Text version

14878

SOW NO. 14878

24 Feb 17

STATEMENT OF WORK

FOR

Seal and Stripe Main Cafeteria Parking Lot, Building 452

ARNOLD ENGINEERING DEVELOPMENT CENTER

ARNOLD AIR FORCE BASE, TENNESSEE 37389-9998

NOT AEDC STINFO

Atch 4 17-R-0025

Table of Contents -1

Table of Contents

Section/Paragraph

1. SCOPE

1.1 Introduction

2. APPLICABLE DOCUMENTS

2.1 Government Documents

2.2 Non-Government Documents

3. REQUIREMENTS

3.1 General

3.2 Safety Requirements

3.3 Submittal Summary

Page - 1

1. SCOPE

1.1 Introduction:

The work consists of providing all materials, labor, and equipment to execute work to repair the Main Cafeteria (Building 452) parking lot. Work includes patching, crack filling, sealing (Approximately 90,000 SF) and restriping (Approximately 2,100 LF). Work shall be performed in accordance with this statement of work, contract documents, and AEDC Paving IDIQ Specification FA9101-17-R-0025 at Arnold Air Force Base, Tennessee.

1.1 Objective:

2. APPLICABLE DOCUMENTS

2.1 Government Documents:

2.1.1 Specifications:

A. IDIQ Specification No. FA9101-17-R-0025 Paving IDIQ.

2.1.2 Drawings: See Appendix A

3. REQUIREMENTS

3.1 General:

3.1.1 A storm water permit will not be required.

3.1.2 Clean up and restore all work areas and adjacent areas which were disturbed during the course of the work.

3.1.3 Provide temporary traffic control devices.

3.1.4 Restripe the parking lot.

3.1.5 Provide proper signage for new handicapped parking spaces.

3.2 Safety Requirements:

3.2.1 All work shall be accomplished in compliance with OSHA Standards

3.3 Submittal Summary:

3.3.1 Submit the following in accordance with Submittal Procedures Part 1.4 of paving specification.

3.3.2 Temporary traffic control plan.

3.3.3 Existing conditions report which should construed as damage resulting from work.

Page - 2

3.3.4 Disallowed products locations.

3.3.5 Safety and health plan.

3.3.6 Hazardous material information.

3.3.7 Crack sealant data

3.3.8 Asphalt sealant data

3.3.9 Imported material source.

3.3.10 As built drawings.

3.3.11 Percentage of recovered material content.

3.3.12 Warranty against defects in workmanship and materials for one year following acceptance or provide manufacturer’s standard warranties, whichever is longer.

3.3.13 Submittal summary table:

No. Section Reference Submittal Description Due 1 3.3.2 Temporary traffic control Prior to onsite work 2 3.3.3 Existing conditions report Prior to onsite work 3 3.3.4 Disallowed products locations Prior to onsite work 4 3.3.5 Safety and health plan Prior to onsite work 5 3.3.6 Hazardous material information Prior to onsite work 14 3.3.15 Imported material source Prior to onsite work 15 3.3.7 Crack Sealant Prior to onsite work 16 3.3.8 Asphalt Sealer Prior to onsite work 17 3.3.16 As built drawings At final inspection 18 3.3.17 Percentage of recovered material content At final inspection

19 3.3.18 Warranty At final inspection

Table I. Required submittal list - Completed.

END OF SOW

Appendix A

Page - 3

SOW NO. 14878
3.1 General:
3.1.1 A storm water permit will not be required.
3.1.2 Clean up and restore all work areas and adjacent areas which were disturbed during the course of the work.
3.1.3 Provide temporary traffic control devices.
3.1.4 Restripe the parking lot.
3.1.5 Provide proper signage for new handicapped parking spaces.
3.2 Safety Requirements:
3.2.1 All work shall be accomplished in compliance with OSHA Standards
3.3 Submittal Summary:
3.3.1 Submit the following in accordance with Submittal Procedures Part 1.4 of paving specification.
3.3.2 Temporary traffic control plan.
3.3.3 Existing conditions report which should construed as damage resulting from work.
3.3.4 Disallowed products locations.
3.3.5 Safety and health plan.
3.3.6 Hazardous material information.
3.3.7 Crack sealant data
3.3.8 Asphalt sealant data
3.3.9 Imported material source.
3.3.10 As built drawings.
3.3.11 Percentage of recovered material content.
3.3.12 Warranty against defects in workmanship and materials for one year following acceptance or provide manufacturer’s standard warranties, whichever is longer.
3.3.13 Submittal summary table: