MACH1 AOI FA8903-27-OT-001 Horizontal Airfield Infrastructure
Solicitation number
FA8903-27-OT-001
Issued by

About this file

This is an Area of Interest (AOI) notice for the Modernized Agile Construction Horizons (MACH-1) Umbrella Program, issued by the 772nd Enterprise Sourcing Squadron (772 ESS) under the Air Force Civil Engineer Center (AFCEC). The AOI solicits commercial partners to execute horizontal airfield infrastructure projects across two Lines of Effort: LOE 1 (Design & Planning) and LOE 2 (Final Design & Physical Construction). The scope encompasses planning, design, engineering, alteration, repair, and construction for airfield pavement assets and associated systems, including runways, taxiways, aircraft parking aprons, airfield lighting and electrical systems, drainage infrastructure, utility corridors, and related civil and geotechnical work on Department of Defense installations.

LOE 1 deliverables include developing a site-specific design package advancing from approximately 35% to 65% design completion, producing an open-book Guaranteed Maximum Price (GMP) with detailed cost substantiation and preliminary baseline schedule, and conducting risk mitigation strategies addressing supply chain, geotechnical, environmental, and utility conflict issues. The final design must comply with Air Force Corporate Standards, Department of War Unified Facilities Criteria (UFC), Anti-Terrorism/Force Protection standards, and all applicable federal regulations and executive orders. Respondents must submit Phase 1 Solution Briefs (white papers) limited to five pages by January 15, 2027 at 10:00 AM CST to 772ESS.PKA.MACH1@us.af.mil, demonstrating qualifications and experience with at least three completed airfield pavement projects on Department of War installations or FAA Part 139 airports exceeding $10 million in value within the past ten years. Evaluation criteria include relevance to the AOI, merit of constructability concept, company viability and federal standing, and schedule execution risk. Selected firms will be retained in a Solutions Repository for twelve months and invited to Phase 2 (Oral Presentation) or Phase 3 (Full Proposal) when specific projects are funded, with potential award via Request for Solutions (RFS) to a single uniquely advantaged respondent or Evaluation Amplification Letter (EAL) to three or more pre-qualified firms. Any resulting agreement will be executed as an Other Transaction Agreement (OTA) under 10 U.S.C. 2808a.

View the file

Other files

File Type Posted
ATTACHMENT_1__PROJECT_LISTINGS.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MACH-1 AREA OF INTEREST (AOI):

Horizontal Airfield Infrastructure Line of Effort (LOE 1) – Design & Planning AOI Notice ID: FA8903-27-OT001 MACH1 Umbrella Program Notice ID: FA8903-OT-MACH1

Issuing Activity: 772nd Enterprise Sourcing Squadron (772 ESS) Requiring Activity: Air Force Civil Engineer Center (AFCEC) This Area of Interest (AOI) is published under the Modernized Agile Construction Horizons (MACH1) Umbrella Program Notice. All provisions, submission rules, statutory authorities (10 U.S.C. § 2808a), and data rights/repository terms set forth in the MACH-1 Umbrella Program Notice—including, but not limited to, Collaborative Department of War (DoW) Sharing (Paragraph 3.3) and Solutions Repository Governance (Paragraph 3.4)—are hereby incorporated by reference with the same force and effect as if set forth herein in full. In the event of a conflict between this AOI and the Umbrella Notice, this AOI shall govern solely with respect to project-specific requirements, evaluation weights, and delivery milestones. Any resulting agreement will be an Other Transaction Agreement (OTA) executed under the statutory authority of 10 U.S.C. § 2808a.

1. Summary of Overall Scope The 772nd Enterprise Sourcing Squadron (772 ESS), in coordination with the Air Force Civil Engineer Center (AFCEC), is seeking a commercial partner to execute airfield paving projects in two distinct Lines of Effort (LOE); Design & Planning (LOE 1), Physical Construction (LOE 2) for the scope defined as follows.

The scope of this AOI encompasses planning, design, engineering, alteration, repair, and physical construction for airfield pavement assets and associated systems. Incidental civil, electrical, mechanical, utility, environmental, and site work directly supporting the primary airfield infrastructure is authorized and included within this scope. All facility types, infrastructure systems, technical specialties, and testing capabilities identified throughout this document are expressly illustrative and non-exhaustive, including but not limited to:

· Horizontal airfield pavements and operating surfaces, including but not limited to runways, taxiways, aircraft parking aprons, arm/de-arm pads, compass swing bases, holding pads, alert pads, aircraft wash-rack pavements, access roadways, perimeter security paths, and all associated horizontal airfield pavements.

