Attachment_1_-_Performance_Work_Statement_(PWS).pdf
PDF 419 KB Posted
- Solicitation number
- FA8818-19-R-0001
About this file
This draft request for proposal and related documents outline requirements for the Orbital Services Program-4 (OSP-4) contract. The Air Force seeks launch services, mission integration, and related support through OSP-4 to meet small launch needs for US government agencies. Offerors must provide feedback on the draft RFP by June 13, 2019. The minimum award task order requires launch service user guide studies. NAICS code 481212 applies. The small business size standard is 1,500 employees, though responses from small and small disadvantaged businesses are encouraged. The program will initially support the Space Test Program Small Spacelift 28 mission. Offerors may also provide input on whether separate contract line items would be useful for different mission assurance categories.
Attachment 1-PWS
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Consolidated_STP-S28_CRM_Response.pdf | ||
| Consolidated_OSP-4_DRFP_CRM.pdf | ||
| STP_S-28_FOPR.pdf | ||
| STP-S28_MRD.pdf | ||
| STP-S28_DRFP_CRM.xlsx | XLSX spreadsheet | |
| OSP-4_draft_RFP_CRM.xlsx | XLSX spreadsheet | |
| Exhibit_E.pdf | ||
| OSP-4_Starts_Here.pdf | ||
| Attachment_4_-_Evaluation_Criteria.pdf | ||
| Exhibit_B.pdf | ||
| Attachment_2_-_DD254.pdf | ||
| Exhibit_C.pdf | ||
| Attachment_5_-_Ordering_Guide.pdf | ||
| Exhibit_A.pdf | ||
| Initial_Minimum_Award_Task_Order.pdf | ||
| Exhibit_D.pdf | ||
| Attachment_3_-_Instructions_to_Offerors.pdf | ||
| FA8818-19-R-0001_Model_Contract_No_Attachments.pdf |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OSP-4 PWS – Basic Page 1 of 50
Attachment 1 Orbital Services Program-4 (OSP-4)
Performance-Based Work Statement (PWS)
OSP-4 PWS – Basic Page 2 of 50
PWS REVISION RECORD
Revision Date Description Pages
Basic 15 April 2019 -- 50
OSP-4 PWS – Basic Page 3 of 50
Table of Contents
1.0 General Information
1.1 Scope and Objectives:
1.2 Program Overview:
1.3 Management and Communications:
1.4 Associate Contractor Agreements and Non-Disclosure Agreements:
1.4.1 Associate Contractor Agreements (ACA):
1.4.2 Non-Disclosure Agreements (NDAs):
1.5 Excess Ballistic Missile Motors:
2.0 Description of Services:
2.1 Design, Integration, MA, & Launch Services (DIMALS) (CLIN 0001):
2.1.1 LS Formal Reviews:
2.1.2 MA Formal Reviews:
2.1.3 Government Readiness Reviews (Cat 2&3 Missions Only):
2.1.4 Launch Campaign:
2.1.5 Integrated Product Team (IPT) Meetings:
2.1.6 Periodic and Technical Interchange Meetings (TIM):
2.1.7 Multi-Manifest Missions:
2.2 Mission Analysis Study (MAS) (CLIN 0003):
2.3 Concept Analysis Study (CAS) (CLIN 0005):
2.4 GFP Closeout Service (CLIN 0007):
2.4.1 Annual Audit:
2.4.2 GFP Quarterly Report:
2.4.3 Returns:
2.5 Hardware Service (CLIN 0009):
3.0 Service Summary
3.1 Contract Surveillance:
4.0 Documents
4.1 Reference Documents:
4.2 Compliance Documents:
Annex 1: MA Category-Specific Mission Analysis Requirements A1-1 Category 1 Analyses
A1-2 Category 2 Analyses
OSP-4 PWS – Basic Page 4 of 50
A1-3 Category 3 Analyses
Annex 2: Performance Threshold Entrance and Exit Criteria Annex 3: Definitions
OSP-4 PWS – Basic Page 5 of 50
1.0 General Information
1.1 Scope and Objectives: The Rocket Systems Launch Program (RSLP) delivers innovative, resilient, and affordable launch solutions for the Department of Defense (DoD), the Intelligence Community (IC) and the United States (U.S.) Government, complementing the National Security Space Launch (NSSL), formerly the Evolved Expendable Launch Vehicle (EELV) program, to provide assured access to space and full-spectrum launch capabilities for the warfighter. The U.S. Air Force Space and Missile Systems Center (SMC) Launch Enterprise Systems Directorate (LE), Small Launch & Targets Division (SMC/LEX) manages the RSLP. The RSLP provides launch services, mission integration, and support for both operational and research and development (R&D) requirements and to date has flown over 700 missions, using 24 booster types, from 20 different launch sites. The RSLP employs 4 primary contract mechanisms to accomplish the full range of payload delivery services; General Services Administration (GSA) schedules are used to procure rideshare services, the Sounding Rocket Program 4 (SRP-4) is used to procure suborbital launch services, Small Rocket Program – Orbital (SRP-O) contracts are used to procure very small orbital (<400 lb to Low Earth Orbit (LEO)) launch services, and the Orbital Service Program-4 (OSP-4) is used to procure orbital launch services greater than 400 lb to LEO.
The objective of the OSP-4 program is to provide flexible small launch capability using Spacelift System (SS) designs based on commercial and/or Government Furnished Property (GFP) motors to meet a variety of mission and Space Vehicle (SV) requirements in 12-24 months. Required services also include special studies. OSP-4 delivers a payload ranging between 400 pounds (lb) to LEO through approx. 8,000 lb to Geostationary Transfer Orbit (GTO). Additional orbits of interest within this performance range include, but are not limited to, Medium Earth Orbit (MEO) and Highly Elliptical Orbits (HEO). The program supports both dedicated launch services and primary launch services. In addition, for some missions the launch solution may consist of multiple SS’s to support mission requirements.
