These are final construction documents for an Air Handling Unit Replacement project at the Veterans Affairs Regional Office (VARO) located at 345 Perry Hill Road in Montgomery, Alabama. The project involves replacing two air handling units (42-AHU-1 and 42-AHU-2) in the mechanical penthouse of Building 42, along with associated mechanical, electrical, fire protection, and control system upgrades. The project number is VB3145 and is being designed by Spur Design, LLC. The new air handling units are Temtrol models with 31,925 and 32,005 CFM capacities, respectively, featuring variable speed fans, chilled water cooling coils, and ultraviolet light systems. The project includes demolition of existing equipment, installation of new air handling units, controls, electrical connections, and associated infrastructure modifications to ensure proper system integration and performance.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C10D25R0012 0003.docx | DOCX document | |
| FINAL RFI Questions 36C10D25R0012 1-118.xlsx | XLSX spreadsheet | |
| 36C10D25R0012 0002.docx | DOCX document | |
| S04 site visit sign-in sheet.pdf | ||
| 36C10D25R0012 0001.docx | DOCX document | |
| FINAL specs.pdf | ||
| P07 Al20250093 03.14.2025 SAM.pdf | ||
| PPQ VBA.doc | DOC document | |
| 36C10D25R0012_1.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
th re e in c h e s o n e fo o t th re e in c h e s o n e fo o t th re e in c h e s o n e fo o t th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t
00 00
11 11 o n e in c h o n e fo o t o n e in c h o n e fo o t o n e in c h o n e fo o t o n e in c h o n e fo o t
00 00
22 22 th re e q u a rt e rs in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t
00 00 22 22 o n e h a lf in c h o n e fo o t o n e h a lf in c h o n e fo o t o n e h a lf in c h o n e fo o t o n e h a lf in c h o n e fo o t
00 00 44 44 th re e e ig h th s in c h o n e fo o t th re e e ig h th s in c h o n e fo o t th re e e ig h th s in c h o n e fo o t th re e e ig h th s in c h o n e fo o t
00 00 44 44 o n e q u a rt e r in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t
00 00 44 44
88 88 o n e e ig h th in c h o n e fo o t o n e e ig h th in c h o n e fo o t o n e e ig h th in c h o n e fo o t o n e e ig h th in c h o n e fo o t
00 00 44 44
88 88
A
B
C
D
E
F
Veterans Benefits
Administration
VA FORM 08-6231
DRAWING TITLE PROJECT TITLE
LOCATION
DATE CHECKED DRAWN
PROJECT NUMBERCONSULTANTS:
DRAWING #
U.S. DEPARTMENT OF VETERANS AFFAIRS
VETERANS BENEFITS ADMINISTRATION APPROVAL:
ARCHITECT:
SPUR DESIGN, LLC
312 SW 25TH STREET
Oklahoma City, OK 73109
(405) 842-6100
EXP. 04/30/2025
EXP. 12/31/2025
MEP/FIRE PROTECTION ENGINEER
SPUR DESIGN
2519 MADISON AVE, STE 100
KANSAS CITY, MO 64108
(913) 369-7200
The information on this document is preliminary or incomplete, not for construction, recording purposes, or implementation.
FULLY SPRINKLERED
1 2 3 4 5 6 7 8 9
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
STAMP:
DRAWING NUMBER
BUILDING NUMBER
ARCH COA NO. CA-0996
ENGR COA NO. ECA-5426
/2
/2
:2 :0
P
M
COVER SHEET
KJW 01 OF 15AJS
FINAL CONSTRUCTION DOCUMENTS
AIR HANDLING UNIT REPLACEMENT (VBA)
VA PROJECT NUMBER: VB3145
AIR HANDLING UNIT
REPLACEMENT (VBA)
10/24/2024
VB3145
VA REGIONAL OFFICE
345 PERRY HILL ROAD,
MONTGOMERY, AL 36109
VETERANS AFFAIRS REGIONAL OFFICE (VARO)
345 PERRY HILL ROAD,
MONTGOMERY, AL 36109
FINAL CONSTRUCTION DOCUMENTS
GI000
SPUR #: 2401
SHEET INDEX
SEQUENCE NUMBER SHEET NAME
[01] GENERAL
01 GI000 COVER SHEET
02 GI001 GENERAL INFORMATION
[02] ARCHITECTURAL
03 AS001 ARCHITECTURAL SITE PLAN
04 AE101 DEMOLITION AND REFERENCE PLAN - BUILDING 42 - PENTHOUSE LEVEL
[03] FIRE PROTECTION
05 FX101 FIRE SPRINKLER FLOOR PLAN - PENTHOUSE LEVEL
[04] MECHANICAL
06 M-000 LEGEND AND ABBREVIATIONS
07 MD101 MECHANICAL HVAC DEMOLITION PLAN - PENTHOUSE LEVEL
08 MH101 MECHANICAL HVAC PLAN - PENTHOUSE LEVEL
09 M-501 MECHANICAL SCHEDULES AND DETAILS
10 M-701 MECHANICAL CONTROLS
11 M-702 MECHANICAL CONTROLS
[05] ELECTRICAL
12 E-001 ELECTRICAL LEGEND AND ABBREVIATIONS
13 ED101 ELECTRICAL DEMOLITION PLAN - BUILDING 42 - PENTHOUSE LEVEL
14 EP101 ELECTRICAL POWER PLAN - BUILDING 42 - PENTHOUSE LEVEL
15 E-601 ELECTRICAL ONE-LINE DIAGRAM
TOTAL SHEETS: 15
LOCATION
PLAN
AREA
PLAN
N
PROJECT LOCATION
N
NUMBER REVISION DESCRIPTION DATE
ABBREVIATIONS CODES STANDARDS AND EXECUTIVE ORDERS
FIXTURE MOUNTING HEIGHTS AND CLEARANCES
DOOR AND FIXTURE CLEARANCES
MATERIALS LEGEND
PURPOSE: THE PUBLIC BUILDINGS AMENDMENT ACT OF 1988, PUBLIC LAW (PUB. L.) 100-678 REQUIRES FEDERAL AGENCIES TO FOLLOW NATIONAL RECOGNIZED "MODEL" BUILDING CODES. THE FEDERAL PARTICIPATION IN THE DEVELOPMENT AND USE OF VOLUNTARY STANDARDS, OFFICE OF MANAGEMENT AND BUDGET (OMB) CIRCULAR A-119, REQUIRES ALL EXECUTIVE AGENCIES TO RELY ON VOLUNTARY STANDARDS, BOTH DOMESTIC AND INTERNATIONAL, WHENEVER FEASIBLE, AND TO PARTICIPATE IN
VOLUNTARY STANDARD BODIES.
GENERAL: VA HAS ADOPTED THE LATEST EDITION OF THE FOLLOWING CODES AND STANDARDS AS A MINIMUM FOR ALL PROJECTS PERFORMED IN THE MODERNIZATION, ALTERATION, ADDITION, OR IMPROVEMENT OF ITS REAL PROPERTY AND THE CONSTRUCTION OF NEW STRUCTURES. VA DESIGN MANUALS AND MASTER SPECIFICATIONS SPECIFY OTHER CODES AND STANDARDS THAT VA FOLLOWS ON ITS PROJECTS. REFERENCE RELEVANT ADDENDA FOR EACH OF THE ADOPTED CODES AND STANDARDS:
• VA DIRECTIVES, DESIGN MANUALS, MASTER SPECIFICATIONS, VA NATIONAL CAD STANDARD APPLICATION GUIDE, AND OTHER GUIDANCE ON THE TECHNICAL
INFORMATION LIBRARY (TIL) (HTTP://WWW.CFM.VA.GOV/TIL/ ).
• 2024 INTERNATIONAL BUILDING CODE (IBC) (ONLY WHEN SPECIFICALLY REFERENCED IN VA DESIGN DOCUMENTS, SEE NOTES BELOW)
• 2024 INTERNATIONAL EXISTING BUILDING CODE (IEBC) (IF APPLICABLE)
• 2024 NFPA 101 LIFE SAFETY CODE (SEE NOTES BELOW)
• 2024 NATIONAL FIRE CODES (NFPA) (WITH THE EXCEPTION OF NFPA 900 AND NFPA 5000)
• OCCUPATIONAL, SAFETY AND HEALTH ADMINISTRATION (OSHA) STANDARDS.
• 2023 VA SEISMIC DESIGN REQUIREMENTS, H-18-8
• 2024 INTERNATIONAL MECHANICAL CODE
• 2023 NATIONAL ELECTRICAL CODE (NEC), NFPA 70
• 2024 INTERNATIONAL PLUMBING CODE (IPC)
• 2022 SAFETY CODE FOR ELEVATORS AND ESCALATORS, AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME) A 17.1.
• ARCHITECTURAL BARRIERS ACT (ABA) STANDARDS INCLUDING VA SUPPLEMENT, VA BARRIER FREE DESIGN STANDARD (PG-18-13)
• 2022 ANSI ICC A117.1 ACCESSIBLE AND USABLE BUILDINGS AND FACILITIES
• 2022 BUILDING CODE REQUIREMENTS FOR STRUCTURAL CONCRETE AND COMMENTARY, AMERICAN CONCRETE INSTITUTE AND COMMENTARY (ACI 318-19)
• 2023 STEEL CONSTRUCTION MANUAL (16TH EDITION), AMERICAN INSTITUTE OF STEEL CONSTRUCTION (AISC)
• ENERGY POLICY ACT OF 2005 (EPACT)
• 2007 DOE INTERIM FINAL RULE: ENERGY CONSERVATION STANDARDS FOR NEW FEDERAL, COMMERCIAL AND MULTI -FAMILY HIGH-RISE RESIDENTIAL BUILDINGS AND
NEW LOW-RISE RESIDENTIAL BUILDINGS, 10 CFR PARTS 433, 434 AND 435.
• 2006 FEDERAL LEADERSHIP IN HIGH PERFORMANCE AND SUSTAINABLE BUILDINGS: MEMORANDUM OF UNDERSTANDING (MOU)
• 2018 EXECUTIVE ORDER 13834: EFFICIENT FEDERAL OPERATIONS
• 2021 THE PROVISIONS FOR CONSTRUCTION AND SAFETY SIGNS. STATED IN THE GENERAL REQUIREMENTS SECTION 010000 OF THE VA MASTER CONSTRUCTION
SPECIFICATION.
