This is a Final Receipt document from the City of Wheat Ridge, Colorado, certifying the completion and final payment of a construction project for the installation of a four-way traffic signal at the intersection of Tabor Street and West 44th Avenue. The project encompassed installation of a new traffic signal system, reconstruction of ADA-compliant curb ramps at each corner of the intersection, and associated signage and pavement striping improvements. The receipt confirms that the City of Wheat Ridge has issued full and final payment to the contractor for all work completed under the project contract, including any extra work and materials furnished during construction.
The Final Receipt certifies that all persons performing work and furnishing materials for the project have been paid in full. The document releases the City of Wheat Ridge from all claims arising from the contract and serves as official certification of project completion and financial settlement. The receipt requires signatures from the contractor's authorized representative, including printed name, signature, title, and date, and contains a blank field indicating the final payment amount to be completed upon execution.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FINAL RECEIPT
DATE:
TO:
(Contractor)
(Address)
FROM: CITY OF WHEAT RIDGE, CO
RE: [ITB-YR-##, PROJECT NAME]
Received this date, of the Owner, as full and final payment of the cost of the improvements provided for in the Project Contract Documents, the amount of $ in cash, being the remainder of the full amount accruing to the undersigned by virtue of said contract.
Said cash also covers and includes full payment for the cost of all extra work and material furnished by the undersigned in the construction of said improvements, and all incidentals thereto.
The undersigned hereby releases said Owner from all claims whatsoever which may develop from said contract.
These presents are to certify that all persons doing work upon or furnishing materials for said improvements under the foregoing contract have been paid in full.