This Performance Work Statement (PWS) delineates the launch service responsibilities of the Launch Service Contractor (LSC) in support of the OSP-4 contract. The requiring activity is the SMC/LE. Contractual direction is provided by the Procuring Contracting Officer (PCO), SMC/ADK, at Kirtland Air Force Base, New Mexico.
1.2 Program Overview: SMC requires complete launch services where the culmination of work results in the LSC’s Launch Solution (LS) meeting mission requirements and demonstrating compliance, through analysis, with this PWS, the Mission Requirements Document’s (MRD), and the RSLP Small Launch Performance Requirements Document (SLPRD) and Small Launch Interface Specification (SLIS). The MRD defines specific mission objectives for each mission. The system and interface requirements are defined in the RSLP SLPRD and SLIS respectively.
The scope of the procured LS consists of completion of design activities and developmental efforts for any Spacelift System (SS) and/or subsystem designs not previously qualified to mission levels; fabrication, test, and integration of the systems, required SS support equipment, integration of the SS with the SVs, provision of launch facilities, operations, training, logistics, and any Government oversight and insight
OSP-4 PWS – Basic Page 6 of 50 required for Independent Verification and Validation (IV&V). These activities also include customization of the proposed system, subsystems, or components to meet mission requirements such as guidance and control systems, SS instrumentation systems, trajectory software, SV(s) integration, range support, facilities, storage and other associated activities.
OSP-4 missions will normally be procured as a dedicated launch service. A dedicated launch service is one in which the Government reserves all capacity of the launch solution. The Government will provide all the SV’s as defined in the MRD, or may provide a mass model instead if the SV becomes unavailable for any reason.
For some OSP-4 missions (specified in the MRD), the LSC may provide the OSP-4 launch service as a multi-manifest mission, where the OSP-4 launch service manifest is the Primary Payload, with Other Government Agency (OGA) Secondary Payloads and/or Commercial Secondary Payloads allowed to utilize any launch solution excess capacity.
The payload may consist of a single SV or multiple SVs. The launch service shall provide multi-manifest services as part of the launch service when multiple SVs are manifested. For more information regarding the multi-manifest mission element, refer to the SLIS and the Rideshare User’s Guide (RUG) or its successor document.
For both dedicated and primary launch services, the launch schedule shall be per the OSP-4 requirement.
1.3 Management and Communications: The Government will assign a Contracting Officer's Representative (COR); the COR will act as the primary interface with the LSC and provide contract surveillance (i.e. quality assurance) as described in Section 3 of this PWS, on behalf of the PCO. The COR will also assess the conformance with requirements of each service provided and make a final recommendation to the PCO for determination of the conformance of the service rendered in accordance with Federal Acquisition Regulation (FAR) 52.246-4(e).
The Government will also assign a Mission Manager (MM) for each task order responsible for leading an Integrated Product Team (IPT) to identify and manage the full breadth of mission planning and issues, including interfacing with the LSC to coordinate activities with stakeholders.
1.4 Associate Contractor Agreements and Non-Disclosure Agreements:
1.4.1 Associate Contractor Agreements (ACA): The LSC shall enter into ACAs for any portion of the contract requiring joint participation in the accomplishment of the Government’s requirement(s). These agreements shall include the basis for sharing information, data, technical knowledge, expertise, and/or resources essential to the conduct of the mission, which shall ensure the greatest degree of cooperation for the development of the program to meet the terms of the contract. Associate contractors are listed in the MRD.
ACAs shall include the following general information:
• Identify the associate contractors and their relationships
• Identify the program involved and the relevant Government contracts of the associate contractors
OSP-4 PWS – Basic Page 7 of 50
• Describe the associate contractor interfaces by general subject matter
• Specify the categories of information to be exchanged or support to be provided
• Include the expiration date (or event) of the ACA
• Identify potential conflicts between relevant Government contracts and the ACA; include agreements on protection of proprietary data and restrictions on employees
A copy of such agreement shall be provided to the PCO for review before execution of the document by the cooperating contractors.
The LSC is not relieved of any contract requirements or entitled to any adjustments to the contract terms because of a failure to resolve a disagreement with an associate contractor. Liability for the improper disclosure of any proprietary data contained in or referenced by any agreement shall rest with the parties to the agreement, and not the Government. All costs associated with the agreements are included in the negotiated prices of applicable orders issued under this contract. The Government will make necessary updates to the agreements when the associate contractor is succeeded by a new contractor.
1.4.2 Non-Disclosure Agreements (NDAs): The LSC shall establish NDAs with other contractors performing related services for the Government such as SV Contractors responsible for SV(s) operations and Mission Assurance Contractor (MAC) who may perform IV&V activities on behalf of the Government.
1.5 Excess Ballistic Missile Motors: The Government will offer excess ballistic missile motors, as well as related handling and test equipment for use, to be furnished as GFP for use at the LSC's discretion. Excess ballistic missile motors are provided in flight worthy condition while all other GFP is furnished as-is. If excess ballistic missile motors are used in the LSC’s solution, excess capacity is reserved for the Government.
Department of Defense (DoD) will not pursue or allow commercial secondary payload opportunities on space launch vehicles derived from excess ICBM assets. The LSC shall manage and maintain GFP (if applicable) using documented LSC procedures when Government-provided procedures are unavailable.
For all other GFP items, the contractor shall be responsible for contacting the appropriate GFP owner and arranging for its use in performance of the contract.
2.0 Description of Services: The following sections outline the launch service requirements.
The LSC shall employ a structured Systems Engineering (SE) approach throughout mission execution (e.g. hardware design, software development, configuration management, quality assurance, material review board, change control, requirements flow-down, processes and procedures) to ensure all requirements are met.
