Nellis_F47_MACH1_AOI_Attachment_F_Commercial_Pricing_V1.docx
DOCX document 47 KB Posted
- Solicitation number
- FA890327M1006
About this file
This file is a commercial pricing parameters attachment for the F-47 Future Campus Progressive Design-Build (PDB) program at Nellis Air Force Base. The Air Force Civil Engineer Center (AFCEC) is establishing a negotiated framework for construction markups, fees, and cost categories to support firm-fixed-price (FFP) construction commitments during Milestone 2 of the program. The Government seeks transparent, commercially competitive pricing that appropriately compensates participating organizations for services, responsibilities, and risks while maximizing facility value delivery. The document outlines 14 proposed commercial pricing parameters organized into three categories: Construction Fees and Markups (prime PDB construction management fees, self-performed construction fees, Principal Construction Execution Firm management fees, trade-partner overhead and profit, and lower-tier trade-partner administration fees); Construction Cost Components (general conditions, home-office overhead, performance and payment bonds, insurance, contractor-owned equipment, construction contingency, and escalation/procurement risk); and Construction Changes and Adjustments (change-order markups and deductive changes).
The Government has established eight commercial pricing rules governing cost calculation: defined cost bases for each fee, prohibition of duplicate compensation, no fee compounding on other fees or overhead, separate application of self-performed and management fees to their respective bases, separate identification of general conditions with staffing assumptions, negotiated maximum contingency percentages with financial benefits retained by the selected vendor for successful risk management, demonstration of commercially competitive trade pricing through qualified competition, and negotiated change-order methodologies. The document invites optional Phase 1 vendor comments on the proposed pricing categories, definitions, and commercial methods using Microsoft Word Track Changes, explicitly noting that no markup percentages, profit rates, construction prices, or pricing commitments are requested during Phase 1 and that non-response has no effect on Phase 1 evaluation. Specific rates and applicable commercial terms will be established through subsequent authorized negotiations incorporated into the resulting PDB Agreement.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| MACH1 Q_A_Comments Final AOI_12NOV26.xlsx | XLSX spreadsheet | |
| MACH1 Q_A_Comments Final AOI_4 NOV 26.xlsx | XLSX spreadsheet | |
| FINAL_Nellis_F47_MACH1_AOI_30OCT26_V1.docx | DOCX document | |
| MACH1 Q_A_Comments Draft AOI Comments_28OCT26.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
| F-47 Future Campus at Nellis Air Force Base | Program Notice ID: FA8903-OT-MACH1 |
| Progressive Design Build Services | October 29, 2026 |
ATTACHMENT F - PROPOSED CONSTRUCTION MARKUPS AND COMMERCIAL PRICING PARAMETERS
MACH1 Area of Interest | Nellis F-47 Future Campus | Optional Phase 1 Industry Comments
1.0 PURPOSE AND COMMERCIAL PRICING PHILOSOPHY
The Air Force Civil Engineer Center (AFCEC) intends to establish negotiated construction markups, fees, cost categories, and related commercial pricing parameters to support development of commercially competitive firm-fixed-price (FFP) construction commitments during Milestone 2 of the Nellis F-47 MILCON Program.
The Government seeks a transparent and commercially practical pricing framework supporting competitive construction procurement, efficient project execution, and appropriate compensation for organizations responsible for delivering the program.
The Government recognizes that construction management costs, overhead, risk allowances, and reasonable profit are legitimate and necessary components of successful project delivery. AFCEC seeks a commercial pricing framework that appropriately compensates each participating organization for the services, responsibilities, and risks it undertakes while achieving transparent, commercially competitive construction pricing.
AFCEC considers these objectives complementary and mutually reinforcing. Appropriate compensation, transparent pricing practices, and effective commercial competition contribute to a sustainable partnership in which both the selected Vendor and the Government can achieve their respective objectives.
The Government intends to work collaboratively with its selected Vendor to establish pricing arrangements that support the commercial success of participating construction organizations while maximizing the value of facilities and infrastructure delivered to the Air Force’s warfighters.
The Government welcomes sophisticated construction organizations involving multiple firms, Principal Construction Execution Firms, and specialized trade partners when they contribute meaningful capabilities. The framework will recognize distinct responsibilities while ensuring transparency in the overall construction price.
2.0 PROPOSED COMMERCIAL PRICING PARAMETERS
The Government anticipates establishing the following parameters. Specific rates and percentages are not requested during Phase 1.
