiring and device installation work. All work done by the FA contractor to be done by UL certified compnay. FA technicians may also be NICET certified in lieu of UL certifications. JDW

FIRE ALARM SYSTEM Is the new fire alarm system to be installed in full conduit? Code does not require a full conduit system and this would be an owner preference if so.

FA system to use 3/4-inch conduit per GSA FA Specifications

JDW

FIRE ALARM SYSTEM Is there a mechanical schedule that can be made available for the existing HVAC units?

The requested inventory list has been uploaded to the contractor files folder.

FIRE ALARM SYSTEM Will there be a cost to be paid and is that value available for after-hours escorts

AS NEEDED?

There will not be any after hour escorts. The duty day is 7:00 am-4:00pm Monday thru Friday. IRS

FIRE ALARM SYSTEM Is there a limit on the number of connex that we can store on site? As long as they fit within the designated laydown area, there is no limit. It is not anticipated that space limitations will be an issue as there is ample space within the designated lay down area.

FIRE ALARM SYSTEM Are there areas of the building that can only be accessed during certain times?

Special escorting requirements etc.

All areas can be accessed during normal duty hours with adequate scheduling and escort coordination. IRS

FIRE ALARM SYSTEM Are ceiling mount devices required to be pendant mounted as currently installed? Ceiling/wall mounting is preferred but pendant mounting is acceptable in case there are ceiling obstructions that would prohibit a ceiling mount. JDW

FIRE ALARM SYSTEM The existing fire alarm system is currently a voice evac system. Code does not require this system to be voice evac, is it the desire of the owner to have a new system with voice evac or can we install an audible system using horns and strobes?

New system to be emergency voice evac system

JDW

FIRE ALARM SYSTEM Is the clean agent suppression system in the data rooms being changed in any way? Is this system functional and only to be monitored?

It is not being changed.

JDW

FIRE ALARM SYSTEM Will a fire command work center aka graphic display be required at a central location on campus?

A graphic display will be required. Final location will be determined during design phase of project. JDW

ROOFING

Please confirm existing roof core information or will there be time available to take a core?

There is no roof core information available and it will not be possible to take a core. The contractor should base their proposals on what is provided in the as-built drawings.

ROOFING

Please confirm spec for new roof system assembly. Insulation layers/thickness, attachment method, etc.

They give roof insulation in accordance with Ashrae 90.1 and 80mil TPO as guidelines but don’t clarify the full assembly requirements.

The design team will need to make this determination if it is not clearly stated in the SOW.

RSME

82 ROOFING Are there any FM requirements? There are no Factory Mutual requirements. IRS

ROOFING

Please confirm metal type/gauge/thicknesses requirements for all edge metal and flashing replacments

The design team will need to make this determination if it is not clearly stated in the SOW. RSME

GENERAL

Please confirm staging area for dumpsters, toilets, and conex/equipment temp office etc. Will electrical power be available at this location?

See attached staging/route map. No power is available at the staging area.

IRS

ROOFING

Will temp waste and restrooom facilities be allowed near roof replacement locations outside of the approved laydown?

For example, for Section E. Do we have to exit the premises and re-enter to access dumpsters at the south side of the building? Same for accessing toilets at this location.

Dumpster/Porta potties will not be allowed o be placed beside modules. Trash to be disposed of will require transport back to the staging area. See attached staging/route map.

IRS

86 ROOFING Please confirm acceptable route on property to access all roof sections. See attached staging/route map. IRS

ROOFING

Please confirm acceptable location for material upload/download points for all roof sections.

See attached staging/route map.

IRS

ROOFING

Please confirm acceptable location for exterior roof access point for all roof sections.

See attached staging/route map.

IRS

ROOFING

Are there any restrictions as to what type of equipment can be used for material upload/download?

No. All existing conditions with building exterior, landscaping and hardscaping must be preseved or restored.

ROOFING

Are there any specific safety requirements for this particular site? No. All existing conditions with building exterior, landscaping and hardscaping must be preseved or restored.

91 ROOFING Are personal vehicles for workers allowed onsite? Yes

ROOFING

Are we to replace the standing seam metal coping at Exterior walls at canteens for Building Modules A, and H, and at entrances to Building Modules E North, DF, and GH with new standing seam metal coping or can it be flat lock or traditional coping installation? Please confirm if the metal needs to be 16oz copper or .040 aluminum?