2.1 Design, Integration, MA, & Launch Services (DIMALS) (CLIN 0001): The LSC shall complete all launch activities and support the LS Formal Reviews, Mission Assurance (MA) Formal Reviews, and Government Readiness Reviews depicted in Figure 1 below. These mission reviews provide insight into the LSC’s structured SE approach and provides the Government an opportunity to conduct contract surveillance
OSP-4 PWS – Basic Page 8 of 50 as described in Section 3.0 – Service Summary. The timing of formal reviews shall be agreed upon by the COR and the LSC. The COR may waive reviews deemed of low value; the COR may also combine reviews for the sake of efficiency.
Figure 1 - OSP-4 Mission Reviews (Notional 24 Month Timeline)
For the formal reviews, the LSC shall leverage analyses and/or data previously presented to the Government. As detailed in Annex 2, the LSC shall submit criteria in two groups: (1) Entry Criteria; and (2) Exit Criteria.
(1) Entry Criteria: The entry criteria shall meet the entry criteria specified for the review as detailed in Annex 2. The Government Red Team of subject matter experts (SMEs) will perform a technical evaluation of the criteria submitted and determine whether the criteria demonstrates the LSC is prepared to conduct the formal review. The COR will communicate the determination of the Government no later than seven (7) calendar days prior to the review. [CDRL A002 - Design Review Information Package (DRIP)]
(2) Exit Criteria: The COR will communicate any formal review deficiencies, commonly referred to as “liens,” to the LSC at the close of the review. Liens will be validated by the COR and considered by the PCO in the determination that the relevant service has been satisfactorily performed.
The LSC is responsible for collecting, logging, disseminating and assigning resources for responding to each lien, and other action items, identified at the review. The LSC will provide a get-well plan, which includes a burn-down plan and schedule to remedy deficiencies to the COR no later than seven (7) calendar days after the review. Closure dates will be agreed to by the COR and the LSC.
Mission Assurance
SR
R
T -2 m o
Design, Integration, & Launch
M D
R -1
T -1 m o
TR
R
T -1 m o (C at
/3 o nl y)
ATP ILC
Q
TR
T
-5 m o (C at
/3 o
PF
R
T +6
0d (C at
/3 o
FR
T -1
4d
LR
T -2 d
Pe di gr ee
R ev ie w
T -8
1d
M
R
P
SR
T -6
0d eI
R T
-3 0d
M D
R -2
T -1 m o
OSP-4 PWS – Basic Page 9 of 50
2.1.1 LS Formal Reviews: The LSC shall host the following MA formal reviews at their facility in order to provide the Government insight into the processes, methodology and progress being made by the LSC [CDRL A018 - Report, Record of Meeting Minutes]:
• Service Requirements Review (SRR)
• Mission Design Review 1 (MDR-1)
• Mission Design Review 2 (MDR-2)
• Pre-ship Readiness Review (PSR) – Required for each SS
• Post-Flight Review (PFR) (Cat 2&3 Missions Only)
2.1.1.1 Requirements Analysis and SRR: The LSC shall perform requirements analysis for the specific mission; including decomposition, allocation tracing, and validation of all SLPRD, SLIS, and MRD requirements. At the conclusion of the requirements analysis the LSC shall hold a SRR NLT 60 calendar days after award or as directed by the COR, in coordination with the LSC. [CDRL A002 -
DRIP]
2.1.1.1.1 Requirements Decomposition, Traceability & Validation:
Requirements shall be decomposed and traced in a hierarchical structure starting with the highest level requirements. These high-level requirements shall be decomposed into functional and performance requirements and allocated across the major elements of the proposed LS, with any new design elements or design changes to meet requirements identified accordingly. The launch service shall flow down and trace all numbered SLPRD requirements to launch service requirements and interface documents. These shall be further decomposed and allocated among lower level elements until a complete set of requirements is achieved.
The complete set of requirements shall be provided in Specification and Requirements Documents, including a System Specification and Interface Control Documents, along with a Documentation/Specification Tree [CDRL A001 - System Performance Specification; A003 - Documentation/Specification Tree; A004 - SS/Payload Interface Control Document (ICD)] At each level of decomposition (solution, system, subsystem, and component), the total set of derived requirements (to include ICDs) shall be traced from and validated against the higher level parent requirements as specified in the SLPRD, SLIS, MRD, and other compliance documents. The launch service shall verify each numbered SLPRD requirement through a combination of demonstration, test, analysis, and inspection and provide verification evidence to SMC/LEX. Compliance with all requirements shall be verified and artifacts of verification provided and cited. Both traceability and verification shall be documented in the Requirements Traceability and Verification Matrix (RTVM). The use of an automated requirements
OSP-4 PWS – Basic Page 10 of 50 management system (e.g., DOORS or JAMA) is encouraged but not required. [CDRL A021 - RTVM]
2.1.1.2 Mission Planning: The LSC shall develop and maintain a Contractor Work Breakdown Structure (CWBS), CWBS Dictionary and an Integrated Schedule (IS) for the mission. The CWBS, CWBS Dictionary and IS shall use a common numbering system. The LSC shall inform the Government of any post-delivery changes to the CWBS, CWBS Dictionary, and any internal documents cited in the CWBS Dictionary, and provide updated revisions within 30 days of being changed. The LSC shall develop a Program Management Plan (PMP) that references and is consistent with the CWBS and IS. [CDRL A019 - Contractor Work Breakdown Structure (CWBS) and CWBS Dictionary; A027 - Integrated Schedule; A037 Program Management Plan]
2.1.1.2.1 The CWBS shall reflect the LSC’s overall view of the effort and serve as the framework for organizing activities involving the LSC and their subcontractors, Government, Range and Associated Contractors. The CWBS shall be defined to no less than level 3 (refer to MIL-HDBK- 881C Appendix J for a sample CWBS showing typical levels).
