FSS_II_Notional_Acquisition_Schedule_31Oct18.pdf
PDF 139 KB Posted
- Attached to
- Facility Support Services Federal contract opportunity
- Solicitation number
- FA9101-18-R-1000
View the file
Other files for this federal contract opportunity
Show all 50
Facility Support Services has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Facility Support Services (FSS) II
Notional Acquisition Schedule
As of 31 October 2018
The notional schedule below provides a summary of milestone dates for the FSS II acquisition.
Please note that the Final RFP release date has been adjusted to 9 November 2018. Likewise, the due dates for Past Performance Volume submission and proposal submission have also been revised to accommodate the change in Final RFP release.
Industry Days No. 1 20 Mar 18
Sources Sought Due 30 Mar 18
Early Strategies and Issues 19 Apr 18
RFI No. 1 Released 9 May 18
Industry Days No. 2 22 May 18
RFI No. 1 responses due 7 Jun 18
Draft RFP release 17 Aug 18
Industry Days No. 3 27 Sep 18
Draft RFP responses due 5 Oct 18
Final RFP release 9 Nov 18
Past Performance Vol. due 21 Dec 18
Proposals due 11 Jan 19
Contract award 12 Jul 19
Contract start 1 Dec 19