About this file

This is a Request for Proposal (RFP) Scope of Work document from Pinellas County, Florida, involving the Florida Department of Environmental Protection (FDEP) for an Urban Stream Restoration project focused on Joe's Creek. The project aims to improve water quality through innovative phosphorus mitigation techniques, specifically targeting a 9.8-mile-long urbanized stream within a 9,256-acre watershed. The demonstration project will be implemented over a 12-month period in summer 2026, utilizing lanthanum-based chemical treatments to sequester phosphorus in both the water column and lake sediments, with the goal of reducing nutrient loads and improving ecosystem function.

The project is funded through a grant with a total budget of $901,840, broken down into four primary tasks: Quality Assurance Project Plan ($5,000), Design and Project Management ($225,000), Treatment Application and Monitoring ($671,840), and Final Report and Presentation ($25,000). The project will employ automated inline injection technology and sediment treatments to mitigate an estimated 2,100 pounds of phosphorus, using approximately 2,700 gallons of EutroSORB SI for sediment and 2,000 gallons of EutroSORB WC for water column treatment. Comprehensive monitoring will be conducted using three NuLAB automated monitoring systems, with water quality and sediment samples analyzed before, during, and after treatment to quantify phosphorus mitigation effectiveness.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP Scope of Work

PROJECT TITLE: Urban Stream Restoration Utilizing Phosphorus Mitigation and Realtime Variable Rate Injection and Monitoring Systems

PROJECT LOCATION: Joe’s Creek (WBID 1668A and 1668E) is a 9.8-mile-long urbanized stream that flows through Lealman and Kenneth City in Pinellas County, Florida. Its watershed spans 9,256 acres. Within Joe’s Creek flow path are four small lakes, which collectively encompass approximately 25 acres. The creek begins at Silver Lake and flows from east to west until it discharges into Cross Bayou, which flows into Boca Ciega Bay, and ultimately, the Gulf of Mexico.

PROJECT BACKGROUND: The 9,256-acre Joe’s Creek Watershed includes the cities of Pinellas Park, Kenneth City, and St. Petersburg, as well as unincorporated Pinellas County (Lealman). There are four small lakes within Joe’s Creek flow path, which encompass approximately 25 acres. The creek is primarily used for stormwater conveyance capacity and flood risk reduction. Pinellas County monitors one fixed site along the freshwater portion of Joe’s Creek eight times a year depicted as site 35-10 in Figure 1. Pinellas County also monitors site 35-04 along Bonn Creek which flows into Joe’s Creek from the north and site 35-12 along Miles Creek, which diverges from Joe’s Creek at 66th St N, and flows through St. Petersburg (Figure 1).

The tidal portion of Joe’s Creek (WBID 1668E) is impaired for dissolved oxygen (DO) and chlorophyll-a, while the freshwater portion is impaired for DO. Joe’s Creek has also exhibited increasing trends in total nitrogen (TN), total phosphorus (TP), total suspended solids, and turbidity. Joe’s Creek is impaired for biology; the most recent (2022) Stream Condition Index score for the creek was 27; a score greater than 40 is deemed “passing.” Many portions of the creek are dominated by nuisance exotic vegetation, such as Hydrilla, Pontedaria crassipes (water hyacinth), and Ludwigia spp.

Phosphorus (P) pollution drives the primary productivity of most surface waters in Florida. The mitigation of this pollution results in the rapid improvement of water quality shifting ecosystem function to a less favorable environment for the formation of harmful algal blooms. These favorable ecosystem shifts to more diverse native species coupled with nutrient reductions are long-lasting environmental transformations that provide enhanced water quality and outdoor recreational benefits to surrounding communities.

PROJECT DESCRIPTION: Pinellas County is invested in improving Joe’s Creek water quality so local urban communities can enjoy outdoor recreational opportunities centered around safe, clean, and enjoyable water. This project involves coupling innovative chemical application and monitoring approaches to remove P within the waters of Joe’s Creek as well as inactivating legacy P in the sediment of the four small lakes within Joe’s Creek flow path. This project proposes an inline automated injection technology for continuous application of a lanthanum-based P sequestration agent into Joe’s Creek, as well as the application of lanthanum-based treatments to sequester sediment-bound P within the four lakes.