• 2022 VENTILATION FOR ACCEPTABLE INDOOR AIR QUALITY – ASHRAE STANDARD 62.1
• 2022 SAFETY STANDARD FOR REFRIGERATION SYSTEMS – ASHRAE STANDARD 15
• 2024 PHYSICAL SECURITY AND RESILIENCY DESIGN MANUAL
LOCAL CODES: AS AN AGENCY OF THE FEDERAL GOVERNMENT, VA IS NOT SUBJECT TO LOCAL IMPOSITION OF CODE ENFORCEMENT PROCEDURES (DRAWING REVIEWS, BUILDING PERMITS, INSPECTIONS, FEES, ETC.). VA MUST FUNCTION AS THE AUTHORITY HAVING JURISDICTION (AHJ) AND THUS HAS THE RESPONSIBILITY TO GUARD
PUBLIC HEALTH AND SAFETY THROUGH ENFORCING ITS ADOPTED CODES. HOWEVER, LOCAL AUTHORITIES SHOULD BE NOTIFIED ABOUT PLANNED PROJECTS AND GIVEN OPPORTUNITY TO REVIEW DRAWINGS PROVIDED THAT VA DOES NOT PAY FOR REVIEW OR INSPECTION FEES.
NOTES:
1. NFPA 101 PRIMARILY ADDRESSES LIFE SAFETY AND FIRE PROTECTION FEATURES WHILE THE IBC ADDRESSES A WIDE RANGE OF CONSIDERATIONS, INCLUDING, BUT
NOT LIMITED TO, STRUCTURAL STRENGTH, SEISMIC STABILITY, SANITATION, ADEQUATE LIGHT AND VENTILATION, AND ENERGY CONSERVATION. VA BUILDINGS MUST MEET THE REQUIREMENTS OF NFPA 101 AND DOCUMENTS REFERENCED BY NFPA 101 IN ORDER TO COMPLY WITH THE ACCREDITATION REQUIREMENTS OF THE JOINT COMMISSION. THEREFORE, DESIGNS SHALL COMPLY WITH THE REQUIREMENTS OF THE LATEST EDITION OF NFPA 101 AND DOCUMENTS REFERENCED THEREIN.
DESIGN FEATURES NOT ADDRESSED BY NFPA 101 OR DOCUMENTS REFERENCED THEREIN SHALL COMPLY WITH THE REQUIREMENTS OF THE LATEST EDITION OF THE IBC OR AS OTHERWISE ADDRESSED ABOVE IN THIS PROGRAM GUIDE. FOR DESIGN FEATURES THAT ARE ADDRESSED BY BOTH THE IBC AS WELL AS NFPA 101 OR A DOCUMENT REFERENCED BY NFPA 101, THE REQUIREMENTS OF NFPA 101 OR THE DOCUMENT REFERENCED BY NFPA 101 SHALL BE USED EXCLUSIVELY (THIS APPLIES
EVEN IF THE IBC REQUIREMENTS ARE DIFFERENT).
2. CONFLICTS BETWEEN NATIONALLY RECOGNIZED CODES AND STANDARDS AND VA REQUIREMENTS – SHOULD A CONFLICT EXIST BETWEEN VA REQUIREMENTS AND VA ADOPTED NATIONALLY RECOGNIZED CODES AND STANDARDS, THE CONFLICT SHALL BE BROUGHT TO THE ATTENTION OF VA. THE RESOLUTION OF THE CONFLICT SHALL BE MADE BY THE AUTHORITY HAVING JURISDICTION FOR VA TO ENSURE A CONSISTENCY SYSTEM WIDE.
ASHRAE 90.1 - 2019 EDITION
BUILDING LOCATION: ST. LOUIS, MO
CLIMATE ZONE (TABLE ANNEX 1-1): ZONE 4A
INTERIOR DESIGN CONDITIONS:
THE INTERIOR DESIGN TEMPERATURES FOR HEATING AND COOLING AS DEPICTED IN THE PROJECT DESIGN CONDITIONS SCHEDULE IN THE MECHANICAL CONTROL DRAWINGS SHALL BE THE MAXIMUM
AND MINIMUM VALUES FOR THE ASSOCIATED TEMPERATURE CONTROL ZONES.
BUILDING ENVELOPE REQUIREMENTS (5.5 )
BUILDING ENVELOPE REQUIREMENTS FOR CLIMATE ZONE 4 (A,B,C)
ROOFS REQUIRED DESIGNED
INSULATION: R-30 c.i. EXISTING TO REMAIN
METAL BUILDINGS: R-19 + R-11 Ls or R-25 + R-8 Ls EXISTING TO REMAIN
ATTIC AND OTHER: R-49 EXISTING TO REMAIN
WALLS, ABOVE GRADE
MASS: R-9.5 c.i. EXISTING TO REMAIN METAL BUILDING: R-0 + R-15.8 c.i. EXISTING TO
REMAIN
STEEL-FRAMED: R-13 + R-7.5 c.i. EXISTING TO REMAIN WOOD-FRAMED AND OTHER: R-13 + R-3.8 c.i. or R-20 EXISTING TO REMAIN
WALL, BELOW GRADE
BELOW-GRADE WALL: R-7.5 c.i. EXISTING TO REMAIN
FLOORS
MASS: R-14.6 c.i. EXISTING TO REMAIN
STEEL-FRAMED: R-30 EXISTING TO REMAIN
WOOD-FRAMED AND OTHER: R-30 EXISTING TO REMAIN
SLAB-ON-GRADE FLOORS
UNHEATED SLABS: R-15 for 24 in. EXISTING TO REMAIN HEATED SLABS: R-20 for 24 in. EXISTING TO REMAIN
OPAQUE DOORS
SWINGING: U-0.370 EXISTING TO REMAIN
NONSWINGING: U-0.310 EXISTING TO REMAIN
FENESTRATION (TABLE 5.5-4):
VERTICAL FENESTRATION, U-FACTOR
FIXED: U-0.36 EXISTING TO REMAIN
OPERABLE: U-0.45 EXISTING TO REMAIN
ENTRANCE DOOR: U-0.63 EXISTING TO REMAIN
DEFINITIONS
c.i = CONTINUOUS INSULATION Ls = LINEAR SYSTEM
NR = NO (INSULATION) REQUIREMENT
ENERGY REQUIREMENTS
N
1. DRAWINGS ARE PART OF A COMPLETE DOCUMENTS SET. CONTRACTOR SHALL CONFIRM
ALL ITEMS REQUIRED BASED UPON THE OVERALL DESIGN INTENT OF THE ENTIRE
DOCUMENT SET.
2. CONTRACTOR SHALL VERIFY ALL EXISTING CONDITIONS, PRIOR TO BEGINNING ANY WORK,
TO CONFIRM THE ACCURACY OF THE DRAWINGS AND REPORT ANY DISCREPANCIES TO
THE ARCHITECT. DO NOT SCALE THE DRAWINGS. FIELD VERIFY ALL DIMENSIONS AND
EXISTING STRUCTURAL CONDITIONS.
3. ALL AREAS NOT INVOLVED IN THE SCOPE OF WORK FOR THIS PROJECT SHALL BE KEPT
CLEAN AND FREE OF OBSTRUCTIONS AT ALL TIMES.
4. ERECT BARRICADES AND WARNING SIGNS TO DIVERT AND WARN PASSERS -BY OF THE
CONSTRUCTION WORK. PROVIDE DUST PROOFING ENCLOSURES TO SEPARATE WORK
AREAS FROM THE EXISTING FACILITIES.
5. ALL TRASH AND DEBRIS TO BE REMOVED ON A DAILY BASIS.
6. PROVIDE PROTECTION FOR ALL EXISTING SURFACES AND CONDITIONS TO REMAIN IN
PLACE DURING THE SCOPE OF WORK. SHOULD ANY DAMAGE OCCUR, PATCH AND REPAIR
ANY DAMAGE TO ADJACENT FINISHES TO MATCH EXISTING.
7. ANY DAMAGE CAUSED TO THE BUILDING OR OWNER EQUIPMENT SHALL BE REPAIRED OR
REPLACED BACK TO ITS ORIGINAL CONDITIONS AT NO ADDITIONAL COST TO THE OWNER.
8. COVER ALL RETURN AIR GRILLES WITHIN THE AREA OF CONSTRUCTION TO PREVENT
PARTICULATE MATERIAL FROM EXHAUSTING INTO SURROUNDING SPACES.
9. APPROPRIATE LIGHT FIXTURES SHALL BE TEMPORARILY SUSPENDED TO PROVIDE
ADEQUATE LIGHTING LEVELS FOR CONSTRUCTION.
10. CONTRACTOR AND SUBCONTRACTORS ARE REQUIRED TO COORDINATE WITH OTHER
DISCIPLINES TO INSTALL COMPLETE AND OPERATIONAL SYSTEMS. DRAWINGS, AS A
WHOLE, REPRESENT A COMPLETE SET AND DEPICT REQUIREMENTS FOR COMPLETE AND
OPERATIONAL SYSTEMS. INDIVIDUAL DRAWINGS MAY NOT DEPICT COMPLETE AND
ACCURATE INFORMATION TO COORDINATE COMPLETE AND OPERATIONAL SYSTEMS, BUT
DO SO AS AN ENTIRE DOCUMENT TO BE REFERENCED WITH OTHER INDIVIDUAL DRAWINGS.
CONTRACTOR AND SUBCONTRACTORS ARE REQUIRED TO REFERENCE OTHER SHEETS
AND SPECIFICATIONS AS AN ENTIRE SET OF CONSTRUCTION DOCUMENTS THAT REFLECT
WORK REQUIRED TO ACHIEVE A COMPLETE AND OPERATIONAL GOAL. LACK OF
COORDINATION AND REVIEW OF DRAWINGS AND SPECIFICATIONS AS AN ENTIRE
DOCUMENT TO INSTALL COMPLETE AND OPERATIONAL SYSTEMS, BEING OBVIOUS AND
TYPICAL INDUSTRY STANDARD, IDENTIFIED IN THE DRAWINGS AND SPECIFICATIONS, SHALL
NOT BE IN ANY WAY AN ADDITIONAL COST TO THE GOVERNMENT.
11. CONTRACTOR SHALL SUBMIT A REQUEST, IN WRITING, TO INTERRUPT ANY SUCH SERVICES
TO COR (CONTRACTING OFFICER’S REPRESENTATIVE) 48 HOURS IN ADVANCE OF
PROPOSED INTERRUPTION. REQUEST SHALL STATE REASON, DATE, EXACT TIME OF, AND
APPROXIMATE DURATION OF SUCH INTERRUPTION. MAJOR INTERRUPTIONS OF ANY
SYSTEM MUST BE REQUESTED, IN WRITING, AT LEAST 60 CALENDAR DAYS PRIOR TO THE
DESIRED TIME AND SHALL BE PERFORMED AS DIRECTED BY THE COR. MAJOR
INTERRUPTIONS SHALL BE COORDINATED WITH OTHER MAJOR INTERRUPTIONS AND MAY
NOT BE SCHEDULED FOR ONE DISCIPLINE MORE THAN TWICE THROUGHOUT THE OVERALL
CONSTRUCTION SCHEDULE UNLESS REQUESTED IN WRITING AND APPROVED BY THE COR.