2.1.1.2.2 The CWBS Dictionary shall define the tasks to be performed in each element of the CWBS and corresponding element of the IS. This task definition shall include a complete definition of the task to be accomplished, the key processes, procedures and specifications to be used when performing the task and the CDRL item(s) to be delivered.
2.1.1.2.3 The IS shall reflect all the tasks/activities in the CWBS, and include all applicable PWS tasks. Tasks/activities shall be logically linked together and show predecessor/successor relationships and establish the logical flow of dates provided by calculating the duration of all tasks using typical schedule networking tools. The IS shall display the critical path as well as schedule margin and deviation. The IS shall be maintained and updated no less than monthly. The IS shall be presented at formal reviews at a detailed level to display milestones and primary processes of interest. The IS shall reflect all planned mission activities, including external dependencies.
2.1.1.3 Mission Design: The LSC shall perform mission design for the specific mission. In this activity the LSC designs the complete mission LS.
2.1.1.3.1 Interface Control Documents (ICD): The LSC shall maintain configuration control and coordinate the ICD change process throughout the life of the mission. The ICDs shall be generated to document the interfaces between the SS and the SV(s), and the Launch Site/Range. The SS to Launch Site/Range ICD shall include a description of the telemetry and video data to be displayed on range consoles. If GFP motors are used, a separate ICD shall be created and maintained for the interface(s) between the GFP motor(s) and the LSC’s hardware. [CDRL A004 - SS/Payload ICD; SS-to-(GFP) Booster ICD]
OSP-4 PWS – Basic Page 11 of 50
Each ICD shall contain a RTVM that shall be maintained throughout the life of the ICD. The RTVM documents how requirements are derived and specifies artifacts required to demonstrate interface verification. [CDRL A021 – Performance Specification Documents]
2.1.1.3.2 Mission Design Review (MDR-1): Prior to conducting a detailed LS design, the LSC shall have a preliminary design that meets (or is converging on meeting) the requirements generated in the requirements analysis. The LSC shall ensure the concepts and preliminary designs are adequate to meet mission requirements. The objective of the MDR- 1 is to demonstrate a preliminary design that satisfies the mission design concept, and presents preliminary designs of design items, interfaces, and design modifications that must be implemented to meet mission requirements.
The LSC shall conduct the MDR-1 NLT 120 days after SRR or as directed by the COR, in coordination with the LSC. After a successful MDR-1 the LSC shall be prepared to execute the detailed design for its LS. [CDRL A002 – DRIP; A018 - Report, Record of Meeting Minutes]
2.1.1.3.3 Mission Design Review (MDR-2): At the conclusion of the mission design phase, the LSC shall hold MDR-2, NLT 120 days after MDR-1.
The objective of the MDR-2 is to demonstrate critical design that satisfies the full mission design concept, and presents complete designs of any design items that were previously only developed to the preliminary design level.
If mission design changes after MDR-2, then a delta review may be required, as directed by the COR, in coordination with the LSC. [CDRL A002 - DRIP; A018, Report, Record of Meeting Minutes]
2.1.1.4 Mission Development: The LSC shall fabricate and test hardware and software to ensure the Government is provided a LS design capable of meeting all the requirements of the SLPRD, SLIS, MRD and this PWS.
2.1.1.4.1 Space Debris Assessment Report (SDAR): The LSC shall perform analysis and produce a SDAR to demonstrate compliance with AFI 91- 217 Attachment 2 for the SS (the SV will not be included in this report/analysis). [CDRL A015 - SDAR]
2.1.1.4.2 Predicted Environments: The LSC shall generate predicted launch environments based upon mission development activities. [CDRL A015 - Predicted Launch Environments Analysis Report]
2.1.1.4.3 Coupled Loads Analyses (CLA): CLA shall be performed by the LSC to predict the maximum loads that can be expected by the SV(s) during the launch event. The CLA shall address key loading events (e.g. lift-off, maximum dynamic pressure, transonic, staging/ignition events, engine cut-offs and restarts, and steady state conditions, as applicable).
The preliminary CLA shall be performed based upon preliminary
OSP-4 PWS – Basic Page 12 of 50
SV(s)-provided models to support SV(s) design and test programs. A final CLA shall be performed with test verified models. [CDRL A015 - CLA Report]
2.1.1.4.4 Fabricate & Test: The LSC shall develop, fabricate and test flight hardware and flight software, necessary to conduct the mission. The LSC shall conduct hardware and software system level testing to meet qualification requirements. Flight hardware and software shall be fabricated and developed under configuration control. All work performed under this effort shall be performed in accordance with the LSC’s processes, procedures and SS specifications
2.1.1.4.5 Design Verification Tests: Design verification tests shall be conducted to establish confidence in compatibility between the LSC hardware and any other contractor or stakeholder hardware, or to verify complex SS functions. The LSC shall prepare a test report summarizing the test set up, the results, and any anomalies. [CDRL A012 - Design Verification Test Procedure; A013 - Design Verification Test Report].
2.1.1.4.5.1 Integrated Mechanical / Structural Analysis and Verification Tests: A series of mechanical/structural tests shall be conducted at the LSC facilities to verify the SS mechanical and structural characteristics. The LSC shall conduct the testing with agreed upon SV(s) participation. The LSC and SV(s) provider shall provide flight representative hardware to support conduct of the testing.
2.1.1.4.5.2 SS/SV(s) Mechanical Interface Verification: A mechanical fit check shall be performed to verify the mechanical compatibility between the SS and the SV(s) separation system as documented in the SS/SV(s) ICD, including cable routing and connections and any areas where there are potential interference issues. The flight representative separation system will be provided by the SV contractor.
The LSC shall provide flight representative hardware to support the fit check. The fit check shall be performed at the LSC facility or the agreed upon alternate facility.