Replace standing seam metal coping adjacent to exterior walls at canteens for Building Modules A, and H, and at entrances to Building Modules E North, DF, and GH. New metal coping shall include a self-adhered modified bitumen underlayment per ASTM D1970 and a slip sheet. Copper roofing sheet materials must comply with ASTM B370 and have a minimum weight of 16 ounces per square foot (0.0216-inch thickness).

Aluminum roofing panels shall comply with ASTM B209 for 3004 alloy aluminum and have a minimum thickness of 0.040 inches. Replace copper with copper and aluminum with aluminum. Pricing should be based on what is stated in the scope of work. RSME

ROOFING

What exactly is meant by “improve roof drain configurations as required to ensure efficient drainage and to prevent ponding and leaks at drains?” What needs to be included in the scope of work for this item?

The contractor must do what is necessary to prevent water from ponding on the roof. As a design build project, this will be left to the contractor to develop a solution that provides for no standing water on the roof. RSME

ROOFING

Is any interior protection needed? It is expected that all interior space will be protected from exterior weather during the course of teh project.

ROOFING

Is there a requirment for structual engineering to evaluate the loading of roofing materials?

The design team should determine if this is necessary to provide a compliant and sound design. RSME

ROOFING

Has an asbestos report been completed? No.

IRS

97 Will the Procurement Team provide a list of general contractors who will be bidding on this project.

Yes, Information is located in the GSA Google Contractor’s Folder, as well as in the amendment documents on SAM.gov.

98 Will the Project Team provide any documents associated with this project? Yes, Information is located in the GSA Google Contractor’s Folder, as well as on SAM.gov.

99 There’s conflicting information in SF1442 & Final SOW Document, what is the Total Project Duration? (1095 or 810 Calendar Days?)

1095 is the suggested total project duration however we are open for a reduced schedule as proposed by the offeror.

100 Blue represents Penthouse wall locations, what does solid purple line represent?

Any associated SOW?

Further clarification needed

The SOW Document calls for repairing parapets on Building Module “I”, which isn’ t in the “yellow”, will all purple lines (parapets?) be included in the joint sealant replacement?

The SOW calls for the replacement of all joint sealants on all paraphets. Not just the paraphets where roof replacement is occurring.

RSME

"Section II.D.(1) requires offerors to submit 3–5 similar projects and defines “similar” as construction or renovation of a fully occupied Government facility or secure civic facility / Class A secured office space (or similar) meeting the following attributes: completed within 10 years, construction cost > $20M, gross square feet > 100K, delivered via Design/Build (or other integrated delivery), and including multiple labor categories (e.g., electrical, HVAC, general construction) We understand and respect the Government’s intent to evaluate relevant past performance based on scope, magnitude, and complexity. However, the solicitation also excludes broad project categories (e.g., dormitories/residential-type facilities, retail-focused projects, warehouse/industrial facilities), which may otherwise demonstrate comparable value, complexity, and execution risk. To support full and open competition consistent, and to ensure offerors can demonstrate relevant past performance, will the Government consider revising the relevancy definition by removing or minimizing the categorical exclusions, while retaining the objective thresholds (10-year recency, >$20M construction cost, >100K GSF, design/build or integrated delivery, and multiple trades)?"

The Government will not be revising the similar projects requirements.

JAIII

Please confirm whether a Mass Notification System (MNS) or Emergency Communications System is required as part of this project.

System to be designed as an emergency voice evacuation system with capabilities to annunciate non-fire emergency automated messages such as active shooter. Final list of automated messages will be determined during the design phase. No additional visual/textual notification is required. JDW

105 Please confirm whether any buildings within the project scope contain elevators. If elevators are present, please provide the quantity and type.

No elevators are present at this campus.

IRS

Please confirm whether the buildings within the project scope are fully sprinklered.

If the buildings are not fully sprinklered, please identify any unsprinklered areas.

In addition, please provide sprinkler system types, the presence of any fire pumps, and any special suppression systems such as clean agent or kitchen hood systems that require fire alarm monitoring or interfaces.

The building has a wet/Dry sprinkler system. The entire facvility is sprinklered. We have a fire pump in the boiler room. There are 2 kitchen fire supression systems one in A MOD and one in Child Care.

IRS

The Agreement references replacement of the “Fire Suppression System,” while the Statement of Work describes replacement of the fire alarm system. Please clarify whether this project includes any fire suppression system replacement work beyond monitoring devices.

The SOW is only to replace the Fire Alarm system which will interface with fire suppression systems. Fire Supression systems will not be replaced under this

SOW.

