This Statement of Work (SOW) details an office addition project for the Air Force Test Center at Edwards Air Force Base, California. The project involves installing demountable walls, electrical outlets, and doors in Building 1220A, specifically modifying a western classroom area. Key installation requirements include: a 40' x 8'10" center wall to separate the office work area from the existing classroom, a 14' x 8'10" wall to create a new office area, installation of 6 each 110v outlets, and two new maple doors (36" X 84" for classroom egress and 3' X 7' for office egress) with silver lever-action lockable handles.

The solicitation (FA930125Q0012) is set aside 100% for small businesses, with a period of performance of 90 days from contract award. Work hours are 0700 to 1600 hours, Monday through Friday, excluding federal holidays. The procurement will be conducted using Simplified Acquisition Procedures, with award based on the Lowest Price Technically Acceptable (LPSF) method. Quotes are due by 25 April 2025 at 1400 PM Pacific Standard Time, to be submitted electronically to the contracting officers Stacey Stuart and Paola Diaz. The NAICS code is 332311 with a size standard of 750 employees.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

DATE OF DOCUMENT: 29 APRIL 2025

TITLE: B1220A Office Addition

Site Support Division

412 MXG/MXLOS

AIR FORCE TEST CENTER

EDWARDS AIR FORCE BASE, CALIFORNIA 93524

This document was updated on Amendment 0002. It supersedes the previous version. All changes are in RED (see page 2). No other changes were made to this SOW.

1. SCOPE AND OBJECTIVE

The Air Force Test Center (AFTC), Edwards AFB, CA, requests a proposal for work to be accomplished for the (MXG) for at Building 1220A within the western classroom. The work to be accomplished includes but is not limited to the following: Erect demountable walls, install doors for room access, Interior Finish each installed area.

2. PURPOSE OF THE DOCUMENT

This Statement of Work serves as a tool for recording customer requirements, ensuring that these requirements are met and evaluating the project design before installation begins. The overall objective is to establish a plan of action for defining and achieving desired results and goals.

3. REQUIREMENTS

Requirements statements in this section are organized for Building installation. The contractor shall accomplish the following:

4. SPECIAL INSTALLATION

Install Contractor furnished demountable walls, electrical outlets, doors.

Install 40' x 8' 10" contractor procured Center wall to separate office work area from existing classroom install contractor procured 14' x 8' 10" wall to create office area.

install power raceway for 6 each 110v outlets on 40' interior wall'

Install new 36" X 84" standard maple door for classroom egress, install new 3' X 7' standard maple door for new office egress, each door should be equipped with silver colored lever action lockable handles.

New installation to match existing structure with product laminate or cloth standard Tan or gray color.

See Appendix 1 for layout plans. The filled orange area room to be modified. The blue rectangles denote doors to be installed. Please print appendix in color.

5. GENERAL REQUIREMENTS

Contractor shall field verify all dimensions prior to installation.

Contractor shall always keep the area clean and remove all waste in a timely manner.

Repair/Replace any items damaged by the contractor employees and/or any sub-contractors while working on this project.

As this area is unclassified, no special security measures are required.

6. SCHEDULE

Period of performance is 90 days from award of contract.

Hours of operation are 0700 to 1600 hours 5 days a week Monday through Friday during the course of a standard business week excluding Federal holidays.

APPENDIX 1

BUILDING LAYOUT

Print appendix 1 in color.

14' x 8' 10"

40' x 8' 10"

Demountable Wall

Door

Area to be made into a room