2.1.1.4.5.3 Non Destructive Testing (NDT): The LSC shall conduct NDT on all flight structures fabricated with composite materials. For structures that do not have other hardware mounted on them, 100% testing shall be performed. For structures that do have other hardware mounted on them, NDT shall be performed to the maximum extent possible.
2.1.1.4.6 Electrical Verification Tests: End-to-end testing shall be conducted to verify the electrical interface between the SS and SV(s). The testing shall use flight-representative hardware furnished by the LSC as well as applicable SV(s) components furnished by the SV(s) and/or separation system contractor. The test shall include the complete exercise of all
OSP-4 PWS – Basic Page 13 of 50 electrical interfaces between the SS, separation system and the SV(s).
Integrated test procedures shall be reviewed and approved by participating agencies. The location of the test will be proposed by the LSC. [CDRL A012 - SS/Payload Electrical Test Procedure; A013 - SS/Payload Electrical Test Report]
2.1.1.4.7 The LSC shall identify, design, test, qualify and approve all GSE and LSE required for flight operations at the Range prior to the PSR. This equipment shall include lifting slings, transportation fixtures and equipment, umbilical electrical harnesses, electrical test equipment (including electrical GSE) and temperature control systems. The LSC shall ensure that all required support equipment for assembly, integration, encapsulation and launch at the launch site has been calibrated, safety-qualified and is in working order and available when needed. [CDRL A012 - Test Procedures; A013 - Test Report; A014 - Qualification Test Anomaly/Failure Report]
2.1.1.5 Pre-Ship Readiness Reviews (PSRs) and Shipping: A PSR must be completed prior to processing any major SS components or support equipment for shipment to the launch site so that the Government and other launch campaign stakeholders may assess LSC launch campaign readiness and schedule risk prior to committing resources to the campaign. The final PSR shall be held at approximately T-60 days to launch or as directed by the COR, in coordination with the LSC. The LSC is responsible for shipment and/or transportation of all SS hardware, Air/Ground Support Equipment (A/GSE), Launch Support Equipment (LSE) and other necessary LSC items to the Launch Site. [CDRL
A002 - DRIP]
2.1.1.5.1 Readiness: At the PSR the LSC shall provide an overview demonstrating completion of the Range Safety preparations and tailoring (if required), an acceptable approach to Flight Safety and Flight Termination, and readiness of the launch site and support facilities. The LSC shall also demonstrate that system level testing has been completed and the SS hardware is prepared for shipment to the launch site. [CDRL A013 - PSR and Shipping Readiness Report; A002
- DRIP]
2.1.1.5.2 Shipment of GFP Motors and Equipment: If GFP motors are used, the Government will be responsible for shipping these motors and direct support equipment from the processing facilities at Hill AF Base, Utah to a motor processing location at or near the launch site in coordination with the LSC and the Range. The LSC shall take responsibility for the GFP motor (via DD Form 1149) upon receiving inspection conducted when the motor is removed from the shipping container at or near the launch site. At the conclusion of a launch campaign the LSC shall refurbish, repackage and return all remaining Government-owned equipment as directed by the PCO. [CDRL A011 - GFP Shipment]
OSP-4 PWS – Basic Page 14 of 50
2.1.2 MA Formal Reviews: The LSC shall conduct Mission Assurance (MA) in accordance with their internal processes and procedures. In parallel, the LSC shall provide support for the Government’s independent MA efforts based on the MA category (e.g., Category 1, 2, and 3). LSC shall support the IV&V effort undertaken by the MAC with deliverables such as flight computer and flight software. The LSC shall host the following MA formal reviews at their facility in order to provide the Government insight into the processes, methodology and progress being made by the LSC [CDRL A018 - Report, Record of Meeting Minutes]:
• Test Readiness Review (TRR) (Cat 2&3 Missions Only)
• Qualification Test Review (QTR) (Cat 2&3 Missions Only)
• Pedigree Review (PR) – Required for each SS
2.1.2.1 Category 1: These missions may be subject to the SMC SpaceFlight Worthiness Certification (SFWC) process and/or be licensed under Federal Aviation Administration (FAA) licensing guidelines as well as the accompanying MAC’s IV&V activities.
2.1.2.1.1 Space Flight Worthiness: For SMC SFWC missions, the LSC shall support the SMC Readiness Review process, the IV&V efforts of the MAC and the SMC Independent Readiness Review Team (IRRT).
Details of the required data submittals are in Annex 1 (A1-2). The LSC shall analyze the SS against each of the applicable criteria, refer to SMC-G-1202 “Space Flight Worthiness Criteria” (SFWC), provide a matrix identifying compliance or non-compliance, and provide and cite confirming evidence and/or associated mitigations for non-compliances. SMC flight worthiness certification is required prior to launch. [CDRL A022 - DRIP (Government Reviews)]
2.1.2.1.1.1 SFWC Discussions: The LSC shall make available
appropriate personnel for the discussion and clarification of status and issues related to the SFWC matrix and items detailed in Annex 1 (A1-2) on a monthly basis during the design, development, and test phase, and weekly during the launch campaign. The LSC shall support additional discussions, as required, to provide the Government, Independent MAC and/or the IRRT with confidence in the accuracy and sufficiency of the information provided. The LSC shall support 2-hr monthly meetings with at least one representative from each design discipline.
2.1.2.1.2 FAA Licensing: For FAA licensed missions, the LSC shall obtain a FAA launch license and is responsible for all requirements to obtain such license. In addition, the LSC shall be responsible for ensuring the applicable launch site meets FAA licensing requirements and any activities required to bring the launch site into licensing compliance.