CONTRACTOR WILL BE ADVISED, IN WRITING, OF APPROVAL OF REQUEST, OR OF WHICH
OTHER DATE AND/OR TIME SUCH INTERRUPTION WILL CAUSE THE LEAST INCONVENIENCE
TO OPERATIONS OF THE MEDICAL CENTER. INTERRUPTION TIME APPROVED BY THE
MEDICAL CENTER MAY OCCUR AT TIMES OTHER THAN CONTRACTOR'S NORMAL WORKING
HOURS. SCHEDULE INTERRUPTION MAY BE ON WEEKENDS OR LATE HOURS AND MAY NOT
BE AN ADDITIONAL COST TO THE GOVERNMENT. COORDINATE ALL INTERRUPTIONS THAT
MAY AFFECT THE NORMAL OPERATION OF THE FACILITY WITH THE COR WHEN SUBMITTING
THE CONSTRUCTION SCHEDULE OR UPDATES TO THE CONSTRUCTION SCHEDULE.
12. NO ASBESTOS CONTAINING MATERIALS ARE TO BE USED ON THIS PROJECT. SPUR DESIGN, THE A/E OF RECORD, CAN CERTIFY THAT NO ASBESTOS CONTAINING BUILDING MATERIALS
(ACBM) OR LEAD BASED PAINT (LBP) PRODUCTS WERE DESIGNED/SPECIFIED AS BUILDING
MATERIAL IN ANY OF THE CONSTRUCTION DOCUMENTS.
13. REFER TO THE DESIGN BINDER FOR THE ICRA INFORMATION DOCUMENTATION.
GENERAL NOTES
AREA NAME
150 SF
A101
A101
SIM
A
00.0
A101
1 1
A101
LEVEL NAME
00'-00"
00'-00" 4B
3A
FIBERGLASS BATT
INSULATION
RIGID INSULATION
CONCRETE / PRECAST
CONCRETE
EARTH / SOIL
SAND, EIFS FINISH, OR
PLASTER FINISH
GYPSUM BOARD FINISH
BRICK
CONCRETE MASONRY
UNIT
STONE / CAST STONE
GYPSUM BOARD SECTION
EXTERIOR SHEATHING
BOARD SECTION
PLYWOOD SECTION
CLEAN UTILITY
000A
150 SF
/1 A101
X0000
ROOM TAG
AREA TAG
SPECIALTY EQUIPMENT TAG
DOOR TAG
KEYED NOTE TAG
WALL TAG
WINDOW TAG
A101
SIM
A101
SIM
A
ACB ACOUSTIC CEILING BAFFLE
ACP ACOUSTIC CEILING PANEL
ACST ACOUSTIC
ADA AMERICANS WITH DISABILITIES ACT
ACT ACOUSTICAL CEILING TILE
ADDL ADDITIONAL
ADDN ADDITION
ADJ ADJACENT, ADJOINING, OR
ADJUSTABLE
ADMIN ADMINISTRATION
AE ARCHITECT/ENGINEER
AF ACCESS FLOORING
AFF ABOVE FINISHED FLOOR
AFG ABOVE FINISHED GRADE
AHJ AUTHORITY HAVING JURISDICTION
AIA AMERICAN INSTITUTE OF
ARCHITECTS
ALT ALTERNATE
ALT NO ALTERNATE NUMBER
ALUM ALUMINIUM (TRIM)
AMT AMOUNT
APPROX APPROXIMATE
ARCH ARCHITECT
ASC ABOVE SUSPENDED CEILING
AT ACOUSTIC CEILING TILE
AVG AVERAGE
B
BD BOARD
BG BUMPER GUARD
BLDG BUILDING
BLKG BLOCKING
BLT IN BUILT-IN
BOS BOTTOM OF STEEL
BOT BOTTOM
BRKT BRACKET
BTWN BETWEEN
C
CAB CABINET
CAV CAVITY
CBB CONCRETE BACKER BOARD
C/C CONTRACTOR PROVIDED /
CONTRACTOR INSTALLED
CD CONSTRUCTION DOCUMENTS
CFM CUBIC FEET PER MINUTE
CFS CUBIC FEET PER SECOND
CG CORNER GUARD
CH BD CHALKBOARD
CIP CAST-IN-PLACE
CJ CONTROL JOINT
CL CENTERLINE
CLG CEILING
CLG HT CEILING HEIGHT
CLR CLEAR
CMU CONCRETE MASONRY UNIT
CO CONTRACTING OFFICER
COL COLUMN
COMM COMMUNICATION
CONC CONCRETE
CONT CONTINUOUS
COORD COORDINATE
COR CONTRACTING OFFICER'S
REPRESENTATIVE
CP CONTRACTOR PROVIDED
CPT CARPET/CARPET TILE
CS CONCRETE SEALED
CSWK CASEWORK
CT CERAMIC TILE
CTB CERAMIC TILE BASE
CTR CENTER
CU FT CUBIC FEET
D
DBL DOUBLE
DEMO DEMOLITION
DEPT DEPARTMENT
DET DETAIL
DIA DIAMETER
DIR DIRECTION
DIST DISTANCE
DOC DOCUMENT
DR DOOR
DS DOWNSPOUT
DWG DRAWING
DWP DIMENSIONAL WALL PANEL
E
EA EACH
EJ EXPANSION JOINT
EL ELEVATION
ELEV ELEVATOR
ENTR ENTRANCE
EPY EPOXY FLOORING
EQ EQUAL
ETR EXISTING TO REMAIN
EX EXISTING
EXP EXPOSED
EXT EXTERIOR
F
FAB FABRIC
FED FEDERAL
FF FINISH FACE
FF EL FINISH FLOOR ELEVATION
FIN FINISH
FIN BS FINISH BOTH SIDES
FIN FLR FINISH FLOOR
FIN GR FINISH GRADE
FIXT FIXTURE
FLDG FOLDING
FLEX FLEXIBLE
FLG FLOORING
FLMT FLUSH MOUNT
FLR FLOOR
FOC FACE OF CONCRETE
FOM FACE OF MASONRY
FP FIRE PROTECTION
FR FIRE RESISTANT
FT FEET
FTG FOOTING
FV FIELD VERIFY
FWC FABRIC WALL COVERING
G
GDR GUARDRAIL
GL GLASS/GLAZING
GRAN GRANITE
GR FL GROUND FLOOR
GT GROUT
GSM GALVANIZED SHEET METAL
GYP BD GYPSUM BOARD
H
HDW HARDWARE
HEPA HIGH EFFICIENCY
PARTICULATE AIR (FILTER)
HM HOLLOW METAL
HORIZ HORIZONTAL
HR HANDRAIL
HT HEIGHT
I
IBC INTERNATIONAL BUILDING CODE
INSUL INSULATION
INT INTERIOR
ILO IN LIEU OF
J
J-BOX JUNCTION BOX
L
LAV LAVATORY
LBS POUND
LDG LANDING
LF LINEAR FEET (FOOT)
LIN LINEAR
LN LINOLEUM
LOC LOCATION
LT LIGHT
LVR LOUVER
LVT LUXURY VINYL TILE
M
MAT CARPET MAT / WALK-OFF MAT
MATL MATERIAL
MAX MAXIMUM
MECH MECHANICAL
MEMB MEMBRANE
MFR MANUFACTURER
MID MIDDLE
MIL STD MILITARY STANDARD
MIN MINIMUM
MISC MISCELLANEOUS
MO MASONRY OPENING
MOD MODIFY
MTG MOUNTING
MTL METAL
MVBL MOVABLE
N
NA NOT APPLICABLE
NIC NOT IN CONTRACT
NO NUMBER
NOM NOMINAL
NTS NOT TO SCALE
O
OA OVERALL
OC ON CENTER
OD OUTSIDE DIAMETER
OPNG OPENING
OPP OPPOSITE
OPR OPERABLE
ORD OVERFLOW ROOF DRAIN
ORIG ORIGINAL
P
P PAINT
PA PUBLIC ADDRESS
PBD PARTICLE BOARD
PCF POUNDS PER CUBIC FOOT
PCT PERCENT
PERF PERFORATED
PERIM PERIMETER
PERP PERPENDICULAR
PL PROPERTY LINE
PLAM PLASTIC LAMINATE
PLBG PLUMBING
PNL PANEL
PR PAIR
PRB PROFILE BASE
PRKG PARKING
PSF POUNDS PER SQUARE FOOT
PSI POUNDS PER SQUARE INCH
PT PORCELAIN TILE
PWR POWER
Q
QA QUALITY ASSURANCE
QC QUALITY CONTROL
QTY QUANTITY
QT QUARRY TILE
REFERENCE SYMBOLS IDENTIFICATION TAGS
NOTE: NOT ALL ABBREVIATIONS OR SYMBOLS WILL BE UTILIZED FOR THIS PROJECT.