· Airfield visual and electrical systems, including but not limited to runway edge and centerline lighting, threshold and end lighting, taxiway guidance lighting, approach lighting systems, precision approach path indicators (PAPIs), airfield signage, electrical duct banks, vault infrastructure, counterpoise grounding grids, automated Airfield Lighting Control and Monitoring Systems (ALCMS), mobile aircraft arresting systems (MAAS), and related navigational and visual aids.

· Civil, drainage, and safety infrastructure, including but not limited to subsurface stormwater drainage networks, detention and retention basins, culverts, erosion and sediment control systems, aircraft arresting system foundations and containment vaults, blast deflectors, airfield perimeter security fencing, and related site-civil infrastructure.

· Subsurface utility corridors and distribution, including but not limited to utility distribution pathways, aircraft grounding grids, communication ductways, fuel servicing distribution pathways supporting horizontal operations, and associated utility routing.

· All other civil, geotechnical, electrical, safety, and operational horizontal airfield infrastructure elements necessary to meet mission requirements, regardless of whether specifically itemized above.

· See Attachment 1 for sample projects which is not all inclusive.

2. Background & Problem Statement The traditional Air Force process projects a construction completion timeline that is unacceptable given the immediate mission-readiness risks. This AOI seeks a partner to 1) rapidly develop a comprehensive, site-specific, and constructible design package and 2) develop and implement a firm, executable plan for the full construction effort. Designs must meet Air Force condition criteria to ensure safe and efficient continued use of the airfield pavement.

3. Desired Objectives & Lines of Effort (LOEs) Projects initiated under this AOI will be executed across two distinct Lines of Effort (LOEs). The activities and deliverables outlined under each LOE are expressly illustrative and non-exhaustive:

LOE 1 — Design & Planning

The primary goal of LOE 1 is to produce the necessary level of Project Definition Deliverable (PDD) maturity and design development beyond initial Government-provided materials, if applicable—typically advancing design elements between approximately 35% to 65% design completion, or as otherwise determined necessary by the proposed construction methodology—to sufficiently define scope, allocate risk, and enable a rapid and predictable approach for LOE 2: Final Design & Physical Construction. Proposed solutions for LOE 1 must address, including but not limited to:

· Objective 1: Site-Specific Design Package.

· Developing a site-specific design package tailored to unique airfield operational, geotechnical, topographical, and utility criteria.

· Advancing design maturity to a validated PDD maturity level (typically corresponding to 35% to 65% design development) to establish early cost confidence.

· Conducting dedicated constructability reviews, construction phasing evaluations, and site logistics analyses to minimize airfield operational disruption.

· Objective 2: Price & Schedule

· Airfield projects carry different levels of subsurface, design, and operational risk. Mach1’s consolidated framework easily accommodates different pricing models.

· Developing an open-book Guaranteed Maximum Price (GMP) package with detailed quantity takeoffs, trade contractor pricing, and transparent cost substantiation.

· Formulating a preliminary baseline schedule with critical path logic, resource leveling, and procurement sequencing.

· Objective 3: Risk Mitigation Strategy

· Performing collaborative risk identification for key project risks, including, but not limited to supply chain issues, site access, geotechnical and environmental risk characterization, utility conflict verification, and unforeseen site condition risk mitigation.

LOE 2 — Final Design & Physical Construction

This line of effort executes physical delivery under negotiated commercial terms, including but not limited to:

· Advancing design maturity from LOE 1 to 100% stamped and sealed drawings and specifications, including the progressive release of phased Issued for Construction (IFC) work packages to accelerate execution where applicable.

· Executing physical construction, modernization, alteration, and repair within the negotiated GMP ceiling.

4. Non-Negotiable Requirements for Final Design The final design must achieve strict compliance with all relevant DoW and federal standards. The design package at the end of LOE 1 must adhere to:

· Department Policy: Air Force Corporate Standards; DoW/Air Force manuals, handbooks, regulations, guidance, and policy letters; Executive Orders (EOs) in effect on the date of issuance of this AOI.

· Facility Criteria: Relevant DoW Unified Facilities Criteria (UFC) for airfield pavement planning, design, and construction.

· Security & Access: Strict Adherence to Anti-Terrorism/Force Protection (AT/FP) standards, all base physical security parameters, and installation/flightline access protocols for construction personnel.

5. Submission Guidelines & Evaluation Criteria This AOI is a request for solutions that follow the multi-phased procedures outlined in the MACH1 Parent Notice: FA8903-OT-MACH1. The initial step is the submission of the Phase 1 Solution Brief to the Submission Portal: 772ESS.PKA.MACH1@us.af.mil.