A. Construction Fees and Markups
| No. |
| Commercial pricing parameter |
| Proposed basis |
| 1 |
| Prime PDB Construction Management Fee |
| Percentage of eligible construction costs managed through trade partners and Principal Construction Execution Firms. |
| 2 |
| Self-Performed Construction Fee |
| Percentage of eligible direct construction costs performed by the prime or a Principal Construction Execution Firm using its own forces. |
| 3 |
| Principal Construction Execution Firm Management Fee |
| Percentage of eligible trade-partner construction costs managed by the Principal Construction Execution Firm. |
| 4 |
| Trade-Partner Overhead and Profit |
| Negotiated percentage or methodology for cost-based trade work and construction changes. |
| 5 |
| Lower-Tier Trade-Partner Administration Fee |
| Percentage applicable to administration of work performed by lower-tier trade partners. |
B. Construction Cost Components
| No. |
| Commercial pricing parameter |
| Proposed basis |
| 6 |
| General Conditions and Field Management |
| Itemized staffing, facilities, supervision, and project-specific costs; negotiated pricing methodology. |
| 7 |
| Home-Office Overhead and G&A |
| Define costs included within construction fees and any separately recoverable categories. |
| 8 |
| Performance and Payment Bonds |
| Actual premium or negotiated rate methodology. |
| 9 |
| Construction Insurance |
| Actual premium or negotiated rate methodology. |
| 10 |
| Contractor-Owned Equipment |
| Negotiated equipment rental and usage rate methodology. |
| 11 |
| Construction Contingency |
| Negotiated maximum percentage; actual allowance established through project-specific risk assessment. |
| 12 |
| Escalation and Procurement Risk |
| Negotiated methodology for material, labor, and long-lead procurement risk. |
C. Construction Changes and Adjustments
| No. |
| Commercial pricing parameter |
| Proposed basis |
| 13 |
| Construction Change-Order Markups |
| Negotiated percentages applicable to additions and changes by contracting tier. |
| 14 |
| Deductive Changes and Credits |
| Negotiated methodology for applicable reductions in fees, markups, and other costs. |
3.0 GOVERNMENT COMMERCIAL PRICING RULES
1. Defined Cost Bases. Each percentage-based fee shall have a clearly defined cost base identifying applicable inclusions and exclusions.
2. No Duplicate Compensation. Construction organizations may receive appropriate compensation for distinct responsibilities. Duplicate compensation for the same services or costs is prohibited.
3. No Fee Compounding. Construction management fees shall not be calculated on other construction management fees, overhead, or profit.
4. Self-Performed Work. Self-performance fees and construction management fees shall apply to their respective eligible cost bases. A firm shall not receive a separate construction management fee for administering its own self-performed work.
5. General Conditions. Project-specific general conditions and field management costs shall be separately identifiable, with staffing and duration assumptions established during construction price development.
6. Construction Contingency. The Government intends to establish a negotiated maximum contingency percentage. Actual contractor-held contingency will reflect the risks allocated to the selected Vendor and will be incorporated into the negotiated FFP. Unused contractor-held contingency will not be reconciled or returned to the Government. The selected Vendor retains the financial benefit of successfully managing its allocated risks.
7. Competitive Trade Procurement. The selected Vendor will demonstrate commercially competitive trade pricing through qualified trade competition or other commercially supportable procurement methods. The Government may independently validate underlying construction costs.
8. Construction Changes. Negotiated change-order markups and credit methodologies will govern applicable adjustments following FFP construction authorization.
9. Commercial Price Validation. Negotiated fees and markups do not independently establish that a proposed construction price is commercially competitive. The Government will evaluate underlying construction costs, market conditions, risk allocation, and total proposed construction price before authorization.
4.0 OPTIONAL PHASE 1 INDUSTRY COMMENTS
The Government invites Vendors to review Sections 2 and 3 and recommend additions, deletions, revisions, or clarifications to the proposed pricing categories and commercial rules.
Vendors electing to comment are requested to use Microsoft Word Track Changes and may include the marked-up memorandum as a separate, optional attachment to their Phase 1 AOI submission.
No response to this memorandum is required. Vendors may elect not to provide comments without any effect on their Phase 1 evaluation. The optional attachment is excluded from the technical narrative page limitations.
The Government is not requesting markup percentages, profit rates, construction prices, or other pricing commitments during Phase 1. Comments should address the proposed categories, definitions, and commercial methods rather than specific rates or amounts.
The Government may consider industry recommendations when developing final commercial pricing provisions. Submission of comments does not obligate the Government to accept any proposed revision.
5.0 STATUS OF PROPOSED COMMERCIAL TERMS
This memorandum identifies proposed commercial pricing parameters and rules for industry consideration. Specific rates, percentages, and applicable commercial terms will be established through subsequent authorized negotiations and incorporated into the resulting PDB Agreement.
The negotiated framework will support development of commercially competitive FFP construction commitments during Milestone 2 while preserving applicable Government pricing review and approval requirements.
The Government’s objective is to establish commercial terms that support prudent stewardship of public resources, appropriate Vendor profitability, and successful delivery of the facilities required for the F-47 mission.
File details come from the government source that posted it. Updated .