Text version

8 March 2023

MEMORANDUM FOR RECORD

TO: CONTRACT FILE

FROM: AFTC/PZI (Arnold)

Attn: Greggory C. Jones

100 Kindel Drive Suite A332

Arnold AFB, TN 37389-1332

SUBJECT: FA9101-23-Q-B019 - Project 16008: Uninterpretable Power Supply: Combined

Synopsis Solicitation – Questions & Answers

Q1) Will the Air Force require the UPS to be TAA Compliant?

- Answer: The Trade Agreements Act (TAA) is not applicable to this procurement;

however, the Buy American Act (FAR 52.225-1), Buy American and Balance of

Payments Program (DFARS 252.225-7001) and Qualifying Country Sources as

Subcontractors (DFARS 252.225-7002) applies.

GREGGORY C. JONES

Contracting Officer

DEPARTMENT OF THE AIR FORCE

HEADQUARTERS AIR FORCE TEST CENTER

(AFMC)

EDWARDS AIR FORCE BASE CALIFORNIA

2023-03-08T06:07:37-0600
JONES.GREGGORY.C.1553886941