This document contains a pricing schedule and statement of work for replacing elevators throughout the Mather Medical Center for the Department of Veterans Affairs. The contractor will replace a total of seven elevators across three clinical line items in priority order. The pricing schedule provides material and labor cost breakdowns by division for each elevator. The statement of work requires the contractor to furnish all labor, materials, and equipment for construction. The contractor must provide new, fully functional elevator systems in accordance with attached drawings and specifications over a 360-day period of performance. No more than one elevator per building may be nonoperational at a time. The contractor is responsible for safety inspections, commissioning, records management, and permitting and must follow federal regulations and VA policies.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Wage Determination - CA20230007 3-17-2023.pdf | ||
| 36C26123R0015 0003.docx | DOCX document | |
| Wage Determination - CA20230007 3-3-2023.pdf | ||
| 36C26123R0015 0002.docx | DOCX document | |
| 36C26123R0015 0001.docx | DOCX document | |
| B650 and B700 Elevator Package.pdf | ||
| 36C26123R0015 Solicitation.docx | DOCX document | |
| Contractor Certification Regarding Safety and Environmental.docx | DOCX document | |
| Factor 2 - Prime Contractor Project Experience.xlsx | XLSX spreadsheet | |
| REQUEST FOR INFORMATION (RFI) FORM--36C26123R0015.docx | DOCX document | |
| Base Bid Item and Deductive Alternates - Bid Schedule.docx | DOCX document | |
| Factor 3 - Past Performance (Questionnaire).docx | DOCX document | |
| Specification_Replace Elevators B650 and B700_UPDATED_01-13-23.pdf | ||
| David Bacon Wage-Rates as of 12-22-2022.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| PRICING SCHEDULE | |||
| Elevator Replacement Throughout Mather Medical Center | |||
| DESCRIPTION | MATERIAL | LABOR | TOTAL |
| CLIN 1 - Mather Building 650 (Elevator 1 and 2) | |||
| SLIN 1 - Mather Building 650 Elevator 1 | |||
| Division 01 - General Requirements | $ | $ | $ |
| Division 02 - Existing Conditions | $ | $ | $ |
| Division 07 - Thermal Moisture Protection | $ | $ | $ |
| Division 09 - Finishes | $ | $ | $ |
| Division 13 - Special Construction | $ | $ | $ |
| Division 14 - Conveying Equipment | $ | $ | $ |
| Division 21 - Fire Suppression | $ | $ | $ |
| Division 23 - HVAC | $ | $ | $ |
| Division 26 - Electrical | $ | $ | $ |
| $ | $ | $ | |
| $ | $ | $ | |
| $ | $ | $ | |
| SLIN 1 Total - Mather Building 650 Elevator 1 | $ | $ | $ |
| SLIN 2 - Mather Building 650 Elevator 2 | |||
| Division 01 - General Requirements | $ | $ | $ |
| Division 02 - Existing Conditions | $ | $ | $ |
| Division 07 - Thermal Moisture Protection | $ | $ | $ |
| Division 09 - Finishes | $ | $ | $ |
| Division 13 - Special Construction | $ | $ | $ |
| Division 14 - Conveying Equipment | $ | $ | $ |
| Division 21 - Fire Suppression | $ | $ | $ |
| Division 23 - HVAC | $ | $ | $ |
| Division 26 - Electrical | $ | $ | $ |
| $ | $ | $ | |
| $ | $ | $ | |
| $ | $ | $ | |
| SLIN 2 Total - Mather Building 650 Elevator 2 | $ | $ | $ |