Implementation of this project is proposed to occur on land owned by Pinellas County. The purpose of this demonstration project is to inactivate legacy P in the four small lakes and reduce water column P concentrations in Joe’s Creek. The benefits of this demonstration include reduced P levels with improved water quality and ecosystem function moving downstream to Cross Bayou, as well as treatment of legacy P in the sediment. This project will be implemented over a one-year period and long-term maintenance and nutrient-mitigation strategies could be developed based upon the results. The management of legacy P will provide rapid water quality improvement in Joe’s Creek and allow for the expansion of native aquatic vegetation and reduction of nutrient loads into Cross Bayou and the Gulf, which will help to enhance a more diverse ecosystem and local economy. The combined estimated P load in the sediment and flowing water of Joe’s Creek to be mitigated during the 12-month demonstration is ~2,100 lbs (includes Joe’s Creek water column and top 4-cm of sediment in the four small lakes). The project cost-effectiveness will be measured by determining the cost/lb-P mitigated in Joe’s Creek compared to costs associated with best management practices approaches, such as Phoslock®, alum treatments, or mechanical removal.

The design of the Joe’s Creek Nutrient Mitigation Plan utilized historical sediment data, recent water quality measurements, and flow data from an active United States Geological Survey (USGS) gaging station to develop a sediment inactivation strategy for the four small lakes along the creek, employing two lanthanum-based chemistries. The approach for Joe’s Creek involves the automated inline injection of EutroSORB WC, a liquid lanthanum-based solution for stripping P from the water column. Another component of the project will include in-lake sediment inactivation within the four small lakes using EutroSORB SI, a liquid P-binding solution for sediment inactivation. Once applied, lanthanum ions react preferentially with phosphate compounds and rapidly form a highly stable insoluble mineral. The resulting mineral complex becomes integrated as an inert component into the natural sediments of the waterbody and is not bioavailable. Due to the specificity of EutroSORB materials to phosphate it will continually bind new incoming P from internal and external sources. During application, EutroSORB SI sediment inactivator is applied as a liquid over the surface of the lakes as a single blanket treatment. The proposed 12-month project would be implemented in the summer of 2026 with the application of no more than 2,700 gallons of EutroSORB SI to mitigate an estimated 1,100 lbs of P in the top 4-cm of sediment and the automated injection of ~2,000 gallons of EutroSORB WC to mitigate an estimated 1,000 pounds of P in the water column of Joe’s Creek.

To monitor success of the project, water quality grab samples as well as continuous data collection with three NuLAB™ automated monitoring systems (Figure 1) will be implemented to collect pre-treatment, during and post-treatment samples over the 12-month demonstration period. At a minimum, the following water quality parameters will be collected/analyzed: TP, soluble reactive P, TN, nitrite, nitrate, DO, turbidity, pH, and temperature. In addition, pre- and post-treatment sediment samples will be collected from the four lakes and analyzed for percent solids in addition to the following P fractions as mg P/kg: labile P, reductant-soluble P, metal-oxide P, organic P, and apatite/residual. The pre-treatment sediment samples will be compared to post-treatment sediment samples to quantify the amount of bioavailable P that transforms into non-bioavailable mineralized forms of P. The Contractor will conduct acute and chronic whole Effluent Toxicity (WET) jar testing prior to the application of EutroSORB WC and EutroSORB SI. The Contractor will also conduct acute and chronic whole Effluent Toxicity (WET) pre- and post-treatment of EutroSORB WC and EutroSORB SI. To quantify demonstration performance the pre-treatment water quality and sediment samples will be compared to post-treatment samples and provide the total pounds of P mitigated in the sediment and water column during the 12-month demonstration.

Task #1: Quality Assurance Project Plan (QAPP) Task Description: The Contractor will prepare, submit, and receive approval on a Quality Assurance Project Plan (QAPP) prior to commencement of any sampling, laboratory experiments and analyses and data analyses associated with the project. The QAPP must specify the sampling procedures, locations, instruments, frequency, and parameters to be sampled.

Deliverable #1a: Draft QAPP:

The Draft QAPP in Word format to Pinellas County (County). Upon request, the Contractor will provide a paper copy of the Draft QAPP to the County.

Performance Standard: The County and Florida Department of Environmental Protection (FDEP) will ensure review of the draft QAPP for compliance with this Agreement and the quality assurance requirements, to ensure sufficient monitoring is planned to measure project effectiveness and provide comments to the Contractor as needed prior to Final QAPP submittal.

Deliverable #1b: Final QAPP Final County-approved QAPP submitted electronically in PDF format to the County. Upon request, the Contractor will provide a paper copy of the Final QAPP to the County.

Performance Standard: The County and FDEP will review the Final QAPP to ensure that draft comments have been incorporated and the Final QAPP is in compliance with this Agreement and the quality assurance requirements. Upon review and written approval from the County and FDEP of the Final QAPP, the Contractor may proceed to Task 2.

Task #2: Design, Permitting and Project Management Task Description: The Contractor will oversee the project design and necessary permitting. The Contractor will also perform project management, to include field services, site meetings with sub-contractor(s), and overall project coordination, implementation, and supervision. As part of the project design the Contractor will conduct acute and chronic jar WET testing using water from the waterbody before treating with Eutrosorb SI and Eutrosorb WC. The Contractor will conduct the WET testing with a combination of the two lanthanum-based chemicals.

Deliverable #2a: The Contractor will submit an electronic copy of 1) the final design, including professional certification as applicable, and 2) a list of all required permits identifying issue dates and issuing authorities submitted to the County. Upon request, the Contractor will provide copies of obtained permits or permit-related correspondence or documentation and/or a paper copy of the final design.

Performance Standard: The County and FDEP will review the deliverables to verify that they meet the specifications in the Grant Work Plan and this task description. Upon review and written acceptance by the County’s Grant Manager of each deliverable under this task the Contractor may proceed with payment request submittal.

Deliverable #2b: The Contractor will submit an electronic copy of the WET testing results to the County for approval. Upon request, the Contractor will provide a paper copy of the results.

Performance Standard: The County and FDEP will review the WET testing results. Upon review and written acceptance by the County and FDEP of all deliverables under this task, the Contractor may proceed to Task 3.

Task #3: Treatment Application & Monitoring Task Description: The Contractor will conduct treatment application and monitoring, and water quality and sediment sampling in accordance with the County-approved QAPP for this project (see Task 1).

Deliverable #4: The Contractor will submit a summary of completed monitoring activities (dates completed, sampling conducted and any not conducted and why, monitoring results along with interpretation of those results (as expected or not as expected)) submitted electronically, along with the draft or final (when submitting final request) laboratory report and sampling logs (must also have field and weather data) to the County. Upon request, the Contractor will provide a paper copy or copies to the County. These deliverables may be submitted no more frequently than monthly.

Performance Standard: The County and FDEP will review the monitoring results for completion and compliance with QAPP requirements. Upon review and written acceptance by the County and FDEP each deliverable under this task, the Contractor may proceed with payment request submittal.

Task #4: Final Report and Presentation Task Description: The Contractor will submit a Final Report and Presentation summarizing the results of the project, including all tasks agreed upon. The Final Report must include at a minimum:

· A 1–2-page executive summary which will include a brief introduction, the purpose of the study, the Contractor’s findings, recommendations, the limitations of the Contractor’s report, any implementation guidelines or procedures, and a conclusion (not included in Final Presentation).

· Project location and background, project description and timeline, grant award amount and anticipated benefits.

· Financial summary of actual costs versus the budget, along with any changes required to the budget. Include any match or locally pledged contributions provided, along with other related project work performed outside of this Agreement to identify the overall project cost.

· Discussion of project schedule versus actual completion, including changes required to the schedule, unexpected site conditions and adjustments, significant unexpected delays and corrections, and/or other significant deviations from the original project plan.

