Question and Answer - FA9401-26-R-0024_14AUG2026.pdf
PDF 49 KB Posted
- Attached to
- Renovate Secure Facility B1049
- Solicitation number
- FA9401-26-R-0024
About this file
This is a Public Question & Answer document for federal contract opportunity FA9401-26-R-0024, issued by Kirtland Air Force Base for the renovation of Secure Facility B1049.
The document addresses two vendor inquiries regarding bonding requirements and project timeline. Both a performance bond and a payment bond are required for this construction project, with details specified in FAR clause 52.228-15. The solicitation deadline for proposal submissions is September 16, 2026, with attendance at a site visit on August 28 encouraged but not mandatory. Contract award is anticipated by the end of September 2026, subject to change. The project schedule will commence following issuance of a Notice to Proceed by the Contracting Officer, with details outlined on page 16 of the Statement of Work.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions Date Rec. Date Ans.
Question 1: Please confirm whether a bid bond, performance bond, and/or payment bond is required for this project. 8/11/2026 Answer 1: Details about bonding requirements can be found in the referenced clause RFO 52.228-15 - Performance and Payment Bonds-Construction. In short, both a performance and a payment bond are required for this opportunity. Please see the full referenced clause at "https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-52#FAR_52_228_15" for complete information.
8/12/2026
Question 2: (a) When is this project expected to go to bid for contractors and;
(b) what is the expected start date for construction?
8/12/2026 Answer 2: (a) This solicitation is currently asking for proposals to be submitted. Interested vendors may submit any time up until the current deadline of September 16th 2026. Attending the 28 Aug site visit is encouraged, but not required.
(b) Page 16 of the SOW outlines the project schedule based off a Notice to Proceed (NTP) issued by the Contracting Officer. NTPs are generally issued soon after contract award. Kirtland has the intention of awarding this contracting by the end of Septermber (barring an unforeseen delays) - subject to change.
8/14/2026
FA9401-26-R-0024 | Renovate Secure Facility B1049 | Updated: 14 Aug 2026, 0930 MST Public Question & Answer