This document is an attachment to a federal contract solicitation for Assured and Trusted Microelectronics Solutions. The solicitation seeks proposals to ensure that legacy, state-of-practice, and future microelectronics technologies remain sustainable, reliable, and secure across military system lifecycles. This includes ensuring microelectronics are acquired exactly as specified without unauthorized additions or alterations, and maintaining robust intellectual property protection during manufacturing and after fielding. The goal is to incorporate commercially available application-specific integrated circuits, system-on-a-chip, and field programmable gate array capabilities without compromising national defense system integrity or security. The Department of the Air Force Materiel Command Research Laboratory is the issuing agency. The attachment provides additional requirements regarding key personnel, packaging and marking, program managers, and implementation of clauses for disclosure of information, patent rights, and environmental compliance that contractors must also address in their proposals.
Statement of Work (SOW) Supplemental Requirements
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| BAA FA8650-18-S-1201 Amd 07.pdf | ||
| BAA Revised Atch 6 - Statement of Objectives.docx | DOCX document | |
| BAA_FA8650-18-S-1201_Amd_04.pdf | ||
| FA8650-18-S-1201-Amd3.pdf | ||
| FA8650-18-S-1201-Amd2.pdf | ||
| FA8650-18-S-1201-Amd1.pdf | ||
| FA8650-18-S-1201-Amd1-Atch8.pdf | ||
| FA8650-18-S-1201.pdf | ||
| FA8650-18-S-1201-Atch3.pdf | ||
| FA8650-18-S-1201-Atch4.pdf | ||
| FA8650-18-S-1201-Atch6.pdf | ||
| FA8650-18-S-1201-Atch5.pdf | ||
| FA8650-18-S-1201-Atch2.pdf | ||
| FA8650-18-S-1201-Atch1.pdf | ||
| NOCA_Announcement_for_ATMS.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA8650-18-S-1201
Attachment 7
Statement of Work (SOW)
Supplemental Requirements
Version 2.6
8 Sep 2017
The following paragraphs are also considered be a part of the SOW requirements and the Contractor is responsible for compliance to the same extent as the rest of the SOW.
1. Implementation of Disclosure of Information - In order to comply with DFARS 252.204-7000, Disclosure of Information, the following copies of the information to be released are required at least 45 days prior to the scheduled release date:
(a) One copy: The Contracting Office (The 88th ABW/PA is hereby designated as the approval authority for the Contracting Officer)
(b) One copy: The Program Manager
2. Key Positions and Minimum Qualifications
(a) Contractor personnel holding the position titles and having the qualifications listed below are considered essential to the work being performed under this contract:
Key Positions: Minimum Qualifications:
(list by job title) (list minimum qualifications in terms of education and/or experience)
(b) The contractor shall notify the contracting officer before the departure of any individual in a key position and identify the proposed substitution. Any proposed personnel substitution that does not meet the minimum qualification requirements described above requires the prior written approval of the contracting officer.
3. Packaging and Marking –
(a) All hardware deliverable contract items shall be packaged in accordance with established commercial practices.
(b) When special delivery and/or handling instructions are required, all boxes and/or crates must contain the following statement in plain sight and in bold letters: INSTRUCTION TO RECEIVING OFFICE -
DO NOT OPEN; CONTENTS ARE SENSITIVE TO DAMAGE WHEN IMPROPERLY OPENED OR HANDLED.
CONTACT THE RESPONSIBLE TECHNICAL PROJECT OFFICER IMMEDIATELY UPON RECEIPT. CONTACT: XX
(TBD)
4. Program Manager – The Government Program Manager for this effort is Glen “Dave” Via, AFRL/RYD, Glen.Via@us.af.mil, 937-713-8694.
5. Program Focal Points - The individuals listed below are identified as focal points for this contract. Principal Investigator: TBD; Technical Contract Manager: TBD; Alternate: TBD.
6. Base Support (if applicable) - Base support may be provided by the Government to the Contractor in accordance with this SOW.
(a) The Contractor will require use of base support on a rent-free, non-interference basis to include
Government-controlled working space, material, equipment, services (including automatic data processing), or other support (excluding use of the Defense Switched Network (DSN)) which the Government determines can be made available at, or through, any Air Force installation where this contract shall be performed.
(b) Unless otherwise stipulated in the contract schedule, the Contractor will use base support on a no-charge-for-use basis and the value shall be a part of the Government's contract consideration.
(c) The Contractor will immediately report (with a copy to the cognizant CAO) inadequacies, defective base support, or nonavailability of support stipulated by the contract schedule, together with a recommended plan for obtaining the required support. Facilities are not be purchased under this contract by the Contractor. Additionally, the Contractor (or authorized representative) will not purchase, or otherwise furnish any base support requirement provided by the SOW/PWS (or authorize others to do so), without prior written approval of the Contracting Officer regarding the price, terms, and conditions of the proposed purchase, or approval of other arrangements.
