FAQ Addendum.pdf
PDF 289 KB Posted
- Solicitation number
- 2025 - Tiverton Pocasset Hill Cemetery Paving
- Issued by
- Newport County, Rhode Island
About this file
This document is a Questions and Answers record from a Pre-Bid Meeting for a roadway construction project, involving the Department of Public Works (DPW), with contact information for DPW Director David Silvia, Jr. The project involves road reconstruction with specific technical requirements, including a roadway width of 11' 6" and a total pavement thickness of 2.5" using RIDOT binder. The work is expected to start as soon as possible and must be completed before November 15, with site preparation, landscaping, and final touches outlined in the Request for Proposal (RFP).
Key project specifications include preparing the site, matching existing pavement elevations, loaming and seeding new edges, and ensuring proper pavement installation. Bidders are advised that prep work should be included in the bid, and the new pavement must align precisely with existing pavement. Additional technical details were discussed during the pre-bid meeting, such as the relevance of orange markers in the southeast corner of the site (which were noted as having no significance). Interested contractors can obtain further information by contacting the DPW Director at the provided phone number.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Pocasset Hill Cemetery Paving - Specs.pdf | ||
| Cemetery Section Map.pdf | ||
| Diagram.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers from 10-1-25 Pre Bid Meeting (For additional questions – contact DPW Director David Silvia, Jr. at 401-625-6760)
1. Prep Work – should this be included in the bid? Yes, in RFP under site preparations. Also, new pavement shall match existing pavement elevation at the start of the pull with existing pavement.
2. Loam & seed new edges? Yes, in RFP under Landscaping and Final touches.
3. Thickness & course (binder & top coat)? Total thickness? 2.5” RIDOT binder
4. Roadway width? 11’ 6”
5. Anticipated start date and work schedule? Start as soon as possible and finish before November 15.
6. Any relevance of the orange sticks/markers currently placed in the top right rear section (south east corner)? No