Final 676-26-702 DDPO SOW.pdf

PDF 349 KB Posted

Attached to
Z2DA--Install DDPO per CSR 676-26-702 Tomah
Solicitation number
36C77626Q0144
Issued by

About this file

This is a Scope of Work Memorandum for a Department of Veterans Affairs construction project at Tomah VA Medical Center in Tomah, Wisconsin. The project (676-26-702) supports the Electronic Health Records Modernization (EHRM) initiative and a 2025 Current State Review (CSR) assessment. The Contracting Officer's Representative is Jason Erdman, and the project completion deadline is 95 calendar days from Notice to Proceed, with a bid walk scheduled at a date and time to be established by the contracting officer.

The contractor must supply all equipment, labor, materials, and supervision to install Data Drops and Power Outlets (DDPOs), fiber cable terminations, and new emergency phone cable at 52 identified locations throughout the medical center. Work includes pulling new CAT 6A cable from new telecommunications closets to existing emergency phones (red phones), elevators, basement phones, and courtesy phones, as well as demolishing existing cables. The contractor must conduct pre-construction risk assessments (PCRA) and Infection Control Risk Assessments (ICRA) per VA Standard EC 02 06 05, replace damaged ceiling tiles, and repair painted surfaces affected by installation work. All work must comply with VA standards, NEC Standards, OEHRM requirements, OIT Design Guide, and Infrastructure Standard for Telecommunication Spaces (ISTS). The contractor must designate a single point of contact for weekly progress reporting and coordination with the COR, submit preconstruction deliverables including an Accident Prevention Plan and Activity Hazard Analyses, maintain proper barricade and signage, and protect all VA non-public information through encryption and secured network storage. Work is scheduled during normal business hours (Monday-Friday, 7:30 AM-4:30 PM), with preliminary milestones including a pre-construction kickoff meeting at NTP+5 days, pre-construction submittals at NTP+10 days, 50% completion at NTP+75 days, and final completion at NTP+90 days.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tomah VA Medical Center Project Engineering

SCOPE OF WORK MEMORANDUM

Project General Data:

o Title: 676-26-702 Install DDPO per CSR o Rev: 1 o Location: Tomah VA Medical Center o Project #: 676-26-702 o COR: Jason Erdman o Time requirement: 95 days from Notice to Proceed o Bid walk: Date and time to be established by the contracting officer

I. Background:

The intent of this project is to provide construction services for a Department of Veteran Affairs Electronic Health Records Modernization (EHRM) project initiative and a 2025 Current State Review (CSR) going on at the Tomah VA medical Center, in Tomah, WI. The initiative is an implementation and the deployment of a new Electronic Health Record (EHR) system across federal entities and install additional Data Drop and Power Outlets (DDPO’s) as identified during the CSR assessment.

II. Project Scope:

1. The construction contractor shall supply all equipment, labor, materials, and supervision to complete project upgrades which includes installation of Data Drops and Power Outlets, fiber cable terminations, and new cable for emergency phones at identified rooms and building locations.

2. Conduct and incorporate pre-construction risk assessments (PCRA) and Infection Control Risk Assessments (ICRA) for air quality, infection control, noise, vibration, or any other hazards applicable to their work per VA Standard EC 02 06 05. See ICRA Matrix of Precautions for Construction and Renovation. See Attachment 1 ICRA Assessments 67626702.

3. Pull new cable (CAT 6A) from new TR closets to existing site emergency (Red Phones), elevators, basement phones, and/or courtesy phones/communications devices at, QTY (52) locations. See “Analog Phone List” below.

o Demo existing cables for existing phones or communications.

Analog Phone List

4. Contractor to complete all work in accordance with:

o VA standards and Construction Specifications.

o NEC Standards o Office of Electronic Health Record Modernization (OEHRM) Site

Infrastructure, and End user Device (EUD) requirements (Latest Revision) o OIT Design Guide, and design templates o Infrastructure Standard for Telecommunication Spaces (ISTS) (Latest

Version).

5. Replace any damaged ceiling tiles due to the course of work.

6. Touchup/repair/paint and damaged walls or ceilings due to new installation of wire and cable, conduit installations, etc.

7. Contractor to perform documented pre-construction risk assessments (PCRA) and

Infection Control Risk Assessments (ICRA) for air quality, infection control, noise, vibration, or any other hazards applicable to their work.

8. Contractor shall identify a single point of contact that will be responsible for reporting progress, conducting weekly progress meetings with updates, submitting RFI’s timely, etc. to the Contracting Officers Representative (COR).

9. All work shall be completed within 95 calendar days after receiving the NTP.

o Schedule:

o NTP = Notice to Proceed o NTP + 5 = Pre-construction kickoff meeting o NTP + 10 days = Pre-construction submittals o NTP + 15 days = VA review of pre-construction submittals o NTP + 20 days = Transport and delivery of materials and construction kickoff meeting o NTP + 75 days = Complete approximately 50% of the work o NTP + 90 days = Complete approximately 100% of the work o NTP + 95 days = Project Closeout o This project shall be completed within Ninety-Five (95) days once NTP is issued.

Pre-construction (kick-off) Meeting is anticipated to be scheduled on the effective date identified in the NTP.

III. Flow of requirements to subcontractors

1. The Contractor shall incorporate the substance of this clause, its terms, and requirements including this paragraph, in all subcontracts under this contract, and require written subcontractor acknowledgment of same.

IV. Flow of requirements to subcontractors

a) Work done on-site at the Tomah VA Medical Center shall be coordinated with the

Contracting Officer Representative (COR) appointed by the CO. Generally, work will be done during normal business hours (M-F 7:30-4:30), holidays excluded.

b) Refer to VA Guidebooks, and specifications for details of this project.

c) The contractor shall attend a project kickoff teleconference.

d) The Contractor shall provide weekly updates, to the COR of completion of work via team’s

e) Contractor shall prepare preconstruction deliverables such as Accident

Prevention Plan, Activity Hazard Analyses, and Waste Management Plan, and provide worker training certificates and product data submittals for the materials to be used.

f) Contractors shall have proper barricade and signage to limit access to work zone(s).

g) The contractor will provide any disposal documentation.

h) The C&A requirements do not apply, and a Security Accreditation Package is not required.

i) The contractor ensures all VA non-public information is protected and will ensure to encrypt when transmitting via email and store information in a secured network.

SCOPE OF WORK MEMORANDUM
o Title: 676-26-702 Install DDPO per CSR
o Rev: 1
o Location: Tomah VA Medical Center
o Project #: 676-26-702
o COR: Jason Erdman
o Time requirement: 95 days from Notice to Proceed
o Bid walk: Date and time to be established by the contracting officer