This document provides details on a planned competitive acquisition by the Department of Defense Air Force Materiel Command for continuing development of the Weapons Planning Software suite. Key information includes:

  • The solicitation is for the Weapon Planning Software (WPS) program to develop WPS version 2.2 and provide enhancements to version 2.1.x. Work will occur in four increments from June 2019 through March 2020.

  • Interested vendors were encouraged to provide feedback on the draft Request for Proposal by June 15, 2018 related to areas like contract types, pricing terms, labor categories and compliance documentation. One-on-one discussion sessions were held with vendors in June 2018 to obtain input.

  • The agency intends to award a competitive contract for work including new feature integration, legacy enhancements and defect repairs, engineering releases, testing and final deliverables. Transition support is also included.

  • Export controlled technical documentation for the requirement was available to interested vendors who completed a request form and acknowledged export control responsibilities. Foreign vendors were noted as ineligible for any resulting contract.

Working Attachment 15 - Initial DO Package Attachment 1 DO SOW Build Plan

View the file

Other files for this federal contract opportunity

Other files attached to Weapon Planning Software (WPS), newest first.
File Type Posted
FA8681-18-R-0006_0002.pdf PDF
FA8681-18-R-0006_Q&A_Round_3.pdf PDF
WPS_FA8681-18-R-0006-Q&A_Round_2.pdf PDF
DO_1_SOW__18_Sep.docx DOCX document
FA8681-18-R-0006_0001.pdf PDF
WPS_FA8681-18-R-0006_Q&A.pdf PDF
Attachment_14_-_Proposal_Cross-Reference_Matrix_13_Aug.xlsx XLSX spreadsheet
ComplianceDocMatrix.xlsx XLSX spreadsheet
Attachment_17_-_Cost_Spreadsheet_27_Aug.xlsx XLSX spreadsheet
DO_Attach_1_-_DO_1_SOW_9_Aug.docx DOCX document
WPS_Second_DRFP_Q&A.pdf PDF
DRFP2_FA8681-18-R-0006_26_July_2018.pdf PDF
Attachment_17_as_of_26July.xlsx XLSX spreadsheet
DRFP_Final_Q&A_13_July.pdf PDF
Attachment_18_-_Export_Controlled_Info_Request.pdf PDF
FA8681-18-R-0006_DRAFT_RFP_5-16-18_Updated.pdf PDF
FA8681-18-R-0006_DRAFT_RFP_5-16-18.pdf PDF
FA8681-18-R-0006_DRAFT_RFP_5-15-18.pdf PDF
Attachment_18_-_Export_Controlled_Info_Request.pdf PDF
Show all 19

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Increment 0

Jun 2019 Increment 1

Jul – Sept 2019 Increment 2

Oct – Dec 2019 Increment 3

Jan – Mar 2020

Notional WPS v2.X Product Build Plan

WPS 2.2 Development New Feature integration per prioritized CR backlog 1)… 2)… 3)…etc

GPS CC– PBR/TIM#1

Sprint reviews & demos

CLIN 0100

V2.1.X Legacy Enhancements: DR/CR fixes Initial Stand up

PGMPS CC

Prioritized DRs/sprint backlog Review CAF priorities JMPS MPE 4.X changes JTM CC prioritized DR list WDL CC prioritized DR list KH CC prioritized DR list Development Builds for v2.1.X

CLIN 0200

X Sprints per Increment

CLIN 0100

CLIN 0100

CLIN 0100

CLIN 0200

CLIN 0200

CLIN 0200

Transition Support Post Award Conference Initial Stand up Obtaining GFI/GFP Establish Baselines Test config & setup Review/Update ACA’s Product Backlog Review

CLIN 0800

WPS 2.2 Development New Feature integration per prioritized CR backlog 1)… 2)… 3)…etc Sprint reviews & demos WPS 2.2 prototype w/GPS CC V2.1.X Legacy Enhancements: DR/CR fixes

PGMPS CC

DRs (prioritized/sprint) Review CAF priorities JMPS MPE 4.X changes JTM CC prioritized DR list WDL CC prioritized DR list KH CC prioritized DR list WPS v2.1.X Engineering Rel.

ER delivery to MPEs Capture critical DRs Draft CDRL delivery WPS 2.2 Development New Feature integration per prioritized CR backlog 1)… 2)… 3)…etc Sprint reviews & demos WPS 2.2 prototype #2 w/GPS CC V2.1.X Legacy Enhancements: DR/CR fixes

PGMPS CC

DRs (prioritized/sprint) Review CAF priorities JMPS MPE 4.X changes JTM CC prioritized DR list WDL CC prioritized DR list KH CC prioritized DR list WPS v2.1.X Beta (FQT prep) Beta release to MPEs Incorporate priority DRs Updated CDRLs

WPS 2.2 Development New Feature integration per prioritized CR backlog 1)… 2)… 3)…etc Sprint reviews & demos WPS 2.2 ER w/GPS CC V2.1.X Legacy Enhancements: DR/CR fixes

PGMPS CC

DRs (prioritized/sprint) Review CAF priorities JMPS MPE 4.X changes JTM CC prioritized DR list WDL CC prioritized DR list KH CC prioritized DR list WPS v2.1.X FQT and CDRLS TRR for final FQT Conduct FQT w/Gov’t Final CDRL delivery

Transition Support Obtaining GFI/GFP Test config/setup Review/Update ACA’s Initial Baseline Review

CLIN 0800

+30 Days for Final CDRL Delivery

Key Milestones

IBR

CA

IPR #2

IPR #3

IPR #4

PBR / IPR#1

End POP

- v2.2 Prototype

- v2.1.x ER

- v2.2 Demo

- v2.1.x Beta

- v2.2 ER

- v2.1.x FQT image5.png image6.gif