GRID HEAD AND
LINE
LEVEL INDICATOR
MATCH LINE AND
VIEW REFERENCE
NORTH ARROW
SPOT ELEVATION
DETAIL
SECTION
WALL
SECTION
BUILDING
SECTION
DETAIL
ELEVATION
INTERIOR
ELEVATION
BUILDING
ELEVATION
1 1
R
RAF RESILIENT ATHLETIC FLOORING
RB RUBBER BASE/RESILIENT BASE
RCP REFLECTED CEILING PLAN
RD ROOF DRAIN
REC RECESSED
REF REFERENCE
REM REMOVABLE
REP REPAIR
REPL REPLACE
REQ REQUIRE
REQD REQUIRED
RES RESINOUS FLOORING
RES-W RESINOUS / EPOXY WALL / CEILING
RF RUBBER FLOORING
RFG ROOFING
RM ROOM
RO ROUGH OPENING
RP RESIN PANEL
RSF RESILIENT SHEET FLOORING
RV ROOF VENT
RWC RIGID VINYL WALLCOVERING
S
SC SPECIALTY COATING
SD STATIC DISSIPATIVE FLOORING/TILE
SCHED SCHEDULE
SECT SECTION
SF SQUARE FOOT (FEET)
SGL SINGLE
SIM SIMILAR
SJ SCORED JOINT
SLNT SEALANT
SM SHEET METAL
SPEC SPECIFICATION
SQ SQUARE
SQ IN SQUARE INCH
SQ YD SQUARE YARD
SS SOLID SURFACE
ST STONE
STD STANDARD
STOR STORAGE
SV SHEET VINYL (ROLLED OR TILE)
SWC STAINLESS STEEL WALLCOVERING
T
TEL TELEPHONE
TEMP TEMPORARY
TER TERRAZZO
TOF TOP OF FOOTING/ FOUNDATION
TOM TOP OF MASONRY
TOS TOP OF SLAB/ STEEL
U
UNO UNLESS NOTED OTHERWISE
UTIL UTILITY
V
VAR VARIES
V/C VA PROVIDED / CONTRACTOR
INSTALLED
VCT VINYL COMPOSITION TILE
VFAT VINYL-FACED ACOUSTICAL TILE
VP VENEERED PLASTER
VT VINYL TILE
V/V VA PROVIDED / VA INSTALLED
VWC VINYL WALLCOVERING
VWF VINYL WALL FABRIC
W
W/ WITH
W/O WITHOUT
W/C WATER CLOSET
WC WHEELCHAIR
WD WOOD
WFAB WALL FABRIC
WPM WATERPROOF MEMBRANE
WSF WELDED SHEET FLOOR
X
X BRACE CROSS BRACE
th re e in c h e s o n e fo o t th re e in c h e s o n e fo o t th re e in c h e s o n e fo o t th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t
00 00
11 11 o n e in c h o n e fo o t o n e in c h o n e fo o t o n e in c h o n e fo o t o n e in c h o n e fo o t
00 00
22 22 th re e q u a rt e rs in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t
00 00 22 22 o n e h a lf in c h o n e fo o t o n e h a lf in c h o n e fo o t o n e h a lf in c h o n e fo o t o n e h a lf in c h o n e fo o t
00 00 44 44 th re e e ig h th s in c h o n e fo o t th re e e ig h th s in c h o n e fo o t th re e e ig h th s in c h o n e fo o t th re e e ig h th s in c h o n e fo o t
00 00 44 44 o n e q u a rt e r in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t
00 00 44 44
88 88 o n e e ig h th in c h o n e fo o t o n e e ig h th in c h o n e fo o t o n e e ig h th in c h o n e fo o t o n e e ig h th in c h o n e fo o t
00 00 44 44
88 88
A
B
C
D
E
F
Veterans Benefits
Administration
VA FORM 08-6231
DRAWING TITLE PROJECT TITLE
LOCATION
DATE CHECKED DRAWN
PROJECT NUMBERCONSULTANTS:
DRAWING #
VETERANS BENEFITS ADMINISTRATION APPROVAL:
ARCHITECT:
SPUR DESIGN, LLC
312 SW 25TH STREET
Oklahoma City, OK 73109
(405) 842-6100
EXP. 04/30/2025
EXP. 12/31/2025
MEP/FIRE PROTECTION ENGINEER
SPUR DESIGN
2519 MADISON AVE, STE 100
KANSAS CITY, MO 64108
(913) 369-7200
The information on this document is preliminary or incomplete, not for construction, recording purposes, or implementation.
FULLY SPRINKLERED
1 2 3 4 5 6 7 8 9
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
STAMP:
DRAWING NUMBER
BUILDING NUMBER
ARCH COA NO. CA-0996
ENGR COA NO. ECA-5426
/2
/2
:0
:4
P
M
GENERAL INFORMATION
KJW 02 OF 15AJS
FINAL CONSTRUCTION DOCUMENTS
AIR HANDLING UNIT
REPLACEMENT (VBA)
10/24/2024
VB3145
VA REGIONAL OFFICE
345 PERRY HILL ROAD,
MONTGOMERY, AL 36109
GI001
SPUR #: 2401NUMBER REVISION DESCRIPTION DATE
1.02
2.10
1. ALL EXISTING LANDSCAPING TO REMAIN. CONTRACTOR TO REPAIR OR RESTORE ANY DAMAGE
CAUSED TO EXISTING LANDSCAPING ELEMENTS OUTSIDE OF PROJECT SCOPE OF WORK.
GENERAL SITE PLAN NOTES
SCOPE BOUNDARY
25'-0" SAFETY SETBACK BUILDING AREA OF WORK
EXISTING BUILDING
SITE PLAN LEGEND
NOTE: NOT ALL SYMBOLS MAY BE USED.
STAGING / CRANE ACCESS
th re e in c h e s o n e fo o t th re e in c h e s o n e fo o t th re e in c h e s o n e fo o t th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t
00 00
11 11 o n e in c h o n e fo o t o n e in c h o n e fo o t o n e in c h o n e fo o t o n e in c h o n e fo o t
00 00
22 22 th re e q u a rt e rs in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t
00 00 22 22 o n e h a lf in c h o n e fo o t o n e h a lf in c h o n e fo o t o n e h a lf in c h o n e fo o t o n e h a lf in c h o n e fo o t
00 00 44 44 th re e e ig h th s in c h o n e fo o t th re e e ig h th s in c h o n e fo o t th re e e ig h th s in c h o n e fo o t th re e e ig h th s in c h o n e fo o t
00 00 44 44 o n e q u a rt e r in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t
00 00 44 44
88 88 o n e e ig h th in c h o n e fo o t o n e e ig h th in c h o n e fo o t o n e e ig h th in c h o n e fo o t o n e e ig h th in c h o n e fo o t
00 00 44 44
88 88
A
B
C
D
E
F
Veterans Benefits
Administration
VA FORM 08-6231
DRAWING TITLE PROJECT TITLE
LOCATION
DATE CHECKED DRAWN
PROJECT NUMBERCONSULTANTS:
DRAWING #
VETERANS BENEFITS ADMINISTRATION APPROVAL:
ARCHITECT:
SPUR DESIGN, LLC
312 SW 25TH STREET
Oklahoma City, OK 73109
(405) 842-6100
EXP. 04/30/2025
EXP. 12/31/2025
MEP/FIRE PROTECTION ENGINEER
SPUR DESIGN
2519 MADISON AVE, STE 100
KANSAS CITY, MO 64108
(913) 369-7200
The information on this document is preliminary or incomplete, not for construction, recording purposes, or implementation.
FULLY SPRINKLERED
1 2 3 4 5 6 7 8 9
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
STAMP:
DRAWING NUMBER
BUILDING NUMBER
ARCH COA NO. CA-0996
ENGR COA NO. ECA-5426
/2
/2
:3 :1
P
M
ARCHITECTURAL SITE PLAN
KJW 03 OF 15AJS
FINAL CONSTRUCTION DOCUMENTS
AIR HANDLING UNIT
REPLACEMENT (VBA)
10/24/2024
VB3145
VA REGIONAL OFFICE
345 PERRY HILL ROAD,
MONTGOMERY, AL 36109
AS001
SPUR #: 2401
N 1" = 40'-0"
SITE PLAN1
KEYNOTE LEGEND
1.02 PROPOSED STAGING/CRANE ACCESS
2.10 EXISTING DUMPSTER TO REMAIN
UP
UP
DN
UP
UP
DN
FD
FD
FD
UP
UP
GENERAL PLAN NOTES
1. ALL DOOR FRAMES TO BE LOCATED 4" FROM OUTSIDE OF FRAME TO FINISH FACE OF ADJACENT
WALL UNLESS NOTED OTHERWISE.
2. ALL WALLS ARE DIMENSIONED TO CENTERLINE OF METAL STUD, UNLESS NOTED OTHERWISE.
3. BLOCK OUT SLAB FOR PENETRATIONS SHALL BE 2" LARGER THAN DUCT SIZE TO ALLOW
TOLERANCE FOR DUCT PASSAGE AND FIRE SAFING. COORDINATE WITH MEP FOR DUCT SIZES.
FLOOR PLAN LEGEND
EXISTING PARTITION
EXISTING DOOR & FRAME
EXISTING WINDOW
AREA NOT IN CONTRACT
NOTE: NOT ALL SYMBOLS MAY BE USED.
PARTITION LEGEND
NOTE: NOT ALL SYMBOLS MAY BE USED
SMOKE PARTITION/BARRIER EXISTING 2 HOUR FIRE
3 HOUR FIRE RATED EXISTING 1 HOUR FIRE
2 HOUR FIRE RATED NEW NON-RATED WALLS
1 HOUR FIRE RATED EXISTING WALL TO REMAIN
5 6 7 8 9 10 11
G
F
E
D
C
B
19'-8" 11'-0" 8'-8" 8'-8" 11'-0" 19'-8"
78'-8"
'-4
'-0
'-0
'-8
'-4
'-4
2.06
2.06
2.07
2.08
2.09
2.05
5 6 7 8 9 10 11
19'-8" 11'-0" 8'-8" 8'-8" 11'-0" 19'-8"
G
F
E
D
C
B
'-0
'-0
'-8
'-4
'-4
78'-8"
'-4 th re e in c h e s o n e fo o t th re e in c h e s o n e fo o t th re e in c h e s o n e fo o t th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t
00 00
11 11 o n e in c h o n e fo o t o n e in c h o n e fo o t o n e in c h o n e fo o t o n e in c h o n e fo o t
00 00
22 22 th re e q u a rt e rs in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t
00 00 22 22 o n e h a lf in c h o n e fo o t o n e h a lf in c h o n e fo o t o n e h a lf in c h o n e fo o t o n e h a lf in c h o n e fo o t
00 00 44 44 th re e e ig h th s in c h o n e fo o t th re e e ig h th s in c h o n e fo o t th re e e ig h th s in c h o n e fo o t th re e e ig h th s in c h o n e fo o t
00 00 44 44 o n e q u a rt e r in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t
00 00 44 44
88 88 o n e e ig h th in c h o n e fo o t o n e e ig h th in c h o n e fo o t o n e e ig h th in c h o n e fo o t o n e e ig h th in c h o n e fo o t
00 00 44 44
88 88
A
B
C
D
E
F
Veterans Benefits
Administration
VA FORM 08-6231
DRAWING TITLE PROJECT TITLE
LOCATION
DATE CHECKED DRAWN
PROJECT NUMBERCONSULTANTS:
DRAWING #
VETERANS BENEFITS ADMINISTRATION APPROVAL:
ARCHITECT:
SPUR DESIGN, LLC
312 SW 25TH STREET
Oklahoma City, OK 73109
(405) 842-6100
EXP. 04/30/2025
EXP. 12/31/2025
MEP/FIRE PROTECTION ENGINEER
SPUR DESIGN
2519 MADISON AVE, STE 100
KANSAS CITY, MO 64108
(913) 369-7200
The information on this document is preliminary or incomplete, not for construction, recording purposes, or implementation.
