This is a final bid results document for the Thompson's Mills Electrical and Fire Risk Reduction Project (OPRD #12488, OregonBuys #S-63400-00012388) administered by Oregon Parks and Recreation Department, with a bid closing date of January 21, 2025. The project consists of three main components: mobilization/overhead, removal of existing electrical equipment and circuitry, and installation of new electrical equipment and circuitry. The document indicates these are preliminary results pending final evaluation.
Two contractors submitted bids for the project: M&W Electric of Albany, OR and La Londe Electric of Estacada, OR. M&W Electric's total bid was $229,976.17, broken down as $30,655.93 for mobilization, $55,682.12 for removal work, and $143,638.12 for new installation. La Londe Electric bid $170,922.00 total, with $11,597.00 for mobilization, $8,978.00 for removal, and $150,347.00 for new installation. A third company, MD Electrical Services from Oregon City, is listed but did not submit pricing. The document notes that M&W Electric's bid was rejected.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FINAL BID RESULTS
FINAL BID RESULS
| OPRD # | 12488 | ||||||||
| OregonBuys # | S-63400-00012388 | ||||||||
| Closing: | 1/21/2025 | ||||||||
| Title: | Thompsons Mills Electrical and Fire Risk Reduction Project | ||||||||
| M&W Electric | La Londe Electric | MD Electrical Services | |||||||
| 29889 Hwy 34 SE | 1000 NW Commerce Court | 20068 Hwy 213 | |||||||
| Albany, OR | Estacada, OR 97023 | Oregon City, OR 97045 | |||||||
| Item # | Description | Quantity | Unit | TOTAL COST | TOTAL COST | TOTAL COST | |||
| A1. | Mobilization/Overhead | All | LS | $ 30,655.93 | $ 11,597.00 | ||||
| A2. | Removal of electrical equipment and circuitry | 1 | LS | $ 55,682.12 | $ 8,978.00 | ||||
| A3. | Installation of new electrical equipment and circuitry | 1 | LS | $ 143,638.12 | $ 150,347.00 | ||||
| Total | bid rejected | $ 229,976.17 | $ 170,922.00 |