108 Please clarify the quantity of generators to be monitored by the fire alarm system. 16 IRS

109 Does the current roof mounted lightning protection system have a UL Master Label?

Yes, we will need to get the UL Master label recertified after the completion of roof ESME

There do not appear to be any bridging documents or as-built plans with the attachments on the SAM advertisement or in the Contractor Files shared via Google Drive. Please provide As-Built or Bridging drawings for Design Build teams to assess the scope relative to the existing buildings, review the building floor plans/layout, and provide a response to the RFP.

All available fire alarm and architectural as-builts were made accessible during the pre-proposal site visit and on a subsequest date during the following week.

There appear to be notes about the potential for CUI documents, however we do not see any of the bid documents marked accordingly as CUI for any category.

Can you confirm there are no CUI documents in the current bid set so we can determine handling restrictions for dissemination to potential vendors and consultants?

Any documents that have been provided in the Contractor Files Folder that pertain to the building scematics or provide detail regarding building components should be considered CUI.

112 SF1442 states period of performance is 810 calendar days while scope of work states 1095 with 180 days added if Option 1 is awarded. Which is correct?

1095 is the suggested total project duration however we are open for a reduced schedule as proposed by the offeror.

Will the arcflash testing being performed by the GSA interfere with any work being performed by the Contractor? Can a schedule for this work be shared with the Contractors?

Arcflash testing will not be performed by GSA. This should be contracted out to a third party testing agency.

ESME

Documents and scope narratives indicate shutdown work will need to be performed on weekends. It was mentioned during the virtual pre-proposal call that weekend work will not be allowed. Please advise how the design build contractor should structure estimate, schedule, and the proposal with respect to shutdowns, weekend work, and shift work if required.

Contractors should assume all work is to occur during normal business hours.

Work Item #2A states that the IRS has spare breakers for the EC to use as replacements for the failed breakers. Work item #2D also refers to “spare” breakers (it is assumed these are the same “spare” breakers”). It was said at the site visit that the IRS does not have any spare breakers to be used. Figure 1 – Breaker Detail also states that there are breakers on-site to be used for rotation.

Question: Does the EC provide NEW breakers to replace the failed breakers listed or are there spare breakers provided by the IRS?

EC to provide new breakers

ESME

116 Can a picture or accurate sketch be provided of a front view of at least one section of the switch gear containing the breakers being replaced?

Provided in the contractor files folder.

IRS

Is retro-filling the failed breakers an option? Eaton believes that a cheaper and better overall option will be to retro-fill the existing breaker panels and install new Magnum PXR breakers in place of the older SPDs.

Yes, this is a option. However you will need to submit a deviation request from the original scope

ESME

It was noted at the site visit that the majority of spaces include raised access floor.

Is there product information available for the current floor to determine both load ratings for equip/scaffolding and figuring allowances for replacement of damaged components? Please provide a bid quantity to assume for replacement so that all proposals are equal in terms of scope.

The government will not provide an assumed amount for broken raised floor components as this is strictly means ans methods. It should be assumed that existing conditions be preserved.

IRS

Please provide any product information available for existing ceilings in order to budget allowances for replacing existing ceiling components due to damage during renovations. Please provide bid quantities for replacement so that all proposals can contain equal scope.

The government will not provide an assumed amount for broken raised floor components as this is strictly means ans methods. It should be assumed that existing conditions be preserved.

IRS

There are a significant amount of GSA and PBS reference documents provided but it is unclear which are applicable to the scope of the contract. For example, COBie standards are included yet we are not being provided a native model of the facility nor do we believe the intent is to create new 3d models for the building with COBie information integrated. Please clearly define the design submittals and the governing criteria for the preparation of proposals.

The SOW determines which documents and/or portions of documents will be applicable.

Specification notates responsibility for extensive lifecycle cost analysis which would involve many systems outside of the current scope (e.g. Cooling Towers).

Please confirm DB Contractor scope relative to gBUILD would be limited to providing information on the new construction within scope for input into the existing database.

Confirmed

Since no existing models or full sets of record documents are available and many portions of the existing facilities are outside of this scope of work, please confirm specifications related to BIM are not applicable.

Confirmed

It was mentioned at the site visit that P-100 was no longer a viable governing document due to administrative direction in February of 2025. Attachment 05 and other portions of the bid documents indicate P-100 2021v w2022 addendum is the primary governing criteria. Please advise what codes, standards and criteria will govern the contract.

References to P-100 are replaced by the Core Building Standards document.

It was mentioned at the site visit that all work will be performed under escort and escorts will be provided by the Government or User at no cost to the contractor and no limit on the number needed. Please confirm that this is correctly understood as stated.