FULLY SPRINKLERED
1 2 3 4 5 6 7 8 9
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
STAMP:
DRAWING NUMBER
BUILDING NUMBER
ARCH COA NO. CA-0996
ENGR COA NO. ECA-5426
/2
/2
:3 :1
P
M
DEMOLITION AND REFERENCE PLAN -
BUILDING 42 - PENTHOUSE LEVEL
KJW 04 OF 15AJS
FINAL CONSTRUCTION DOCUMENTS
AIR HANDLING UNIT
REPLACEMENT (VBA)
10/24/2024
VB3145
VA REGIONAL OFFICE
345 PERRY HILL ROAD,
MONTGOMERY, AL 36109
AE101
SPUR #: 2401
N 1/8" = 1'-0"
PENTHOUSE LEVEL - DEMOLITION PLAN1N
1/8" = 1'-0"
PENTHOUSE LEVEL - REFERENCE PLAN2
KEYNOTE LEGEND
2.05 EXISTING EQUIPMENT PADS TO BE REUSED.
2.06 DEMOLISH EXISTING AIR HANDLER UNIT.
2.07 DEMOLISH EXISTING DUCTWORK.
2.08 REMOVE EXISTING FAN AND STORE FOR REUSE.
2.09 REMOVE AND STORE EXISTING LOUVER FOR MECHANICAL EQUIPMENT TO BE INSTALLED.
LOUVER TO BE RE-INSTALLED AFTER.
G
F
E
D
C
B
5 6 7 8 9 10 11
SOUND
ATTENUATOR
FD2
FD1
FD3
G
F
E
D
C
B
5 6 7 8 9 10 11
F1
F1
GENERAL NOTES:
1) ALL FIRE SPRINKLER PIPING IS TO BE REMOVED AND RE-INSTALLED IN THE EXISTING
LOCATION. PIPING IS SHOWN IN GENERAL LOCATION FOR REFERENCE ONLY, FIRE
SPRINKLER CONTRACTOR SHALL BE RESPONSIBLE FOR FIELD VERIFYING EXISTING
SPRINKLER PIPE AND HEAD LOCATIONS.
2) THE DESIGN AN INSTALLATION OF THE FIRE PROTECTION, FIRE SUPPRESSION SYSTEM
MUST BE IN ACCORDANCE WITH U.S. DEPARTMENT OF VETERANS AFFAIRS FIRE
PROTECTION DESIGN MANUAL, NINTH EDITION, NOVEMBER 2023: NFPA: STANDARD FOR THE
INSTALLATION OF SPRINKLER SYSTEMS, 2022 EDITION.
3) THIS INFORMATION HAS BEEN PREPARED TO PROVIDE GUIDANCE FOR BIDDING. THE FIRE
PROTECTION CONTRACTOR SHALL BE FULLY RESPONSIBLE FOR PROVIDING A COMPLETE AND
FULLY OPERABLE SYSTEM WHICH SHALL BE IN STRICT ACCORDANCE WITH PROJECT
SPECIFICATIONS AND APPLICABLE CODES AND STANDARDS. THE WORK THAT IS INDICATED IN
THIS DOCUMENT IS AN OVERVIEW OF THE PROJECT, INTENDED TO ESTABLISH THE MINIMUM
SCOPE REQUIREMENTS FOR THE PROJECT AS WELL AS THE CONTRACTOR’S RESPONSIBILITIES.
THE CONTRACTOR SHALL SUBMIT A COMPLETE SET OF WORKING DRAWINGS, EQUIPMENT, AND
CALCULATIONS TO THE OWNER’S REPRESENTATIVE AND AHJ FOR REVIEW AND APPROVAL
PRIOR TO FABRICATION AND INSTALLATION WITH THEIR ENGINEERS SEAL. UNLESS
SPECIFICALLY NOTED OTHERWISE, THE CONTRACTOR SHALL PERFORM ALL ACCEPTANCE
TESTING IN ACCORDANCE WITH THE APPLICABLE DESIGN CRITERIA AND THE EQUIPMENT
MANUFACTURER’S INSTRUCTIONS.
4) FIRE SPRINKLER CONTRACTOR SHALL COORDINATE ALL SPRINKLER PIPING TO BE
REMOVED AND REPLACED WITH MECHANICAL CONTRACTOR AND COR PRIOR TO DEMOLITION.
5) FIRE SPRINKLER CONTRACTOR SHALL BE REPSONSIBLE FOR DRAINING ALL PENTHOUSE
SPRINKLER PIPING PRIOR TO DEMOLITION. COORDINATE BOTH SYSTEM DRAIN AND FILL
WITH COR.
6) FIRE SPRINKLER CONTRACTOR SHALL BE RESPONSIBLE FOR INSPECTION OF ANY
AND ALL PIPING, SPRINKLER HEADS OR PIPE FITTING BEING REMOVED AND RE-INSTALLED
EXISTING LOCATION. COORDINATE ON-SITE STORAGE OF EXISTING SPRINKLER PIPE
WITH COR. REPLACE ALL DAMAGED PIPE AS REQUIRED.
7) FIRE SPRINKLER CONTRACTOR SHALL BE RESPONSIBLE FOR PROVIDING AS-BUILT
DRAWINGS TO OWNER AND ANY CALCULATIONS REQUIRED BY THE VBA OR AHJ.
8) EXISTING PENTHOUSE SHALL BE CLASSIFIED AS FOLLOWS:
BUILDING OCCUPANCY: OFFICES
CLASSIFICATION: LIGHT HAZARD (NFPA 13 HAZARD CLASSIFICATION TABLE 5.0),
CONFIRM ACTUAL CLASSIFICATION WITH AHJ.
PIPE MATERIAL: PER NFPA13 REQUIREMENTS.
SPACE OCCUPANCY CLASSIFICATIONS: ORDINARY HAZARD (GROUP 1)
MINIMUM SPRINKLER FLOW DENSITY = 0.15 GPM/FT2.
KEY PLAN
N
FIRE SPRINKLER HAZARD
CLASSIFICATION LEGEND
LIGHT HAZARD
ORDINARY HAZARD 1
ORDINARY HAZARD 2
th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t o n e e ig h th in c h o n e fo o t
A
B
C
D
E
F
Veterans Benefits
Administration
VA FORM 08-6231
DRAWING TITLE PROJECT TITLE
LOCATION
DATE CHECKED DRAWN
PROJECT NUMBERCONSULTANTS:
DRAWING #
VETERANS BENEFITS ADMINISTRATION APPROVAL:
ARCHITECT:
SPUR DESIGN, LLC
312 SW 25TH STREET
Oklahoma City, OK 73109
(405) 842-6100
EXP. 04/30/2025
EXP. 12/31/2025
MEP/FIRE PROTECTION ENGINEER
SPUR DESIGN
2519 MADISON AVE, STE 100
KANSAS CITY, MO 64108
(913) 369-7200
The information on this document is preliminary or incomplete, not for construction, recording purposes, or implementation.
FULLY SPRINKLERED
1 2 3 4 5 6 7 8 9
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
STAMP:
DRAWING NUMBER
BUILDING NUMBER
ARCH COA NO. CA-0996
ENGR COA NO. ECA-5426
/2
/2
:2 :3
P
M
FIRE SPRINKLER FLOOR PLAN -
PENTHOUSE LEVEL
DSM 05 OF 15RJS
FINAL CONSTRUCTION DOCUMENTS
AIR HANDLING UNIT
REPLACEMENT (VBA)
10/24/2024
VB3145
VA REGIONAL OFFICE
345 PERRY HILL ROAD,
MONTGOMERY, AL 36109
FX101
SPUR #: 2401
N 1/8" = 1'-0"
FIRE SPRINKLER DEMOLITION FLOOR PLAN - PENTHOUSE LEVEL1N
1/8" = 1'-0"
FIRE SPRINKLER FLOOR PLAN - PENTHOUSE LEVEL2
KEYNOTES
F1 RE-INSTALL EXISTING SPRINKLER PIPING IN EXISTING LOCATION, MATCH EXISTING PIPE SIZES.
REPLACE ALL EXISTING FITTINGS, SPRINKLER HEADS, TEES, ETC. AS REQUIRED.
DEMOLITION KEYNOTES
FD1 REMOVE SECTION OF SPRINKLER PIPING IN FRONT OF EAST LOUVER, INCLUDING BUT NOT
LIMITED TO FITTINGS, SPRINKLER HEADS, TEES, ETC.
FD2 REMOVE SECTION OF SPRINKLER PIPING ABOVE AIR HANDLING UNIT FOR REMOVAL AND
INSTALLATION HVAC EQUIPMENT. DEMOLITION SHALL INCLUDE BUT IS NOT LIMITED TO
FITTINGS, SPRINKLER HEADS, TEES, ETC.
FD3 REMOVE SECTION OF MAIN SPRINKLER PIPING, INCLUDING LOW HANGING AND VERTICAL
RISER FOR REMOVAL AND INSTALLATION HVAC EQUIPMENT. DEMOLITION SHALL INCLUDE
BUT IS NOT LIMITED TO FITTINGS, SPRINKLER HEADS, TEES, ETC.
