Questions and Responses Set 2.pdf
PDF 95 KB Posted
- Solicitation number
- FA8604-21-R-B016
About this file
This document contains a federal solicitation for a storage aid system project at two Air Force bases. The solicitation seeks proposals for the design, fabrication, installation, and testing of storage racking and pallet racking systems at Charlotte Air National Guard Base in North Carolina and Buckley Air Force Base in Colorado. Proposals are due by July 13, 2021 and award will be made to the technically acceptable offeror providing the lowest price. Evaluation will follow the lowest price technically acceptable process. The storage aid systems must meet all specifications and drawings provided in the solicitation attachments. The contract performance period is 240 days from award.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| MMHS Storage Aid System Buckley Charlotte (2).zip | ZIP file | |
| Questions and Responses Set 1.pdf | ||
| Questions and Responses Set 1.pdf | ||
| Solicitation - FA860421RB016 (1).pdf | ||
| MMHS Storage Aid System Buckley Charlotte.zip | ZIP file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA860421RB016
Charlotte ANGB NC and Buckley AFB CO Questions/Answers Set 2 6 July 2021
Question 1: App C Bin shelving – 3.2.4.1. & dwg say 96” tall – 3.2.5.1. says 86” – which is accurate?
Response 1: Section 3.2.5.1 has been updated to reflect 96”.
Question 2: App F – 3.2.1.1 – Chart shows MDC height of 89 +/- ¼” – should be “59” ???
Response 2: Chart is 3.2.1.1 has been updated to reflect 59”.
Question 3: Assuming the pallet rack for Buckley portion is the “A” configuration? No note in appendix of on drawing
Response 3: Yes, the pallet racks at Buckley shall be in the “A” configuration.
Question 4: RE: Cover – Demo – who is responsible for removing the materials that are being taken down? Contractor of DRMO?
Response 4: The contractor shall be responsible for removing the materials that are taken down.
Question 5: Just had the sheet metal rack mfg’er ask if a folding rack was requested, or a rack that the front shelf supports are permanently in place was the request.
Response 5: A rack with permanent front shelf supports is required.
FA860421RB016
Charlotte ANGB NC and Buckley AFB CO Questions/Answers Set 1
24 Jun 2021
Question 1: Due to the drawing provided I can’t tell how much room is available for the VLM’s.
Our dimensions do not fit the spec as described – we are 114.7”W VS the requested 110”W & 124.9”D VS the 122”D requested – will those dimensions be acceptable?
Response 1: Specified dimensions must be met to meet mission/space requirements therefore the proposed dimensions are not acceptable.
Question 2: Not seeing available power supply for either location – is there 480V 3 ph available for the VLM hookup?
Response 2: Equipment is being installed in a new building with sufficient power supply to power VLMs. Electrical hookup will not exceed 100 feet from equipment installation location.
Question 3: Cover PD – 3.1.10. – pilf cage States “free standing” meaning no attachment to a wall etc. Then states – 3 sides and a top cap. Drawing 805-2 shows 4 sides – OA dims of 6’ x 30’
– Please have engineer clarify what he is wanting – 3 side or 4 side.
Response 3: Cage shall have 3 sides and a top cap with the adjacent wall severing as the 4th side.