The LSC shall demonstrate that all required FAA licenses have been obtained at the PSR. Obtaining applicable licenses shall not relieve the LSC from the requirements described in Section 1.9. Failure to obtain
OSP-4 PWS – Basic Page 15 of 50 applicable licenses shall not relieve the LSC from its responsibilities under this contract. [CDRL A010 – Technical Report – Study/Services]
2.1.2.1.3 See Annex 1 (A1-1) for additional analyses required for Category 1 missions to support SV integration. [CDRL A015 - Technical Report as listed in A1-1]
2.1.2.1.4 Pedigree Review (PR): The LSC shall host a PR at approximately T-81 days to launch (or as directed by the COR, in coordination with the LSC). The main purpose of a PR is to ensure that the flight hardware/software has been built and tested to establish flight worthiness in accordance with the released design qualification documentation. [CDRL A024 - Pedigree Review; A002 - DRIP] A delta review may be required, as directed by the COR, in coordination with the LSC.
2.1.2.2 Category 2: The LSC shall provide additional information and support for the Government’s MA efforts and the Government’s Independent Readiness Review Team (IRRT). In addition, the following launch service requirements shall be applicable for these missions (in addition to the launch service requirements detailed in paragraph 2.1, DIMALS):
2.1.2.2.1 Space Flight Worthiness: The mission will be certified space flight worthy by SMC, which requires the LSC to support the SMC Readiness Review process, the IV&V efforts of the MAC and the SMC IRRT.
Details of the required data submittals are in Annex 1 (A1-2). The LSC shall analyze the SS against each of the applicable criteria listed in SMC-G-1202 “Space Flight Worthiness Criteria” (SFWC), provide a matrix identifying compliance or non-compliance, and provide and cite confirming evidence and/or associated mitigations for non-compliances. SMC flight worthiness certification is required prior to launch. [CDRL A022 - DRIP (Government Reviews)]
2.1.2.2.1.1 SFWC Discussions: The LSC shall make available
appropriate personnel for the discussion and clarification of status and issues related to the SFWC matrix and items detailed in Annex 1 (A1-2) on a monthly basis during the design, development, and test phase, and weekly during the launch campaign. The LSC shall support additional discussions, as required, to provide the Government, Independent MAC and/or the IRRT with confidence in the accuracy and sufficiency of the information provided. The LSC shall support 2-hr monthly meetings with at least one representative from each design discipline.
2.1.2.2.2 Flight Software: The LSC shall develop flight software requirements, design, and source code with version description, test description, and test reports. [CDRL A005 - Software Requirements Specifications (SRS); A006 - Software Design Documents (SDD); A007 - Software
OSP-4 PWS – Basic Page 16 of 50
Source Code and Software Version Description; A008 - Software Test Description (STD); A009 - Software Test Report (STR)]
2.1.2.2.3 Flight Computer: The LSC shall deliver a flight representative computer to the Government NLT 45 calendar days after MDR-2. This computer will be used by the MAC to run hardware-in-the-loop simulations. The LSC shall assign to the computer an Item Unique Identification (IUID) number for material tracking. Any hardware or software modifications that are subsequently made to the actual flight computer (on any mission) shall also be made available by the LSC to the representative flight-like computer at no additional cost to the Government. The LSC shall provide technical support as needed and design information to the MAC to facilitate integration of the computer with the MAC’s test bed.
2.1.2.2.4 Risk Assessment. Risk assessments shall include the LSC's assessment of SS risks, to include those identified by other organizations as provided by the COR, and follow guidance from the SMC Risk Management Process Guide criteria for consequences (severity) and likelihood (probability). [CDRL A022 - DRIP (Government Reviews)]
2.1.2.2.5 Test Planning and Qualification/Acceptance Testing: The LSC shall perform Test Planning and Qualification Testing to ensure that the Government is provided with a LS design that is qualified and capable of meeting all the requirements.
The LSC shall identify all data products developed during the launch service. [CDRL A036 – Data Accession List]
2.1.2.2.5.1 Test Planning: All testing shall be consistent with Test- Like-You-Fly (TLYF) practices; any planned deviations from TLYF practices shall be documented and presented at the Test Readiness Review (TRR). Any deviations from TLYF due to unforeseen test circumstances shall be presented at the Pedigree Review (PR) and summarized at the PSR. The LSC is required to inform the COR of testing milestones so that Government representation may be present. Government representatives and the MAC may witness some or all of these tests. [CDRL A012 – Test Procedures]
2.1.2.2.5.2 Test Readiness Review (TRR): At the conclusion of the test planning phase (approximately T-10 months to launch, or as directed by the COR, in coordination with the LSC) the LSC shall hold one or more TRR to review the adequacy of the planned testing. [CDRL A002 - DRIP]
2.1.2.2.5.3 Qualification Testing: For qualification testing, the LSC shall release all drawings under configuration control, and manufacture, fabricate or acquire the qualification items.
OSP-4 PWS – Basic Page 17 of 50
The LSC shall then perform qualification testing on flight-representative qualification items in accordance with the LTS 10-2010-04. In instances where the LSC is developing equipment that will be used on an OSP-4 mission under company proprietary, Industry Research & Development (IRAD) or other non-OSP direct funding, the MAC must be allowed to review the documentation in the LSC’s facility.
The LSC shall report and assess test anomalies and failures.