ORDINARY HAZARD 1 -
ABBREVIATIONS
HVAC PIPING TYPES
GENERAL DUCT SYMBOLS
A/E ARCHITECT / ENGINEER
AAHX AIR TO AIR HEAT EXCHANGER
AB AIR BLENDER
AAV AUTOMATIC AIR VENT
ACC AIR COOLED CONDENSER
ACU AIR CONDITIONING UNIT
AF AFTER FILTER
AFCV AIR FLOW CONTROL VALVE
AFF ABOVE FINISHED FLOOR
AFW AIR FOIL WHEEL (FAN)
AHU AIR-HANDLING UNIT
AMP AMPERAGE
AP ACCESS PANEL
APD AIR PRESSURE DROP
ARI AIR CONDITIONING AND REFRIGERATION
INSTITUTE
AS AIR SEPARATOR
ASME AMERICAN SOCIETY OF MECHANICAL
ENGINEERS
AW AIR WASHER
AXF AXIAL FLOW
B
B BOILER
BD BUTTERFLY DAMPER
BDD BACKDRAFT DAMPER
BFP BACKFLOW PREVENTER
BHP BRAKE HORSEPOWER
BHX BOILER BLOWDOWN HEAT EXCHANGER
BIW BACKWARD INCLINED WHEEL (FAN)
BSC BIOLOGICAL SAFETY CABINETS
BT BLOWOFF TANK
BTU BRITISH THERMAL UNIT
BTUH BRITISH THERMAL UNIT PER HOUR
C
C CENTIGRADE (CELSIUS)
CC COOLING COIL
CCD COOLING COIL CONDENSATE DRAIN
CENT CENTRIFUGAL
CFH CUBIC FEET PER HOUR
CFM CUBIC FEET PER MINUTE
CFT CUBIC FEET
CFP CHEMICAL FEED PUMP
CH CHILLER
CHP CHILLED WATER PUMP
CHW CHILLER WATER
CHR CHILLED WATER RETURN
CHS CHILLED WATER SUPPLY
CI CAST IRON
CM CUBIC METER
CM/S CUBIC METER PER SECOND
CO CARBON MONOXIDE
CO2 CARBON DIOXIDE
COMP COMPRESSOR UNIT
COP COEFFICIENT OF PERFORMANCE
CP CONDENSATE PUMP
CS CONDENSATE STORAGE TANK
CSG CLEAN STEAM GENERATOR
CT COOLING TOWER
CU CONDENSING UNIT
CUH CABINET UNIT HEATER
CV CONSTANT VOLUME
CW COLD WATER (POTABLE)
CC CHILLED WATER COOLING COIL
CWP CONDENSER WATER PUMP
CWR CONDENSER WATER RETURN
CWS CONDENSER WATER SUPPLY
A
F
F FAHRENHEIT
F&T FLOAT AND THERMOSTATIC
FA FREE AREA
FC FLEXIBLE CONNECTION
FCU FAN COIL UNIT
FCUC FAN COIL UNIT COOLING ONLY
FCUH FAN COIL UNIT HEATING ONLY
FCW FORWARD CURVED WHEEL (FAN)
E
EA EXHAUST AIR
EAT ENTERING AIR TEMPERATURE
EC EVAPORATIVE COOLER
ECC ENGINEERING CONTROL CENTER
ECU EVAPORATIVE CONDENSER UNIT
EDH ELECTRIC DUCT HEATER
EER ENERGY EFFICIENCY RATIO
EF EXHAUST FAN
EGS EMERGENCY GAS SHUTOFF
EGT ENTERING GLYCOL TEMPERATURE
EH EXHAUST HOOD
EJ EXPANSION JOINT
EMD END OF MAIN DRIP (STEAM)
ENT ENTERING
ERC ELECTRIC REHEAT COIL
ERP ELECTRIC RADIANT PANEL
ESP EXTERNAL STATIC PRESSURE
ET EXPANSION TANK
ETO ETHYLENE OXIDE
ETR EXISTING TO REMAIN
EUH ELECTRIC UNIT HEATER
EWC EVAPORATIVE WATER COOLER
EWT ENTERING WATER TEMPERATURE
EX. EXISTING
D
DB DECIBELS
Db DRY-BULB TEMPERATURE
DDC DIRECT DIGITAL CONTROLS
DEG DEGREE
DIA DIAMETER
DIW DEIONIZED WATER
DP DEW POINT TEMPERATURE
DPA DIFFERENTIAL PRESSURE ASSEMBLY
DPS DIFFERENTIAL PRESSURE SENSOR
DX DIRECT EXPANSION
FD FIRE DAMPER
FF FINAL FILTER
FHX FLUE GAS/FEEDWATER HEAT EXCHANGER
FM FLOW METER
FOP FUEL OIL PUMP
FOT FUEL OIL TANK
FOHX FUEL OIL HEAT EXCHANGER
FPM FEET PER MINUTE
FPS FEET PER SECOND
FPTU FAN POWERED TERMINAL UNIT
FRP FIBER REINFORCED POLYESTER
FS FLOW SWITCH
FSTAT FREEZESTAT
FT FEET
FT-LB FOOT-POUND
FTR FIN TUBE RADIATION
FV FACE VELOCITY
FSD COMBINATION FIRE / SMOKE DAMPER
G
GA GAUGE
GAL GALLONS
GH GRAVITY HOOD
GPD GALLONS PER DAY
GPH GALLONS PER HOUR
GPM GALLONS PER MINUTE
GPR GAS PRESSURE REGULATOR
GS GALVANIZED STEEL
K kg KILOGRAM kg/HR KILOGRAM PER HOUR kPa KILOPASCAL kW KILOWATT kWh KILOWATT HOUR
J
J INTENTIONALLY LEFT BLANK
I/O INPUT/OUTPUT
IAQ INDOOR AIR QUALITY
IBT INVERTED BUCKET TRAP
ICF IN-LINE CENTRIFUGAL FAN
ID INSIDE DIAMETER
IFB INTEGRAL FACE AND BYPASS
IN INCHES
IN HG INCHES OF MERCURY
IN WC INCH WATER COLUMN
IN WG INCH WATER GAUGE
IN-LB INCH-POUND
IPLV INTEGRATED PART LOAD VALUE
IRH INFRARED HEATER
IS INSECT SCREEN
IU INDUCTION UNIT
IV INLET VANES
H
HU HUMIDIFIER
H&CW HOT & COLD WATER
HAC HOUSEKEEPING AID CLOSET
HB HOSE BIBB
HC HEATING COIL
HD HEAD
HOA HAND/OFF/AUTOMATIC
HP HEAT PUMP
HP HORSEPOWER
HPDT HIGH PRESSURE DRIP TRAP
HPC HIGH PRESSURE STEAM CONDENSATE RETURN
HPS HIGH PRESSURE STEAM (61-300 PSIG)
HRC HEAT RECOVERY COIL
HRD HEAT RECOVERY DEVICE
HRP HYDRONIC RADIANT (CEILING) PANEL
HRW HEAT RECOVERY WHEEL
HSTAT HUMIDISTAT
HTM HUMIDIFIER TERMINAL
HUM HUMIDIFIER UNIT MOUNTED
HVU HEATING AND VENTILATING UNIT
HW HOT WATER
HC HOT WATER HEATING COIL
HHP HEATING HOT WATER PUMP
HHR HEATING HOT WATER RETURN
HHS HEATING HOT WATER SUPPLY
HHUH HOT WATER UNIT HEATER
HX HEAT EXCHANGER
HZ HERTZ
I
L
L LITER
L/h LITERS PER HOUR (OR LITERS/HOUR) L/m LITERS PER MINUTE (OR LITERS/MINUTE) L/s LITERS PER SECOND (OR LITERS/SECOND)
LAT LEAVING AIR TEMPERATURE
LBS/HR POUNDS PER HOUR
LF LINEAR FOOT (FEET)
LGT LEAVING GLYCOL TEMPERATURE
LH LATENT HEAT
LPG LIQUID PROPANE GAS
LPC LOW PRESSURE STEAM CONDENSATE RETURN
CLPC LOW PRESSURE STEAM CONDENSATE (CLEAN)
LLHX LIQUID TO LIQUID HEAT EXCHANGER
LPS LOW PRESSURE STEAM (0-15 PSIG)
CLPS LOW PRESSURE STEAM (CLEAN)
LSD LINEAR SLOT DIFFUSER
LTCP LOCAL TEMPERATURE CONTROL PANEL
LVG LEAVING
LVR LOUVER
LWT LEAVING WATER TEMPERATURE
NOM NOMINAL
NPLV NON-STANDARD PART LOAD VALUE
NPSH NET POSITIVE SUCTION HEAD
NTS NOT TO SCALE
N
NA NOT APPLICABLE
NC NOISE CRITERIA
NG NATURAL GAS
NGFM NATURAL GAS FLOWMETER
NOAA NATIONAL OCEANIC & ATMOSPHERIC
ADMINISTRATION
M
M METER, SI UNIT
M/s METERS PER SECOND
(OR METERS/SECOND)
MA MIXED AIR
MAT MIXED AIR TEMPERATURE
MAU MAKE-UP AIR UNIT
MAV MANUAL AIR VENT
MAX MAXIMUM
MB MIXING BOX
MBH 1000 BTUH
MCA MINIMUM BRANCH CIRCUIT AMPACITY
MERV MINIMUM EFFICIENCY REPORTING VALUE
MH MANHOLE
MHP MOTOR HORSEPOWER
MIN MINIMUM
MM MILLIMETER
MOV MOTOR OPERATED VALVE
MPC MEDIUM PRESSURE STEAM CONDENSATE
RETURN
MPS MEDIUM PRESSURE STEAM (16-60 PSIG)
MTD MEAN TEMPERATURE DIFFERENCE
MVD MANUAL VOLUME DAMPER
MZ MULTI-ZONE
P
P PUMP
PA PASCAL
PC PUMPED CONDENSATE
PCF POUNDS PER CUBIC FOOT (FEET)
PD PRESSURE DROP
PF PRE-FILTER
PG PRESSURE GAGE
PGW PROPYLENE GLYCOL-WATER (SOLUTION)
PHC PREHEAT COIL
PPM PARTS PER MILLION
PRS PRESSURE REGULATING (VALVE) STATION
PRV PRESSURE REGULATING VALVE
PSI POUNDS PER SQUARE INCH
PSIA POUNDS PER SQUARE INCH – ABSOLUTE
PSIG POUNDS PER SQUARE INCH – GAGE
PSS PRIMARY SECONDARY SYSTEM
PSV PRESSURE SAFETY VALVE
PTAC PACKAGED TERMINAL AIR CONDITIONER
O
OA OUTSIDE AIR
OAI OUTSIDE AIR INTAKE
OD OUTSIDE DIAMETER
OFM OIL FLOWMETER
OSD ORGANIC SOIL FILTER
Q
Q INTENTIONALLY LEFT BLANK
T&PCV TEMPERATURE AND PRESSURE
CONTROL VALVE
TAB TESTING, ADJUSTING, BALANCE
TD TEMPERATURE DIFFERENCE
TDH TOTAL DYNAMIC HEAD
TDS TOTAL DISSOLVED SOLIDS
TG TRANSFER GRILLE
TP TRAP
TSP TOTAL STATIC PRESSURE
TSTAT THERMOSTAT
TU TERMINAL UNIT
TWU THRU-WALL UNIT
SA SUPPLY AIR
SAD SOUND ATTENUATING DEVICE
SAT SUPPLY AIR TEMPERATURE
SC SHADING COEFFICIENT
SCFM STANDARD CUBIC FEET PER MINUTE
SCR SILICON CONTROLLED RECTIFIER
DSD DUCT SMOKE DETECTOR
SD SMOKE DETECTOR
SEN SENSIBLE HEAT
SF SUPPLY FAN
SH STEAM HUMIDIFIER
SHC STEAM HEATING COIL
SI SQUARE INCHES
SP STATIC PRESSURE
SP GR SPECIFIC GRAVITY
SPS STATIC PRESSURE SENSOR
SQ FT SQUARE FOOT (FEET)
SS STAINLESS STEEL
SSHX STEAM TO STEAM HEAT EXCHANGER
SSR SOLID SEPARATOR
ST STEAM TRAP
SUH STEAM UNIT HEATER
SVS STEAM VENT SILENCER
SWHX STEAM TO WATER HEAT EXCHANGER
R
R/E RETURN OR EXHAUST
RA RETURN AIR
RAD REFRIGERANT AIR DRYER
RAF RADIO FREQUENCY
RAHX ROTARY AIR HEAT EXCHANGER
RAT RETURN AIR TEMPERATURE
RCCH REMOTE CONDENSER CHILLER
RCU RECIPROCATING CHILLER UNIT
RD REFRIGERANT DISCHARGE
REA RELIEF AIR
RF RETURN FAN
RH RELATIVE HUMIDITY
RHC REHEAT COIL
RHG REFRIGERANT HOT GAS
RL REFRIGERANT LIQUID LINE
RLA RUN LOAD AMPERE
RO REVERSE OSMOSIS
RPM REVOLUTIONS PER MINUTE
RS REFRIGERANT SUCTION
RTU ROOF TOP UNIT
RV RELIEF VALVE
T
UC UNDER CUT
UH UNIT HEATER
UL UNDERWRITERS LABORATORY
URV UPBLAST UNIT VENTILATOR
U
X INTENTIONALLY LEFT BLANK
W
W WATTS
WAG WASTE ANESTHESIA GAS
Wb WET-BULB (TEMPERATURE)
WC WATER COOLED
WCCH WATER COOLED CHILLER
WCCU WATER COOLED CONDENSING UNIT
WCHP WATER COOLED HEAT PUMPS
WCPU WATER COOLED PACKAGED UNIT
WF WATER FILTER
WFM WATER FLOWMETER
WG WATER GAGE
WPD WATER SIDE PRESSURE DROP
V VALVE
VAF VANE-AXIAL FAN
VAV VARIABLE AIR VOLUME
VD VOLUME DAMPER (MANUAL OPPOSED BLADE)
VFD VARIABLE FREQUENCY DRIVE
VI VIBRATION ISOLATOR
VIV VARIABLE INLET VANES
VP VACUUM PUMP
VPS VARIABLE PRIMARY SYSTEM
VR VACUUM (STEAM CONDENSATE) RETURN
VSD VARIABLE SPEED DRIVE
VUH VERTICAL UNIT HEATER
X
V
GENERAL NOTES:
A. MECHANICAL PLANS AND SECTIONS ARE INTENDED TO ACCURATELY ILLUSTRATE THE
SCOPE OF WORK BUT ARE STILL DIAGRAMMATIC IN NATURE.