| CLIN 2 - Mather Building 700 (Elevator 3, 4, and 5) | |||
| SLIN 1 - Mather Building 700 Elevator 3 | |||
| Division 01 - General Requirements | $ | $ | $ |
| Division 02 - Existing Conditions | $ | $ | $ |
| Division 07 - Thermal Moisture Protection | $ | $ | $ |
| Division 09 - Finishes | $ | $ | $ |
| Division 13 - Special Construction | $ | $ | $ |
| Division 14 - Conveying Equipment | $ | $ | $ |
| Division 21 - Fire Suppression | $ | $ | $ |
| Division 23 - HVAC | $ | $ | $ |
| Division 26 - Electrical | $ | $ | $ |
| $ | $ | $ | |
| $ | $ | $ | |
| $ | $ | $ | |
| SLIN 1 Total - Mather Building 700 Elevator 3 | $ | $ | $ |
| SLIN 2 - Mather Building 700 Elevator 4 | |||
| Division 01 - General Requirements | $ | $ | $ |
| Division 02 - Existing Conditions | $ | $ | $ |
| Division 07 - Thermal Moisture Protection | $ | $ | $ |
| Division 09 - Finishes | $ | $ | $ |
| Division 13 - Special Construction | $ | $ | $ |
| Division 14 - Conveying Equipment | $ | $ | $ |
| Division 21 - Fire Suppression | $ | $ | $ |
| Division 23 - HVAC | $ | $ | $ |
| Division 26 - Electrical | $ | $ | $ |
| $ | $ | $ | |
| $ | $ | $ | |
| $ | $ | $ | |
| SLIN 2 Total - Mather Building 700 Elevator 4 | $ | $ | $ |
| SLIN 3 - Mather Building 700 Elevator 5 | |||
| Division 01 - General Requirements | $ | $ | $ |
| Division 02 - Existing Conditions | $ | $ | $ |
| Division 07 - Thermal Moisture Protection | $ | $ | $ |
| Division 09 - Finishes | $ | $ | $ |
| Division 13 - Special Construction | $ | $ | $ |
| Division 14 - Conveying Equipment | $ | $ | $ |
| Division 21 - Fire Suppression | $ | $ | $ |
| Division 23 - HVAC | $ | $ | $ |
| Division 26 - Electrical | $ | $ | $ |
| $ | $ | $ | |
| $ | $ | $ | |
| $ | $ | $ | |
| SLIN 3 Total - Mather Building 700 Elevator 5 | $ | $ | $ |
| CLIN 3 - Mather Building 700 (Elevator 1 and 2) | |||
| SLIN 1 - Mather Building 700 Elevator 1 | |||
| Division 01 - General Requirements | $ | $ | $ |
| Division 02 - Existing Conditions | $ | $ | $ |
| Division 07 - Thermal Moisture Protection | $ | $ | $ |
| Division 09 - Finishes | $ | $ | $ |
| Division 13 - Special Construction | $ | $ | $ |
| Division 14 - Conveying Equipment | $ | $ | $ |
| Division 21 - Fire Suppression | $ | $ | $ |
| Division 23 - HVAC | $ | $ | $ |
| Division 26 - Electrical | $ | $ | $ |
| $ | $ | $ | |
| $ | $ | $ | |
| $ | $ | $ | |
| SLIN 1 Total - Mather Building 700 Elevator 1 | $ | $ | $ |
| SLIN 2 - Mather Building 700 Elevator 2 | |||
| Division 01 - General Requirements | $ | $ | $ |
| Division 02 - Existing Conditions | $ | $ | $ |
| Division 07 - Thermal Moisture Protection | $ | $ | $ |
| Division 09 - Finishes | $ | $ | $ |
| Division 13 - Special Construction | $ | $ | $ |
| Division 14 - Conveying Equipment | $ | $ | $ |
| Division 21 - Fire Suppression | $ | $ | $ |
| Division 23 - HVAC | $ | $ | $ |
| Division 26 - Electrical | $ | $ | $ |
| $ | $ | $ | |
| $ | $ | $ | |
| $ | $ | $ | |
| SLIN 2 Total - Mather Building 700 Elevator 2 | $ | $ | $ |
| Other | |||
| Bonds | $ | $ | $ |
| Insurance | $ | $ | $ |
| Other Total | $ | $ | $ |
| GRAND TOTAL | $ | $ | $ |
| NOTE: If a division is not accounted for please insert in the extra space provided. |