[CDRL A012 - Qualification Test Procedures; A013 - Qualification Test Report; A014 - Qualification Test Anomaly/Failure Report]
2.1.2.2.5.4 Acceptance Testing: Once the design has been qualified, acceptance testing of flight hardware may commence. In instances where the LSC is developing equipment that will be used on an OSP-4 mission under company proprietary, IRAD or other non-OSP direct funding, the MAC as a minimum must be allowed to review the documentation in the LSC’s facility. [CDRL A012 - Acceptance Test Procedure; A013 - Acceptance Test Report]
2.1.2.2.5.5 Formal Testing Results: Results from all formal testing (qualification data summary, acceptance test data, and system test data) shall be summarized and reviewed as part of the PSR, including test anomalies and failures. [CDRL
A002 - DRIP]
2.1.2.2.5.6 Flight Hardware Risks: The LSC shall evaluate flight hardware risks associated with Government-Industry Data Exchange Program (GIDEP) and Missile Defense Agency advisories. The LSC shall have an internal process to identify sibling issues and evaluate associated flight hardware risks. [CDRL A023 - GIDEP, Sibling Alert, and MDA Advisory Dispositions]
2.1.2.2.5.7 Qualification Testing Review (QTR): At the conclusion of the qualification testing phase (approximately T-5 months to launch or as directed by the COR, in coordination with the LSC) the LSC shall hold a Qualification Testing Review (QTR) to review the qualification testing results. [CDRL
A002 - DRIP]
2.1.2.3 Category 3: These missions shall meet all the requirements of Category 2, and also shall be subject to increased breadth and depth of Government IV&V and Government insight into LSC System Engineering, Program Management, MA, and other processes/tasks as defined in Annex 1 and Annex 2. The LSC shall support the MAC, SMC/IRRT, and customer-designated MA processes to establish confidence in the accuracy and sufficiency of the data provided by the LSC. Up to 10 dedicated IRRT reviews may be required, with monthly 1-day
OSP-4 PWS – Basic Page 18 of 50
Program Management Reviews throughout the period of performance, as well as weekly 2-hour telecoms to communicate current status of concerns and action items.
2.1.3 Government Readiness Reviews (Cat 2&3 Missions Only): The following readiness reviews will be conducted to support the SMC Readiness Review Process leading to Flightworthiness Certification. The LSC shall support the following Government readiness reviews by providing presentation material and technical data; the LSC’s programmatic and technical personnel shall be required to attend. These reviews will typically be held at Government facilities.
• Mission Readiness Review (MRR) T-60 Days
• Executive Incremental Readiness Review (eIRR) T-30 Days
• Flight Readiness Review (FRR) T-14 Days
• Launch Readiness Review (LRR) T-2 Days
This support will include summarizing analyses, test results, technical data, subassembly graphics, and other information on current, emerging and closed launch service issues. [CDRL A022 - DRIP (Government Reviews)]
2.1.4 Launch Campaign: The LSC shall execute the launch campaign, coordinate all safety operations with the Range, and ensure that critical skills and qualified personnel are available when required for integration, testing, and on-console operations. The LSC shall also provide calibrated, certified and qualified LSE and GSE as required for the completion of range integration tasks to process, prepare and launch the SS with the integrated SV(s). This activity requires close cooperation between the Government, LSC, SV(s) provider, and the Range.
2.1.4.1 Launch Site and Services: The Government will provide Government services at Government ranges (e.g., Flight Safety, Telemetry, and Radar). The LSC shall specify all required Government range services/support. All spaceport services, non-Government range services, and launch site services shall be provided by the LSC unless otherwise stated in the MRD. [CDRL A010 - Range/License Related Documentation]
2.1.4.2 Range Requirements Coordination and Documentation: The LSC shall comply with all Range processes to ensure that the requirements specified in the SS to Range ICD and other range interfaces (e.g. range facilities requirements document) are safely executed and coordinated with the Range. The LSC is responsible for obtaining, producing and/or coordinating all items required by the Range. The LSC shall develop and provide Universal Documentation System (UDS) or other range-required documentation inputs for submittal by the program office to the Range as required by the launch site. The LSC shall participate in Range working groups as required. [CDRL A010 - Range/License Related Documentation]
2.1.4.3 System Safety: The LSC shall comply with AFSPCMAN 91-710 (or equivalent, when specified by the cognizant range) for all applicable launch site activities. These safety requirements may be tailored, but the LSC is
OSP-4 PWS – Basic Page 19 of 50 responsible for obtaining approval for any range safety tailoring. The LSC shall plan system safety activities for the entire system lifecycle (from development through disposal) as executed under this Task Order in accordance with MIL- STD-882E Task 102. The LSC shall coordinate scheduling all activities and/or operations with the Range Safety Office, as applicable. [CDRL A010 - Range/License Related Documentation; A020 – Lifecycle System Safety Program Plan]
2.1.4.4 Ground and Flight Safety Hazard Analyses: Ground and flight safety hazard analyses shall be performed in accordance with AFSPCMAN 91-710 (or equivalent when specified by the cognizant Range) and MIL-STD-882E Task 106, Task 202 and Task 205.
The LSC shall work with the cognizant range safety office in coordination with program office to tailor (if required) the applicable flight safety requirements for the SS, complete development of a compliant flight safety system and gain range safety approval for the implementation of its flight safety system. The LSC shall make prompt waiver requests to the COR if unable to meet range safety requirements due to technical issues with the design or flight hardware.