B. MECHANICAL DRAWINGS DO NOT SHOW ALL ACCESSORIES TO BE INSTALLED. THE
CONTRACTOR IS RESPONSIBLE FOR ENSURING THAT ALL SYSTEMS ARE FULLY
FUNCTIONAL AND COMPLIANT WITH APPLICABLE CODES.
C. THE EXISTING CONDITIONS DEPICTED IN THESE PLANS ARE BASED ON AS-BUILT
DOCUMENTATION AND INFORMATION OBTAINED FROM FIELD SURVEYS AND ARE AS
ACCURATE AS POSSIBLE. DUE TO OBSTRUCTIONS, CEILINGS, ETC., NOT ALL CONDITIONS
COULD BE VERIFIED. THE CONTRACTOR SHALL SURVEY THE SITE PRIOR TO BID AND
NOTIFY THE ARCHITECT/ENGINEER OF ANY CONFLICTS, OBSTRUCTIONS, OR
INCONSISTENCIES PREVENTING INSTALLATION OF THE MECHANICAL SYSTEM.
D. ALL EXPOSED UNINSULATED PIPING SHALL BE PAINTED PER THE SPECIFICATION SECTION
"PAINTING".
E. COORDINATE FAN COIL (FCU) AND TERMINAL UNIT (TU/VAV/CV) REHEAT COIL RIGHT OR
LEFT HAND COIL CONNECTIONS WITH PIPING PLANS.
F. ALL FLUE AND COMBUSTION AIR PIPING FROM GAS-FIRED EQUIPMENT SHALL BE SIZED BY
THE GAS-FIRED EQUIPMENT MANUFACTURER BASED ON THE SPECIFIC PIPE ROUTING AND
ELEVATIONS FOR THIS PROJECT. REFER TO MANUFACTURERS INSTALLATION MANUAL AND
LOCAL CODE REQUIREMENTS FOR REQUIRED FLUE AND COMBUSTION AIR PIPING
MATERIALS.
G. PROVIDE VIBRATION ISOLATION FOR ALL MECHANICAL EQUIPMENT TO PREVENT
TRANSMISSION OF VIBRATION TO BUILDING STRUCTURE.
H. PROVIDE VIBRATION ISOLATORS FOR ALL PIPING SUPPORTS CONNECTED TO AND WITHIN
50' OF ISOLATED EQUIPMENT (EXCEPT AT BASE ELBOW SUPPORTS AND ANCHOR POINTS)
THROUGHOUT MECHANICAL EQUIPMENT ROOMS. DO THE SAME FOR SUPPORTS OF STEAM
MAINS WITHIN 50' OF BOILER OR PRESSURE REDUCING VALVES.
I. COORDINATE CONSTRUCTION OF ALL MECHANICAL WORK WITH ARCHITECTURAL,
STRUCTURAL, CIVIL, ELECTRICAL WORK, ETC., SHOWN ON OTHER CONTRACT DOCUMENT
DRAWINGS.
J. MAINTAIN A MINIMUM OF 6′-8″ CLEARANCE TO UNDERSIDE OF PIPES, DUCTS, CONDUITS,
SUSPENDED EQUIPMENT, ETC., THROUGHOUT ACCESS ROUTES IN MECHANICAL ROOMS.
K. ALL TESTS SHALL BE COMPLETED BEFORE ANY MECHANICAL EQUIPMENT OR PIPING
INSULATION IS APPLIED.
L. LOCATE ALL TEMPERATURE, PRESSURE, AND FLOW MEASURING DEVICES IN ACCESSIBLE
LOCATIONS WITH STRAIGHT SECTION OF PIPE OR DUCT UP AND DOWNSTREAM AS
RECOMMENDED BY THE MANUFACTURER FOR GOOD ACCURACY.
M. COORDINATE ALL EQUIPMENT CONNECTIONS WITH MANUFACTURERS CERTIFIED
DRAWINGS. COORDINATE AND PROVIDE ALL DUCT AND PIPING TRANSITIONS REQUIRED
FOR FINAL EQUIPMENT CONNECTIONS TO FURNISHED EQUIPMENT. FIELD VERIFY AND
COORDINATE ALL DUCT AND PIPING DIMENSIONS BEFORE FABRICATION.
CWR
CWS
CD
LPC
LPS
MPC
MPS
HPC
HPS
CONDENSATE DRAIN
CONDENSER WATER SUPPLY
CONDENSER WATER RETURN
HIGH PRESSURE STEAM CONDENSATE
HIGH PRESSURE STEAM SUPPLY
MEDIUM PRESSURE STEAM CONDENSATE
MEDIUM PRESSURE STEAM SUPPLY
LOW PRESSURE STEAM CONDENSATE
LOW PRESSURE STEAM SUPPLY
VACUUM RETURN
FEEDWATER PUMP DISCHARGE
FEEDWATER PUMP SUCTION
VR
CONTINUOUS BLOWDOWN
CHEMICAL FEED
BOILER BLOWOFF BO
CF
CBD
FWPD
FWPS
A. PROVIDE ALL MATERIALS AND EQUIPMENT AND PERFORM ALL LABOR REQUIRED TO
INSTALL COMPLETE AND OPERABLE PIPING SYSTEMS AS INDICATED ON THE DRAWINGS, AS
SPECIFIED AND AS REQUIRED BY CODE.
B. ELEVATIONS AS SHOWN ON THE DRAWINGS ARE TO THE CENTERLINE OF ALL PRESSURE
PIPING AND TO THE INVERT OF ALL GRAVITY PIPING.
C. MAINTAIN A MINIMUM OF 3′-6″ OF GROUND COVER OVER ALL UNDERGROUND HVAC PIPING
(EDIT DEPTH OF GROUND COVER TO SUIT FROST LINE DEPTH AND PROJECT
REQUIREMENTS).
D. UNLESS OTHERWISE NOTED, ALL CHILLED WATER AND HEATING WATER PIPING SHALL BE
3/4" SIZE (EDIT SYSTEM TYPE OR PIPE SIZE TO SUIT PROJECT REQUIREMENTS).
E. PROVIDE AN AIR VENT AT THE HIGH POINT OF EACH DROP IN THE HEATING WATER, CHILLED
WATER, AND OTHER CLOSED WATER PIPING SYSTEMS (EDIT SYSTEM TYPES TO SUIT
PROJECT REQUIREMENTS). ALL PIPING SHALL GRADE TO LOW POINTS. PROVIDE HOSE END
DRAIN VALVES AT THE BOTTOM OF ALL RISERS AND LOW POINTS.
F. UNLESS OTHERWISE NOTED, ALL PIPING IS OVERHEAD, TIGHT TO UNDERSIDE OF
STRUCTURE OR SLAB, WITH SPACE FOR INSULATION IF REQUIRED.
G. INSTALL PIPING SO THAT ALL VALVES, STRAINERS, UNIONS, TRAPS, FLANGES, AND OTHER
APPURTENANCES REQUIRING ACCESS ARE ACCESSIBLE.
H. ALL VALVES SHALL BE INSTALLED SO THAT VALVE REMAINS IN SERVICE WHEN EQUIPMENT
OR PIPING ON EQUIPMENT SIDE OF VALVE IS REMOVED.
I. ALL BALANCING VALVES AND BUTTERFLY VALVES SHALL BE PROVIDED WITH POSITION
INDICATORS AND MAXIMUM ADJUSTABLE STOPS (MEMORY STOPS).
J. PROVIDE CHAINWHEEL OPERATORS FOR ALL VALVES IN EQUIPMENT ROOMS MOUNTED
GREATER THAN 7′-0″ ABOVE FLOOR LEVEL; CHAIN SHALL EXTEND TO 7′-0″ ABOVE FLOOR
LEVEL.
K. ALL VALVES (EXCEPT CONTROL VALVES) AND STRAINERS SHALL BE FULL SIZE OF PIPE
BEFORE REDUCING SIZE TO MAKE CONNECTIONS TO EQUIPMENT AND CONTROLS.
L. UNIONS AND/OR FLANGES SHALL BE INSTALLED AT EACH PIECE OF EQUIPMENT, IN
BYPASSES, AND IN LONG PIPING RUNS (100' OR MORE) TO PERMIT DISASSEMBLY FOR
ALTERATION AND REPAIRS.
M. PITCH STEAM PIPING DOWNWARD IN THE DIRECTION OF FLOW 1/4" IN 10' (1" IN 40') MINIMUM.
PITCH ALL STEAM RETURN LINES DOWNWARD IN THE DIRECTION OF CONDENSATE FLOW
1/2" PER 10' (1" IN 20') MINIMUM. WHERE LENGTH OF BRANCH LINES ARE LESS THAN 8', PITCH
BRANCH LINES TOWARD MAINS 1/2" PER FOOT MINIMUM.
N. PITCH UP ALL STEAM AND CONDENSATE RUNOUTS TO RISERS AND EQUIPMENT 1/2" PER
FOOT. WHERE THIS PITCH CANNOT BE OBTAINED, RUNOUTS OVER 8' IN LENGTH SHALL BE
ONE SIZE LARGER THAN NOTED.
O. TAP ALL BRANCH LINES FROM TOP OF STEAM MAINS (45° PREFERRED, 90° ACCEPTABLE).
A. PROVIDE ALL MATERIALS AND EQUIPMENT AND PERFORM ALL LABOR REQUIRED TO
INSTALL COMPLETE AND OPERABLE HVAC SYSTEMS AS INDICATED ON THE DRAWINGS, AS
SPECIFIED AND AS REQUIRED BY CODE.
B. CERTAIN ITEMS SUCH AS RISES AND DROPS IN DUCTWORK, ACCESS DOORS, VOLUME
DAMPERS, ETC., ARE INDICATED ON THE CONTRACT DOCUMENT DRAWINGS FOR CLARITY
FOR A SPECIFIC LOCATION REQUIREMENT AND SHALL NOT BE INTERPRETED AS THE
EXTENT OF THE REQUIREMENTS FOR THESE ITEMS.
C. IN CORRIDORS WHERE CEILING SPEAKERS AND AIR DIFFUSERS ARE INDICATED BETWEEN
THE SAME LIGHT FIXTURES, INSTALL BOTH DEVICES AT THE QUARTER POINTS BETWEEN
THE SAME FIXTURE.
D. UNLESS OTHERWISE SHOWN, LOCATE ALL ROOM THERMOSTATS AND HUMIDISTATS 4′-0″
(CENTERLINE) ABOVE FINISHED FLOOR.
E. ALL DUCTWORK SHALL CLEAR DOORS AND WINDOWS.
F. ALL DUCTWORK DIMENSIONS, AS SHOWN ON THE DRAWINGS, ARE INTERNAL CLEAR
DIMENSIONS AND DUCT SIZE SHALL BE INCREASED TO COMPENSATE FOR DUCT LINING
THICKNESS.
G. PROVIDE ALL 90° SQUARE ELBOWS WITH DOUBLE RADIUS TURNING VANES UNLESS
OTHERWISE INDICATED. ELBOWS IN DISHWASHER, KITCHEN, AND LAUNDRY EXHAUST
SHALL BE UNVANED SMOOTH RADIUS CONSTRUCTION WITH A RADIUS EQUAL TO 1.5 TIMES
THE WIDTH OF THE DUCT. PROVIDE ACCESS DOORS UPSTREAM OF ALL ELBOWS WITH
TURNING VANES.
H. COORDINATE DIFFUSER, REGISTER, AND GRILLE LOCATIONS WITH ARCHITECTURAL
REFLECTED CEILING PLANS, LIGHTING, AND OTHER CEILING ITEMS AND MAKE MINOR DUCT
MODIFICATIONS TO SUIT.
I. FIELD ERECTED AND FACTORY ASSEMBLED AIR HANDLING UNIT COILS SHALL BE
ARRANGED FOR REMOVAL FROM THE UPSTREAM SIDE WITHOUT DISMANTLING SUPPORTS.
PROVIDE GALVANIZED STRUCTURAL STEEL SUPPORTS FOR ALL COILS (EXCEPT LOWEST
COIL) IN BANKS OVER TWO COILS HIGH TO PERMIT INDEPENDENT REMOVAL OF ANY COIL.
J. ALL AIR HANDLING UNITS SHALL OPERATE WITHOUT MOISTURE CARRYOVER.
K. LOCATE ALL MECHANICAL EQUIPMENT (SINGLE DUCT, DUAL DUCT, VARIABLE VOLUME,
CONSTANT VOLUME AND FAN POWERED BOXES, FAN COIL UNITS, CABINET HEATERS, UNIT
HEATERS, UNIT VENTILATORS, COILS, STEAM HUMIDIFIERS, ETC.) FOR UNOBSTRUCTED
ACCESS TO UNIT ACCESS PANELS, CONTROLS AND VALVING.
L. FINNED TUBE RADIATION ENCLOSURES SHALL BE WALL TO WALL UNLESS OTHERWISE
INDICATED.
M. PROVIDE FLEXIBLE CONNECTIONS IN ALL DUCTWORK SYSTEMS (SUPPLY, RETURN, AND
EXHAUST) CONNECTED TO AIR HANDLING UNITS, FANS, AND OTHER EQUIPMENT WHICH
REQUIRE VIBRATION ISOLATION. FLEXIBLE CONNECTIONS SHALL BE PROVIDED AT THE
POINT OF CONNECTION TO THE EQUIPMENT UNLESS OTHERWISE INDICATED.
PIPING GENERAL NOTES: HVAC/SHEET METAL GENERAL NOTES:
EXISTING TO BE DEMOLISHED
LIMIT OF DEMOLITION
CONNECT NEW TO EXISTINGEXISTING TO REMAIN
NEW DUCT (INSIDE DIMENSIONS: W" X D")
RS
RL
REFRIGERANT SUCTION
REFRIGERANT LIQUID
SUPPLY AIR DUCT UP
SUPPLY AIR DUCT DOWN
H
T
H
T
26-P-3
MH-100
PUMP NO. 3 IN BUILDING NO. 26
EQUIPMENT ABBREVIATION (PUMP)
DETAIL NUMBER
SHEET NUMBER
SHEET NUMBER
SECTION NUMBER
THERMOSTAT
HUMIDISTAT
TEMPERATURE SENSOR
HUMIDITY SENSOR
BUILDING NUMBER WHERE EQUIPMENT IS LOCATED
26-TU-1-1
ITEM NUMBER (TERMINAL UNIT NO. 1)
ITEM (TERMINAL UNIT)
BUILDING NUMBER WHERE EQUIPMENT IS LOCATED
SERVED BY AIR HANDLER UNIT NO. 1
TERMINAL UNIT TAG
MECHANICAL EQUIPMENT TAG
1 OWNER FURNISHED, CONTRACTOR
INSTALLED EQUIPMENT DESIGNATION
EXISTING TO BE DEMOLISHED
EXISTING TO REMAIN
NEW PIPE
CONNECT NEW TO EXISTING
LIMIT OF DEMOLITION
GENERAL PIPING SYMBOLS
GENERAL ANNOTATIONS
AV
STRAINERFLOAT & THERMOSTATIC
STEAM TRAP
INVERTED BUCKET
STEAM TRAP
FLANGE CONNECTION PIPE DROP
PIPE RISER TEE DOWN
TEE UP
UNION
PRESSURE REDUCING
VALVE
BALL VALVE
ANGLE GLOBE VALVE
SAFETY RELIEF VALVE
GLOBE VALVE
MANUAL OR
AUTOMATIC AIR VENT
EXPANSION JOINT
EJ
PRESSURE AND
TEMPERATURE TEST PLUG
QUICK-COUPLE HOSE
CONNECTOR
FLOW METER
HVAC PIPING SYMBOLS
CHILLED WATER RETURN
CHILLED WATER SUPPLY
CHR
CHS
HEATING HOT WATER RETURN
HEATING HOT WATER SUPPLY
HHR
HHS QV CRYOGEN VENT
DR DRIP RETURN
CAP
REDUCER (ECCENTRIC)
TYPE
AIRFLOW (CFM)
SD-1
TYPE
AIRFLOW (CFM)
RG-1
TYPE
AIRFLOW (CFM)
EG-1
SQUARE TO ROUND TRANSITION
ELBOW WITH TURNING
VANES
ROUND ELBOW
EXHAUST, RELIEF, MAKE UP, OR
OUTSIDE AIR DUCT DOWN
EXHAUST, RELIEF, MAKE UP, OR
OUTSIDE AIR DUCT UP
RETURN DUCT DOWN
RETURN DUCT UP
BRANCH DUCT WITH HIGH EFFICIENCY
TAKE-OFF (HETO) BRANCH FITTING &
MANUAL VOLUME DAMPER
BRANCH DUCT WITH CONICAL
FITTING & MANUAL VOLUME
DAMPER
DAMPERS: (BD, FD, FSD, MD, SD, VD)
BD
XX-XX
ANCHOR
TEEDIRECTION OF FLOW
S
N. CONCRETE HOUSEKEEPING PADS TO SUIT MECHANICAL EQUIPMENT SHALL BE SIZED AND
LOCATED BY THE MECHANICAL CONTRACTOR. MINIMUM CONCRETE PAD THICKNESS SHALL
BE 4". PAD SHALL EXTEND BEYOND THE EQUIPMENT A MINIMUM OF 4" ON EACH SIDE.
CONCRETE HOUSEKEEPING PADS SHALL BE PROVIDED BY THE GENERAL CONTRACTOR. IT
SHALL BE THE RESPONSIBILITY OF THE MECHANICAL CONTRACTOR TO COORDINATE SIZE
AND LOCATION OF CONCRETE HOUSEKEEPING PADS.
O. WHEN MECHANICAL WORK (HVAC, PLUMBING, SHEET METAL, ETC.) IS SUB-CONTRACTED, IT
SHALL BE THE MECHANICAL CONTRACTOR’S RESPONSIBILITY TO COORDINATE
SUBCONTRACTORS AND THE ASSOCIATED CONTRACTS. WHEN DISCREPANCIES ARISE
PERTAINING TO WHICH CONTRACTOR PROVIDES A PARTICULAR ITEM OF THE MECHANICAL
CONTRACT OR WHICH CONTRACTOR PROVIDES FINAL CONNECTIONS FOR A PARTICULAR
ITEM OF THE MECHANICAL CONTRACT, IT SHALL BE BROUGHT TO THE ATTENTION OF THE
MECHANICAL CONTRACTOR, WHOSE DECISION SHALL BE FINAL.
P. THE LOCATIONS OF ALL ITEMS SHOWN ON THE DRAWINGS OR CALLED FOR IN THE
SPECIFICATIONS THAT ARE NOT DEFINITELY FIXED BY DIMENSIONS ARE APPROXIMATE
ONLY. THE EXACT LOCATIONS NECESSARY TO SECURE THE BEST CONDITIONS AND
RESULTS MUST BE DETERMINED BY THE PROJECT SITE CONDITIONS AND SHALL HAVE THE
APPROVAL OF THE ENGINEER BEFORE BEING INSTALLED. DO NOT SCALE DRAWINGS.
Q. ALL MISCELLANEOUS STEEL REQUIRED TO ENSURE PROPER INSTALLATION AND AS SHOWN
IN DETAILS FOR PIPING, DUCTWORK, AND EQUIPMENT (UNLESS OTHERWISE NOTED) SHALL
BE FURNISHED AND INSTALLED BY THE MECHANICAL CONTRACTOR.
R. PROVIDE ACCESS PANELS FOR INSTALLATION IN WALLS AND CEILINGS WHERE…