(d) Written authorization must be requested from the Contracting Officer for support not later than
90 days before the required in-place dates at each Air Force installation, and immediately for any required changes.Ensure the facilities are available and concurrence for their use has been obtained from the cognizant contracting officer before finalizing contract negotiations and/or source selection. In competitive acquisitions, the RFP/RFQ should request the contractor propose a cost in the event that the facilities are not available. This is necessary in order to make a valid comparison of all contractors’ proposals.
(e) The base support to be furnished under this contract is (insert list of support items). Because of the nature and location(s) of the work performed, the value of such support is undeterminable.
mailto:Glen.Via@us.af.mil
The Contractor is not authorized to incur any costs resulting from nonsupport prior to Contracting Officer direction.
7. Implementation of Patent Rights Clause –
(a) “Interim or Final Invention Reports 1) listing the subject invention(s) and stating that all subject inventions have been disclosed, or 2) stating that there are no such inventions, shall be sent to both the Administrative Contracting Officer (at the address located on the face of the contract) and to det1.afrl.pk.patents@us.af.mil within the timeframes specified in the Patent Rights clause of this contract.
(b) Contractors are highly encouraged to use DD Form 882, Report of Invention and Subcontracts, to submit these reports. The DD Form 882 may also be used for the notification of an award of any subcontract(s) for experimental, developmental or research work which contain a “Patent Rights” clause.
(c) All other notifications required by the contract shall also be sent to the addresses in paragraph (a). This provision also constitutes the request for the following information for any subject invention for which the contractor has retained ownership (1) the filing date, (2) serial number and title, (3) a copy of the patent application, and (4) patent number and issue date. Submittal shall be to (insert contact information for person(s) at the procuring contract office who will handle patent administration, e.g., name and/or position, email, phone numbers, etc.).
8. Implementation of Pollution Prevention and Right-To-Know Information-
To comply with FAR Clause 52.223-5 "Pollution Prevention and Right-to-Know Information, Alt 1, and Environmental Management System (EMS) requirements, the contractor is required to complete Initial EMS Awareness-Level training for all personnel working on an Air Force installation.
(a) The installation office responsible for providing the EMS training is 88CEG/CEIEA.
(b) The training requires 30 minutes.
(c) The EMS Awareness-level training shall be accomplished within 60 days of contract (or modification) award. New contract employees shall be trained within 30 days of starting work on the installation.
(d) The EMS Awareness-level training is available via ADLS (AF Portal) https://golearn.adls.af.mil/kc/main/kc_frame.asp?blnWhatsNew=True&guid=06E7AFBFA518DA
701B9F40120E3497B563AB99BC8230618E239831D35CB0E42275B3950F901EA1D8.
(e) Upon completion of the training, the contractor shall provide to the AF program manager (PM) a list of the contractor employees' names and the date the training was completed.
9. Information Regarding Non-US Citizens Assigned to this Project –
(a) Contractor employees requiring access to USAF bases, AFRL facilities, and/or access to U.S.
Government Information Technology (IT) networks in connection with the work on this contract must be U.S. citizens. For the purpose of base and network access, possession of a permanent resident card (“Green Card”) does not equate to U.S. citizenship. This requirement does not apply to foreign nationals approved by the U.S. Department of Defense or U.S. State Department under international personnel exchange agreements with foreign governments.
Any waivers to this requirement must be granted in writing by the Contracting Officer prior to providing access. The above requirements are in addition to any other contract requirements related to obtaining a Common Access Card (CAC).
https://cs2.eis.af.mil/sites/21119/PK/AFRL/Standardized%20Documents/det1.afrl.pk.patents@us.af.mil https://golearn.adls.af.mil/kc/main/kc_frame.asp?blnWhatsNew=True&guid=06E7AFBFA518DA701B9F40120E3497B563AB99BC8230618E239831D35CB0E42275B3950F901EA1D8 https://golearn.adls.af.mil/kc/main/kc_frame.asp?blnWhatsNew=True&guid=06E7AFBFA518DA701B9F40120E3497B563AB99BC8230618E239831D35CB0E42275B3950F901EA1D8
(b) For purposes of paragraph (a) above, if an IT network/system does not require AFRL to endorse a contractor’s application to said network/system in order to gain access, the organization operating the IT network/system is responsible for controlling access to its system. If an IT network/system requires an U.S. Government sponsor to endorse the application in order for access to the IT network/system; AFRL will only endorse the following types of applications;
consistent with the requirements above:
(1) Contractor employees who are U.S. citizens performing work under this contract.
(2) Contractor employees who are non-U.S. citizens and who have been granted a waiver.
Any additional access restrictions established by the IT network/system owner apply.