Failure to obtain approval for the desired tailoring shall not relieve the LSC of its responsibilities under this contract. [CDRL A010 - Range/License Related Documentation; A020 - Preliminary Hazard Analysis, System Hazard Analysis]
2.1.4.4.1 Safety and Environmental Documentation: The LSC shall support the Government safety and environmental documentation required for safety, hazards, debris, and environmental analysis in accordance with MIL-STD-882E Task 301. Documentation includes System Safety Program Plan, Safety Assessment Report, Failure Modes Effects and Criticality Analysis (FMECA), Reliability reports, and AF Form 813 Environmental Impact Analysis inputs. [CDRL A020 - Safety Assessment Report; A033 FMECA]
2.1.4.5 Facilities and Services: The LSC shall provide the required facilities and services at the launch site, which meet all mission requirements defined in the SLPRD, SLIS, and MRD. These requirements shall include, but are not limited to, safety, contamination control, SV(s) integration, flight control facilities, transportation, lifting/stacking and fueling infrastructure, unless otherwise specified. The SV(s) Processing Facility (capable of accommodating LSC encapsulation activities) will be provided by the SV(s) contractor unless otherwise stated in the MRD. [CDRL A010 - Range/License related Documentation]
2.1.4.6 Approvals and Waivers: The LSC shall obtain any necessary coordination or approval from the cognizant range for activities taking place at the cognizant range. The LSC shall obtain appropriate documentation, approvals, and perform other necessary actions to secure access to GFP, equipment, facilities, etc. If waivers are required, the LSC shall obtain them prior to initiating facility activation or modification. The LSC shall brief equivalent levels of safety requests at range working groups and formal reviews. The LSC's failure to gain
OSP-4 PWS – Basic Page 20 of 50 a required approval or waiver shall not relieve the LSC of any responsibilities under this contract. If the LSC identifies any work outside the scope of this contract that is required to meet range requirements, the LSC shall immediately notify the PCO. The LSC shall provide the Government with the necessary information to support approval processes for the launch (i.e. SS RF Frequency approval, Indemnification). [CDRL A010 - Range/License Related Documentarian]
2.1.4.7 New Strategic Arms Reduction Treaty (START) Requirements: If the SS uses GFP motors subject to New START treaty considerations (e.g. Minuteman III ICBM first stage motors), the LSC shall provide “interpretive data” on all telemetry that is transmitted prior to the SS achieving burnout for incorporation into documents required by the New START Treaty. Encryption of telemetry data may not be permitted when launch is subject to the New START Treaty.
[CDRL A017 - New START Treaty Interpretive Data]
2.1.4.8 Cybersecurity: Classification requirements for the mission will be specified in the MRD.
2.1.4.8.1 Unclassified Information: The LSC shall obtain range authority to connect approval(s) for all commercial information systems planned to support the launch.
2.1.4.8.2 Classified Information: All nonfederal computer systems and software packages that will be used for processing, transmitting, and/or storing Government classified information shall be accredited following the Defense Security Service (DSS) Office of the Designated Approving Authority (ODAA) certification and accreditation process. This is the standard process under which commercial information systems handling DoD classified information achieve and maintain Authority To Operate. [CDRL A025 - Cybersecurity Implementation Plan]
2.1.4.9 Classified Payloads: Payloads may be classified to varying degrees and the LSC shall be able to accept delivery and process all payloads. When classified payloads are processed the LSC shall provide trained people with the proper clearance to perform the required work in compliance with the applicable Security Classification Guide. Classification requirements for each mission will be specified in the MRD.
2.1.4.10 SS/SV(s) Operations: The LSC shall integrate the SV(s) with the SS in a clean room environment as specified in the MRD, and perform end-to-end testing with the SV(s). End-to-end verifications tests are tests of the hardware/software to obtain or validate engineering data on the performance of the system prior to the execution of the launch operation. All integrated operations shall be performed using procedures approved by participating agencies. [CDRL A012 - Integration Test Procedure]
2.1.4.10.1 Launch Verification Testing: An integrated field processing procedure shall be prepared by the LSC test conductor in each test. All anomalies
OSP-4 PWS – Basic Page 21 of 50 shall be documented by the LSC. [CDRL A012 - Payload Integration Test Procedure]
2.1.4.10.2 SS/SV(s) Mating: Unless otherwise specified in the MRD, the SV(s) contractor will be responsible for all SV(s) integration activities prior to payload mating. During payload mating, the Payload Contractor will furnish certified handling/GSE required to interface from the crane hook (or other GSE) to the payload, as required during the integration process. The SV(s) contractor will transfer responsibility for the SV(s) to the LSC when the SV(s) is prepared for immediate mating with the SS and is approximately three inches (3”) away from the SS mating surfaces. The LSC shall conduct mechanical mating, spurious voltage, and electrical connection checks in concert with the SV(s) contractor.
2.1.4.10.3 SS/SV(s) Integrated Processing: Integrated SS/SV(s) processing shall be performed in preparation for SV(s) emplacement on the SS at the launch site. During integrated processing the LSC shall accommodate the SV(s) GSE at the launch site. The LSC shall assist the SV(s) contractor in conducting post-mate checks that may include the SV(s) operational assurance tests and a compatibility test of the SS and SV(s) systems, and the GSE interfaces. Following the post-mate checks, the LSC shall encapsulate the mated SV(s).
2.1.4.10.4 SS/ SV(s) Flight Integration Tests: The flight integration test shall be performed using the flight hardware to verify electrical compatibility and system performance between the SV(s) and the SS upper section(s) prior to movement to the launch site (typically performed within a processing facility at the launch range). The LSC shall provide hardware for any SS-required tests and the SV(s) contractor will provide hardware for any SV(s)-required tests.
2.1.4.10.5 SV(s) Support Equipment and Ground System Checkout: The SV(s) contractor will install the required SV(s) Support Equipment at the launch site in locations to be defined in the SS/SV(s) ICD. A design compatibility test to establish high confidence in electrical compatibility of the SV(s) and SV(s) GSE with the launch complex will be performed at the launch site. The SV(s) provider will prepare the test procedure and conduct the test. The LSC shall provide support personnel, facilities access, and the SV(s) contractor will supply all SV(s)-related GSE. The LSC shall provide support to the SV(s) contractor to test the installed equipment. [CDRL A012]
2.1.4.11 Simulations & Rehearsals: The LSC shall coordinate and conduct one green card (simulated countdown) dress rehearsal and one full mission dress rehearsal.
The mission dress rehearsal is a simulated countdown, exercising range interfaces to verify the operational readiness of the entire Aerospace Vehicle Equipment (AVE)/ground system with all launch team members) and one wet dress rehearsal (for liquid propulsion SSs only). (The term AVE refers to the entire SS). The mission dress rehearsal and wet dress rehearsal may be
OSP-4 PWS – Basic Page 22 of 50 combined into one rehearsal, contingent upon approval by the COR. These simulations must include all launch day participants (e.g., Range, LSC, SV(s) contractor, Government, and others as applicable) unless otherwise specified.