Phase 1: Solution Brief (White Paper):

Respondents shall submit a White Paper (Solution Brief), which is strictly limited to five (5) pages demonstrating qualifications, airfield construction expertise, and conceptual technical approach. The Solution Brief must include:

1. Title Page: Company Name, Title, Date, Point of Contact (Name, Email, Phone), and Address. Specifically identify this AOI. The title page does not count against the 5-page limit.

2. Executive Summary (1 Page Max): A concise overview of your team’s approach to delivering LOE 1 design and planning objectives.

3. Core Concept: Clearly describe your methodology for developing the site-specific design and strategy for arriving at a firm GMP and schedule. Include a high-level milestone schedule for completing this LOE 1 design effort.

4. Credentials: Provide a brief overview of the company, top-line gross sales/revenues, and go-to-market strategy. Include examples of at least three completed airfield pavement projects on DoW installations or commercial FAA Part 139 airport projects within the past 10 years and with a project value exceeding $10M.

Under MACH1 guidelines, submitted Phase 1 briefs will be placed in a Solutions Repository and remain valid for 12 months. When new requirements emerge within this period, retained briefs will be reviewed and firms will be invited to participate in Phase 2 or Phase 3 without re-advertising on SAM.gov.

Evaluation Criteria:

Phase 1 Solution Briefs (White Papers) will be evaluated on their own merit against the following criteria:

1. Relevance to AOI: Does the executive summary accurately target the problem outlined in the AOI? (If irrelevant, evaluation stops here).

2. Merit of Constructability Concept: Does the submission outline a methodology that is technically reasonable, credible, and worthy of further investigation?

3. Company Viability: Does the company demonstrate the necessary experience to execute the work, and are they in good standing (including verification that the company is not on the federal excluded parties list)? For projects submitted as part of “Credentials”, additional consideration will be given to pavement projects completed at/or near project sites.

4. Schedule & Execution Risk: Confidence in the realism of the proposed schedule for delivering the full LOE 1 design package, pre-construction, mobilization, execution, and project closeout, including schedule risk mitigation.

Based on this evaluation, the Government will determine if Phase 1 submissions possess sufficient capability to either progress to Phase 2 (Oral Presentation) or proceed directly to Phase 3 in accordance with MACH1 procedures. The Government reserves the right to limit the number of companies invited to Phase 2.

How We Compete Specific Projects: When a specific project is finalized and funded, we will not issue a new AOI. Instead, we will issue either a Request for Solutions (RFS) directly to a single respondent if that respondent is evaluated to be uniquely advantageous and of outstanding merit or an Evaluation Amplification Letter (EAL) exclusively to 3 or more pre-qualified firms in the Solutions Repository.

The EAL is a project-specific addendum outlining actual site specifications, utility data, and localized requirements. The pre-qualified firms will then be invited to present in Phase 2 Pitch or go straight to Phase 3 and compete with their pricing and tailored execution plans in a rapid, streamlined "bake-off."

Phase 2: Pitch (Oral Presentation):

An interactive presentation of the proposed project approach which may include but is not limited to topics such as logistics, rough orders of magnitude (ROM), and schedule.

We will evaluate and down-select the highest-rated Phase 1 respondents to participate in Oral Presentations. Here, we will evaluate constructability, mobilization capabilities, and strategies for schedule acceleration.

Phase 3: Full Proposal (Evaluation Amplification Letters):

The Government will determine if Phase 1 submissions possess sufficient capability to either progress to Phase 2 (Oral Presentation) or proceed directly to Phase 3 in accordance with MACH1 procedures.

Collaborative project planning and direct negotiation of the OTA via either direct pathway or a competitive "bake-off."

The requirement for a Phase 3 Full Proposal prior to award is dependent on the acquisition strategy of the specific EAL. For certain collaborative delivery models, such as Progressive Design-Build (PDB), the Government may elect to forego a Phase 3 Full Proposal during the initial selection process. In such cases, the Government may select an OT-holder based on the results of Phases 1 and 2 to negotiate an initial agreement for pre-construction and design services. The 'full proposal' (e.g., a Guaranteed Maximum Price) would then be developed post-award during the collaborative design phase, incorporating established 'off-ramps' if an agreement on final construction costs cannot be reached.

Submission Deadline:

Phase 1 Solution Briefs are due: 15 January 2027 at 10:00 AM CST. Submit responses to org box: 772ESS.PKA.MACH1@us.af.mil and include the AOI Notice ID in the subject line: FA8903-27-OT-001 Horizontal Airfield Infrastructure.