· Summary of activities completed as well as those not completed and why, as well as a brief summary of any additional phases yet to be completed.

· Date-stamped photographic documentation of work performed (before, during and after), appropriate figures (site location, site plan[s]. etc.), appropriate tables summarizing data/information relevant to the project’s FDEP Grant Work Plan tasks, and appropriate attachments relevant to the project.

· Summary of research activities completed and any not completed and why, experimental results, and an interpretation of data based on planned versus realized results.

· Discussion of whether the anticipated benefits have been/will be realized.

The Contractor has the option to provide the County and FDEP with a virtual presentation (Microsoft Teams) or an in-person presentation of their Final Report. Please note that travel expenses for the in-person presentation are not reimbursable or allowable. The presentation will be no more than 60 minutes and will have sufficient time for questions and answers.

Deliverable #4a: Draft Final Report The Contractor will submit an electronic copy of the draft Final Report in Word format to the County’s Grant Manager for review prior to submission of the Final Report. Upon request, the Contractor will provide a paper copy of the draft Final Report.

Performance Standard: The County and FDEP will review the submitted draft Final Report to verify that it meets the specifications in the project’s FDEP Grant Work Plan and this task description and provide any comments to the Contractor for incorporation into the Final Report.

Deliverable #4b: Final Report The Contractor will submit an electronic copy of the Final Report, with all suggested changes incorporated, in PDF format, to the County for review and approval by the County and FDEP. Upon request, the Contractor will provide a paper copy of the Final Report.

Performance Standard: The County and FDEP will review the Final Report to verify that it meets the specifications in the project’s FDEP Grant Work Plan and this task description. Upon review and written approval by the County and FDEP of the Final Report, the Contractor may proceed with the Final Report Presentation.

Deliverable #4c: Project Presentation The Contractor will submit an electronic copy of the Project Presentation prior to presentation day. Upon request, the Contractor will provide a paper copy of the Project Presentation.

Performance Standard: Upon completion of the presentation of the project and written approval by the County and FDEP of the Project Presentation, the Contractor may proceed with payment request submittal for this task.

PROJECT TIMELINE: The tasks must be completed by the corresponding task end date and all deliverables must be received by the designated due date.

Task/ Deliverable No.
Task or Deliverable Title
Task Start Date
Task End Date
Deliverable Due Date/ Frequency
1
Quality Assurance Project Plan
Upon Execution
180 days after Execution
1a
Draft QAPP

90 Days before the Task End Date

1b
Final QAPP

30 Days before the Task End Date

2
Design, Permitting, and Project Management
Upon Execution
09/01/2026
Upon Completion of Task
3
Treatment Application and Monitoring
Upon Execution
09/01/2027
Upon Completion of Task
4
Final Report and Presentation
Upon Execution
1/31/2028
4a
Draft Final Report

10/31/2027

4b
Final Report

11/30/2027

4c
Final Presentation

12/31/2027

PROJECT BUDGET SUMMARY: Cost reimbursable grant funding must not exceed the category totals for the project as indicated below.

Category Totals
Grant Funding, Not to Exceed, $
Contractual Services Total
$337,941.00
Miscellaneous/Other/Supplies Expenses Total
$563,899.00
Total:
$901,840.00
Task and Description
Cost
Payment Type
Task 1 Quality Assurance Project Plan (QAPP)
$5,000
Lump Sum
Task 2 Design, Permitting and Project Management
$225,000
Lump Sum
Task 3 Treatment Application & Monitoring
$671,840
Lump Sum
Task 4 Final Report and Presentation
$25,000
Lump Sum
Grand Total Fee
$901,840

Figure 1. Map of the proposed treatment area of Joe's Creek. The yellow, numbered points represent water quality stations that are monitored by Pinellas County periodically up to eight times a year. Each continuous monitoring station will contain a NuLAB™ automated monitoring system.

Attachment 3, DEP Agreement #:

Rev. 03/28/2025 image1.jpg

File details come from the government source that posted it. Updated .